CN109139055A - Wholecircle jacked piles with small section needle beam trolley lining construction method - Google Patents

Wholecircle jacked piles with small section needle beam trolley lining construction method Download PDF

Info

Publication number
CN109139055A
CN109139055A CN201811267253.XA CN201811267253A CN109139055A CN 109139055 A CN109139055 A CN 109139055A CN 201811267253 A CN201811267253 A CN 201811267253A CN 109139055 A CN109139055 A CN 109139055A
Authority
CN
China
Prior art keywords
construction
lining
section
lining cutting
construction section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811267253.XA
Other languages
Chinese (zh)
Inventor
程凯
赵香萍
史振宇
王学军
李晓
王灵敏
郝建宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201811267253.XA priority Critical patent/CN109139055A/en
Publication of CN109139055A publication Critical patent/CN109139055A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of wholecircle jacked piles with small section needle beam trolley lining construction method, comprising the following steps: S1) wholecircle jacked piles with small section is divided into multiple construction sections;S2) using dividing sequence lining method to carry out lining construction to workshop section of each institute, the lining construction of each construction section includes that part brings down stocks step, lining cutting step, brings down stocks lining cutting step and pour step;Step is brought down stocks in the part of each construction section and the lining cutting step of a upper construction section is performed simultaneously, it brings down stocks step and is performed simultaneously in the part for bringing down stocks lining cutting step and next construction section of the lining cutting step of each construction section and a upper construction section, each construction section bring down stocks lining cutting step and the lining cutting step for pouring step and next construction section of a upper construction section is performed simultaneously, each construction section pour step and the lining cutting step of bringing down stocks of next construction section is performed simultaneously;S3) tunnel conserves.Lining construction method provided by the invention saves the time for waiting the concrete setting of each construction section, substantially increases construction efficiency.

Description

Wholecircle jacked piles with small section needle beam trolley lining construction method
Technical field
The present invention relates to water conservancy tunnel construction technical fields, and in particular, to a kind of wholecircle jacked piles with small section needle beam trolley Lining construction method.
Background technique
With the continuous development of Chinese society economy, water conservancy infrastructure is also being rapidly developed, and water conservancy tunnel accounts for water conservancy and builds If the ratio of project is also constantly increasing.Because of the particularity of use environment, the construction of concrete lining of water conservancy tunnel becomes entire Important link in water conservancy inrush during tunneling.Guaranteeing the same of water conservancy tunnel concrete liner construction safety and construction quality When, the construction speed for how accelerating lining cutting becomes the problem of all kinds of engineering staffs pay close attention to jointly.In practice of construction, can usually it meet It is circular tunnel to water conservancy tunnel section, at present when carrying out the lining construction of round water conservancy tunnel, using in completion water conservancy Concreting is carried out to the laying section using needle beam trolley at once after a certain section of lining cutting reinforcing bar is laid in tunnel, is poured to the section The laying of lining cutting reinforcing bar and concreting for carrying out next section after the concrete setting built again, are waiting concrete setting in this way The expansion that not can be carried out other subsequent constructions in the process is unfavorable for the process optimization of entire Construction of Tunnel Liner, seriously affects Construction efficiency.
Summary of the invention
The object of the present invention is to provide a kind of wholecircle jacked piles with small section needle beam trolley lining construction methods, are able to solve existing In technology the problem of the lining construction inefficiency of wholecircle jacked piles with small section.
To achieve the goals above, the embodiment of the present invention provides a kind of wholecircle jacked piles with small section needle beam trolley lining construction side Method, the construction method is the following steps are included: S1) according to the depth of the wholecircle jacked piles with small section, by the wholecircle light section Tunnel is divided into multiple construction sections;S2) using dividing sequence lining method to carry out lining construction to each construction section, until completing institute The lining construction of tunnel is stated, wherein the lining construction of each construction section includes to the hole wall of the construction section in circumferencial direction On the part cleared up of specified region bring down stocks step, fitting completes the part and brings down stocks the hole wall of step to be laid with opening direction The lining cutting step of the No.1 lining cutting reinforced steel bar ring with the first opening angle on ground, cleaning are not laid with the hole of No.1 lining cutting reinforced steel bar ring No. two lining cutting reinforced steel bar rings that wall and the hole wall being bonded after cleaning laying are connected in a circumferential direction with the No.1 lining cutting reinforced steel bar ring To form bringing down stocks lining cutting step and performing pouring for trolley concreting for the closing Lining Ring for closing Lining Ring Step;Wherein step is brought down stocks in the part of each construction section and the lining cutting step of a upper construction section is performed simultaneously, each construction section The part for bringing down stocks lining cutting step and next construction section of lining cutting step and a upper construction section is brought down stocks step and is performed simultaneously, each construction Section bring down stocks lining cutting step and the lining cutting step for pouring step and next construction section of a upper construction section is performed simultaneously, each construction Section pour step and the lining cutting step of bringing down stocks of next construction section is performed simultaneously;S3) to complete lining construction the tunnel into Row maintenance.
Further, the step S2) further include: it is right after the wholecircle jacked piles with small section is divided into multiple construction sections Part is completed in each construction section to bring down stocks the hole wall after step and bring down stocks cleaning in lining cutting step to complete not to be laid with No.1 The hole wall of lining cutting reinforced steel bar ring executes just pneumatically placed concrete and reaches first thickness.
Preferably, the first thickness is between 2-3cm.
Further, step S2) in, the step that pours includes: when executing the lining cutting step to the tunnel Longitudinal direction promotes needle beam trolley to the casting position of the construction section, completes to bring down stocks lining cutting step described in the construction section Afterwards, the formwork for placing on the needle beam trolley is adjusted to and the No.1 lining cutting reinforced steel bar ring of the construction section and No. two described Kept between lining cutting reinforced steel bar ring the first interannular away from;By on the formwork for placing pour window to the formwork for placing with it is described Concrete is injected between the hole wall of construction section to complete described to pour step.
Preferably, first interannular is away between 45-55mm.
Preferably, first opening angle is between 250 ° -280 °.
Wholecircle jacked piles with small section needle beam trolley lining construction method provided by the invention, wholecircle jacked piles with small section is divided into more A construction section alternately applies part to multiple construction sections and brings down stocks step, lining cutting step, brings down stocks lining cutting step and pour step Suddenly, the closed lining cutting reinforced steel bar ring in each construction section is divided into two sections, the No.1 lining cutting reinforced steel bar ring being respectively open and It is connected No. two lining cutting reinforced steel bar rings of closing cyclization, lining construction side of the invention in circumferencial direction with the No.1 lining cutting reinforced steel bar ring Method executes the lining cutting step of a upper construction section while step is brought down stocks in the part for carrying out one of construction section, applies executing this Executed while workshop section's lining cutting step a upper construction section bring down stocks lining cutting step and step is brought down stocks in the part of next construction section, holding The lining cutting step for pouring step and next construction section that a upper construction section is executed while bringing down stocks lining cutting step of the row construction section, After the No.1 lining cutting reinforced steel bar ring of the construction section and No. two lining cutting reinforcing bar ring seals cyclization, execute the construction section to pour step same Once construction section brings down stocks lining cutting step to Shi Zhihang, can construct simultaneously to multiple construction sections in this way, and in the prior art It needs to complete just execute after waiting the concrete setting poured in the construction section after the complete lining construction an of construction section The lining construction of next construction section is compared, lining construction method provided by the invention, is saved and is waited each construction section The time of concrete setting substantially increases the construction efficiency of entire tunnel.
Other features and advantages of the present invention will the following detailed description will be given in the detailed implementation section.
Detailed description of the invention
Attached drawing is and to constitute part of specification for providing further understanding of the present application, with following tool Body embodiment is used to explain the application together, but does not constitute the limitation to the application.In the accompanying drawings:
Fig. 1 is the step flow chart of wholecircle jacked piles with small section needle beam trolley lining construction method provided by the invention.
Specific embodiment
Below in conjunction with attached drawing, detailed description of the preferred embodiments.It should be understood that this place is retouched The specific embodiment stated is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
In the present invention, in the absence of explanation to the contrary, the noun of locality used such as " upper and lower, top, bottom " is usually needle For direction shown in the drawings either for it is vertical, on vertical or gravity direction for each component mutual alignment relation Word is described.
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
Fig. 1 is the step process for the wholecircle jacked piles with small section needle beam trolley lining construction method that embodiment of the present invention provides Figure.Lining construction method provided by the invention is the following steps are included: S1) according to the depth of the wholecircle jacked piles with small section, by institute It states wholecircle jacked piles with small section and is divided into multiple construction sections;S2) lining cutting is carried out to each construction section using point sequence lining method to apply Work, until the lining construction of the tunnel is completed, wherein the lining construction of each construction section includes to the construction section Step is brought down stocks in the part that the specified region of hole wall in a circumferential direction is cleared up, the hole that step is brought down stocks in the part is completed in fitting Wall be laid with opening towards ground the No.1 lining cutting reinforced steel bar ring with the first opening angle lining cutting step, clear up be not laid with No.1 What the hole wall of lining cutting reinforced steel bar ring and the hole wall being bonded after cleaning laying were connected in a circumferential direction with the No.1 lining cutting reinforced steel bar ring No. two lining cutting reinforced steel bar rings with formed closing Lining Ring bring down stocks lining cutting step and for the closing Lining Ring perform trolley mix What solidifying soil poured pours step;Wherein step is brought down stocks in the part of each construction section and the lining cutting step of a upper construction section is held simultaneously Row, it is same that step is brought down stocks in the part for bringing down stocks lining cutting step and next construction section of the lining cutting step of each construction section and a upper construction section Shi Zhihang, each construction section bring down stocks lining cutting step and the lining cutting step for pouring step and next construction section of a upper construction section is same Shi Zhihang, each construction section pour step and the lining cutting step of bringing down stocks of next construction section is performed simultaneously;S3) completion lining cutting is applied The tunnel of work is conserved.
Wherein, wholecircle jacked piles with small section needle beam trolley lining construction method provided by the invention, with existing lining construction Method is compared using the lining construction for being further continued for next section of tunnel after the complete lining construction for completing one section of tunnel, and the present invention provides Construction method be that the tunnel is divided into multiple construction sections, bring down stocks step using in the part for carrying out one of construction section It is performed simultaneously the lining cutting step of a construction section, bringing down stocks for a upper construction section is executed while executing the construction section lining cutting step The part of lining cutting step and next construction section brings down stocks step, and upper one is performed simultaneously when bringing down stocks lining cutting step executing the construction section The lining cutting step for pouring step and next construction section of construction section, in the No.1 lining cutting reinforced steel bar ring and No. two linings that the construction section is laid with After building reinforcing bar ring seal cyclization, execute the construction section pour that step is performed simultaneously construction section bring down stocks lining cutting step, this The process that sample can be performed simultaneously the lining construction of multiple construction sections is conducive to the construction efficiency for improving wholecircle jacked piles with small section.
In one embodiment, the wholecircle jacked piles with small section is divided into multiple construction sections, to the multiple construction section point It is not marked in sequence, is labeled as the first construction section, the second construction section ... N construction section, the lining cutting of each construction section is applied Work process includes four steps: bringing down stocks step, lining cutting step, brings down stocks lining cutting step and pour step in part.It is applied in execution first When step is brought down stocks in the part of workshop section, needs to clear up sundries on the hole wall part of the first construction section, native mud and loosen rock, become silted up Mud, loose weak interlayer, the hole wall range of cleaning, which is subject to, to be covered by the No.1 lining cutting reinforced steel bar ring, and when cleaning is first used anti- It is thick clear that shovel carries out basis, then is cleared up by hand fit's mini-excavator thin portion, and artificial sled is cleared up except relaxed rockmass and with high-pressure blast. Side and roof arch is manually prized using reinforcement trolley except broken sillar is loosened, and Forward-testing, processing part owe to dig, based on hydraulic breaking hammer It carries out owing digging processing, if bursting work is needed to carry out owing digging processing, treatment principle is: maximum single blow blasting charge is not greater than 40g, quick-fried Pouring concrete surface, sealing and exposed steel bar must be protected comprehensively before broken, the method for protection can use waste and old wheel Tire, circle weedtree, plank or the method for straw mat covering, after the completion of locally bringing down stocks step, fitting completes the part and brings down stocks step The first construction section hole wall be laid with No.1 lining cutting reinforced steel bar ring to complete lining cutting step.The No.1 lining cutting reinforced steel bar ring is with the The non-close reinforced steel bar ring of one opening angle, it is preferable that first angle is between 250 ° -280 °, it is further preferable that described first Angle is 270 °.Second construction section adjacent with the first construction section is executed while executing the lining cutting step of the first construction section Step is brought down stocks in part, and the first construction section is continued to execute after the completion of the lining cutting step of the first construction section brings down stocks lining cutting step simultaneously Step is brought down stocks in the part of the lining cutting step and third construction section that execute the second construction section, brings down stocks lining cutting in the first construction section of completion It is executed after step and pours step, walked in the lining cutting of bringing down stocks for executing the second construction section while pouring step for executing the first construction section Step is brought down stocks in the rapid and lining cutting step of third construction section and the part of the 4th construction section, to the first construction section to pour step complete Lining construction at rear first construction section terminates, in existing after the completion of bringing down stocks lining cutting step to needle beam trolley for the second construction section After the demoulding of first construction section, start the second construction section execute pour that step is performed simultaneously third construction section bring down stocks lining cutting step And the 4th construction section lining cutting step and the part of the 5th construction section bring down stocks step, simultaneously be unfolded to serve as a contrast in multiple construction sections in this way The part built in working procedure brings down stocks step, lining cutting step, brings down stocks lining cutting step and pour step, until wholecircle jacked piles with small section In the steps that pours of all construction sections be fully completed, the lining construction of entire wholecircle jacked piles with small section terminates.
Construction method provided by the invention can be after in the period for the concrete setting for waiting each construction section to pour The continuous other process for executing next construction section, for example, being able to carry out first while executing the lining cutting step of the second construction section Construction section bring down stocks lining cutting step and step is brought down stocks in the part of third construction section, optimize the entire lining construction work of the tunnel Sequence improves the construction efficiency of the lining construction of the tunnel.
Before carrying out lining construction to wholecircle jacked piles with small section, need to carry out the hole wall of wholecircle jacked piles with small section clear Reason, further, the step S2) further include: after the wholecircle jacked piles with small section is divided into multiple construction sections, to each institute It states the hole wall after completing locally to bring down stocks step in construction section and brings down stocks cleaning in lining cutting step and complete not being laid with No.1 lining cutting steel The hole wall of muscle ring executes just pneumatically placed concrete and reaches first thickness.
In the above-described embodiments, after step is brought down stocks in the part for completing the first construction section, in the first construction section cleaned out Hole wall on just pneumatically placed concrete reach first thickness, equally when lining cutting step is brought down stocks in execution, complete be not laid with No.1 lining cutting It is thick to pneumatically placed concrete at the beginning of the hole wall for not being laid with No.1 lining cutting reinforced steel bar ring after cleaning up to first after the cleaning of the hole wall of reinforced steel bar ring Degree, it is preferable that the first thickness is between 2-3cm.
Further, step S2) described in pour step include: when executing the lining cutting step to the vertical of the tunnel Deep direction promotes needle beam trolley to the casting position of the construction section, completes to bring down stocks lining cutting step described in the construction section Afterwards, the formwork for placing on the needle beam trolley is adjusted to and the No.1 lining cutting reinforced steel bar ring of the construction section and No. two described Kept between lining cutting reinforced steel bar ring the first interannular away from;By on the formwork for placing pour window to the formwork for placing with it is described Concrete is injected between the hole wall of construction section to complete described to pour step.
In one embodiment, needle beam platform is promoted to the longitudinal direction of tunnel when executing the lining cutting step of a certain construction section Vehicle is laid in the hole wall for being bonded the construction section to the casting position of the construction section and completes No.1 lining cutting reinforced steel bar ring and No. two lining cutting Step is poured in construction section execution after reinforced steel bar ring and No.1 lining cutting reinforced steel bar ring and No. two lining cutting reinforcing bar closing cyclization;Execution pours When step, the formwork for placing of needle beam trolley is adjusted to and the No.1 lining cutting reinforced steel bar ring of the construction section and No. two lining cutting reinforced steel bar rings Formation closing Lining Ring between interannular away from for the first interannular away from, it is preferable that first interannular is away between 45-55mm;It adjusts When whole formwork for placing, using the vertical oil cylinder in needle beam trolley front and back end and cross cylinder, needle beam trolley front and back end absolute altitude is adjusted, and make Trolley center is overlapped with canal axes, the bed die string beam of formwork for placing can be used as level measurement basic point, bed die when adjusting absolute altitude Center is adjusted as trolley center;After trolley center is overlapped with canal axes, formwork for placing hydraulic system is controlled to one Side Dong Bi, which is overhanged, pours side mode, is finely adjusted with the lead screw of helical screw jack, makes what front and back end overhanged to pour side mode size Reach design size and (reaches interannular between formwork for placing and the No.1 lining cutting reinforced steel bar ring of the construction section away from for the first interannular Away from), same control formwork for placing hydraulic system is overhanged to other side Dong Bi pours side mode, with the lead screw of helical screw jack It is finely adjusted, the side mode size that pours for overhanging front and back end reaches design size;All helical screw jack are finally screwed, are closed Motor is closed, the operation handle of hydraulic valve in waggle hydraulic system makes system release, installs head plate, formwork for placing adjustment It completes.After the completion of formwork for placing adjustment, window casting concrete is poured by what is opened up on formwork for placing, to complete the construction The described of section pours step.
Wholecircle jacked piles with small section needle beam trolley lining construction method provided by the invention, wholecircle jacked piles with small section is divided into more A construction section alternately applies part to multiple construction sections and brings down stocks step, lining cutting step, brings down stocks lining cutting step and pour step Suddenly, the closed lining cutting reinforced steel bar ring in each construction section is divided into two sections, the No.1 lining cutting reinforced steel bar ring being respectively open and It is connected No. two lining cutting reinforced steel bar rings of closing cyclization, lining construction side of the invention in circumferencial direction with the No.1 lining cutting reinforced steel bar ring Method executes the lining cutting step of a upper construction section while step is brought down stocks in the part for carrying out one of construction section, applies executing this Executed while workshop section's lining cutting step a upper construction section bring down stocks lining cutting step and step is brought down stocks in the part of next construction section, holding The lining cutting step for pouring step and next construction section that a upper construction section is executed while bringing down stocks lining cutting step of the row construction section, After the No.1 lining cutting reinforced steel bar ring of the construction section and No. two lining cutting reinforcing bar ring seals cyclization, execute the construction section to pour step same Once construction section brings down stocks lining cutting step to Shi Zhihang, can construct simultaneously to multiple construction sections in this way, and in the prior art It needs to complete just execute after waiting the concrete setting poured in the construction section after the complete lining construction an of construction section The lining construction of next construction section is compared, lining construction method provided by the invention, is saved and is waited each construction section The time of concrete setting substantially increases the construction efficiency of entire tunnel.
It is described the prefered embodiments of the present invention in detail above in conjunction with attached drawing, still, the present invention is not limited to above-mentioned realities The detail in mode is applied, within the scope of the technical concept of the present invention, a variety of letters can be carried out to technical solution of the present invention Monotropic type, these simple variants all belong to the scope of protection of the present invention.
It is further to note that specific technical features described in the above specific embodiments, in not lance In the case where shield, can be combined in any appropriate way, in order to avoid unnecessary repetition, the present invention to it is various can No further explanation will be given for the combination of energy.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally The thought of invention, it should also be regarded as the disclosure of the present invention.

Claims (6)

1. a kind of wholecircle jacked piles with small section needle beam trolley lining construction method, which is characterized in that the construction method includes following Step:
S1) according to the depth of the wholecircle jacked piles with small section, the wholecircle jacked piles with small section is divided into multiple construction sections;
S2 it) uses and sequence lining method is divided to carry out lining construction to each construction section, until the lining construction of the tunnel is completed, Wherein the lining construction of each construction section includes carrying out to the specified region of the hole wall of the construction section in a circumferential direction Step is brought down stocks in the part of cleaning, the hole wall laying opening that step is brought down stocks in the part is completed in fitting has first opening towards ground After the lining cutting step of the No.1 lining cutting reinforced steel bar ring of bicker degree, cleaning are not laid with the hole wall of No.1 lining cutting reinforced steel bar ring and are bonded cleaning Hole wall is laid with No. two lining cutting reinforced steel bar rings being connected in a circumferential direction with the No.1 lining cutting reinforced steel bar ring to form closing Lining Ring Bring down stocks lining cutting step and pour step for what the closing Lining Ring performed trolley concreting;It is wherein each to apply Step is brought down stocks in the part of workshop section and the lining cutting step of a upper construction section is performed simultaneously, and the lining cutting step of each construction section is applied with upper one The part for bringing down stocks lining cutting step and next construction section of workshop section is brought down stocks step and is performed simultaneously, and each construction section brings down stocks lining cutting step It is performed simultaneously with the lining cutting step for pouring step and next construction section of a upper construction section, each construction section pours step under The lining cutting step of bringing down stocks of one construction section is performed simultaneously;
S3) tunnel for completing lining construction is conserved.
2. lining construction method according to claim 1, which is characterized in that the step S2) further include:
After the wholecircle jacked piles with small section is divided into multiple construction sections, step is brought down stocks to part is completed in each construction section It rear hole wall and brings down stocks cleaning in lining cutting step and completes not to be laid with the hole wall of No.1 lining cutting reinforced steel bar ring to execute just pneumatically placed concrete and reach First thickness.
3. lining construction method according to claim 2, which is characterized in that the first thickness is between 2-3cm.
4. lining construction method according to claim 1, which is characterized in that step S2) in, the step that pours includes:
Needle beam trolley is promoted to pour position to the construction section to the longitudinal direction of the tunnel when executing the lining cutting step It sets, after the completion of bringing down stocks lining cutting step described in the construction section, the formwork for placing on the needle beam trolley is adjusted to and institute State kept between the No.1 lining cutting reinforced steel bar ring of construction section and No. two lining cutting reinforced steel bar rings the first interannular away from;
Coagulation is injected between the formwork for placing and the hole wall of the construction section by the window that pours on the formwork for placing Soil is to complete described to pour step.
5. lining construction method according to claim 4, which is characterized in that first interannular is away between 45-55mm.
6. lining construction method according to claim 1, which is characterized in that first opening angle between 250 °- 280°。
CN201811267253.XA 2018-10-29 2018-10-29 Wholecircle jacked piles with small section needle beam trolley lining construction method Pending CN109139055A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811267253.XA CN109139055A (en) 2018-10-29 2018-10-29 Wholecircle jacked piles with small section needle beam trolley lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811267253.XA CN109139055A (en) 2018-10-29 2018-10-29 Wholecircle jacked piles with small section needle beam trolley lining construction method

Publications (1)

Publication Number Publication Date
CN109139055A true CN109139055A (en) 2019-01-04

Family

ID=64806542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811267253.XA Pending CN109139055A (en) 2018-10-29 2018-10-29 Wholecircle jacked piles with small section needle beam trolley lining construction method

Country Status (1)

Country Link
CN (1) CN109139055A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4613258A (en) * 1984-05-11 1986-09-23 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Apparatus for setting and removing tunnel casing rings
CN102425435A (en) * 2011-12-30 2012-04-25 广汉金达隧道机械有限公司 Ultra-large whole-circle needle beam type hydraulic steel mould trolley and demoulding method thereof
CN102434171A (en) * 2011-11-17 2012-05-02 广汉金达隧道机械有限公司 Tunnel bottom concrete side-slipping lining construction method and side-slipping needle beam bottom board trolley
CN103603677A (en) * 2013-11-21 2014-02-26 上海市基础工程集团有限公司 Secondary lining casting device and secondary lining casting method for tunnels
CN105926630A (en) * 2016-04-27 2016-09-07 中天建设集团有限公司 Annular support change and sequence construction method for quickening construction of deep and large underground structures
CN107882578A (en) * 2017-10-24 2018-04-06 中国电建集团华东勘测设计研究院有限公司 A kind of reinforced concrete lined tunnel single stope dual stage car lining cutting continuous placing technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4613258A (en) * 1984-05-11 1986-09-23 Hochtief Aktiengesellschaft Vorm. Gebr. Helfmann Apparatus for setting and removing tunnel casing rings
CN102434171A (en) * 2011-11-17 2012-05-02 广汉金达隧道机械有限公司 Tunnel bottom concrete side-slipping lining construction method and side-slipping needle beam bottom board trolley
CN102425435A (en) * 2011-12-30 2012-04-25 广汉金达隧道机械有限公司 Ultra-large whole-circle needle beam type hydraulic steel mould trolley and demoulding method thereof
CN103603677A (en) * 2013-11-21 2014-02-26 上海市基础工程集团有限公司 Secondary lining casting device and secondary lining casting method for tunnels
CN105926630A (en) * 2016-04-27 2016-09-07 中天建设集团有限公司 Annular support change and sequence construction method for quickening construction of deep and large underground structures
CN107882578A (en) * 2017-10-24 2018-04-06 中国电建集团华东勘测设计研究院有限公司 A kind of reinforced concrete lined tunnel single stope dual stage car lining cutting continuous placing technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨玉友: "全圆式针梁钢模液压台车在向家坝水电站右岸灌溉洞进口段衬砌施工中的应用", 《陕西水利》 *

Similar Documents

Publication Publication Date Title
CN106351670B (en) A kind of closed pre support tunnel structure
CN101397909B (en) Artificial digging repair novel construction method for collapse ultra-deep shaft
CN111997622A (en) Tunnel IV-grade and V-grade weak surrounding rock full-section and micro-step mechanized matching construction method
CN205503146U (en) Novel supporting construction of shallow tunnel suitable for city sensitizing range
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN108286442A (en) Excavation method suitable for a Support System in Soft Rock Tunnels quick closure cyclization of two steps
CN103821523A (en) Excavating method for extending existing single-hole two-driveway tunnel into four-driveway tunnel
CN109026026A (en) Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method
CN110469341A (en) A kind of assembly of Underground Subway Station combines integrated morphology and construction method with pouring
JP2023545610A (en) tunnel drilling shield
CN108979644A (en) A kind of rich water tunnel solution cavity collapses processing and tunnel excavation construction method
CN106555593A (en) A kind of big cross section soft rock tunnel is got out of a predicament or an embarrassing situation the construction method of excavation synchronous with inverted arch
CN107035383A (en) The supporting construction of extra-large cross-section loess tunnel and its excavation method
CN110985003B (en) Tunnel construction method for penetrating through earth-rock boundary stratum
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN201826302U (en) Boring device for large-diameter cast-in-situ thin-walled concrete composite pile
CN102677657B (en) Townhouse waters the construction treating methods of knot thin-walled concrete composite pile wall
CN110700860A (en) Construction method of soil-stone boundary tunnel crossing loess valley
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN109184753A (en) The processing method of limit is invaded for deformation after Tunnel
CN109139055A (en) Wholecircle jacked piles with small section needle beam trolley lining construction method
CN206144569U (en) Confined is advance in advance and is protected tunnel structure
CN109594995A (en) A kind of Support System in Soft Rock Tunnels micro-disturbance machinery branch driving engineering method
CN105862725A (en) Underground construction preliminary grouting waterproof and anti-seepage supporting technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104

RJ01 Rejection of invention patent application after publication