CN109057370A - The application method of rack jack-up construction Compact Mounts - Google Patents

The application method of rack jack-up construction Compact Mounts Download PDF

Info

Publication number
CN109057370A
CN109057370A CN201810919742.2A CN201810919742A CN109057370A CN 109057370 A CN109057370 A CN 109057370A CN 201810919742 A CN201810919742 A CN 201810919742A CN 109057370 A CN109057370 A CN 109057370A
Authority
CN
China
Prior art keywords
tube body
adjustable
length
rack
limit arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810919742.2A
Other languages
Chinese (zh)
Other versions
CN109057370B (en
Inventor
陈宗学
宋胜东
朱允
谢建鹏
郭江倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Group Corp Ltd
Original Assignee
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Group Corp Ltd filed Critical Hebei Construction Group Corp Ltd
Priority to CN201810919742.2A priority Critical patent/CN109057370B/en
Publication of CN109057370A publication Critical patent/CN109057370A/en
Application granted granted Critical
Publication of CN109057370B publication Critical patent/CN109057370B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1808Holders for bricklayers' lines, bricklayers' bars; Sloping braces
    • E04G21/1816Adjustable positioning means between line-holder bars and construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of application methods of rack jack-up construction Compact Mounts, first cover upper tube body in the upper end of middle tube body, and lower tube body is covered in the lower end of middle tube body, are inserted into the length of middle tube body when adjusting width by adjusting upper tube body and lower tube body;Secondly the first tube body in adjustable-length position limit arm is inserted into the second tube body, is inserted into the distance of the second tube body by adjusting the first tube body in adjustable-length position limit arm to adjust the length of position limit arm;The third tube body on adjustable-length angle limit arm is covered on the 4th tube body again, the other end of 4th tube body is connected by sleeve with middle tube body, the distance of third tube body is inserted into adjust the length of position limit arm by adjusting the 4th tube body when adjusting length, rotates adjustable-length angle limit arm around middle tube body when adjusting the angle.The present invention can limit its sidesway in the horizontal direction in Elements of Space Grid Truss jack-up construction, guarantee the verticality of jacking process rack, prevent the generation of quality and safety accident.

Description

The application method of rack jack-up construction Compact Mounts
Technical field
The present invention relates to steel grid structure jack-up construction engineering device technique fields, use more particularly, to a kind of rack jack-up construction The application method of Compact Mounts.
Background technique
Steel grid structure has good integrity, the spy that space stiffness is big, anti-seismic performance is good, environmentally protective, speed of application is fast Point is widely used in industry and public building.The installation method of steel grid structure have Assembly in pieces at height, lift-on/lift-off system, Lift method, accumulative sliding technique, jack-block etc. are a variety of, and jack-block construction is low, small by field conditions with construction cost, operates Convenient feature is that rack installs relatively effective method.
Rack will be stepped up the height of jacking frame frame body when jack-block is constructed, to reach Elements of Space Grid Truss jacking to setting Meter requires the purpose of absolute altitude.But since jacking frame production and the presence of installation error can be led with the increase of top lifting height Elements of Space Grid Truss is caused to generate the sidesway of horizontal direction in the horizontal direction, there is no limit rack sidesway to arrange for construction method used at present It applies, if sidesway is smaller can be corrected by satisfactory after correcting, if sidesway is larger, is not only difficult to rectify a deviation, or even safety can occur Accident.
Summary of the invention
The object of the present invention is to provide a kind of application methods of rack jack-up construction Compact Mounts, can be in steel mesh Its sidesway in the horizontal direction is limited in frame jack-up construction, is guaranteed the verticality of jacking process rack, is prevented quality and safe thing Therefore generation.
To achieve the above object, the present invention provides a kind of application method of rack jack-up construction Compact Mounts, Rack jack-up construction Compact Mounts include adjustable-width principal arm, the adjustable length that adjustable-width principal arm both ends are arranged in Degree position limit arm and the adjustable-length angle limit arm being arranged in the middle part of the adjustable-width principal arm;
The adjustable-width principal arm is made of upper tube body, lower tube body and middle tube body, and the both ends of the middle tube body are arranged respectively In the upper tube body and the lower tube body, the internal diameter of the lower tube body and the upper tube body is all larger than the outer of the middle tube body Diameter;
The adjustable-length position limit arm by the first tube body for being connect with the upper tube body and the lower tube body and under rack The second connected tube body of chord node, second tube body are set on first tube body;
The adjustable-length angle limit arm is by the third tube body that is connected with rack lower-chord panel point and is set in the third Intracorporal 4th tube body is managed, the other end of the 4th tube body is connected by sleeve with the middle tube body;
The application methods of rack jack-up construction Compact Mounts the following steps are included:
Firstly, installation adjustable-width principal arm, upper tube body is covered in the upper end of middle tube body, lower tube body covers under middle tube body End is inserted into the length of middle tube body by adjusting upper tube body and lower tube body when adjusting width;
Secondly, installation adjustable-length position limit arm, the first tube body in adjustable-length position limit arm is inserted into the second tube body, The other end of first tube body is connect with upper tube body and lower tube body, and the other end of the second tube body is mounted on rack lower-chord panel point, so The distance of the second tube body is inserted by adjusting the first tube body in adjustable-length position limit arm afterwards to adjust the length of position limit arm;
Again, adjustable-length angle limit arm is installed, the third tube body on adjustable-length angle limit arm is covered the 4th On tube body, the other end of third tube body is mounted on rack lower-chord panel point, and the other end of the 4th tube body passes through sleeve and middle tube body It is connected, is inserted into the distance of third tube body by adjusting the 4th tube body when adjusting length to adjust the length of position limit arm, works as tune Adjustable-length angle limit arm is rotated around middle tube body when whole angle;
Finally, installing two idler wheels, on middle tube body in the concrete column surface scrolls of support rack.
Preferably, by 100mm's on the upper tube body, the lower tube body, second tube body and the third tube body Spacing bores fixation hole, and the welded nut on the outside of fixation hole, and fastening bolt is screwed into nut makes screw rod end hold out against middle tube body Realize that position is fixed.
Preferably, the internal diameter of the upper tube body is identical as the internal diameter of the lower tube body, the internal diameter of the lower tube body and described The internal diameter of upper tube body is all larger than the outer diameter 2-5mm of the middle tube body.
Preferably, the upper tube body and the lower tube body are connect with first pipe welding, first tube body Outer diameter is less than the internal diameter of second tube body.
Preferably, two idler wheels are symmetricly set on the two sides of the sleeve.
Preferably, the sleeve is made of first sleeve and the second casing, and second casing and the first sleeve are hung down Directly, the first sleeve is set on the middle tube body, and second casing is set on the 4th tube body, the 4th pipe The outer diameter of body is less than the internal diameter of the third tube body.
Preferably, the upper tube body and the lower tube body are connect with the first tube body vertical welding.
Therefore, the application method of the rack jack-up construction Compact Mounts of the present invention using the above structure, Neng Gou Its sidesway in the horizontal direction is limited in Elements of Space Grid Truss jack-up construction, is guaranteed the verticality of jacking process rack, is prevented quality and peace The generation of full accident.
Below by drawings and examples, technical scheme of the present invention will be described in further detail.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of rack jack-up construction Compact Mounts of the present invention;
Fig. 2 is the mounting structure schematic diagram of rack jack-up construction Compact Mounts of the present invention;
Fig. 3 is the mounting structure top view of rack jack-up construction Compact Mounts of the present invention;
Fig. 4 is the axonometric drawing of rack jack-up construction Compact Mounts of the present invention.
Specific embodiment
Embodiment
Fig. 1 is the structural schematic diagram of rack jack-up construction Compact Mounts of the present invention, and Fig. 2 is rack of the present invention jacking The mounting structure schematic diagram of the flat limiting device of construction water, Fig. 3 are the peace of rack jack-up construction Compact Mounts of the present invention Assembling structure top view, Fig. 4 are the axonometric drawing of rack jack-up construction Compact Mounts of the present invention.As shown, the present invention mentions For a kind of application method of rack jack-up construction Compact Mounts, rack jack-up construction Compact Mounts 1 include Adjustable-width principal arm 11, the adjustable-length position limit arm 12 that 11 both ends of adjustable-width principal arm are arranged in and setting are in adjustable-width principal arm The adjustable-length angle limit arm 13 at 11 middle parts;Adjustable-width principal arm 11 is by 112 structure of upper tube body 110, lower tube body 111 and middle tube body At the both ends of middle tube body 112 are respectively sleeved in upper tube body 110 and lower tube body 111, the internal diameter of lower tube body 111 and upper tube body 110 It is all larger than the outer diameter 2-5mm of middle tube body 112, the internal diameter of upper tube body 110 is identical as the internal diameter of lower tube body 111, and upper tube body 110 is under Tube body 111 is welded to connect with the first tube body 120, freely slidable between middle tube body and upper tube body and lower tube body and do not generated Big gap;Adjustable-length position limit arm 12 by the first tube body 120 for being connect with upper tube body 110 and lower tube body 111 and under rack The second connected tube body 121 of chord node 2, the second tube body 121 are set on the first tube body 120, and the outer diameter of the first tube body 120 is less than The internal diameter of second tube body 121;Adjustable-length angle limit arm 13 is by the third tube body 130 that is connected with rack lower-chord panel point 2 and set The other end of the 4th tube body 131 being located in third tube body 130, the 4th tube body 131 is connected by sleeve 3 with middle tube body 112;
The application methods of rack jack-up construction Compact Mounts the following steps are included:
Firstly, installation adjustable-width principal arm 11, by 110 sets of the upper tube body upper ends in middle tube body 112,111 sets of lower tube body exists The lower end of middle tube body 112 is inserted into the length of middle tube body, by adjusting upper tube body and lower tube body to adapt to when adjusting width The width of rack grid in different engineerings guarantees that adjustable-length position limit arm can correspond to the node of rack;
Secondly, installation adjustable-length position limit arm 12, is inserted into second for the first tube body 120 in adjustable-length position limit arm 12 In tube body 121, the other end of the first tube body 121 is connect with upper tube body 110 and lower tube body 111, the other end peace of the second tube body 121 On rack lower-chord panel point 2, the distance of the second tube body is then inserted by adjusting the first tube body in adjustable-length position limit arm To adjust the length of position limit arm;
Again, adjustable-length angle limit arm 13 is installed, by 130 sets of third tube body on adjustable-length angle limit arm 13 On the 4th tube body 131, the other end of third tube body 131 is mounted on rack lower-chord panel point 2, the other end of the 4th tube body 131 It is connected by sleeve 3 with middle tube body 112, is inserted into the distance of third tube body by adjusting the 4th tube body when adjusting length to adjust The length of whole position limit arm rotates adjustable-length angle limit arm around middle tube body when adjusting the angle, to adapt to different thickness Spend the position of chord node on rack;
Finally, on middle tube body 112 install two idler wheels 4, for support rack 7 surface scrolls of concrete column, both Horizontal direction position-limiting action is played, and can guarantee that rack moves up along the vertical direction during jacking, two idler wheels 4 are symmetrical The two sides of sleeve 3 are set, and sleeve 3 is made of first sleeve 31 and the second casing 32, and the second casing 32 hangs down with first sleeve 31 Directly, first sleeve 31 is set on middle tube body 112, and the second casing 32 is set on the 4th tube body 131, outside the 4th tube body 131 Diameter is less than the internal diameter of third tube body 131.
It bores and fixes by the spacing of 100mm on upper tube body 110, lower tube body 111, the second tube body 121 and third tube body 131 Hole, and welded nut 5 on the outside of fixation hole, fastening bolt 6 is screwed into nut 5 makes screw rod end hold out against middle tube body realization position Fixed, upper tube body 110 and lower tube body 111 are connect with 121 vertical welding of the first tube body.
Therefore, the application method of the rack jack-up construction Compact Mounts of the present invention using the above structure, Neng Gou Its sidesway in the horizontal direction is limited in Elements of Space Grid Truss jack-up construction, is guaranteed the verticality of jacking process rack, is prevented quality and peace The generation of full accident.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention rather than is limited, Although the present invention is described in detail with reference to preferred embodiments, those skilled in the art should understand that: its according to So can be with modification or equivalent replacement of the technical solution of the present invention are made, and these modifications or equivalent replacement cannot also make to repair Technical solution after changing is detached from the spirit and scope of technical solution of the present invention.

Claims (7)

1. a kind of application method of rack jack-up construction Compact Mounts, it is characterised in that:
Rack jack-up construction Compact Mounts include adjustable-width principal arm, adjustable-width principal arm both ends are set can The adjustable-length angle limit arm adjusting length position limit arm and being arranged in the middle part of the adjustable-width principal arm;
The adjustable-width principal arm is made of upper tube body, lower tube body and middle tube body, and the both ends of the middle tube body are respectively sleeved at institute It states in upper tube body and the lower tube body, the internal diameter of the lower tube body and the upper tube body is all larger than the outer diameter of the middle tube body;
The adjustable-length position limit arm by the first tube body for being connect with the upper tube body and the lower tube body and with chord joint under rack The second connected tube body of point, second tube body are set on first tube body;
The adjustable-length angle limit arm is by the third tube body that is connected with rack lower-chord panel point and is set in the third tube body The other end of the 4th interior tube body, the 4th tube body is connected by sleeve with the middle tube body;
The application methods of rack jack-up construction Compact Mounts the following steps are included:
Firstly, installation adjustable-width principal arm, upper tube body is covered in the upper end of middle tube body, lower tube body is covered in the lower end of middle tube body, is adjusted The length of middle tube body is inserted into when whole width by adjusting upper tube body and lower tube body;
Secondly, installation adjustable-length position limit arm, the first tube body in adjustable-length position limit arm is inserted into the second tube body, first The other end of tube body is connect with upper tube body and lower tube body, and the other end of the second tube body is mounted on rack lower-chord panel point, is then led to The first tube body crossed in adjustment adjustable-length position limit arm is inserted into the distance of the second tube body to adjust the length of position limit arm;
Again, adjustable-length angle limit arm is installed, the third tube body on adjustable-length angle limit arm is covered in the 4th tube body On, the other end of third tube body is mounted on rack lower-chord panel point, and the other end of the 4th tube body is connected by sleeve with middle tube body, The distance of third tube body is inserted into adjust the length of position limit arm by adjusting the 4th tube body when adjusting length, works as adjustment angle When adjustable-length angle limit arm is rotated around middle tube body;
Finally, installing two idler wheels, on middle tube body in the concrete column surface scrolls of support rack.
2. the application method of rack jack-up construction Compact Mounts according to claim 1, it is characterised in that: in institute It states and bores fixation hole by the spacing of 100mm on upper tube body, the lower tube body, second tube body and the third tube body, and solid Determine welded nut on the outside of hole, be screwed into nut fastening bolt make screw rod end hold out against middle tube body realize position fix.
3. the application method of rack jack-up construction Compact Mounts according to claim 2, it is characterised in that: described The internal diameter of upper tube body is identical as the internal diameter of the lower tube body, and the internal diameter of the internal diameter of the lower tube body and the upper tube body is all larger than institute State the outer diameter 2-5mm of middle tube body.
4. the application method of rack jack-up construction Compact Mounts according to claim 3, it is characterised in that: described Upper tube body and the lower tube body are connect with first pipe welding, and the outer diameter of first tube body is less than second tube body Internal diameter.
5. the application method of rack jack-up construction Compact Mounts according to claim 4, it is characterised in that: two The idler wheel is symmetricly set on the two sides of the sleeve.
6. the application method of rack jack-up construction Compact Mounts according to claim 5, it is characterised in that: described Sleeve is made of first sleeve and the second casing, and second casing is vertical with the first sleeve, and the first sleeve is arranged On the middle tube body, second casing is set on the 4th tube body, and the outer diameter of the 4th tube body is less than described the The internal diameter of three tube bodies.
7. the application method of rack jack-up construction Compact Mounts according to claim 6, it is characterised in that: described Upper tube body and the lower tube body are connect with the first tube body vertical welding.
CN201810919742.2A 2018-08-14 2018-08-14 Use method of horizontal limiting device for net rack jacking construction Active CN109057370B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810919742.2A CN109057370B (en) 2018-08-14 2018-08-14 Use method of horizontal limiting device for net rack jacking construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810919742.2A CN109057370B (en) 2018-08-14 2018-08-14 Use method of horizontal limiting device for net rack jacking construction

Publications (2)

Publication Number Publication Date
CN109057370A true CN109057370A (en) 2018-12-21
CN109057370B CN109057370B (en) 2020-09-01

Family

ID=64678209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810919742.2A Active CN109057370B (en) 2018-08-14 2018-08-14 Use method of horizontal limiting device for net rack jacking construction

Country Status (1)

Country Link
CN (1) CN109057370B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450425A (en) * 2022-07-04 2022-12-09 中建三局集团有限公司 Fixing device for net rack lifting hovering plane and using method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55145212A (en) * 1979-04-28 1980-11-12 Shimizu Constr Co Ltd Plumbing device for cylindrical steel frame
JPH04161565A (en) * 1990-10-24 1992-06-04 Tokyu Constr Co Ltd Construction of large space building
CN202706203U (en) * 2012-08-15 2013-01-30 山西一建集团有限公司 Toppling preventing and correcting net rack jacking device
CN104631337A (en) * 2015-02-16 2015-05-20 中交第二航务工程局有限公司 Guide deviation correcting device for large concrete component pushing
CN105672638A (en) * 2016-02-17 2016-06-15 浙江精工钢结构集团有限公司 Scaffold with supporting and sliding functions and net rack mounting method
CN205531392U (en) * 2016-02-02 2016-08-31 中国建筑第六工程局有限公司 Stop device that topples is prevented in steel space frame jacking
CN206942161U (en) * 2017-06-16 2018-01-30 中国五冶集团有限公司 A kind of jacking adjusting apparatus for high-altitude wire frame

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55145212A (en) * 1979-04-28 1980-11-12 Shimizu Constr Co Ltd Plumbing device for cylindrical steel frame
JPH04161565A (en) * 1990-10-24 1992-06-04 Tokyu Constr Co Ltd Construction of large space building
CN202706203U (en) * 2012-08-15 2013-01-30 山西一建集团有限公司 Toppling preventing and correcting net rack jacking device
CN104631337A (en) * 2015-02-16 2015-05-20 中交第二航务工程局有限公司 Guide deviation correcting device for large concrete component pushing
CN205531392U (en) * 2016-02-02 2016-08-31 中国建筑第六工程局有限公司 Stop device that topples is prevented in steel space frame jacking
CN105672638A (en) * 2016-02-17 2016-06-15 浙江精工钢结构集团有限公司 Scaffold with supporting and sliding functions and net rack mounting method
CN206942161U (en) * 2017-06-16 2018-01-30 中国五冶集团有限公司 A kind of jacking adjusting apparatus for high-altitude wire frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450425A (en) * 2022-07-04 2022-12-09 中建三局集团有限公司 Fixing device for net rack lifting hovering plane and using method
CN115450425B (en) * 2022-07-04 2023-09-05 中建三局集团西南有限公司 Fixing device for lifting hovering plane of net rack and using method

Also Published As

Publication number Publication date
CN109057370B (en) 2020-09-01

Similar Documents

Publication Publication Date Title
CN109057370A (en) The application method of rack jack-up construction Compact Mounts
CN208668988U (en) Rack jack-up construction Compact Mounts
CN220268640U (en) Round metal pipeline anti-seismic support and hanger
CN209398930U (en) A kind of Pipe installing adjustable-size antidetonation suspension and support
CN207829241U (en) Curved surface curtain wall
CN204267231U (en) A kind of mounting bracket of survey wind devices of wind power generating set
CN110761299B (en) Bracket for mounting steel support on foundation pit purlin and construction method thereof
CN112610059A (en) Power transmission online monitoring device installation platform and installation method thereof
CN217003616U (en) Pipeline expansion joint convenient to install
CN207065024U (en) A kind of adjustable height tray rack suitable for high-rise building
CN210196758U (en) Anti-seismic support
CN110925898A (en) Outer quick-witted fixed bolster of air conditioner convenient to installation
CN219734461U (en) Pipeline support and hanger convenient to dismouting
CN218265385U (en) Protective coaming for constructional engineering
CN205981132U (en) A adjustable bracket for erection equipment
CN203905421U (en) Adjustable assembled operating platform
CN220822457U (en) Cable bridge fixing support
CN220246647U (en) Adjustable bailey piece support frame
CN205560210U (en) Pillar joint Assembly
CN215861203U (en) Adjustable screw
CN216042777U (en) Building structure reinforcing apparatus
CN211713739U (en) Construction warning baffle with adjustable municipal works are used
CN109882657B (en) Pipeline flexible support and inner and outer pipeline mounting structure
CN211423775U (en) Ground deformation monitoring connecting device
CN219268440U (en) Pipeline mounting rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant