Prior art keywords
reaming
plate
side wall
reaming plate
tube filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810945306.2A
Other languages
Chinese (zh)
Other versions
CN109056707B (en
Inventor
王基圣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chuzhou Chess Decoration Engineering Co Ltd
Original Assignee
Chuzhou Chess Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chuzhou Chess Decoration Engineering Co Ltd filed Critical Chuzhou Chess Decoration Engineering Co Ltd
Priority to CN201810945306.2A priority Critical patent/CN109056707B/en
Publication of CN109056707A publication Critical patent/CN109056707A/en
Application granted granted Critical
Publication of CN109056707B publication Critical patent/CN109056707B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of tube filling pedestal pile construction equipments, including hydraulic stem, electric pushrod, reaming plate and crushing rod, the outer wall of electric pushrod is fixedly installed circular guideway by rivet, guide rail is internally provided with sliding block, one end of sliding block offers through-hole setting gag lever post, and the outside of gag lever post is socketed with two interlocking levers, one end of interlocking lever is connected to the upper end of reaming plate, one end side wall of reaming plate is provided with mounting plate, reaming plate is under the rotation of the second motor, broken scrape is carried out to primitive soil in the pore-forming of reaming plate contact, and the setting of the heeling condition because of reaming plate, the primitive soil scraped can be crushed to carry, after club-footed pile process finishing, primitive soil can be driven to the outside of hole stake, it ensure that the construction effect that hole-expanding pile is carried out to pore-forming, improve the work processed using club-footed pile equipment Efficiency.

Description

A kind of tube filling pedestal pile construction equipment
Technical field
The present invention relates to underground engineering equipment technical field more particularly to a kind of tube filling pedestal pile construction equipments.
Background technique
With the fast development of construction industry, each metropolitan high buildings and large mansions are rised sheer from level ground, and skyscraper is to foundation bearing capacity Requirement it is also higher and higher.In order to increase bearing capacity of single pile, club-footed pile is used often to reduce the distribution density and drop of foundation pile Low cost, bottom-expanding equipment come into being.Nevertheless, previous bottom-expanding equipment is not well positioned to meet the base expanding and base expanding of driven cast-in-place pile It needs, and bottom-expanding equipment mostly constructs that accuracy is poor, and construction effect and control ability are low.
Summary of the invention
Mostly constructing the purpose of the present invention is to solve bottom-expanding equipment existing in the prior art, accuracy is poor, and construction is imitated Fruit and the low disadvantage of control ability, and a kind of tube filling pedestal pile construction equipment proposed.
To achieve the goals above, present invention employs following technical solutions:
A kind of tube filling pedestal pile construction equipment, including hydraulic stem, electric pushrod, reaming plate and crushing rod, it is described electronic to push away The outer wall of bar is fixedly installed circular guideway by rivet, and the guide rail is internally provided with sliding block, and one end of the sliding block is opened Gag lever post is set equipped with through-hole, and the outside of gag lever post is socketed with two interlocking levers, one end of the interlocking lever is connected to reaming The upper end of plate, one end side wall of the reaming plate is provided with mounting plate, and the upper end of mounting plate is provided with admittedly by screw buckle Determine block, and the side wall hinges of fixed block are connected with connecting rod, one end hinges of the connecting rod are connected with fixed block, And one end of fixed block is arranged in the upper end of bearing frame, the bearing frame is internally provided with first motor, first motor it is defeated Outlet is connected with crushing rod.
Preferably, there are four sliding blocks for the internal slide connection of the guide rail, and one end side wall of sliding block offers screw thread Gag lever post is arranged in hole, and the equal movable sleeve in the outside of gag lever post is connected to interlocking lever.
Preferably, one end of the interlocking lever offers through-hole and is plugged with fixed link, and the threaded one end of fixed link connects It connects in the inside of reaming plate.
Preferably, the upper end side wall of the sliding block is fixedly installed gear frame, and one end connection of gear frame by screw In the output end of the second motor, the inside of rack is arranged in the second motor, and the upper end side wall of rack is provided with hydraulic stem.
Preferably, the outer wall of the bearing frame is fixed with round sliding rail by rivet, and the side walls of sliding rail are connected with Four fixed blocks, the equal hinges of the side wall of fixed block are connected with connecting rod, and the equal hinges in one end of connecting rod are connected with solid Determine block, the base end wall of mounting plate is arranged in fixed block, and the upper end that the reaming plate is arranged in is welded in one end of mounting plate.
Preferably, one end of the crushing rod is connected to the output end of first motor, and the bottom of crushing rod by shaft coupling End welding is provided with crushing shell.
The beneficial effects of the present invention are:
1, of the invention, pass through hydraulic stem, electric pushrod.Sliding block, circular guideway, connecting rod, reaming plate, gear frame and interlocking lever etc. The setting of structure, reaming plate under the rotation of the second motor, to primitive soil in the pore-forming of reaming plate contact carry out it is broken scrape, and And the setting of the heeling condition because of reaming plate, the primitive soil scraped can be crushed and carried, after club-footed pile process finishing, The outside that primitive soil can be driven to hole stake, ensure that the construction effect for carrying out hole-expanding pile to pore-forming, improves and utilize club-footed pile The working efficiency that equipment is processed.
2, of the invention, pass through hydraulic stem, electric pushrod.Sliding block, circular guideway, connecting rod, reaming plate, gear frame and gearing The isostructural setting of bar, electric pushrod do stretching motion after being powered, make connecting rod under the connection of fixed block and mounting plate, will push away The adjustment variation of dynamic reaming plate tilt angle, increases the position angle between reaming plate and connecting rod, starts the second motor band The rotation of dynamic gear frame, interlocks the rotation of sliding block and reaming plate, carries out one end side wall of reaming plate in bottom stake side wall from contact Club-footed pile processing is rotated, the increase in stake space at the bottom of when making to process pore-forming hole-expanding pile.
Detailed description of the invention
Fig. 1 is a kind of forward sight structural schematic diagram of tube filling pedestal pile construction equipment proposed by the present invention;
Fig. 2 is a kind of present invention looks up structural representation of tube filling pedestal pile construction equipment proposed by the present invention;
Fig. 3 is a kind of overlooking structure diagram of the crushing rod of tube filling pedestal pile construction equipment proposed by the present invention.
In figure: 1 hydraulic stem, 2 racks, 3 electric pushrods, 4 sliding blocks, 5 connecting rods, 6 reaming plates, 7 bearing frames, 8 crushing rods, 9 first motors, 10 mounting plates, 11 interlocking levers, 12 guide rails, 13 gear frames, 14 second motors.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Embodiment 1: referring to Fig.1-3, the upper end side wall of a kind of tube filling pedestal pile construction equipment, sliding block 4 passes through screw It is fixedly installed gear frame 13, and one end of gear frame 13 is connected to the output end of the second motor 14, the setting of the second motor 14 exists The inside of rack 2, the upper end side wall of rack 2 are provided with hydraulic stem 1, and hydraulic stem 1 is the drilling machine for being connected to club-footed pile processing On, drilling machine can drive the movement of club-footed pile equipment, set club-footed pile in the case where that can do the connection of hydraulic stem 1 of stretching motion Club-footed pile processing is carried out for the inside for being moved to pore-forming is driven, under the drive of flexible hydraulic stem 1, moves club-footed pile equipment It moves to the bottom position of pore-forming, then first motor 9 and motor start simultaneously, and first motor 9 will drive crushing rod 8 and crushing shell Rotation, broken perforation processing is carried out to the bottom end primitive soil of pore-forming, and in the case where hydraulic stem 1 does the promotion slowly stretched, do to The expansion stake in downside direction is processed, and coupled frame movement will be driven after the starting of the second motor 14, coupled frame is made to drive four sliding blocks 4 along circle Shape guide rail 12 moves in a circle, and the rotation of sliding block 4 drives the rotation of reaming plate 6, reaming plate 6 under the connection of interlocking lever 11 The rotation of connecting rod 5 is driven, connecting rod 5 drives the fixed block of one end hinges connection to move in a circle around circular guideway 12, Make reaming plate 6 under the rotation of the second motor 14, primitive soil be crushed and is scraped in the pore-forming contacted to reaming plate 6, and because The setting of the heeling condition of reaming plate 6 can be crushed the primitive soil scraped and be carried, can after club-footed pile process finishing Primitive soil to be driven to the outside of hole stake, it ensure that the construction effect for carrying out hole-expanding pile to pore-forming, improve and set using club-footed pile The standby working efficiency processed.
Embodiment 2: referring to Fig.1-3, a kind of tube filling pedestal pile construction equipment, bearing frame 7 is internally provided with first Motor 9, the output end of first motor 9 are connected with crushing rod 8, and one end of crushing rod 8 is connected to first motor 9 by shaft coupling Output end, and the bottom end welding of crushing rod 8 is provided with crushing shell, first motor 9 turns while driving crushing rod 8 and crushing shell It is dynamic, drilling processing is carried out to the bottom end plane of pore-forming, crushing shell plays effect broken in advance to the bottom end plane of pore-forming, is broken Guiding is played the role of in broken 8 club-footed pile of bar processing, and crushing rod 8 is allow efficiently to carry out broken add to the bottom end primitive soil of pore-forming Work is improved the continuous effective for carrying out base expanding and base expanding processing to pore-forming using club-footed pile equipment.
Embodiment 3: referring to Fig.1-3, a kind of tube filling pedestal pile construction equipment, the outer wall of electric pushrod 3 passes through rivet It is fixedly installed circular guideway 12, there are four sliding blocks 4 for the internal slide connection of guide rail 12, and one end side wall of sliding block 4 opens up There is threaded hole that gag lever post is set, the equal movable sleeve in the outside of gag lever post is connected to interlocking lever 11, and one end of interlocking lever 11 offers logical Hole is plugged with fixed link, and the threaded one end of fixed link is connected to the inside of reaming plate 6, and one end side wall of reaming plate 6 is provided with Mounting plate 10, and the upper end of mounting plate 10 is provided with fixed block, and the side wall hinges connection of fixed block by screw buckle There is connecting rod 5, one end hinges of connecting rod 5 are connected with fixed block, and one end of fixed block is snapped connection by screw The outer wall of the upper end of bearing frame 7, bearing frame 7 is fixed with round sliding rail by rivet, and there are four the side walls connections of sliding rail Fixed block, and the equal hinges of side wall of fixed block are connected with connecting rod 5, the equal hinges in one end of connecting rod 5 are connected with solid Determine block, the base end wall of mounting plate 10 is arranged in fixed block, and the upper end that reaming plate 6 is arranged in is welded in one end of mounting plate 10.
Interlocking lever 11 plays the role of connection to sliding block 4 and reaming plate 6, pushes away in the connecting rod 5 that reaming plate 6 is fixed length When dynamic, reaming plate 6 will do the adjustment of angle around fixed link, when being crushed the increase of angle to primitive soil to reaming plate 6, first will Second motor 14 stops operating, and stretching motion is done after so that electric pushrod 3 is powered, and drives the rising of 7 position of bearing frame, bearing frame 7 After the adjustment of position, the movement of fixed block will be driven, fixed block drives the variation of 5 tilt angle of connecting rod of hinges connection, Make connecting rod 5 under the connection of fixed block and mounting plate 10, the adjustment of 6 tilt angle of reaming plate will be pushed to change, make reaming plate 6 Position angle between connecting rod 5 increases, and then by 3 power down process of electric pushrod, protects the angle adjusted of reaming plate 6 It holds, the second motor 14 of starting drives the rotation of gear frame 13, interlocks the rotation of sliding block 4 and reaming plate 6, makes one end of reaming plate 6 Side wall carries out rotation club-footed pile processing, the increase in stake space at the bottom of when making to process pore-forming hole-expanding pile in bottom stake side wall from contact.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", It is " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " suitable The orientation or positional relationship of the instructions such as hour hands ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, merely to just In description the present invention and simplify description, rather than the equipment of indication or suggestion meaning or element must have a particular orientation, with Specific orientation construction and operation, therefore be not considered as limiting the invention.
In addition, term " first ", " second " are used for description purposes only, it is not understood to indicate or imply relatively important Property or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Person implicitly includes one or more of the features.In the description of the present invention, the meaning of " plurality " is two or two with On, unless otherwise specifically defined.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (6)

1. a kind of tube filling pedestal pile construction equipment, including hydraulic stem (1), electric pushrod (3), reaming plate (6) and crushing rod (8), which is characterized in that the outer wall of the electric pushrod (3) is fixedly installed circular guideway (12), the guide rail by rivet (12) be internally provided with sliding block (4), one end of the sliding block (4) offer through-hole setting gag lever post, and the outside of gag lever post There are two interlocking lever (11) for socket, and one end of the interlocking lever (11) is connected to the upper end of reaming plate (6), the reaming plate (6) One end side wall be provided with mounting plate (10), and the upper end of mounting plate (10) is provided with fixed block by screw buckle, and fixed The side wall hinges of block are connected with connecting rod (5), and one end hinges of the connecting rod (5) are connected with fixed block, and solid The one end for determining block is arranged in the upper end of bearing frame (7), and the bearing frame (7) is internally provided with first motor (9), first motor (9) output end is connected with crushing rod (8).
2. a kind of tube filling pedestal pile construction equipment according to claim 1, which is characterized in that the guide rail (12) There are four sliding block (4) for internal slide connection, and one end side wall of sliding block (4) offers threaded hole setting gag lever post, gag lever post The equal movable sleeve in outside be connected to interlocking lever (11).
3. a kind of tube filling pedestal pile construction equipment according to claim 2, which is characterized in that the interlocking lever (11) One end offer through-hole and be plugged with fixed link, and the threaded one end of fixed link is connected to the inside of reaming plate (6).
4. a kind of tube filling pedestal pile construction equipment according to claim 1, which is characterized in that the sliding block (4) Upper end side wall is fixedly installed gear frame (13) by screw, and one end of gear frame (13) is connected to the defeated of the second motor (14) Outlet, the second motor (14) are arranged in the inside of rack (2), and the upper end side wall of rack (2) is provided with hydraulic stem (1).
5. a kind of tube filling pedestal pile construction equipment according to claim 1, which is characterized in that the bearing frame (7) Outer wall round sliding rail is fixed with by rivet, and the side walls connection of sliding rail, there are four fixed block, the side wall of fixed block is equal Hinges are connected with connecting rod (5), and the equal hinges in one end of connecting rod (5) are connected with fixed block, and fixed block setting is being pacified The base end wall of loading board (10), one end of mounting plate (10), which is welded, to be arranged in the upper end of the reaming plate (6).
6. a kind of tube filling pedestal pile construction equipment according to claim 1, which is characterized in that the crushing rod (8) One end the output ends of first motor (9) is connected to by shaft coupling, and the bottom end welding of crushing rod (8) is provided with crushing shell.
CN201810945306.2A 2018-08-20 2018-08-20 Immersed tube filling pedestal pile construction equipment Active CN109056707B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810945306.2A CN109056707B (en) 2018-08-20 2018-08-20 Immersed tube filling pedestal pile construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810945306.2A CN109056707B (en) 2018-08-20 2018-08-20 Immersed tube filling pedestal pile construction equipment

Publications (2)

Publication Number Publication Date
CN109056707A true CN109056707A (en) 2018-12-21
CN109056707B CN109056707B (en) 2021-01-26

Family

ID=64686478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810945306.2A Active CN109056707B (en) 2018-08-20 2018-08-20 Immersed tube filling pedestal pile construction equipment

Country Status (1)

Country Link
CN (1) CN109056707B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958327A (en) * 2021-10-20 2022-01-21 中铁六局集团有限公司 Shield tunneling machine underground diaphragm wall construction device and construction method thereof
CN117780250A (en) * 2024-02-26 2024-03-29 山东海盛海洋工程集团有限公司 Immersed tube filling club-footed pile construction equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101153488A (en) * 2006-09-26 2008-04-02 王国奋 Bottom-expanding and piling method for immersed tube bottom-expanding pile
CN104179173A (en) * 2014-08-12 2014-12-03 福建工程学院 Pile pipe extrusion reamer
CN107060649A (en) * 2017-03-09 2017-08-18 上海工程机械厂有限公司 A kind of reaming rig

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101153488A (en) * 2006-09-26 2008-04-02 王国奋 Bottom-expanding and piling method for immersed tube bottom-expanding pile
CN104179173A (en) * 2014-08-12 2014-12-03 福建工程学院 Pile pipe extrusion reamer
CN107060649A (en) * 2017-03-09 2017-08-18 上海工程机械厂有限公司 A kind of reaming rig

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958327A (en) * 2021-10-20 2022-01-21 中铁六局集团有限公司 Shield tunneling machine underground diaphragm wall construction device and construction method thereof
CN113958327B (en) * 2021-10-20 2024-03-29 中铁六局集团有限公司 Construction device and construction method for shield tunneling machine underground diaphragm wall
CN117780250A (en) * 2024-02-26 2024-03-29 山东海盛海洋工程集团有限公司 Immersed tube filling club-footed pile construction equipment
CN117780250B (en) * 2024-02-26 2024-06-11 山东海盛海洋工程集团有限公司 Immersed tube filling club-footed pile construction equipment

Also Published As

Publication number Publication date
CN109056707B (en) 2021-01-26

Similar Documents

Publication Publication Date Title
CN109056707A (en) A kind of tube filling pedestal pile construction equipment
CN214833559U (en) Beam column connection structure is built in room
CN105128151A (en) Anti-precipitating stirring slurry tank for aerated block production
CN104674873B (en) A kind of metamorphic mechanisms formula can casting excavator
CN207360860U (en) A kind of construction site steel pipe fixture
CN216551925U (en) Constructional engineering pile equipment
CN114622648A (en) Steel construction connecting piece that combination connection formula can buckle each other
CN208966197U (en) A kind of housing construction foundation pile drilling equipment
CN215658801U (en) Steel pipe welding device for civil engineering construction
CN108978621A (en) One kind preventing inclined rigid and flexible pile composite foundation
CN209050023U (en) A kind of construction site formed reinforcing steel bars device
CN203654263U (en) Drain board inserting equipment
CN107999664A (en) It is a kind of that there is the angle bender of compound bending
CN106760652B (en) A kind of construction site equipment radical occlusion device
CN216477392U (en) Subway shield segment horizontal assembling machine
CN104278823A (en) Wall plastering device
CN205637510U (en) Quick -witted special orientation lever of plastering wall
CN220599709U (en) Movable device for supporting side slope of dam
CN220890109U (en) Building engineering foundation ditch construction soil perforating device
CN220815070U (en) Steel frame with adjusting structure
CN216465515U (en) Agitating unit is used in polyisocyanurate foam production
CN215565782U (en) Telescopic drill rod and multifunctional telescopic high-pressure rotary jet drilling machine
CN210917316U (en) Foundation reinforcing and repairing device
CN221031658U (en) Civil engineering support column
CN116398056B (en) Efficient intelligent pore-forming system for soil body and application method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 239000 room 613, block C, 1999 Fung Road, Chuzhou, Anhui (Changjiang Fortune Plaza).

Applicant after: Anhui Qiran Construction Technology Co., Ltd

Address before: 239000 room 613, block C, 1999 Fung Road, Chuzhou, Anhui (Changjiang Fortune Plaza).

Applicant before: CHUZHOU QIRAN DECORATION ENGINEERING Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant