CN109137745A - A kind of construction method doubling as buckling and hanging system dorsal funciculus using end bay pressure Tasso - Google Patents
A kind of construction method doubling as buckling and hanging system dorsal funciculus using end bay pressure Tasso Download PDFInfo
- Publication number
- CN109137745A CN109137745A CN201811226844.2A CN201811226844A CN109137745A CN 109137745 A CN109137745 A CN 109137745A CN 201811226844 A CN201811226844 A CN 201811226844A CN 109137745 A CN109137745 A CN 109137745A
- Authority
- CN
- China
- Prior art keywords
- dorsal funciculus
- buckling
- tasso
- hanging system
- tension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Electric Cable Installation (AREA)
Abstract
The present invention provides a kind of construction method that buckling and hanging system dorsal funciculus is doubled as using end bay pressure Tasso herein;When solution conventional cable lifting pressure Tasso and buckling and hanging system are designed as mutually independent system, since its partial function repeats, material utilization amount is caused to increase, anchor case difficult arrangement and cumbersome problem.Its operating procedure includes: the installation of (1) CABLEWAY ERECTION SYSTEM;(2) the 1st ~ the N-1 sections of arch rib installations;(3) N sections of arch rib installations;(4) restore pressure Tasso to original state.The present invention can reduce by one of dorsal funciculus for relatively conventional " button one is hung " structural system, greatly reduce dorsal funciculus steel strand wires dosage, save engineering cost directly using pressure Tasso dorsal funciculus as the last one rib-lifting section buckling and hanging system dorsal funciculus;And one of knotted rope installation procedure is saved, the engineering construction duration is accelerated, reduces high-altitude application risk;Single king-post reduces a dorsal funciculus anchor case simultaneously, saves Sarasota space, reduces Sarasota load, increase structural reliability.
Description
Technical field
The present invention relates to Arch Bridge Construction fields, be specifically it is a kind of using end bay pressure Tasso as buckling and hanging system dorsal funciculus
Construction method.
Background technique
It when deck type or half-through arch bridge are constructed, generallys use and withholds integrated structure type, therefore it presses Tasso and button
Extension system is all set on same king-post.Shown according to structural finite element analysis and previous Arch Bridge Construction actual measurement data
As buckling and hanging system is constantly installed, Sarasota absolute deviation of tower top under identical hoist operating condition is constantly reducing, but due to pressing tower
Rope is different from buckling and hanging system effect, now usually accounts for as mutually independent system when arch bridge conceptual design.This side
Formula will increase steel strand wires dosage and when anchor case number, especially Large Span Structure of Arch bridge construction, due to buckling and hanging system anchor case number compared with
It is more, it is more difficult that anchor case arrangement is limited by king-post space.
Summary of the invention
Therefore, in order to solve above-mentioned deficiency, the present invention provide herein it is a kind of using end bay pressure Tasso as buckling and hanging system back
The construction method of rope;When solution conventional cable lifting pressure Tasso and buckling and hanging system are designed as mutually independent system, by
It is repeated in its partial function, causes material utilization amount to increase, anchor case difficult arrangement and cumbersome problem.
The invention is realized in this way a kind of construction method that buckling and hanging system dorsal funciculus is doubled as using end bay pressure Tasso is constructed,
It is characterized by: directly also serving as part buckling and hanging system dorsal funciculus using end bay pressure Tasso, buckling and hanging system dorsal funciculus quantity is reduced to play
Purpose;
Its operating procedure is as follows:
(1) CABLEWAY ERECTION SYSTEM is installed: being installed CABLEWAY ERECTION SYSTEM, is needed to install pressure Tasso according to Structure Calculation, and by calculating
Tension carries out tensioning operation to pressure Tasso, and end bay pressure Tasso tension is T1 at this time, and middle cross-pressure Tasso tension is T1 ';
(2) the 1st ~ the N-1 sections of arch rib installations:
The 1st ~ the N-1 sections of rib-lifting sections are successively lifted, and set gradually buckling and hanging system knotted rope and dorsal funciculus as required, according to design
Load tensioning buckling and hanging system knotted rope and dorsal funciculus, it is ensured that arch rib line style and design line style are coincide;
(3) N sections of arch rib installations: N sections of arch ribs of lifting to installation site install the road N buckling and hanging system knotted rope, according to design lotus
It carries simultaneous tension N road knotted rope and end bay presses Tasso dorsal funciculus, complete the installation of the last one rib-lifting section;Due to tensioning front across
Pressure Tasso dorsal funciculus has had tension T1, therefore presses Tasso dorsal funciculus category two times tensioning, its tension is T2 after tensioning;
(4) restore pressure Tasso to original state: arch rib needs to remove buckling and hanging system after being installed, the unloading of the road N knotted rope
When, opposite side cross-pressure Tasso should be synchronized and unloaded, until its tension restores from T2 to T1, then remove the road N knotted rope, then according to
It is secondary to remove remaining button, dorsal funciculus.
The present invention has the advantage that the construction method is directly using pressure Tasso dorsal funciculus as the last one rib-lifting section
Buckling and hanging system dorsal funciculus has following features;
Its 1: relatively conventional " button one is hung " structural system, the invention patent unilateral side rib-lifting section can reduce by one of dorsal funciculus, drop significantly
Low dorsal funciculus steel strand wires dosage, saves engineering cost;
Its 2: save one of knotted rope installation procedure, accelerate the engineering construction duration, reduce high-altitude application risk;
Its 3: single king-post reduces a dorsal funciculus anchor case, saves Sarasota space, reduces Sarasota load, increasing structure can
By degree.
Detailed description of the invention
Fig. 1 is the corresponding construction elevation of this patent;
Fig. 2 is the corresponding A-A sectional view of Fig. 1;
Fig. 3 is the corresponding B-B sectional view of Fig. 1.
Wherein: cable crane 1, anchorage 2, Sarasota 3, end bay pressure Tasso 4(double as dorsal funciculus), middle cross-pressure Tasso 5, knotted rope 6, back
Rope 7, arch rib 8.
Specific embodiment
Below in conjunction with attached drawing 1- Fig. 3, the present invention is described in detail, technical solution in the embodiment of the present invention into
Row clearly and completely describes, it is clear that described embodiments are only a part of the embodiments of the present invention, rather than whole realities
Apply example.Based on the embodiments of the present invention, those of ordinary skill in the art are obtained without making creative work
Every other embodiment, shall fall within the protection scope of the present invention.
The present invention provides a kind of construction method for pressing Tasso to double as buckling and hanging system dorsal funciculus using end bay by improving herein;
As shown in Figure 1, system structure: by cable crane 1, anchorage 2, Sarasota 3, end bay pressure Tasso 4, middle cross-pressure Tasso 5, knotted rope 6,
Dorsal funciculus 7 and arch rib 8 form, and core is that end bay pressure Tasso is directly utilized to also serve as part buckling and hanging system dorsal funciculus, are subtracted with playing
The purpose of few buckling and hanging system dorsal funciculus quantity.
Wherein, corresponding operating procedure is as follows:
(1) CABLEWAY ERECTION SYSTEM is installed: being installed CABLEWAY ERECTION SYSTEM, is needed to install pressure Tasso according to Structure Calculation, and by calculating
Tension carries out tensioning operation to pressure Tasso, and end bay pressure Tasso tension is T1 at this time, and middle cross-pressure Tasso tension is T1 ';
(2) the 1st ~ the N-1 sections of arch rib installations: the 1st ~ the N-1 sections of rib-lifting sections are successively lifted, and sets gradually button as required and hangs system
System knotted rope and dorsal funciculus, according to design load tensioning buckling and hanging system knotted rope and dorsal funciculus, it is ensured that arch rib line style and design line style are coincide;
(3) N sections of arch rib installations: N sections of arch ribs of lifting to installation site install the road N buckling and hanging system knotted rope, according to design lotus
It carries simultaneous tension N road knotted rope and end bay presses Tasso dorsal funciculus, complete the installation of the last one rib-lifting section.Due to tensioning front across
Pressure Tasso dorsal funciculus has had tension T1, therefore presses Tasso dorsal funciculus category two times tensioning, its tension is T2 after tensioning;
(4) restore pressure Tasso to original state: arch rib needs to remove buckling and hanging system after being installed, the unloading of the road N knotted rope
When, opposite side cross-pressure Tasso should be synchronized and unloaded, until its tension restores from T2 to T1, then remove the road N knotted rope, then according to
It is secondary to remove remaining button, dorsal funciculus.
When implementing by aforesaid way, corresponding advantage and have the beneficial effect that this construction method directly using pressure Tasso carry on the back
The last one rib-lifting section buckling and hanging system dorsal funciculus of Suo Zuowei, (1) relatively conventional " button one is hung " structural system, the invention patent are unilateral
Rib-lifting section can reduce by one of dorsal funciculus, greatly reduce dorsal funciculus steel strand wires dosage, save engineering cost;(2) it saves together
Knotted rope installation procedure accelerates the engineering construction duration, reduces high-altitude application risk;(3) single king-post reduces a dorsal funciculus
Anchor case saves Sarasota space, reduces Sarasota load, increases structural reliability.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention.
Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention
It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one
The widest scope of cause.
Claims (1)
1. a kind of construction method for doubling as buckling and hanging system dorsal funciculus using end bay pressure Tasso, it is characterised in that: directly utilize end bay pressure
Tasso also serves as part buckling and hanging system dorsal funciculus, to play the purpose for reducing buckling and hanging system dorsal funciculus quantity;
Its operating procedure is as follows:
(1) CABLEWAY ERECTION SYSTEM is installed: being installed CABLEWAY ERECTION SYSTEM, is needed to install pressure Tasso according to Structure Calculation, and by calculating
Tension carries out tensioning operation to pressure Tasso, and end bay pressure Tasso tension is T1 at this time, and middle cross-pressure Tasso tension is T1 ';
(2) the 1st ~ the N-1 sections of arch rib installations:
The 1st ~ the N-1 sections of rib-lifting sections are successively lifted, and set gradually buckling and hanging system knotted rope and dorsal funciculus as required, according to design
Load tensioning buckling and hanging system knotted rope and dorsal funciculus, it is ensured that arch rib line style and design line style are coincide;
(3) N sections of arch rib installations: N sections of arch ribs of lifting to installation site install the road N buckling and hanging system knotted rope, according to design lotus
It carries simultaneous tension N road knotted rope and end bay presses Tasso dorsal funciculus, complete the installation of the last one rib-lifting section;Due to tensioning front across
Pressure Tasso dorsal funciculus has had tension T1, therefore presses Tasso dorsal funciculus category two times tensioning, its tension is T2 after tensioning;
(4) restore pressure Tasso to original state: arch rib needs to remove buckling and hanging system after being installed, the unloading of the road N knotted rope
When, opposite side cross-pressure Tasso should be synchronized and unloaded, until its tension restores from T2 to T1, then remove the road N knotted rope, then according to
It is secondary to remove remaining button, dorsal funciculus.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811226844.2A CN109137745B (en) | 2018-10-22 | 2018-10-22 | Construction method for using side span tower pressing cable as back cable of buckling and hanging system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811226844.2A CN109137745B (en) | 2018-10-22 | 2018-10-22 | Construction method for using side span tower pressing cable as back cable of buckling and hanging system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109137745A true CN109137745A (en) | 2019-01-04 |
CN109137745B CN109137745B (en) | 2020-06-23 |
Family
ID=64808838
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811226844.2A Active CN109137745B (en) | 2018-10-22 | 2018-10-22 | Construction method for using side span tower pressing cable as back cable of buckling and hanging system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109137745B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110438908A (en) * | 2019-08-22 | 2019-11-12 | 中铁二十局集团第三工程有限公司 | A kind of deck type box arch bridge rebuilding construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5811205A (en) * | 1981-07-14 | 1983-01-22 | 横河工事株式会社 | Back stay anchor installation in cable erection method of arch bridge |
CN101476293A (en) * | 2009-01-16 | 2009-07-08 | 广东省长大公路工程有限公司 | Non-stand construction method for large bridge arch rib |
CN202012047U (en) * | 2011-03-03 | 2011-10-19 | 中铁十三局集团第一工程有限公司 | Steel strand inclined pulling and buckling system of tower |
CN103643637A (en) * | 2013-12-03 | 2014-03-19 | 中铁八局集团市政工程有限公司 | Long-span concrete filled steel tube arch bridge construction method achieved through integral lifting on site after vertical turning |
JP2017048611A (en) * | 2015-09-02 | 2017-03-09 | 三井住友建設株式会社 | Bridging method of arch bridge |
CN108374347A (en) * | 2018-04-12 | 2018-08-07 | 中铁上海工程局集团有限公司 | A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method |
-
2018
- 2018-10-22 CN CN201811226844.2A patent/CN109137745B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5811205A (en) * | 1981-07-14 | 1983-01-22 | 横河工事株式会社 | Back stay anchor installation in cable erection method of arch bridge |
CN101476293A (en) * | 2009-01-16 | 2009-07-08 | 广东省长大公路工程有限公司 | Non-stand construction method for large bridge arch rib |
CN202012047U (en) * | 2011-03-03 | 2011-10-19 | 中铁十三局集团第一工程有限公司 | Steel strand inclined pulling and buckling system of tower |
CN103643637A (en) * | 2013-12-03 | 2014-03-19 | 中铁八局集团市政工程有限公司 | Long-span concrete filled steel tube arch bridge construction method achieved through integral lifting on site after vertical turning |
JP2017048611A (en) * | 2015-09-02 | 2017-03-09 | 三井住友建設株式会社 | Bridging method of arch bridge |
CN108374347A (en) * | 2018-04-12 | 2018-08-07 | 中铁上海工程局集团有限公司 | A kind of high-speed railway large span cable-carried arch bridge steel lagging jack buckling and hanging system construction method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110438908A (en) * | 2019-08-22 | 2019-11-12 | 中铁二十局集团第三工程有限公司 | A kind of deck type box arch bridge rebuilding construction method |
CN110438908B (en) * | 2019-08-22 | 2022-02-08 | 中铁二十局集团第三工程有限公司 | Deck-type box-type arch bridge reconstruction construction method |
Also Published As
Publication number | Publication date |
---|---|
CN109137745B (en) | 2020-06-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102444086B (en) | Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge | |
CN202012047U (en) | Steel strand inclined pulling and buckling system of tower | |
CN107380012B (en) | Existing electrified railway contact net holds, leads the synchronous replacement construction technology of two-wire | |
CN207312925U (en) | A kind of adjustable multifunctional suspender | |
CN109137745A (en) | A kind of construction method doubling as buckling and hanging system dorsal funciculus using end bay pressure Tasso | |
CN105178167B (en) | A kind of double-deck steel cable bridge and its erection method | |
CN104631329A (en) | Method for adjusting overall line shape of continuous catwalk of suspension bridge | |
CN208981163U (en) | One kind monitoring system for parallel steel stranded wire stayed Cable Construction Cable Force uniformity | |
CN215574327U (en) | Precast beam prestress wire detection device | |
ATE370911T1 (en) | APPARATUS AND METHOD FOR USE IN HANDLING A LOAD | |
CN106758855B (en) | Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method | |
CN107161879A (en) | Attached wall provision for disengagement and its method for dismounting on rear side of derrick crane | |
CN212000575U (en) | Anchor device is detained in installation of arch ring strength nature skeleton | |
CN209732122U (en) | Warmhouse booth assembled film pressing device | |
CN206693063U (en) | A kind of galvanized wire for suspension bridge of head-rope series-mode frame hangs load bearing system | |
CN204510001U (en) | Suspension cable with steel sheath divides fiber tube saddle | |
CN211150958U (en) | Buckle | |
CN102515038A (en) | Prestress steel wire rope row and manufacturing method thereof | |
CN207775737U (en) | Bridge post-cast strip ruggedized construction | |
CN206069145U (en) | A kind of elevator flex holder | |
JPH0220709A (en) | Oblique hanging method for building arch bridge | |
CN212895913U (en) | Temporary fastening device for main cable strand | |
CN106915686B (en) | A kind of device for auxiliary hanging lifting scaffold steel pipe | |
CN114575245B (en) | Construction method of spatial main cable suspension bridge handrail rope | |
CN110768129A (en) | Block terminal cable through wires hole shutoff mud anticreep cover |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |