CN109083620A CN201810748274.7A CN201810748274A CN109083620A CN 109083620 A CN109083620 A CN 109083620A CN 201810748274 A CN201810748274 A CN 201810748274A CN 109083620 A CN109083620 A CN 109083620A
Authority
CN
China
Prior art keywords
acid
thickening
fluid
viscous
displacement fluid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810748274.7A
Other languages
Chinese (zh)
Other versions
CN109083620B (en
Inventor
姚花平
王焰魁
尹良田
王博
丁金刚
张宏岗
张兴科
魏江伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Ruitong Energy Engineering Technology Co.,Ltd.
Original Assignee
Puyang Huaruitong Energy Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Puyang Huaruitong Energy Engineering Technology Co Ltd filed Critical Puyang Huaruitong Energy Engineering Technology Co Ltd
Priority to CN201810748274.7A priority Critical patent/CN109083620B/en
Publication of CN109083620A publication Critical patent/CN109083620A/en
Application granted granted Critical
Publication of CN109083620B publication Critical patent/CN109083620B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B37/00Methods or apparatus for cleaning boreholes or wells
    • E21B37/06Methods or apparatus for cleaning boreholes or wells using chemical means for preventing, limiting or eliminating the deposition of paraffins or like substances
    • CCHEMISTRY; METALLURGY
    • C09DYES; PAINTS; POLISHES; NATURAL RESINS; ADHESIVES; COMPOSITIONS NOT OTHERWISE PROVIDED FOR; APPLICATIONS OF MATERIALS NOT OTHERWISE PROVIDED FOR
    • C09KMATERIALS FOR MISCELLANEOUS APPLICATIONS, NOT PROVIDED FOR ELSEWHERE
    • C09K8/00Compositions for drilling of boreholes or wells; Compositions for treating boreholes or wells, e.g. for completion or for remedial operations
    • C09K8/52Compositions for preventing, limiting or eliminating depositions, e.g. for cleaning
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor

Abstract

The invention belongs to oil well acidation technical fields, and in particular to a kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water.Include the following steps: to be recycled pit shaft well-flushing with flushing fluid to clean;Huge discharge injects viscous acid pretreatment fluid;Sleeve gate is fastened, is then set viscous acid pretreatment fluid using thickening displacement fluid;Closing well reacts 2 hours;Sleeve gate is opened, is filled pit shaft with thickening displacement fluid;Retaining sleeve gate opens wide, and squeezes into viscous acid main process task liquid then for thickening displacement fluid is set, is continuously injected into viscous acid main process task liquid;Injection thickening displacement fluid;Closing well reacts 3 hours;Aspirate the row of returning.Acidization tool provided by the invention improves the success rate of well stimulation, improves the oil increasing effect of restricting water supply of measure, improves stimulation amplitude and extends the validity period of measure.

Description

A kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water
Technical field
The invention belongs to oil well acidation technical fields, and in particular to a kind of for the oil well advanced by leaps and bounds along fractuer direction injection water Acidization tool.
Background technique
Acidification is a kind of effective stimulation of well, it can effectively release formation blockage, improves oil well output.? It brings in early period, since there are the heterogeneity row on stratum, reservoir properties are poor, and there are the oil testing and fractures of early period, therefore Containing more crack, cause water injection profile and production profile extremely uneven.
Due to the presence in crack, cause nearly well band reservoir heterogeneity very strong, that is, injection treatment fluid is easy to edge Crack enters, and treatment fluid hardly enters the main oil storage of the fracture surface two sides of blocking, seepage channel, so the journey of acidification de-plugging Satisfactory result is not achieved in degree, oil increasing effect, validity period;The presently preferred yield-increasing technology suitable for such oil well It is exactly work-in-progress control technology or water blockoff Acidizing Technology.Work-in-progress control technology is the oil-soluble temporary plugging agent using variable grain size, Before injection is acidified host agent, first diverting agent is injected, reduces the physical size in crack by the diverting agent deposition of injection to rise To the ability of fluid flowing is reduced, to play the amount that treatment fluid is flowed along fractuer direction that reduces, force treatment fluid to crack side To flowing, acidification and oil increasing effect are improved, still, the height extended due to the of different sizes of crack of different oil reservoirs, vertical, horizontal Degree, distance are different, so, selection and the performance evaluation difficulty for carrying out diverting agent are larger, and specific aim is poor, leads to work-in-progress control skill Success rate of the art in application is lower, and oil increasing effect of restricting water supply is limited;Water blockoff Acidizing Technology used at present, it is same because in oil reservoir The difference in crack causes the specific aim of water shutoff agent to have some limitations, and leads to success of the water blockoff Acidizing Technology in application Rate is relatively low, and oil increasing effect of restricting water supply is limited certain limitation.And it is carried out with conventional oil well acidation technology for such oil well Acidification success rate, the oily amplitude of increasing are lower, and the validity period of measure is shorter, and even, considerable oil well causes aqueous big after acidification Amplitude is further up or water logging, and oil well is caused to scrap.
Summary of the invention
It is a kind of for along fractuer direction injection water it is an object of the invention to provide aiming at the problems existing in the prior art The acidization tool for the oil well advanced by leaps and bounds, the acidization tool improve the success rate of well stimulation, improve the oil increasing effect of restricting water supply of measure, mention High stimulation amplitude and the validity period for extending measure.
The technical scheme is that
A kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, includes the following steps: one, uses flushing fluid Pit shaft well-flushing is recycled to clean;Two, huge discharge injects viscous acid pretreatment fluid;Three, the viscous acid pretreatment fluid arrival injected is penetrated More than hole section at 300 meters, keeps perforated interval and nearby there is in oil reservoir viscous acid pretreatment fluid, fasten sleeve gate, then make With less than one times flow line volume 2m3Thickening displacement fluid viscous acid pretreatment fluid is set to the above 300m of perforated interval and processing half At diameter 0.2m;Four, closing well reacts 2 hours;Sleeve gate is opened, pit shaft is filled with thickening displacement fluid, gas in casing is replaced It sets clean until all thickening displacement fluids of cannula exit;Six, retaining sleeve gate opens wide, and then squeezes into viscous acid main process task Liquid is for thickening displacement fluid is set, when the amount of injection viscous acid main process task liquid is greater than flow line volume 5m3When, sleeve gate is fastened, continuously Viscous acid main process task liquid is injected, perforated interval is kept and nearby there is in oil reservoir viscous acid main process task liquid;Seven, injection thickening replaces Liquid, less than one times flow line volume 3m of amount of injection thickening displacement fluid3When stop;Eight, closing well reacts 3 hours;Nine, the row of returning is aspirated, Acidification raffinate is pumped out and carries out the row of returning thoroughly.
Specifically, the main constituents of the flushing fluid are 0.5%AES, 1% potassium chloride and 1 ℅ by weight HEDP, remaining is water.
Specifically, the main component of the viscous acid pretreatment fluid is by weight are as follows: 0.5% polypropylene acid, 0.5% HEDP, 10% hydrochloric acid, 3% phosphoric acid, 2%HF, 1% acidification corrosion inhibitor, 0.5%AES, 2% potassium chloride and 1% citric acid, remaining For water, viscosity >=50mPa.s of the viscous acid pretreatment fluid.
Specifically, the main component of the thickening displacement fluid is by weight are as follows: the cruel amine of 0.3% polypropylene, 1% chlorination Potassium, 2% phosphoric acid and 0.5%AES, remaining is water, viscosity >=50mPa.s of the thickening displacement fluid.
Specifically, the main component of the thickening main process task liquid be by weight 0.5% polyacrylic acid, 8% hydrochloric acid, It 4%HF, 3% formic acid, 3% acetic acid, 2% phosphoric acid, 1% corrosion inhibiter, 3% potassium chloride, 1%HEDP, 1% citric acid and O.5% breaks Emulsion, remaining is water, viscosity >=50mPa.s of the thickening main process task liquid.
Specifically, huge discharge refers to the injection rate greater than 500 public assorted/minute in the step two.
The beneficial effects of the present invention are: preventing, limiting well head pressure and fluid column pressure by the viscosity for improving pretreatment fluid It is mobile to earth formation deep to push dynamic pretreatment fluid, the high reaction speed of viscosity is slow, slows down pretreatment fluid to infiltration fissure channel Physical size further expansion, furthermore viscosity itself can be made to increase severely since tackifier (EAB) are reacted with bivalent metal ion, therefore meeting Further limitation pretreatment fluid is flowed to the crack depths of infiltration.The present invention is by injecting main acid front exhaust technique, substantially Degree reduces influence of the compressibility of gas to design metering, main acid accurately can be pumped into design position, to make main process task sour The blocking for causing oil productive capacity in oil reservoir is effectively released, de-plugging efficiency and measure effect are improved.
Specific embodiment
A kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, includes the following steps: one, uses flushing fluid Pit shaft well-flushing is recycled to clean;Two, huge discharge injects viscous acid pretreatment fluid, and huge discharge refers to the note greater than 500 public assorted/minute Enter amount, principle is the tamper blocked on the tamper and crack side of perforation eye by acid dissolution, reduces the main place of viscous acid It manages liquid injection pressure and improves acidification liquid to the amount laterally injected, viscous acid is reduced and limited due to viscosity with higher The amount and speed that viscous acid pretreatment fluid and viscous acid main process task liquid processed enter along crack;Three, the viscous acid pretreatment fluid injected It reaches at 300 meters of perforated interval or more, keep perforated interval and nearby there is in oil reservoir viscous acid pretreatment fluid, fasten sleeve gate, Then less than one times flow line volume 2m is used3Thickening displacement fluid by viscous acid pretreatment fluid for set the above 300m of perforated interval and At treatment radius 0.2m, the effect for being thickened displacement fluid is liquid of the limitation after thickening displacement fluid in well head pressure and fluid column Under pressure effect, viscous acid is pushed into deeper oil reservoir along crack, to avoid further being acidified water outlet crack, reduction contains Water is further up;Four, closing well reacts 2 hours;Five, sleeve gate is opened, is filled pit shaft with viscous acid displacement fluid, by casing Middle gas is clean up to all viscous acid displacement fluids of cannula exit guarantee low-kappa number with the exhaust of viscous acid displacement fluid for setting Liquid arrives design position by note by design, improves acidizing effect;Six, retaining sleeve gate opens wide, and then squeezes into the main place of viscous acid Reason liquid is for viscous acid displacement fluid is set, when the amount of injection viscous acid main process task liquid is greater than flow line volume 5m3When, sleeve gate is fastened, It is continuously injected into viscous acid main process task liquid, keep perforated interval and nearby there is in oil reservoir viscous acid main process task liquid;Seven, injection thickening top For liquid, less than one times flow line volume 3m of amount of injection thickening displacement fluid3When stop;Eight, closing well reacts 3 hours;Nine, suction is returned Acidification raffinate is pumped out and carries out the row of returning thoroughly by row, and the row of returning thoroughly, reduces ginseng acid and further migrates along crack, reduce water outlet Degree, reduce pollution of the secondary injury to stratum.
The main constituents of the flushing fluid are 0.5%AES, 1% potassium chloride and 1 ℅ HEDP by weight, remaining For water.The main component of the viscous acid pretreatment fluid is by weight are as follows: 0.5% polypropylene acid, 0.5%HEDP, 10% salt Acid, 3% phosphoric acid, 2%HF, 1% acidification corrosion inhibitor, 0.5%AES, 2% potassium chloride and 1% citric acid, remaining is water, described Viscosity >=50mPa.s of viscous acid pretreatment fluid.The main component of the thickening displacement fluid is by weight are as follows: 0.3% poly- third The cruel amine of alkene, 1% potassium chloride, 2% phosphoric acid and 0.5%AES, remaining is water, viscosity >=50mPa.s of the thickening displacement fluid. The main component of the thickening main process task liquid is 0.5% polyacrylic acid, 8% hydrochloric acid, 4%HF, 3% formic acid, 3% by weight Acetic acid, 2% phosphoric acid, 1% corrosion inhibiter, 3% potassium chloride, 1%HEDP, 1% citric acid and O.5% demulsifier, remaining is water, described Thickening main process task liquid viscosity >=50mPa.s.
During viscous acid pretreatment fluid is for setting, viscous acid pretreatment fluid makes to be thickened to the above 300m of perforated interval, purpose Low-kappa number liquid is thorough by perforated interval and nearby processing, increases measure degree for the treatment of, improves measure effect;And pretreatment is replaced Liquid dosage reduces 2m3, or the thickening displacement fluid dosage for replacing viscous acid main process task liquid is reduced 3m3, and purpose is in viscous acid When pretreatment fluid or viscous acid main process task liquid react, viscous acid pretreatment fluid or the main place of viscous acid in perforated interval and are nearby maintained Liquid is managed, can guarantee that perforated interval, perforation eye and perforated interval nearly well oil reservoir duct, which are handled thoroughly restricting water supply for raising measure, increases the width of oil Degree and validity period, increase the economic benefit of measure.
And conventional processing method is, when replacing pretreatment fluid or main process task liquid, displacement fluid dosage is equal to flow line volume (from well head to the oil pipe inner volume of tubing string end), in this case, pretreatment fluid or main process task liquid can be in inlet pressures and fluid column It under the action of pressure, is promoted to earth formation deep, causes to be the liquid without acid in perforated interval and nearly well oil reservoir hole, thus substantially Degree reduces treatment fluid to the dissolution rate of tamper in perforated interval and neighbouring oil reservoir, because these positions directly affect the production of oil well Amount, therefore can recover greatly reduces success rate, treatment effect and the validity period of the measure of processing of acidification.
It can be seen that the relatively conventional existing acidization tool acidizing effect of acidization tool provided by the invention more preferably and, have The success rate for improving well stimulation improves the oil increasing effect of restricting water supply of measure, improves stimulation amplitude and extends the effective of measure The effect of phase.
Finally it should be noted that: the above embodiments are merely illustrative of the technical scheme of the present invention and are not intended to be limiting thereof;To the greatest extent The present invention is described in detail with reference to preferred embodiments for pipe, it should be understood by those ordinary skilled in the art that: still It can modify to a specific embodiment of the invention or some technical features can be equivalently replaced;Without departing from this hair The spirit of bright technical solution should all cover within the scope of the technical scheme claimed by the invention.

Claims (6)

1. a kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which comprises the steps of:
One, pit shaft well-flushing is recycled to clean with flushing fluid;
Two, huge discharge injects viscous acid pretreatment fluid;
Three, the viscous acid pretreatment fluid injected reaches at 300 meters of perforated interval or more, keeps perforated interval and nearby in oil reservoir with thick Change low-kappa number liquid, fastens sleeve gate, then use less than one times flow line volume 2m3Thickening displacement fluid viscous acid is located in advance Reason liquid, which replaces, to be set at the perforated interval above 300m and treatment radius 0.2m;
Four, closing well reacts 2 hours;
Five, sleeve gate is opened, is filled pit shaft with thickening displacement fluid, gas in casing is set clean until cannula exit is complete Portion is thickening displacement fluid;
Six, retaining sleeve gate opens wide, and then squeezes into viscous acid main process task liquid for thickening displacement fluid is set, as injection viscous acid master The amount for the treatment of fluid is greater than flow line volume 5m3When, fasten sleeve gate, be continuously injected into viscous acid main process task liquid, keep perforated interval and Nearby there is in oil reservoir viscous acid main process task liquid;
Seven, injection thickening displacement fluid, less than one times flow line volume 3m of amount of injection thickening displacement fluid3When stop;
Eight, closing well reacts 3 hours;
Nine, the row of returning is aspirated, acidification raffinate is pumped out and carries out the row of returning thoroughly.
2. according to claim 1 for the acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which is characterized in that institute The main component for the flushing fluid stated is by weight are as follows: 0.5%AES, 1% potassium chloride and 1 ℅ HEDP, remaining is water.
3. according to claim 1 for the acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which is characterized in that institute The main component for the viscous acid pretreatment fluid stated is by weight are as follows: 0.5% polypropylene acid, 0.5%HEDP, 10% hydrochloric acid, 3% Phosphoric acid, 2%HF, 1% acidification corrosion inhibitor, 0.5%AES, 2% potassium chloride and 1% citric acid, remaining is water, the viscous acid Viscosity >=50mPa.s of pretreatment fluid.
4. according to claim 1 for the acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which is characterized in that institute The main component for the thickening displacement fluid stated is by weight are as follows: the cruel amine of 0.3% polypropylene, 1% potassium chloride, 2% phosphoric acid and 0.5% AES, remaining is water, viscosity >=50mPa.s of the thickening displacement fluid.
5. according to claim 1 for the acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which is characterized in that institute The main component for the thickening main process task liquid stated is by weight are as follows: 0.5% polyacrylic acid, 8% hydrochloric acid, 4%HF, 3% formic acid, 3% acetic acid, 2% phosphoric acid, 1% corrosion inhibiter, 3% potassium chloride, 1%HEDP, 1% citric acid and O.5% demulsifier, remaining is water, Viscosity >=50mPa.s of the thickening main process task liquid.
6. according to claim 1 for the acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water, which is characterized in that institute Huge discharge refers to the injection rate greater than 500 public assorted/minute in the step of stating two.
CN201810748274.7A 2018-07-10 2018-07-10 Acidification method for oil well with water injected in crack direction and capable of entering suddenly Active CN109083620B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810748274.7A CN109083620B (en) 2018-07-10 2018-07-10 Acidification method for oil well with water injected in crack direction and capable of entering suddenly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810748274.7A CN109083620B (en) 2018-07-10 2018-07-10 Acidification method for oil well with water injected in crack direction and capable of entering suddenly

Publications (2)

Publication Number Publication Date
CN109083620A true CN109083620A (en) 2018-12-25
CN109083620B CN109083620B (en) 2021-03-26

Family

ID=64837349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810748274.7A Active CN109083620B (en) 2018-07-10 2018-07-10 Acidification method for oil well with water injected in crack direction and capable of entering suddenly

Country Status (1)

Country Link
CN (1) CN109083620B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4578201A (en) * 1984-03-05 1986-03-25 Phillips Petroleum Company N-vinyl lactam/unsaturated amide copolymers in thickened acid compositions
CN102041987A (en) * 2009-10-13 2011-05-04 中国石油天然气股份有限公司 Method for water control and oil production increasing acidification of oil well at water content increasing stage of low-pressure heterogeneous reservoir
CN103953324A (en) * 2014-04-29 2014-07-30 惠建龙 Fracture height-adjustable acid fracturing method adopting polyatomic acid and steering acid
CN104653164A (en) * 2013-11-22 2015-05-27 中国石油天然气股份有限公司 Water-controlling blockage removing and yield increasing method for oil well of low-pressure bottom water oil reservoir
CN104910037A (en) * 2015-06-02 2015-09-16 中国石油天然气股份有限公司 Preparation method of amide surface-active acid thickener
CN104975840A (en) * 2015-06-18 2015-10-14 中国石油化工股份有限公司 Self-born acid composite acid fracturing process for high-temperature deep well carbonate rock reservoir

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4578201A (en) * 1984-03-05 1986-03-25 Phillips Petroleum Company N-vinyl lactam/unsaturated amide copolymers in thickened acid compositions
CN102041987A (en) * 2009-10-13 2011-05-04 中国石油天然气股份有限公司 Method for water control and oil production increasing acidification of oil well at water content increasing stage of low-pressure heterogeneous reservoir
CN104653164A (en) * 2013-11-22 2015-05-27 中国石油天然气股份有限公司 Water-controlling blockage removing and yield increasing method for oil well of low-pressure bottom water oil reservoir
CN103953324A (en) * 2014-04-29 2014-07-30 惠建龙 Fracture height-adjustable acid fracturing method adopting polyatomic acid and steering acid
CN104910037A (en) * 2015-06-02 2015-09-16 中国石油天然气股份有限公司 Preparation method of amide surface-active acid thickener
CN104975840A (en) * 2015-06-18 2015-10-14 中国石油化工股份有限公司 Self-born acid composite acid fracturing process for high-temperature deep well carbonate rock reservoir

Also Published As

Publication number Publication date
CN109083620B (en) 2021-03-26

Similar Documents

Publication Publication Date Title
CN110159243B (en) Acid fracturing method for seam network of carbonate rock reservoir
CN105089600B (en) The method that temporarily stifled diverting material auxiliary water horizontal well carries out drawing type water-jet transformation
CN106223922A (en) Staged fracturing technique is blocked up in the seam inner shield of shale gas horizontal well proppant temporarily
CN101353958A (en) Acid fracturing process of oil gas well mining temperature control various mucic acid
CN106194105B (en) Launch profile control method in blocking agent deep
US20210108491A1 (en) Integrated construction method of fracturing and tertiary oil recovery for low-permeability reservoir
CN104847317A (en) Method for raising recovery efficiency of super-deep low permeability heavy oil reservoir
CN104653164B (en) A kind of low pressure bottom water reservoir oil well control blockage method for increasing
CN105625981A (en) Composite profile control method for middle-high permeability oil reservoirs
CN107664020B (en) Water plugging method for bottom water reservoir horizontal well
CN103422842B (en) Oil well blocks up, adjusts, washes technique
CN110552675A (en) non-crack type water-breakthrough oil well repeated transformation method
CN109630066A (en) The method of low-permeability oilfield high-water-cut oil-producing well water blockoff and acidification integration of operation
CN109083620A (en) A kind of acidization tool for the oil well advanced by leaps and bounds along fractuer direction injection water
RU2482269C2 (en) Method for increasing oil recovery of deposit in carbonate reservoirs of fracture-pore type
RU2451160C1 (en) Method of acid treatment of bottom-hole formation zone with carbonate reservoir
RU2597305C1 (en) Method for development of oil deposit in carbonate reservoirs
CN103912247B (en) A kind of multistage slug Technology of gas well horizontal well
CN111502628B (en) Segmented water control acidification method for low permeability reservoir fracturing well completion horizontal well
CN107603575A (en) One kind control water reservoir reconstruction method
CN103541713A (en) Coalbed methane near-wellbore area chemical block removing method
RU2579093C1 (en) Method for repeated hydraulic fracturing
CN114482918A (en) Profile control method for low-speed discontinuous injection
CN101949283A (en) Water reducing, de-plugging and yield increasing integrated process
CN112878953A (en) Design method of slug for adjustment construction of flow channel of solution-breaking reservoir

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 08 East Road, 50 meters south of the intersection of Subei Road and Xindong Road, Puyang City, Henan Province, 457001

Patentee after: Henan Ruitong Energy Engineering Technology Co.,Ltd.

Address before: 457000 North Road, 200m east of the intersection of Wuyi Road and Wenming Road, Puyang City, Henan Province

Patentee before: PUYANG HUARUITONG ENERGY ENGINEERING TECHNOLOGY Co.,Ltd.