CN109098100A - The advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring - Google Patents

The advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring Download PDF

Info

Publication number
CN109098100A
CN109098100A CN201811117901.3A CN201811117901A CN109098100A CN 109098100 A CN109098100 A CN 109098100A CN 201811117901 A CN201811117901 A CN 201811117901A CN 109098100 A CN109098100 A CN 109098100A
Authority
CN
China
Prior art keywords
web
steel
steel web
construction
segment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811117901.3A
Other languages
Chinese (zh)
Other versions
CN109098100B (en
Inventor
谢广恕
张汉
张汉一
黄飞杰
陈军
姜东升
张晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Municipal Engineering Branch of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Municipal Engineering Branch of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Municipal Engineering Branch of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201811117901.3A priority Critical patent/CN109098100B/en
Publication of CN109098100A publication Critical patent/CN109098100A/en
Application granted granted Critical
Publication of CN109098100B publication Critical patent/CN109098100B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the advanced installation engineering methods of web in Wavelike steel webplate continuous bridge cantilever pouring, it includes boom segments construction and closure section construction, hanging basket advancing synchronous push method is used in boom segments work progress, the advanced installation method of steel web is used in the boom segments work progress, and next segment steel web is installed using the strong period such as this section section concrete.Advantages of the present invention: using the advanced mounting technique of steel web, and the installation of steel web is advanceed to a upper segment and is carried out, and with the strong shared flow beat such as the concrete of a upper segment, shortens the segmental construction period;By the typical round bolt hole innovative design of closure section Wavelike steel webplate at nose circle shape long hole, side bolt hole is aligned when not only solving the installation of closure section Wavelike steel webplate, other side bolt hole misalignment problem, and solve the problems, such as because of temperature, concrete shrinkage, creeping etc. influences bring constructional difficulties, reduce Wavelike steel webplate bending deformation, construction benefit is improved, quality control on construction is reinforced.

Description

The advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring
Technical field
The present invention relates to the advanced installation engineering methods of web in Wavelike steel webplate continuous bridge cantilever pouring, belong to building Field of engineering technology.
Background technique
A kind of special construction of the variable cross-section Pre-Stressed Concrete Composite Box-Girder Bridge with Corrugated Steel Webs as variable cross-section continuous beam, but construction party Method is as concrete variable cross-section Continuous Box Girder Bridge, using cantilever construction.According to incompletely statistics, so far, it is domestic build again and More than 60 built Pre-Stressed Concrete Composite Box-Girder Bridge with Corrugated Steel Webs, the bridge of 70m or more across footpath are all made of Hanging Basket cantilever pouring.Hanging Basket is outstanding Arm casting method is widely used in variable cross-section concrete box-beam bridge as a kind of conventional construction method.But for waveform steel abdomen Board group mould assembling beam bridge, since structural system has differences, construction technology and conventional cantilever construction are different, so that Wavelike steel webplate The cantilever construction of combination box beam bridge becomes complicated, in Hanging Basket type selecting, installation, needs to consider the easy for installation of steel web;Together When processed in plant produced due to corrugated web, site operation needs to consider reasonable transport, Hoisting Program.However it is applied in segment Work is seen on the occupied time, due to the installation of steel web, individually occupies a flow beat, is become compared to concrete web and is cut Face Continuous Box Girder Bridge, a segmental construction period will extend 4~5 days.Currently construction or completed Wavelike steel webplate One segment of the construction of PC combination box beam bridge, Normal practice needs 13~14 days.But continuous beam identical for across footpath, although wave Shape steel web box girder segmental length can do longer, reduce cantilever number of segment, but the construction time of corresponding segment increase 40%~ 50%, on total construction period, the advantage of Pre-Stressed Concrete Composite Box-Girder Bridge with Corrugated Steel Webs does not embody.
Although the new structure of Pre-Stressed Concrete Composite Box-Girder Bridge with Corrugated Steel Webs is widely used to China, external prestressing is applied Work, Wavelike steel webplate installation etc. need, so that construction technology becomes complicated, compared with concrete web variable cross-section continuous beam, The advantage of Pre-Stressed Concrete Composite Box-Girder Bridge with Corrugated Steel Webs is not obvious, especially on construction period, it may be said that advantage is very small or even does not have There is any advantage.International application and development are made a general survey of, present status in China is compared, carries out Wavelike steel webplate variable cross-section PC box girder bridge Key Techniques in Construction research, adds fuel to the flames to the application of this kind of bridge type.
Using single steel web, positioning method, single segment amount to 8 blocks of steel webs to the location and installation of traditional steel web one by one, Full-bridge boom segments are more, and the method work efficiency is low, and the duration is at high cost.
The installation of closure section Wavelike steel webplate is the important working procedure of Wavelike steel webplate Continuous Box Girder Bridge, traditional Wavelike steel webplate Bolt hole is circular hole, when reality is joined the two sections of a bridge, etc, is easy to appear hole location to not upper situation, accurately smoothly can install closure section steel web will Directly affect closure section construction.
Summary of the invention
The technical problem to be solved in the present invention is that the web provided in Wavelike steel webplate continuous bridge cantilever pouring is advanced The installation of steel web is advanceed to a upper segment and carried out by installation engineering method, strong shared with the concrete of a upper segment etc. Flow beat shortens the segmental construction period, reduces time cost.
The present invention is realized by following proposal: the advanced installation of web in Wavelike steel webplate continuous bridge cantilever pouring Engineering method comprising boom segments are constructed and closure section construction, using the synchronous top of hanging basket advancing in the boom segments work progress Method is pushed away, uses the advanced installation method of steel web in the boom segments work progress, utilizes the strong period such as this section section concrete Next segment steel web is installed.
The both ends of closure section steel web are divided into fixing end and free end in the closure section construction, and fixing end opens circular hole, from It is first drilled by holding, then again along bridge, to circular hole is wealthy at long hole, long hole length is 80mm~100mm.
Boom segments construction the following steps are included:
Step 1: boom segments steel web is installed in advance: Hanging Basket is transported to behind scene on 0# block assembled, pre- using tower crane progress Pressure, after upper segment concrete reaches C20 grade, carries out this segment web and installs in advance, using the advanced mounting technique of steel web, The installation of steel web is advanceed to a upper segment to carry out, steel web is lifted by crane, is just connected;
Step 2: tensioning mud jacking in segment after concrete reaches design tensioning intensity in segment, carries out prestressed stretch-draw, first longitudinal Again laterally, tensioning is completed to carry out hole path pressure grouting in 48 hours;
Step 3: hanging basket advancing, adjustment, after the completion of the concrete tensioning mud jacking of segment, the hydraulic synchronization pushing tow side that is controlled using PLC Method carries out hanging basket advancing;
Step 4: boom segments steel web is accurately positioned installation, and steel web is accurately positioned respectively in terms of plane and elevation two It is adjusted;
Step 5: steel web welding.
It is completed in segment concreting, the age of concrete meets 3 days or more, and after reaching the intensity of C20, in prestressing force Before steel Shu Zhangla, start to lift next segment steel web;The installation of next segment steel web is advanceed to a upper segment to apply It is carried out between duration, with the strong shared flow beat such as the concrete of a upper segment.
Numbered in lifting process and just connection according to steel web in steel web, feeds corresponding positions from cantilever section front end It sets, the steel web tail portion of next segment is just connect with the cantilever end of this segment steel web, after steel web feeds corresponding position, is pressed According to reserved hole location be aligned, vertically pop up position line in the position distance steel web end position 120mm, to steel web lengthwise position into Row adjustment, then by upper and lower bolt fastening, then remaining bolt is successively tightened from the bottom up, until closely being pasted between two blocks of steel webs It closes.
The steel web accurate positioning is adjusted in terms of plane and elevation two respectively, and specific adjustment mode is first high Plane after journey.
Elevation method of adjustment: steel web front end first, upper perforated panel crosses screw-thread steel as steel web front end suspension centre, Chain block one end is fixed on main truss cradle brace, and one end is fixed with screw-thread steel, before adjusting steel web by chain block Absolute altitude is held, retains top bolt and is in tightening state, the connection bolt of remaining fastening is unclamped, so that steel plate washer and steel web It is bonded but does not stress, instruct given beam face crest level to extrapolate the design altitude of every piece of steel web front end according to monitoring, pass through The chain block being fixed on hanging basket main truss is adjusted the front end elevation of monolithic steel web, before level observes side web Absolute altitude is held, until reaching design altitude, then fastens all connection bolts, web elevation adjustment in side is completed;Then in two pieces of side abdomens It is fixed after tightening with construction auxiliary line connection between plate top, intermediate steel web front end is measured with steel tape and construction assists The height difference of line, adjusts chain block, and up-regulation or decentralization steel web are completed so that steel web front end is overlapped with construction auxiliary line The elevation of intermediate steel web is accurately positioned;Plane method of adjustment: being popped up side web axis using total station in bottom plate, First piece of side web adjustment is first carried out, adjustment is fixed in steel web front end middle position with underframe longitudinal member with chain block, passes through line Hammer method determines the deviation of steel web practical axis and setting-out axis, and is adjusted with chain block, hangs between two blocks of steel webs Arm end is installed in parallel using the identical channel steel of design spacing, carries out the adjustment of one block of side web, remaining corrugated web is in plane position It sets while being adjusted in place, then carry out interconnection in channel steel and steel web weld, the verticality of monolithic steel web is carried out Accurate adjustment.
The closure section construction sequence is as follows: cast-in-place section concrete reaches G20 → lifting of steel web, first connection → tensioning pressure Slurry → closure section hanger Forward, adjustment → steel web accurate positioning → welding of steel web, concreting.
Progress closure section steel bar template while steel web is accurately positioned is carried out after the closure section hanger Forward, adjustment to apply Then work carries out the welding of closure section stiff skeleton, finally carry out the welding of steel web, concreting.
After cast-in-place section concrete reaches G20, tensioning is carried out when concrete reaches design tensioning intensity after concrete etc. is strong Mud jacking.
The invention has the benefit that
1, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention is advanced using steel web The installation of steel web is advanceed to a upper segment and carried out by mounting technique, with the strong shared flowing water such as the concrete of a upper segment Beat shortens the segmental construction period, reduces time cost, Wavelike steel webplate is lifted process, with concrete strength generation process It carries out simultaneously, each segment can at least save the lifting time of segment steel web, greatly shorten the segmental construction period;
2, the construction speed of the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention is fast, pacifies Total quality is controllable;
3, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention is to waveform steel from now on Web bridge cantilever segmental construction has biggish reference value;
4, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention is by closure section waveform steel Web typical round bolt hole innovative design not only solves side bolt when the installation of closure section Wavelike steel webplate at nose circle shape long hole Hole alignment, other side bolt hole misalignment problem, and solve because of temperature, concrete shrinkage, creeping etc. influences bring construction Difficult problem reduces Wavelike steel webplate bending deformation, improves construction benefit, reinforces quality control on construction;
5, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention and previous large span connect Continuous box Cantilever Construction compares, and due to using the advanced mounting technique of steel web, the construction period of standard segment is controlled 9 In it, the efficient rapid construction of segment cantilever construction is realized;
6, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention duration shorten, only according to The whole installation process of steel web is completed by tower crane, operation rate of machinery is low, and human input is also accordingly reduced,
7, the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring of the present invention utilizes sash weight, bracing wire etc. Positioning method, simplifies the localization method of steel web, while also ensuring segment positioning accuracy.
Detailed description of the invention
Fig. 1 is cantilever pouring construction flow chart in the present invention.
Fig. 2 is closure section construction process flow chart in the present invention.
Fig. 3 is closure section steel web slotted hole structural schematic diagram in the present invention.
Specific embodiment
Below with reference to Fig. 1-3, the present invention is further described, but the scope of the present invention does not limit to the content.
For clarity, not describing whole features of practical embodiments, in the following description, it is not described in detail well known function And structure, because they can make the present invention chaotic due to unnecessary details, it will be understood that opening in any practical embodiments In hair, it is necessary to make a large amount of implementation details to realize the specific objective of developer, such as according to related system or related business Limitation, changes into another embodiment by one embodiment, additionally, it should think that this development may be complicated and expend Time, but to those skilled in the art it is only routine work.
The advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring comprising boom segments construction And closure section construction, hanging basket advancing synchronous push method is used in boom segments work progress, is adopted in boom segments work progress With the advanced installation method of steel web, next segment steel web is installed using the strong period such as this section section concrete.
The both ends of closure section steel web are divided into fixing end and free end in closure section construction, and fixing end opens circular hole, free end It first drills, then again along bridge, to circular hole is wealthy at long hole, long hole length is 80mm~100mm.
Boom segments construction the following steps are included:
Step 1: boom segments steel web is installed in advance: Hanging Basket is transported to behind scene on 0# block assembled, pre- using tower crane progress Pressure, after upper segment concrete reaches C20 grade, carries out this segment web and installs in advance, using the advanced mounting technique of steel web, The installation of steel web is advanceed to a upper segment to carry out, steel web is lifted by crane, is just connected;
Step 2: tensioning mud jacking in segment after concrete reaches design tensioning intensity in segment, carries out prestressed stretch-draw, first longitudinal Again laterally, tensioning is completed to carry out hole path pressure grouting in 48 hours;
Step 3: hanging basket advancing, adjustment, after the completion of the concrete tensioning mud jacking of segment, the hydraulic synchronization pushing tow side that is controlled using PLC Method carries out hanging basket advancing;
Step 4: boom segments steel web is accurately positioned installation, and steel web is accurately positioned respectively in terms of plane and elevation two It is adjusted;
Step 5: steel web welding.
It is completed in segment concreting, the age of concrete meets 3 days or more, and after reaching the intensity of C20, in prestressing force Before steel Shu Zhangla, start to lift next segment steel web;The installation of next segment steel web is advanceed to a upper segment to apply It is carried out between duration, with the strong shared flow beat such as the concrete of a upper segment.
Numbered in lifting process and just connection according to steel web in steel web, feeds corresponding positions from cantilever section front end It sets, the steel web tail portion of next segment is just connect with the cantilever end of this segment steel web, just connection uses C grades of M20 bolts, single The self weight of block steel web is mainly born by the power of the bolt transmitting after tightening, for the adjustment convenient for segment steel web middle line, absolute altitude, if Meter bolt hole opening diameter is 45mm, and diameter 80mmQ345D antirust steel plate washer is used on the outside of bolt hole, using M20C grade bolt into Row is fixed, and steel plate washer center and bolt hole center are concentric, after steel web feeds corresponding position, is aligned according to reserved hole location, two pieces The lap of splice is 120mm between steel web, can vertically pop up position line in the position distance steel web end position 120mm, is utilized Gap between stud and bolt hole is adjusted steel web lengthwise position, and longitudinal bias is no more than 10mm, then by upper and lower spiral shell Bolt fastening, then remaining bolt is successively tightened from the bottom up, until being fitted closely between two blocks of steel webs.
The accurate positioning of steel web is adjusted in terms of plane and elevation two respectively, after specific adjustment mode is first elevation Plane.
Elevation adjustment: steel web front end first, upper perforated panel crosses 32 screw-thread steel of Φ as steel web front end suspension centre, The long 50cm of screw-thread steel, 5t chain block one end are fixed on main truss cradle brace, and one end is fixed with 32 screw-thread steel of Φ, by pulling Cucurbit adjusts the front end absolute altitude of steel web, retains top bolt and is in tightening state, the connection bolt of remaining fastening is unclamped, So that steel plate washer is bonded but does not stress with steel web, before instructing given beam face crest level to extrapolate every block of steel web according to monitoring The design altitude at end is adjusted the front end elevation of monolithic steel web by the chain block being fixed on hanging basket main truss, Technical staff observes side web front end absolute altitude using DSZ2 level, until reaching design altitude, then fastens all connection bolts, Web elevation adjustment in side is completed;Then it between the web top of two pieces of sides (A, D two o'clock), is connected with construction auxiliary line, after tightening It is fixed, the height difference (δ 1 and δ 2) of intermediate steel web front end and auxiliary line of constructing is measured with steel tape, adjusts chain block, up-regulation Or decentralization steel web, so that steel web front end is overlapped with construction auxiliary line, the elevation for completing intermediate steel web is accurately positioned;It is flat Face adjustment: being popped up side web axis using total station in bottom plate, first carries out first piece of side web adjustment, adjustment 3t hand Cucurbit is drawn to fix in steel web front end middle position with underframe longitudinal member, technical staff determines the practical axis of steel web by plumb bob method And the deviation of setting-out axis, and be adjusted with chain block, cantilever end is identical using design spacing between two blocks of steel webs [14 channel steels are installed in parallel, need to only carry out the adjustment of one block of side web, remaining corrugated web is adjusted in place simultaneously in plan-position, Then interconnection is carried out using the flower basket bolt of M20 in channel steel and steel web weld, to the verticality of monolithic steel web into Row accurate adjustment.
Closure section construction sequence is as follows: cast-in-place section concrete reach G20 → steel web lifting, first connection → tensioning mud jacking → The Forward of closure section hanger, adjustment → steel web accurate positioning → welding of steel web, concreting.
It carries out carrying out the construction of closure section steel bar template while steel web is accurately positioned after the Forward of closure section hanger, adjustment, Then the welding of closure section stiff skeleton is carried out, the welding of steel web, concreting are finally carried out.
After cast-in-place section concrete reaches G20, tensioning is carried out when concrete reaches design tensioning intensity after concrete etc. is strong Mud jacking.
Application example: closing overgrown with weeds across the Yu Xi river bridge of high speed interconnection engineering, span setting be 55m+93m+83m+55m= 286m, girder use three Room box girder with corrugated steel webs of double width list case, and concrete uses C50.
The river Yu Xi bridge continuous beam suspension segment is more, and the installation of Wavelike steel webplate cantilever is inclined by design longitudinal slope, processing The influence of deformation during difference and concrete suspension casting etc., linear and precision controlling difficulty are big.The engineering is connection Wu Hujiang The main thoroughfare of Bei Chanyejizhongqu and Jiangnan main city zone, for local important people's livelihood engineering, owner is tight to construction period.Waveform The installation effectiveness of steel web is an important factor for restricting continuous beam segmental construction, how efficiently to complete the construction of cantilever segment, be The technological difficulties of this engineering.
Using the advanced installation engineering method of steel web, successfully solves the key technology difficulty of construction.The engineering is in 2017 Year September smoothly completes full-bridge closure, and the indexs such as quality, safety, economy have reached target, obtain owner, management and The consistent favorable comment of expert.
The river Yu Xi bridge will become Anhui Province's seat of honour, four innings of the first Wavelike steel webplate continuous box girders after building up, fill up me The construction technology blank of three Room large span antinode plate continuous beam of single case is saved, is laid for the construction of later wave shape steel web continuous bridge Solid foundation.
1 cantilever section steel web of table installs economic efficiency contrast table
2 closure section steel web of table installs economic efficiency contrast table
Duration of the invention shortens, and only relies on the whole installation process that tower crane completes steel web, operation rate of machinery is low, human input It is corresponding to reduce, amount to 5,400,000 yuan of save the cost.
Although having done more detailed elaboration to technical solution of the present invention and having enumerated, it should be understood that for ability For field technique personnel, modifications to the embodiments described above may be made or uses equivalent alternative solution, this is to those skilled in the art It is it is clear that these modifications or improvements without departing from theon the basis of the spirit of the present invention, belong to the present invention for member Claimed range.

Claims (10)

1. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring, it is characterised in that: it includes outstanding Arm segmental construction and closure section construction use hanging basket advancing synchronous push method, the cantilever section in boom segments work progress The advanced installation method of steel web is used in section work progress, next segment steel abdomen is installed using the strong period such as this section section concrete Plate.
2. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: the both ends of closure section steel web are divided into fixing end and free end in the closure section construction, fixing end opens circular hole, Free end first drills, then again along bridge, to circular hole is wealthy at long hole, long hole length is 80mm~100mm.
3. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: boom segments construction the following steps are included:
Step 1: boom segments steel web is installed in advance: Hanging Basket is transported to behind scene on 0# block assembled, pre- using tower crane progress Pressure, after upper segment concrete reaches C20 grade, carries out this segment web and installs in advance, using the advanced mounting technique of steel web, The installation of steel web is advanceed to a upper segment to carry out, steel web is lifted by crane, is just connected;
Step 2: tensioning mud jacking in segment after concrete reaches design tensioning intensity in segment, carries out prestressed stretch-draw, first longitudinal Again laterally, tensioning is completed to carry out hole path pressure grouting in 48 hours;
Step 3: hanging basket advancing, adjustment, after the completion of the concrete tensioning mud jacking of segment, the hydraulic synchronization pushing tow side that is controlled using PLC Method carries out hanging basket advancing;
Step 4: boom segments steel web is accurately positioned installation, and steel web is accurately positioned respectively in terms of plane and elevation two It is adjusted;
Step 5: steel web welding.
4. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: completing in segment concreting, the age of concrete meets 3 days or more, and after reaching the intensity of C20, pre- Before stress steel Shu Zhangla, start to lift next segment steel web;The installation of next segment steel web is advanceed into a upper section Section construction period carries out, with the strong shared flow beat such as the concrete of a upper segment.
5. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: numbered in lifting process and just connection according to steel web in steel web, from cantilever section front end, feeding is corresponding The steel web tail portion of next segment is just connect by position with the cantilever end of this segment steel web, after steel web feeds corresponding position, It is aligned according to reserved hole location, position line is vertically popped up in the position distance steel web end position 120mm, to steel web lengthwise position It is adjusted, then by upper and lower bolt fastening, then successively tightens remaining bolt from the bottom up, until closely being pasted between two blocks of steel webs It closes.
6. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: the steel web accurate positioning is adjusted in terms of plane and elevation two respectively, specific adjustment mode is Plane after first elevation.
7. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 6, It is characterized by: elevation method of adjustment: steel web front end first, upper perforated panel crosses screw-thread steel as steel web front end and hangs Point, chain block one end are fixed on main truss cradle brace, and one end is fixed with screw-thread steel, adjust steel web by chain block Front end absolute altitude retains top bolt and is in tightening state, the connection bolt of remaining fastening is unclamped, so that steel plate washer and steel abdomen Plate is bonded but does not stress, and instructs given beam face crest level to extrapolate the design altitude of every piece of steel web front end according to monitoring, leads to It crosses the chain block being fixed on hanging basket main truss to be adjusted the front end elevation of monolithic steel web, level observes side web Front end absolute altitude until reaching design altitude, then fastens all connection bolts, and web elevation adjustment in side is completed;Then on two pieces of sides It is fixed after tightening with construction auxiliary line connection between web top, intermediate steel web front end is measured with steel tape and construction is auxiliary The height difference of index contour adjusts chain block, up-regulation or decentralization steel web, so that steel web front end is overlapped with construction auxiliary line, it is complete It is accurately positioned at the elevation of intermediate steel web;Plane method of adjustment: utilize total station by side web axis bullet in bottom plate Out, first piece of side web adjustment is first carried out, steel web front end middle position is fixed with underframe longitudinal member with chain block, passed through by adjustment Plumb bob method determines the deviation of steel web practical axis and setting-out axis, and is adjusted with chain block, between two blocks of steel webs Cantilever end is installed in parallel using the identical channel steel of design spacing, carries out the adjustment of one block of side web, remaining corrugated web is in plane Position is adjusted in place simultaneously, then carries out interconnection in channel steel and steel web weld, to the verticality of monolithic steel web into Row accurate adjustment.
8. the advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring according to claim 1, It is characterized by: the closure section construction sequence is as follows: cast-in-place section concrete reaches G20 → lifting of steel web, just connection → and opens Tension and compression slurry → closure section hanger Forward, adjustment → steel web accurate positioning → welding of steel web, concreting.
9. the advanced installation engineering method of web in the Wavelike steel webplate continuous bridge cantilever pouring stated according to claim 8, It is characterized in that: carrying out carrying out closure section steel bar template while steel web is accurately positioned after the closure section hanger Forward, adjustment Then construction carries out the welding of closure section stiff skeleton, finally carry out the welding of steel web, concreting.
10. the advanced installation engineering method of web in the Wavelike steel webplate continuous bridge cantilever pouring stated according to claim 8, It is characterized in that: after cast-in-place section concrete reaches G20, carrying out tensioning when concrete reaches design tensioning intensity after concrete etc. is strong Mud jacking.
CN201811117901.3A 2018-09-26 2018-09-26 Web advanced installation construction method in cantilever casting of corrugated steel web continuous beam bridge Active CN109098100B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811117901.3A CN109098100B (en) 2018-09-26 2018-09-26 Web advanced installation construction method in cantilever casting of corrugated steel web continuous beam bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811117901.3A CN109098100B (en) 2018-09-26 2018-09-26 Web advanced installation construction method in cantilever casting of corrugated steel web continuous beam bridge

Publications (2)

Publication Number Publication Date
CN109098100A true CN109098100A (en) 2018-12-28
CN109098100B CN109098100B (en) 2021-03-05

Family

ID=64867543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811117901.3A Active CN109098100B (en) 2018-09-26 2018-09-26 Web advanced installation construction method in cantilever casting of corrugated steel web continuous beam bridge

Country Status (1)

Country Link
CN (1) CN109098100B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797659A (en) * 2019-03-21 2019-05-24 东南大学 A kind of mobile asynchronous construction method of bracket of Wavelike steel webplate continuous bridge
CN111455874A (en) * 2020-04-26 2020-07-28 中国建筑第七工程局有限公司 Construction method for overlong side span straight line segment of high pier of corrugated steel web PC bridge
CN114525740A (en) * 2022-03-07 2022-05-24 中交三航局第三工程有限公司 Safety early warning method for steel box girder pushing process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080000716A (en) * 2006-06-28 2008-01-03 신대철 Structure which combined corrugated steel plate web and concrete with stud
CN203668810U (en) * 2013-12-30 2014-06-25 郑州大学 PC combined box girder of corrugated steel webs
CN204000564U (en) * 2014-07-31 2014-12-10 中国路桥工程有限责任公司 Greatly across thin-walled prestressed concrete box girder
CN106758856A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN106758857A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of precast block formula secondary prestress Wavelike steel webplate combination beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080000716A (en) * 2006-06-28 2008-01-03 신대철 Structure which combined corrugated steel plate web and concrete with stud
CN203668810U (en) * 2013-12-30 2014-06-25 郑州大学 PC combined box girder of corrugated steel webs
CN204000564U (en) * 2014-07-31 2014-12-10 中国路桥工程有限责任公司 Greatly across thin-walled prestressed concrete box girder
CN106758856A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN106758857A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of precast block formula secondary prestress Wavelike steel webplate combination beam

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
百度: "波形钢腹板高效安装技术中铁四局市政公司", 《科技前沿交流》 *
邓超: "《宜万铁路工程总结》", 31 December 2013, 西南交通大学出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797659A (en) * 2019-03-21 2019-05-24 东南大学 A kind of mobile asynchronous construction method of bracket of Wavelike steel webplate continuous bridge
CN111455874A (en) * 2020-04-26 2020-07-28 中国建筑第七工程局有限公司 Construction method for overlong side span straight line segment of high pier of corrugated steel web PC bridge
CN111455874B (en) * 2020-04-26 2022-05-24 中国建筑第七工程局有限公司 Construction method for high-pier overlong side span straight-line segment of corrugated steel web PC bridge
CN114525740A (en) * 2022-03-07 2022-05-24 中交三航局第三工程有限公司 Safety early warning method for steel box girder pushing process

Also Published As

Publication number Publication date
CN109098100B (en) 2021-03-05

Similar Documents

Publication Publication Date Title
CN108179700B (en) Prefabricating and mounting method for ultrahigh-performance concrete through-type plate arch bridge segment
CN108914785B (en) Hanging basket cantilever pouring construction method of multi-chamber corrugated steel web continuous beam bridge
CN103614970B (en) Steel truss girder assembling construction longitudinal pull and lateral pushing sliding system
CN103614969B (en) Steel truss girder assembling, erecting and construction process
CN109098100A (en) The advanced installation engineering method of web in Wavelike steel webplate continuous bridge cantilever pouring
WO2021238024A1 (en) Asymmetric installation construction method for straddle-type light rail special steel box girder extradosed bridge
CN108060636B (en) The construction method of overall assembled composite beam bridge
CN105970836A (en) Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
CN109853394A (en) Arch bridge cable hoisting tower button integrated construction engineering method
CN108004925B (en) Prestress reinforced concrete circular arch tower construction method
CN108252220A (en) A kind of construction method of super-large span stiff skeleton
CN108716189A (en) Large span T-steel structure beam sections for joining island bridge install closure method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN110093863A (en) A kind of double face integration Bridge Erector being not provided with front leg strut
CN110468734A (en) Steel lagging jack pushing tow system and steel lagging jack push construction method
CN212426753U (en) Tooth block pull rod combined cable tower anchoring structure of cable-stayed bridge
CN207047613U (en) A kind of railway roadbed changeover portion support meanss and railway roadbed changeover portion support system
CN107447598A (en) A kind of building method of railway roadbed changeover portion support meanss and railway roadbed changeover portion support system
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
CN211737157U (en) Tunnel primary support structure of steel arch frame
CN113944114A (en) Dismantling construction method for large-span prestressed concrete cable-stayed bridge
CN211472116U (en) Railway assembled steel diagonal brace combination PC roof beam
CN209722908U (en) Steel structure body
CN207419388U (en) A kind of stiff skeleton structure of arched aqueduct box arch ring closure section
CN111254827A (en) Stay cable and bridge tower anchoring structure and manufacturing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant