CN109056526A CN201810786277.XA CN201810786277A CN109056526A CN 109056526 A CN109056526 A CN 109056526A CN 201810786277 A CN201810786277 A CN 201810786277A CN 109056526 A CN109056526 A CN 109056526A
Authority
CN
China
Prior art keywords
steel wire
fiber grating
parallel steel
tapered sleeve
wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810786277.XA
Other languages
Chinese (zh)
Inventor
周成顺
曾利
宋强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Anchor Polytron Technologies Inc
Original Assignee
Zhejiang Anchor Polytron Technologies Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Anchor Polytron Technologies Inc filed Critical Zhejiang Anchor Polytron Technologies Inc
Priority to CN201810786277.XA priority Critical patent/CN109056526A/en
Publication of CN109056526A publication Critical patent/CN109056526A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of HiAm anchorage of parallel steel wire intelligence rope provided by the invention, comprising: more parallel steel wires;Positioned at parallel steel wire side and inner couplings have the intelligent steel wire of fiber grating;Anchor cup, inside are equipped with several fixing sleeves and tapered sleeve;Fixation hole is equipped in the fixing sleeve, the fixation hole and parallel steel wire one end are interference fitted;Mounting hole is equipped in the tapered sleeve, the mounting hole and intelligent steel wire are interference fitted.The HiAm anchorage that the present invention solves existing parallel steel wire intelligence rope fixes parallel steel wire, bothersome defect that is laborious, being easy error using wire sub-panel.

Description

A kind of HiAm anchorage and production method of parallel steel wire intelligence rope
Technical field
The present invention relates to bridge construction fields, and in particular to a kind of HiAm anchorage and production method of parallel steel wire intelligence rope.
Background technique
Parallel steel wire cable body is to be parallel to each other to tie up and coating outer cover is formed using more steel wires, and actual loading is internal Steel wire realize.Currently, common monitoring method has: pressure rings monitoring method, magnetic flux transducer monitoring method, hydraulic biography Sensor monitoring method.But to the load-bearing monitor of cable systems be a need measure for a long time and real-time monitoring work, need to examine Consider durability, survival rate and the stability of monitoring devices.Existing monitoring devices belongs to greatly anchorage additional article, higher cost, Volume increases after installation.With the development of technology, fiber grating gradually applies in the monitoring of parallel steel wire rope.
Such as patent: a kind of parallel steel wire bridge intelligence suspension cable (number of patent application: CN201710237787.7;Publication number: CN107059619A) and patent: a kind of parallel steel wire intelligence suspension cable (number of patent application: CN201710237788.1;It is open Number: a kind of intracorporal steel wire surface setting groove of parallel steel wire rope CN107144387A) is disclosed, optical fiber light is set in groove Grid are realized suspension cable real-time monitoring, while can also be protected to fiber grating.The mode proposed solves fiber grating and exists Laying survival rate and service life in steel wire, improve the range of fiber grating.
But fiber grating is to be coupled into inside steel wire, and the sub-wire in HiAm anchorage manufacturing process and pier nose process need at present Behaviour is carried out to the end of steel wire to do, and steel wire end is made to generate certain deformation, to the optical fiber light being coupled into high tensile steel wire Grid can generate very big destruction.Therefore a kind of packaging system of the fiber grating wire jumper of parallel steel wire intelligence rope is needed to propose.
Summary of the invention
(1) technical problems to be solved
It is an object of the present invention to provide a kind of HiAm anchorages of parallel steel wire intelligence rope, solve the cold of parallel steel wire intelligence rope The destruction in anchor encapsulation journey to the pier nose process of steel wire end to intelligent steel wire end is cast, while fiber grating can be damaged, is reduced Laying survival rate and service life of the fiber grating in steel wire, reduces the defect of the range of fiber grating.
It is a further object to provide a kind of novel parallel steel wire HiAm anchorages, solve existing novel parallel steel Silk HiAm anchorage fixes parallel steel wire, bothersome defect that is laborious, being easy error using wire sub-panel.
It is a further object to provide a kind of HiAm anchorages of parallel steel wire intelligence rope, solve existing in pier nose During, steel wire end can be by certain damage, and pier nose quality always will appear difference, will lead to the anchoring efficiency of steel wire not It is sufficient and variant between each other, to generate stress unevenness, lacked to what the pouring quality tool of chill casting had a certain impact It falls into.
Of the invention a further object is provides a kind of HiAm anchorage of parallel steel wire intelligence rope, solves intelligent steel wire and is pacifying It is easy when filling tapered sleeve to the defect to the issuable destruction of fiber grating.
Of the invention a further object is provides a kind of HiAm anchorage of parallel steel wire intelligence rope, solves fiber grating from steel After silk end is drawn, the defect of destruction is easily generated due to by shearing force.
Of the invention a further object is provides a kind of HiAm anchorage of parallel steel wire intelligence rope, solves fiber grating and is making Make to be easy the defect destroyed with transport work progress.
(2) technical solution
In order to solve the above technical problem, the present invention provides a kind of parallel steel wire intelligence rope HiAm anchorage, comprising: more are parallel Steel wire;Positioned at parallel steel wire side and inner couplings have the intelligent steel wire of fiber grating;Anchor cup, inside are equipped with several fixing sleeves And tapered sleeve;Fixation hole is equipped in the fixing sleeve, the fixation hole and parallel steel wire one end are interference fitted;It is equipped in the tapered sleeve Mounting hole, the mounting hole and intelligent steel wire are interference fitted.
In a first aspect, the intelligent steel wire of coupling fiber grating is handled after passing through wire sub-panel without pier nose, replace Be to be slightly less than the tapered sleeve of intelligent steel wire diameter using internal diameter to be interference fitted, when making HiAm anchorage, tapered sleeve need to only be penetrated Steel wire end will not damage fiber grating, improve laying survival rate and service life of the fiber grating in steel wire, expand The big range of fiber grating.Wherein, tapered sleeve and intelligent steel wire are interference fit, assemble the circumference stress of generation as intelligent steel wire Anchor force is provided, while tapered sleeve provides protection for the fiber grating of end.More preferably, magnitude of interference is less than on fiber grating The spacing on surface and intelligent steel wire surface, to guarantee that fiber grating will not be contacted in tapered sleeve installation process, so as to cause optical fiber The fracture of grating.
Currently, largely with parallel wire stay system as its main bearing member, Yi Taoping in Bridges in Our Country engineering Row wire digging line system mainly bears the load of structure with cable body and both ends anchorage.Parallel wire stay system is as bridge An important component in engineering, production are typically all to be made in workshop in specialized factory, by steel wire essence Manufacture crafts, the last reels such as true blanking, steel wire row silk twisting, extrusion molding, HiAm anchorage perfusion transport to engineering site.
The essential step as parallel wire stay manufacture craft is perfused in HiAm anchorage, and fabrication cycle and production quality are serious Production Time and the quality of parallel steel wire oblique pull cable system are restrict, to influence the construction procedure of science of bridge building, and to whole The safety of a bridge generates strong influence.
Currently used HiAm anchorage mainly by: anchor cup, wire sub-panel, chill casting filler etc. form.Anchorage is packed into rope when production In body, steel wire is respectively penetrated in the corresponding hole location of wire sub-panel, and carries out pier nose processing in the end of steel wire, finally carries out chill casting The perfusion of material.
In the filling process of HiAm anchorage, steel wire, which penetrates wire sub-panel this process, will expend a lot of manpower and time, When especially parallel steel wire quantity increases, and during wearing silk, steel wire fallibility hole is done over again, and need to be taken a substantial amount of time.
The HiAm anchorage that the present invention solves existing parallel steel wire intelligence rope fixes parallel steel wire using wire sub-panel, bothersome Arduously, it is easy the defect of error.This invention also solves parallel steel wire HiAm anchorages in the prior art during filling anchor, and steel wire is worn The problem of steel wire and wire sub-panel corresponding aperture dislocation position are done over again when entering wire sub-panel, provides a kind of novel parallel steel wire HiAm anchorage, and every Steel wire is inserted in the fixing sleeve that diameter is slightly less than steel wire in a free state, mutually indepedent between fixing sleeve, pre-tightens it in axial force There is no limit effect, each steel wire may be at optimum position for the preceding radial position to steel wire, when having avoided wire sub-panel structure, because It misdraws hole location and leads to the case where frequently doing over again.
Second aspect, existing during pier nose, steel wire end can be by certain damage, and pier nose quality always goes out Existing difference, the anchoring efficiency that will lead to steel wire is insufficient and variant between each other, so that stress unevenness is generated, to chill casting Pouring quality tool have a certain impact.This invention also solves parallel steel wire HiAm anchorages in the prior art in the process for filling anchor In, when steel wire end carries out pier nose operation, damage and pier nose qualitative difference to steel wire end, and the anchoring of steel wire is caused to be imitated The problem of rate and stress unevenness, provides a kind of novel parallel steel wire HiAm anchorage, and every steel wire only need to be inserted in internal diameter in end It is slightly less than the fixing sleeve of steel wire, is connected between fixing sleeve and steel wire for interference, be not required to again operate steel wire ontology, avoid The damage of steel wire, when parallel steel wire cable body blanking, every steel wire length is consistent, and internal diameter is slightly less than the ruler of the fixing sleeve of steel wire It is very little to be also consistent, therefore can guarantee that the stress of every steel wire is consistent.
Preferably, the lateral surface of the fixing sleeve is truncated cone-shaped, and the outer diameter of bottom end is greater than top outer diameter;The anchor cup Inner sidewall at least locally has the conical surface compatible with fixing sleeve lateral surface;The fixation hole penetrates through fixing sleeve;The tapered sleeve packet Include rotary table section and cylindrical section, the biggish one end connecting cylinder section of the outer diameter of the rotary table section.On the other hand, " the inner sidewall of anchor cup At least part has the conical surface compatible with fixing sleeve lateral surface " with reference to first aspect, change the interior coning angle of existing anchor cup, matches Conjunction fixing sleeve forms the auto-lock anchorage to parallel wire unit and intelligent steel wire end.
Preferably, cylindrical section one end of the tapered sleeve has hollow out section, has hollow hole in the hollow out section.More preferably, By fiber grating wire jumper direction be positioned as with the same axial direction of fiber grating inside steel wire, and epoxy is filled to tapered sleeve inside Resin treatment positions fiber grating and is protected, and failure by shear is prevented.
Preferably, the intelligent steel wire is equipped with groove, and the groove is for coupling fiber grating;When installation, the light Fine grating diameter is lower than the depth of groove.With reference to first aspect, the top of groove is lower than at the top of setting fiber grating, so that optical fiber Grating is fully packaged into groove, enhances the protection to light grating, more preferably, epoxide-resin glue, filling is filled in groove Height is lower than the height of adjacent bare fibre section, and difference in height is the thickness of sheath.The structure ensure that fiber grating in steel wire Height in groove is consistent, to exclude the shearing force that fiber grating is generated by the difference in height of arrangement.The present invention is to cone Set is internal to be filled epoxy resin processing, is positioned and is protected to fiber grating, prevents failure by shear.
Preferably, the fiber grating includes free segment and bare wire section, and the free segment is equipped with high temperature resistant protective case;It is described Bare wire section is bare optical silk;The naked line end connects optical fiber jumper terminal.The third aspect, tapered sleeve one end cylinder of the invention The side of structure carries out hollow processing, when installation, first penetrates the lead-out wire of fiber grating by one end of non-hollow out, and from hollow out Place is drawn, and is further applied load to tapered sleeve end face, tapered sleeve is packed into intelligent steel cord end, hollow-out part protects fiber grating installing It will not be destroyed during tapered sleeve;Fiber grating is solved after steel wire end extraction, easily generates destruction due to by shearing force Defect.Meanwhile high temperature resistant protective case being housed on fiber grating surface, avoid the processing temperature pair in HiAm anchorage manufacturing process Its influence.Preferably, connecting cylinder is cased with outside the tapered sleeve end;The connecting cylinder is detachably connected tapered sleeve;The connecting cylinder Protection cap is cased with outside end;The protection cap is detachably connected connecting cylinder.Fourth aspect, the present invention is outside tapered sleeve by removable Fix a connecting cylinder with unloading, general using being threadedly coupled, more preferably, the overlapping region of the connecting cylinder and tapered sleeve is completely covered The hollow out section of tapered sleeve after installing connecting cylinder, fiber grating wire jumper direction is positioned as same with the fiber grating inside steel wire It is axial;Fiber grating is solved after steel wire end extraction, the defect of destruction is easily generated due to by shearing force.5th aspect, this Protection cap is arranged in invention outside connecting cylinder, general using being threadedly coupled with connecting cylinder by detachably connected, is in protection cap Optical patchcord or connector, the effect of protection cap are protection wire jumper and connector, prevent from meeting in production and transport work progress To destruction.
Preferably, the connecting cylinder bottom end is equipped with annular support surface, and the optical fiber jumper terminal is fixed on annular support surface; Sealing structure is formed between the protection cap and connecting cylinder;Filled with buffering material in gap between the bare wire section and tapered sleeve.
Preferably, the connecting cylinder is equipped with bottom plate, and the protection cap bottom is equipped with bottom plate, and the bottom plate is equipped with first Fiber grating through-hole;The bottom plate is equipped with the second fiber grating through-hole;The bare wire section is also cross the first fiber grating Through-hole and the second fiber grating through-hole;Filled with buffering material in gap between the bare wire section and tapered sleeve and connecting cylinder.
Preferably, chill casting material is filled in the anchor cup;The fixing sleeve side is equipped with sealing plate, and the sealing plate is for close Sealing off and covering anchorage cup;The anchor cup is recessed inwardly to form heavy platform far from one end of sealing plate, and the heavy platform is provided with constraint circle;In the anchor cup Wall has mounting groove, and the mounting groove is located at heavy platform side, and the fixing sleeve is located in mounting groove;The mounting groove internal diameter is by sealing It is gradually restrained to heavy platform one end plate one end.In the present invention, the steel wire beam diameter after expansion is greater than anchor cup material filling section, and cooperates anchor cup Interior coning angle, to guarantee that there are enough tension pulls out force in steel tendon end.
The invention also discloses a kind of production methods of the HiAm anchorage of parallel steel wire intelligence rope, comprising the following steps:
1) groove of the intelligent steel cord end of the coupling fiber grating in parallel steel wire intelligence rope is carried out it is expanding, and by the section and The fiber grating of free segment is inserted in protective case resistant to high temperature, later pastes the fiber grating comprising protective case in steel wire groove It is interior, keep optical fiber to be in sustained height;
2) after parallel steel wire penetrates anchor cup, the small one end of fixing sleeve diameter is penetrated in hawser body, big one end of diameter after installation Concordant with parallel steel wire distal end faces, the fixing sleeve being inserted in by parallel steel wire end expands parallel wire unit anchored end Diameter, the steel wire beam diameter after expansion is greater than anchor cup material filling section, to cooperate the interior coning angle of anchor cup.
3) the fiber grating wire jumper of intelligent steel wire end is penetrated from one end of tapered sleeve, is drawn from hollow out section, tapered sleeve is pacified It is attached to intelligent steel wire end;
4) connecting cylinder is protruded into tapered sleeve, the depth protruded at least will be more than the hollow out section of tapered sleeve, after protruding into, to fiber grating Wire jumper is positioned, and guarantees that wire jumper and groove inner fiber are in same axis direction, then using epoxide-resin glue in tapered sleeve Portion is filled;
5) excess fiber grating is cut off, there are the length for being adapted to fit fiber grating jumper terminal, install fiber grating wire jumper and connect Head, and jumper terminal progress position is fixed in the position that screws by adjusting connecting cylinder, and it is logical that cylinder end is reconnected after being installed Cross threaded connection protection cap;
6) protection cap and connecting cylinder are connected;
7) parallel steel wire penetrate fixing sleeve it is in place after, in parallel steel wire end and anchor cup far from installing anchor cup between steel wire side The sealing plate of close contact;
8) parallel wire unit after will be expanding is installed into anchor cup, be irrigated later chill casting material filling and vibration compacting, Solidification.
The invention also discloses the production methods of the HiAm anchorage of another parallel steel wire intelligence rope, comprising the following steps:
1) groove of the intelligent steel cord end of the coupling fiber grating in parallel steel wire intelligence rope is carried out it is expanding, and by the section and The fiber grating of free segment is inserted in protective case resistant to high temperature, is inserted in second layer protective layer again except fiber grating sheath;Later Fiber grating comprising protective case and second layer protective layer is pasted in steel wire groove, optical fiber is kept to be in sustained height;
2) after parallel steel wire penetrates anchor cup, the small one end of fixing sleeve diameter is penetrated in hawser body, big one end of diameter after installation Concordant with parallel steel wire distal end faces, the fixing sleeve being inserted in by parallel steel wire end expands parallel wire unit anchored end Diameter, the steel wire beam diameter after expansion is greater than anchor cup material filling section, to cooperate the interior coning angle of anchor cup;
3) the fiber grating wire jumper of intelligent steel wire end is penetrated from one end of tapered sleeve, is drawn from hollow out section, tapered sleeve is installed to Intelligent steel wire end;
4) connecting cylinder is protruded into tapered sleeve, the depth protruded at least will be more than the hollow out section of tapered sleeve, after protruding into, to fiber grating Wire jumper is positioned, and guarantees that wire jumper and groove inner fiber are in same axis direction, then using epoxide-resin glue in tapered sleeve Portion is filled;
5) installation that fiber grating wire jumper carries out jumper terminal after protection cap through-hole passes through when being mounted in connecting cylinder Adjust the overlap length of connecting cylinder and tapered sleeve, fixed jumper terminal;
6) protection cap and connecting cylinder are connected;
7) parallel steel wire penetrate fixing sleeve it is in place after, in parallel steel wire end and anchor cup far from installing anchor cup between steel wire side The sealing plate of close contact;
8) parallel wire unit after will be expanding is installed into anchor cup, be irrigated later chill casting material filling and vibration compacting, Solidification.
(3) beneficial effect
A kind of HiAm anchorage of parallel steel wire intelligence rope provided by the invention, has the advantage that
1, in a first aspect, the intelligent steel wire of coupling fiber grating is handled after passing through wire sub-panel without pier nose, instead It is to be slightly less than the tapered sleeve of intelligent steel wire diameter using internal diameter to be interference fitted, when making HiAm anchorage, only tapered sleeve need to be penetrated steel Silk end, will not damage fiber grating, improve laying survival rate and service life of the fiber grating in steel wire, expand The range of fiber grating.Wherein, tapered sleeve and intelligent steel wire are interference fit, assemble the circumference stress of generation and mention for intelligent steel wire Anchor force is supplied, while tapered sleeve provides protection for the fiber grating of end.More preferably, magnitude of interference is less than table on fiber grating The spacing in face and intelligent steel wire surface, to guarantee that fiber grating will not be contacted in tapered sleeve installation process, so as to cause optical fiber light The fracture of grid.
The HiAm anchorage that the present invention solves existing parallel steel wire intelligence rope fixes parallel steel wire using wire sub-panel, bothersome Arduously, it is easy the defect of error.This invention also solves parallel steel wire HiAm anchorages in the prior art during filling anchor, and steel wire is worn The problem of steel wire and wire sub-panel corresponding aperture dislocation position are done over again when entering wire sub-panel, provides a kind of novel parallel steel wire HiAm anchorage, and every Steel wire is inserted in the fixing sleeve that diameter is slightly less than steel wire in a free state, mutually indepedent between fixing sleeve, pre-tightens it in axial force There is no limit effect, each steel wire may be at optimum position for the preceding radial position to steel wire, when having avoided wire sub-panel structure, because It misdraws hole location and leads to the case where frequently doing over again.
Second aspect, existing during pier nose, steel wire end can be by certain damage, and pier nose quality always goes out Existing difference, the anchoring efficiency that will lead to steel wire is insufficient and variant between each other, so that stress unevenness is generated, to chill casting Pouring quality tool have a certain impact.This invention also solves parallel steel wire HiAm anchorages in the prior art in the process for filling anchor In, when steel wire end carries out pier nose operation, damage and pier nose qualitative difference to steel wire end, and the anchoring of steel wire is caused to be imitated The problem of rate and stress unevenness, provides a kind of novel parallel steel wire HiAm anchorage, and every steel wire only need to be inserted in internal diameter in end It is slightly less than the fixing sleeve of steel wire, is connected between fixing sleeve and steel wire for interference, be not required to again operate steel wire ontology, avoid The damage of steel wire, when parallel steel wire cable body blanking, every steel wire length is consistent, and internal diameter is slightly less than the ruler of the fixing sleeve of steel wire It is very little to be also consistent, therefore can guarantee that the stress of every steel wire is consistent.
Detailed description of the invention
Fig. 1 is the HiAm anchorage structural schematic diagram of the parallel steel wire intelligence rope of the embodiment of the present invention 1;
Fig. 2 is the partial enlargement structural representation of the A of Fig. 1 of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 1;
Fig. 3 is the part B partial enlargement structural representation of Fig. 2 of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 1 Figure;
Fig. 4 is the tapered sleeve structural schematic diagram of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 1;
Fig. 5 is the connecting cylinder structural schematic diagram of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 1;
Fig. 6 is the fixing sleeve the schematic diagram of the section structure of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 1;
Fig. 7 is the HiAm anchorage structural schematic diagram of the parallel steel wire intelligence rope of the embodiment of the present invention 2;
Fig. 8 is the protection cap structural schematic diagram of the HiAm anchorage of the parallel steel wire intelligence rope of the embodiment of the present invention 2.
1, parallel steel wire;2, intelligent steel wire;3, anchor cup;4, fixing sleeve;5, tapered sleeve;6, fixation hole;7, mounting hole;8, it bores Face;9, rotary table section;10, cylindrical section;11, hollow out section;12, hollow hole;13, groove;14, free segment;15, bare wire section;16, resistance to height Warm protective case;17, connecting cylinder;18, protection cap;19, annular support surface;21, buffering material;22, chill casting material;23, sealing plate;24, it sinks Platform;25, constraint circle;26, mounting groove;27, bottom plate;28, bottom plate;29, the first fiber grating through-hole;30, the second fiber grating Through-hole;31, optical fiber jumper terminal;32, fiber grating;33, the second protective case.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Following instance For illustrating the present invention, but it is not intended to limit the scope of the invention.
The bottom of fixing sleeve in the present invention is steel wire end side, otherwise is top, the mounting structure left side of comparative diagram 1 For bottom, right side is top.
Buffering material uses epoxy resin in the present invention.
Embodiment 1:
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6, a kind of HiAm anchorage of parallel steel wire intelligence rope provided by the invention, packet It includes: more parallel steel wires 1;Positioned at parallel steel wire side and inner couplings have the intelligent steel wire 2 of fiber grating 32;Anchor cup 3, it is internal Equipped with several fixing sleeves 4 and tapered sleeve 5;Fixation hole 6, the fixation hole and the interference of parallel steel wire one end are equipped in the fixing sleeve Cooperation;Mounting hole 7 is equipped in the tapered sleeve, the mounting hole and intelligent steel wire are interference fitted.
The magnitude of interference of tapered sleeve and intelligent steel wire is less than the spacing of fiber grating upper surface and intelligent steel wire surface, to guarantee Fiber grating will not be contacted in tapered sleeve installation process, so as to cause the fracture of fiber grating.
The lateral surface of the fixing sleeve is truncated cone-shaped, and the outer diameter of bottom end is greater than top outer diameter;The inner sidewall of the anchor cup At least part has the conical surface 8 compatible with fixing sleeve lateral surface;The fixation hole penetrates through fixing sleeve;The tapered sleeve includes rotary table Section 9 and cylindrical section 10, the biggish one end connecting cylinder section of the outer diameter of the rotary table section.
Cylindrical section one end of the tapered sleeve has hollow out section 11, has hollow hole 12 in the hollow out section.By fiber grating Wire jumper direction be positioned as with the same axial direction of fiber grating inside steel wire, and to tapered sleeve inside be filled epoxy resin processing, Fiber grating is positioned and is protected, failure by shear is prevented.
The intelligence steel wire is equipped with groove 13, and the groove is for coupling fiber grating;When installation, the fiber grating Diameter is lower than the depth of groove.Epoxide-resin glue is filled in groove, packed height is lower than the height of adjacent bare fibre section, high Degree difference is the thickness of sheath.
The fiber grating includes free segment 14 and bare wire section 15, and the free segment is equipped with high temperature resistant protective case 16;It is described Bare wire section is bare optical silk;The naked line end connects optical fiber jumper terminal 31.High temperature resistant protective case outer surface also has There is the second protective case 33.
Connecting cylinder 17 is cased with outside the tapered sleeve end;The connecting cylinder is threadedly coupled tapered sleeve;Connecting cylinder end housing There is protection cap 18;The protection cap is threadedly coupled connecting cylinder.Tapered sleeve is completely covered in the overlapping region of the connecting cylinder and tapered sleeve After installing connecting cylinder, fiber grating wire jumper direction is positioned as and the same axial direction of fiber grating inside steel wire for hollow out section.
The connecting cylinder bottom end is equipped with annular support surface 19, and the optical fiber jumper terminal is fixed on annular support surface;It is described Sealing structure is formed between protection cap and connecting cylinder;Filled with buffering material 21 in gap between the bare wire section and tapered sleeve.
Chill casting material 22 is filled in the anchor cup;The fixing sleeve side is equipped with sealing plate 23, and the sealing plate is for sealing Anchor cup;The anchor cup is recessed inwardly to form heavy platform 24 far from one end of sealing plate, and the heavy platform is provided with constraint circle 25;The anchor cup Inner wall has mounting groove 26, and the mounting groove is located at heavy platform side, and the fixing sleeve is located in mounting groove;The mounting groove internal diameter It is gradually restrained from sealing plate one end to heavy platform one end.
When the embodiment of the present invention is implemented, when HiAm anchorage makes, after parallel wire unit penetrates anchor cup, light is not coupled at every The parallel steel wire end of fine grating is all installed by fixing sleeve.When fixing sleeve is installed, major diameter is penetrated by rotary table diameter minor diameter direction Direction, after being installed, fixing sleeve major diameter end face is concordant with parallel steel wire distal end faces.
It couples and is inserted in protective case, while this section of steel wire outside the intelligent steel wire end section fiber grating and free segment of fiber grating Set groove carries out expansion processing, and the depth and width of groove meet the fiber grating wire jumper comprising protective case is complete Comprising into the filling of epoxide-resin glue in intelligent steel wire body, is first carried out in groove, packed height is lower than the height of adjacent bare wire section, Its difference in height is the thickness of sheath.
After the processing of intelligent steel wire is completed, fiber grating wire jumper is penetrated from tapered sleeve one end first and from the hollow out of hollow out section Place is pierced by, and logical tapered sleeve is crossed imposed load and will be installed to steel wire end, and charge weight is the rotary table section of tapered sleeve, and is no more than engraving for tapered sleeve Dead band.Fiber grating wire jumper is drawn from tapered sleeve hollow out section, penetrates connecting cylinder, and connecting cylinder and tapered sleeve are screwed by screw thread, And the hollow out section of tapered sleeve be contained in connecting cylinder and tapered sleeve screw section, jumper location adjustment is drawn as with intelligent steel wire end The section same axial location of fiber grating fills epoxide-resin glue inside tapered sleeve and fiber grating wire jumper is fixed and is protected. Excess fiber grating is cut off, there are the length for being adapted to fit fiber grating jumper terminal, fiber grating jumper terminal is installed, and lead to Screwing for connecting cylinder is overregulated, position is carried out to jumper terminal by connecting cylinder supporting surface and is fixed, reconnects cylinder after being installed End is connected through a screw thread protection cap.
After every steel wire of parallel wire unit installs tapered sleeve, end diameter will expand, the parallel steel after will be enlarged by Tow is inserted in anchor cup, and the cone angle on the inside of anchor cup is cooperated to anchor parallel wire unit.After parallel wire unit installation is in place, Novel HiAm anchorage is irrigated and fills chill casting material, the operation such as vibration compacting, solidification.
Embodiment 2:
As shown in Figure 7, Figure 8, a kind of HiAm anchorage of parallel steel wire intelligence rope provided by the invention, comprising: more parallel steel wires;Position In parallel steel wire side and inner couplings have the intelligent steel wire of fiber grating;Anchor cup, inside are equipped with several fixing sleeves and tapered sleeve; Fixation hole is equipped in the fixing sleeve, the fixation hole and parallel steel wire one end are interference fitted;Mounting hole is equipped in the tapered sleeve, The mounting hole and intelligent steel wire are interference fitted.
The magnitude of interference of tapered sleeve and intelligent steel wire is less than the spacing of fiber grating upper surface and intelligent steel wire surface, to guarantee Fiber grating will not be contacted in tapered sleeve installation process, so as to cause the fracture of fiber grating.
The lateral surface of the fixing sleeve is truncated cone-shaped, and the outer diameter of bottom end is greater than top outer diameter;The inner sidewall of the anchor cup At least part has the conical surface compatible with fixing sleeve lateral surface;The fixation hole penetrates through fixing sleeve;The tapered sleeve includes rotary table Section and cylindrical section, the biggish one end connecting cylinder section of the outer diameter of the rotary table section.
Cylindrical section one end of the tapered sleeve has hollow out section, has hollow hole in the hollow out section.By fiber grating wire jumper Direction be positioned as with the same axial direction of fiber grating inside steel wire, and to tapered sleeve inside be filled epoxy resin processing, to light Fine grating is positioned and is protected, and failure by shear is prevented.
The intelligence steel wire is equipped with groove, and the groove is for coupling fiber grating;When installation, the fiber grating is straight Diameter is lower than the depth of groove.Epoxide-resin glue is filled in groove, packed height is lower than the height of adjacent bare fibre section, height Difference is the thickness of sheath.
The fiber grating includes free segment and bare wire section, and the free segment is equipped with high temperature resistant protective case;The bare wire section For bare optical silk;The naked line end connects optical fiber jumper terminal.High temperature resistant protective case outer surface also has the second guarantor Sheath.
Connecting cylinder is cased with outside the tapered sleeve end;The connecting cylinder is threadedly coupled tapered sleeve;It is cased with outside the connecting cylinder end Protection cap;The protection cap is threadedly coupled connecting cylinder.The hollow out of tapered sleeve is completely covered in the overlapping region of the connecting cylinder and tapered sleeve Section, after installing connecting cylinder, fiber grating wire jumper direction is positioned as and the same axial direction of fiber grating inside steel wire.
The connecting cylinder is equipped with bottom plate 27, and the protection cap bottom is equipped with bottom plate 28, and the bottom plate is equipped with the first light Fine grating through-hole 29;The bottom plate is equipped with the second fiber grating through-hole 30;The bare wire section is also cross the first optical fiber light Grid through-hole and the second fiber grating through-hole;Filled with buffering material in gap between the bare wire section and tapered sleeve and connecting cylinder.
Chill casting material is filled in the anchor cup;The fixing sleeve side is equipped with sealing plate, and the sealing plate is for sealing anchor cup; The anchor cup is recessed inwardly to form heavy platform far from one end of sealing plate, and the heavy platform is provided with constraint circle;The anchor cup inner wall has Mounting groove, the mounting groove are located at heavy platform side, and the fixing sleeve is located in mounting groove;The mounting groove internal diameter is by sealing plate one end It is gradually restrained to heavy platform one end.
When the embodiment of the present invention is implemented, with embodiment the difference is that: fiber grating is drawn wire jumper and is increased, and optical fiber After grating wire jumper is drawn from tapered sleeve hollow out position, it is inserted in second layer protective layer again except fiber grating sheath, connecting cylinder is installed Fiber grating position is fixed afterwards and fiber grating is not wiped out to being filled after epoxide-resin glue in tapered sleeve;Protection cap end Portion opens up through-hole, and fiber grating wire jumper passes through the installation of progress jumper terminal after protection cap through-hole, ring is perfused inside connecting cylinder 5 Oxygen resin glue, remaining structure are installed with embodiment 1.
Embodiment 3
The invention also discloses a kind of production methods of the HiAm anchorage of parallel steel wire intelligence rope, comprising the following steps:
1) groove of the intelligent steel cord end of the coupling fiber grating in parallel steel wire intelligence rope is carried out it is expanding, and by the section and The fiber grating of free segment is inserted in protective case resistant to high temperature, later pastes the fiber grating comprising protective case in steel wire groove It is interior, keep optical fiber to be in sustained height;
2) after parallel steel wire penetrates anchor cup, the small one end of fixing sleeve diameter is penetrated in hawser body, big one end of diameter after installation Concordant with parallel steel wire distal end faces, the fixing sleeve being inserted in by parallel steel wire end expands parallel wire unit anchored end Diameter, the steel wire beam diameter after expansion is greater than anchor cup material filling section, to cooperate the interior coning angle of anchor cup.
3) the fiber grating wire jumper of intelligent steel wire end is penetrated from one end of tapered sleeve, is drawn from hollow out section, tapered sleeve is pacified It is attached to intelligent steel wire end;
4) connecting cylinder is protruded into tapered sleeve, the depth protruded at least will be more than the hollow out section of tapered sleeve, after protruding into, to fiber grating Wire jumper is positioned, and guarantees that wire jumper and groove inner fiber are in same axis direction, then using epoxide-resin glue in tapered sleeve Portion is filled;
5) excess fiber grating is cut off, there are the length for being adapted to fit fiber grating jumper terminal, install fiber grating wire jumper and connect Head, and jumper terminal progress position is fixed in the position that screws by adjusting connecting cylinder, and it is logical that cylinder end is reconnected after being installed Cross threaded connection protection cap;
6) protection cap and connecting cylinder are connected;
7) parallel steel wire penetrate fixing sleeve it is in place after, in parallel steel wire end and anchor cup far from installing anchor cup between steel wire side The sealing plate of close contact;
8) parallel wire unit after will be expanding is installed into anchor cup, be irrigated later chill casting material filling and vibration compacting, Solidification.
Embodiment 4:
The invention also discloses the production methods of the HiAm anchorage of another parallel steel wire intelligence rope, comprising the following steps:
1) groove of the intelligent steel cord end of the coupling fiber grating in parallel steel wire intelligence rope is carried out it is expanding, and by the section and The fiber grating of free segment is inserted in protective case resistant to high temperature, is inserted in second layer protective layer again except fiber grating sheath;Later Fiber grating comprising protective case and second layer protective layer is pasted in steel wire groove, optical fiber is kept to be in sustained height;
2) after parallel steel wire penetrates anchor cup, the small one end of fixing sleeve diameter is penetrated in hawser body, big one end of diameter after installation Concordant with parallel steel wire distal end faces, the fixing sleeve being inserted in by parallel steel wire end expands parallel wire unit anchored end Diameter, the steel wire beam diameter after expansion is greater than anchor cup material filling section, to cooperate the interior coning angle of anchor cup;
3) the fiber grating wire jumper of intelligent steel wire end is penetrated from one end of tapered sleeve, is drawn from hollow out section, tapered sleeve is installed to Intelligent steel wire end;
4) connecting cylinder is protruded into tapered sleeve, the depth protruded at least will be more than the hollow out section of tapered sleeve, after protruding into, to fiber grating Wire jumper is positioned, and guarantees that wire jumper and groove inner fiber are in same axis direction, then using epoxide-resin glue in tapered sleeve Portion is filled;
5) installation that fiber grating wire jumper carries out jumper terminal after protection cap through-hole passes through when being mounted in connecting cylinder Adjust the overlap length of connecting cylinder and tapered sleeve, fixed jumper terminal;
6) protection cap and connecting cylinder are connected;
7) parallel steel wire penetrate fixing sleeve it is in place after, in parallel steel wire end and anchor cup far from installing anchor cup between steel wire side The sealing plate of close contact;
8) parallel wire unit after will be expanding is installed into anchor cup, be irrigated later chill casting material filling and vibration compacting, Solidification.
The various embodiments described above are merely to illustrate the present invention, wherein the structure of each component, connection type etc. are all can be Variation, all equivalents and improvement carried out based on the technical solution of the present invention should not be excluded of the invention Except protection scope.

Claims (10)

1. a kind of HiAm anchorage of parallel steel wire intelligence rope characterized by comprising
More parallel steel wires;
Positioned at parallel steel wire side and inner couplings have the intelligent steel wire of fiber grating;
Anchor cup, inside are equipped with several fixing sleeves and tapered sleeve;It is equipped with fixation hole in the fixing sleeve, the fixation hole and parallel steel Silk one end interference fit;Mounting hole is equipped in the tapered sleeve, the mounting hole and intelligent steel wire are interference fitted.
2. the HiAm anchorage of parallel steel wire intelligence rope as described in claim 1, which is characterized in that the lateral surface of the fixing sleeve is The outer diameter of truncated cone-shaped, bottom end is greater than top outer diameter;The inner sidewall of the anchor cup at least locally has and fixing sleeve lateral surface phase The conical surface of adaptation;The fixation hole penetrates through fixing sleeve;The tapered sleeve includes rotary table section and cylindrical section, the outer diameter of the rotary table section compared with Big one end connecting cylinder section.
3. the HiAm anchorage of parallel steel wire intelligence rope as described in claim 1, which is characterized in that cylindrical section one end of the tapered sleeve With hollow out section, there is hollow hole in the hollow out section.
4. the HiAm anchorage of parallel steel wire intelligence rope as described in claim 1, which is characterized in that the intelligence steel wire is equipped with recessed Slot, the groove is for coupling fiber grating;When installation, the fiber grating diameter is lower than the depth of groove.
5. the HiAm anchorage of parallel steel wire intelligence rope as described in claim 1, which is characterized in that the fiber grating includes freely Section and bare wire section, the free segment are equipped with high temperature resistant protective case;The bare wire section is bare optical silk;The naked line end connection Optical fiber jumper terminal.
6. the HiAm anchorage of the parallel steel wire intelligence rope as described in claims 1 or 2 or 3 or 4 or 5, which is characterized in that the tapered sleeve Connecting cylinder is cased with outside end;The connecting cylinder is detachably connected tapered sleeve;Protection cap is cased with outside the connecting cylinder end;The protection Lid is detachably connected connecting cylinder.
7. the HiAm anchorage of parallel steel wire intelligence rope as claimed in claim 6, which is characterized in that the connecting cylinder bottom end is equipped with ring Shape supporting surface, the optical fiber jumper terminal are fixed on annular support surface;Sealing structure is formed between the protection cap and connecting cylinder; Filled with buffering material in gap between the bare wire section and tapered sleeve.
8. the HiAm anchorage of parallel steel wire intelligence rope as claimed in claim 6, which is characterized in that the connecting cylinder is equipped with bottom plate, The protection cap bottom is equipped with bottom plate, and the bottom plate is equipped with the first fiber grating through-hole;The bottom plate is equipped with second Fiber grating through-hole;The bare wire section is also cross the first fiber grating through-hole and the second fiber grating through-hole;The bare wire section Filled with buffering material in gap between tapered sleeve and connecting cylinder.
9. the HiAm anchorage of the parallel steel wire intelligence rope as described in claims 1 or 2 or 3 or 4 or 5, which is characterized in that the anchor cup It is interior to be filled with chill casting material;The fixing sleeve side is equipped with sealing plate, and the sealing plate is for sealing anchor cup;The anchor cup is far from sealing plate One end be recessed inwardly to form heavy platform, the heavy platform is provided with constraint circle;The anchor cup inner wall has mounting groove, the mounting groove Positioned at heavy platform side, the fixing sleeve is located in mounting groove;The mounting groove internal diameter is gradually received from sealing plate one end to heavy platform one end It holds back.
10. a kind of production method of the HiAm anchorage of parallel steel wire intelligence rope, which is characterized in that the parallel steel wire intelligence rope it is cold Cast the HiAm anchorage that anchor is parallel steel wire intelligence rope described in claim 1 to 9 any one claim;The following steps are included:
1) groove of the intelligent steel cord end of the coupling fiber grating in parallel steel wire intelligence rope is carried out it is expanding, and by the section and The fiber grating of free segment is inserted in protective case resistant to high temperature, later pastes the fiber grating comprising protective case in steel wire groove It is interior, keep optical fiber to be in sustained height;
2) after parallel steel wire penetrates anchor cup, the small one end of fixing sleeve diameter is penetrated in hawser body, big one end of diameter after installation Concordant with parallel steel wire distal end faces, the fixing sleeve being inserted in by parallel steel wire end expands parallel wire unit anchored end Diameter, the parallel steel wire beam diameter after expansion is greater than anchor cup material filling section, to cooperate the interior coning angle of anchor cup;
3) the fiber grating wire jumper of intelligent steel wire end is penetrated from one end of tapered sleeve, is drawn from hollow out section, tapered sleeve is installed to Intelligent steel wire end;
4) connecting cylinder is protruded into tapered sleeve, the depth protruded at least will be more than the hollow out section of tapered sleeve, after protruding into, to fiber grating Wire jumper is positioned, and guarantees that wire jumper and groove inner fiber are in same axis direction, then using epoxide-resin glue in tapered sleeve Portion is filled;
5) fiber grating end install fiber grating jumper terminal, when being mounted in connecting cylinder, by adjust connecting cylinder with The overlap length of tapered sleeve, fixed jumper terminal;
6) protection cap and connecting cylinder are connected;
7) parallel steel wire penetrate fixing sleeve it is in place after, in parallel steel wire end and anchor cup far from installing anchor cup between steel wire side The sealing plate of close contact;
8) parallel wire unit after will be expanding is installed into anchor cup, be irrigated later chill casting material filling and vibration compacting, Solidification.
CN201810786277.XA 2018-07-17 2018-07-17 A kind of HiAm anchorage and production method of parallel steel wire intelligence rope Pending CN109056526A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810786277.XA CN109056526A (en) 2018-07-17 2018-07-17 A kind of HiAm anchorage and production method of parallel steel wire intelligence rope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810786277.XA CN109056526A (en) 2018-07-17 2018-07-17 A kind of HiAm anchorage and production method of parallel steel wire intelligence rope

Publications (1)

Publication Number Publication Date
CN109056526A true CN109056526A (en) 2018-12-21

Family

ID=64816925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810786277.XA Pending CN109056526A (en) 2018-07-17 2018-07-17 A kind of HiAm anchorage and production method of parallel steel wire intelligence rope

Country Status (1)

Country Link
CN (1) CN109056526A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110306430A (en) * 2019-07-27 2019-10-08 浙锚科技股份有限公司 A kind of perception parallel steel wire HiAm anchorage and production method certainly
CN110847038A (en) * 2019-12-22 2020-02-28 智性纤维复合加固南通有限公司 Self-sensing parallel steel wire inhaul cable and manufacturing method thereof
CN110939062A (en) * 2019-12-22 2020-03-31 智性纤维复合加固南通有限公司 Self-sensing extrusion inhaul cable and manufacturing method thereof
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Method for manufacturing polymer rubber-insulated-wire fiber grating strain sensor and intelligent cable
CN113513122A (en) * 2021-03-22 2021-10-19 广东坚宜佳五金制品有限公司 Hot-cast anchor of intelligent steel strand inhaul cable and manufacturing method
CN114526685A (en) * 2022-02-15 2022-05-24 柳州欧维姆机械股份有限公司 Replaceable fiber grating intelligent inhaul cable and replacement method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200992682Y (en) * 2006-12-29 2007-12-19 柳州欧维姆机械股份有限公司 Cold-cast pier anchor cable implanting optical fiber grating reinforced smart bars
CN102392414A (en) * 2011-09-01 2012-03-28 江苏法尔胜泓昇集团有限公司 Intelligent cable rope for bridge
CN203049919U (en) * 2013-01-18 2013-07-10 杭州浙锚预应力有限公司 Epoxy coating steel strand anchoring structure
CN106121134A (en) * 2016-08-29 2016-11-16 智性纤维复合加固南通有限公司 A kind of optical fiber built-in FRP muscle leading-out wire protective structure and preparation method thereof
WO2016203649A1 (en) * 2015-06-19 2016-12-22 東京製綱株式会社 Continuous fiber-reinforced material tensioning device, tensioning method for continuous fiber-reinforced material, and wedge body
CN106908909A (en) * 2017-04-26 2017-06-30 桂林理工大学 A kind of intelligent steel strand End optical fibers joint package connector and its installation method
CN107675835A (en) * 2017-10-24 2018-02-09 桂林理工大学 A kind of compound anchorage and its anchoring construction method
CN107740297A (en) * 2017-11-14 2018-02-27 浙锚科技股份有限公司 Intelligence extruding drag-line and preparation method based on filled-type epoxy coating strand
CN207498830U (en) * 2017-11-09 2018-06-15 浙锚科技股份有限公司 A kind of filling anchor plugging structure of fixing end chill casting anchorage

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200992682Y (en) * 2006-12-29 2007-12-19 柳州欧维姆机械股份有限公司 Cold-cast pier anchor cable implanting optical fiber grating reinforced smart bars
CN102392414A (en) * 2011-09-01 2012-03-28 江苏法尔胜泓昇集团有限公司 Intelligent cable rope for bridge
CN203049919U (en) * 2013-01-18 2013-07-10 杭州浙锚预应力有限公司 Epoxy coating steel strand anchoring structure
WO2016203649A1 (en) * 2015-06-19 2016-12-22 東京製綱株式会社 Continuous fiber-reinforced material tensioning device, tensioning method for continuous fiber-reinforced material, and wedge body
CN106121134A (en) * 2016-08-29 2016-11-16 智性纤维复合加固南通有限公司 A kind of optical fiber built-in FRP muscle leading-out wire protective structure and preparation method thereof
CN106908909A (en) * 2017-04-26 2017-06-30 桂林理工大学 A kind of intelligent steel strand End optical fibers joint package connector and its installation method
CN107675835A (en) * 2017-10-24 2018-02-09 桂林理工大学 A kind of compound anchorage and its anchoring construction method
CN207498830U (en) * 2017-11-09 2018-06-15 浙锚科技股份有限公司 A kind of filling anchor plugging structure of fixing end chill casting anchorage
CN107740297A (en) * 2017-11-14 2018-02-27 浙锚科技股份有限公司 Intelligence extruding drag-line and preparation method based on filled-type epoxy coating strand

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110306430A (en) * 2019-07-27 2019-10-08 浙锚科技股份有限公司 A kind of perception parallel steel wire HiAm anchorage and production method certainly
CN110306430B (en) * 2019-07-27 2024-05-24 浙锚科技股份有限公司 Self-sensing parallel steel wire cold cast anchor and manufacturing method thereof
CN110847038A (en) * 2019-12-22 2020-02-28 智性纤维复合加固南通有限公司 Self-sensing parallel steel wire inhaul cable and manufacturing method thereof
CN110939062A (en) * 2019-12-22 2020-03-31 智性纤维复合加固南通有限公司 Self-sensing extrusion inhaul cable and manufacturing method thereof
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Method for manufacturing polymer rubber-insulated-wire fiber grating strain sensor and intelligent cable
CN111442735B (en) * 2020-04-03 2022-05-31 广西大学 Method for manufacturing polymer rubber-insulated-wire fiber grating strain sensor and intelligent cable
CN113513122A (en) * 2021-03-22 2021-10-19 广东坚宜佳五金制品有限公司 Hot-cast anchor of intelligent steel strand inhaul cable and manufacturing method
CN114526685A (en) * 2022-02-15 2022-05-24 柳州欧维姆机械股份有限公司 Replaceable fiber grating intelligent inhaul cable and replacement method thereof

Similar Documents

Publication Publication Date Title
CN109056526A (en) A kind of HiAm anchorage and production method of parallel steel wire intelligence rope
CN200992682Y (en) Cold-cast pier anchor cable implanting optical fiber grating reinforced smart bars
CN107740297B (en) Intelligent extrusion inhaul cable based on filled epoxy coating steel strand and manufacturing method
CN108221670B (en) Intelligent parallel steel wire rope suitable for stay ropes, suspension ropes and hanging rod ropes
KR20020063507A (en) Device for anchoring one end of a stay to a base
CN101787676B (en) Method for assembling cable built-in fiber bragg grating strain transducer
CN209211276U (en) A kind of HiAm anchorage of parallel steel wire intelligence rope
CN111075487A (en) Anchor rod with function of measuring surrounding rock strain and temperature coupling
CN110835864A (en) Intelligent inhaul cable with replaceable monitoring element and manufacturing, installing and constructing method thereof
CN110258299B (en) Tapered anti-slip key anchoring steel strand inhaul cable with fork lugs and construction method thereof
CN209353151U (en) A kind of smart stay cable of interchangeable monitoring element
CN201614548U (en) Mounting structure of built-in fiber grating strain transducer of cable
CN108035254A (en) Carbon fiber cable-cabin structure
CN208717746U (en) Carbon fiber oblique pull cable system
CN216157693U (en) Hollow grouting intelligent anchor rod
CN109024274A (en) A kind of novel parallel steel wire HiAm anchorage and preparation method thereof
CN109024273A (en) A kind of leaded packages and production method of parallel steel wire intelligence rope
CN113638759A (en) Hollow grouting intelligent anchor rod and installation and layout method thereof
CN203065966U (en) Partially cable-stayed bridge sub-wire tube cable saddle capable of resisting slippage of steel strands of stay cable
CN209211275U (en) A kind of novel parallel steel wire HiAm anchorage
CN211571399U (en) Self-sensing parallel steel wire inhaul cable
US20220205209A1 (en) Foundation Structure of an Offshore Structure With a Transmission Cable and a Protection Element
CN102745093B (en) Ratchet wheel compensation mechanism for overhead line system of electrified railway and design method
CN101864725B (en) FRP (Fiber Reinforce Plastic) tendon and steel strand connector and compound stay cable
CN201738241U (en) FRP rib and steel strand connector and composite inhaul cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Changle

Inventor after: Cha Yu

Inventor after: Zhou Chengshun

Inventor after: Zeng Li

Inventor after: Song Qiang

Inventor after: Hu Yaoqing

Inventor before: Zhou Chengshun

Inventor before: Zeng Li

Inventor before: Song Qiang

CB03 Change of inventor or designer information
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221

RJ01 Rejection of invention patent application after publication