CN109025293A - A kind of slab side form post-cast strip erection method - Google Patents
A kind of slab side form post-cast strip erection method Download PDFInfo
- Publication number
- CN109025293A CN109025293A CN201810849209.3A CN201810849209A CN109025293A CN 109025293 A CN109025293 A CN 109025293A CN 201810849209 A CN201810849209 A CN 201810849209A CN 109025293 A CN109025293 A CN 109025293A
- Authority
- CN
- China
- Prior art keywords
- hose
- cast strip
- post
- muscle
- side form
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The present invention relates to the realm of building construction more particularly to a kind of slab side form post-cast strip erection methods, comprising the following steps: (1) designs plank thickness in the alter-pouring strips mould plate construction drawing of 300mm or more;(2) preparation of construction: preparation hose, flitch, multi-layer board, inflator pump, air inflation nozzle and hose clamp;(3) reinforcing bar binds and installs hose: carrying out binding gluten and bottom muscle according to the alter-pouring strips mould plate construction drawing of design, and hose is mounted in the air column installation cavity bound out between bottom muscle and gluten;(4) hose is fixed, is inflated: hose being fixed, and completes to block with air inflation nozzle by the both ends of hose by hose clamp, completes the inflation of hose by inflator pump to form the air column for playing the role of side form;(5) concreting: the concreting at position other than slab post-cast strip region is completed;(6) demoulding, hose are deflated, are extracted out;(7) hose cleaning, recycling.The air column formed after being inflated using hose obstructs concrete, has haved the function that side form.
Description
Technical field
The present invention relates to the realm of building construction more particularly to a kind of slab side form post-cast strip erection methods.
Background technique
In order to meet the needs of social development demand at this stage, especially building function and appearance and modeling, engineering construction rule
Mould also gradually expands, also higher and higher to the overall structure quality requirement of engineering works.At this stage, it in post empiricism, adopts
Formwork erection is carried out with wooden model or steel wire, template occurs and is difficult to fix, is easy the problems such as quick-fried mould, spillage, poor molding effect.
Construction technology is obviously unable to do what one wishes, gradually highlights the necessity of construction technology innovation.
Summary of the invention
The purpose of the present invention is to provide a kind of slab side form post-cast strip erection method, the gas formed after being inflated using hose
Column obstructs concrete, has haved the function that side form.
Technical program of the present invention lies in: a kind of slab side form post-cast strip erection method, comprising the following steps:
(1) alter-pouring strips mould plate construction drawing of the design plank thickness in 300mm or more;
(2) preparation of construction: preparation hose, flitch, multi-layer board, inflator pump, air inflation nozzle and hose clamp;
(3) reinforcing bar binds and installs hose: carrying out binding gluten and bottom muscle according to the alter-pouring strips mould plate construction drawing of design, and will be soft
Pipe is mounted in the air column installation cavity bound out between bottom muscle and gluten;
(4) hose is fixed, is inflated: hose being fixed, and completes to block with air inflation nozzle by the both ends of hose by hose clamp, is led to
It overcharges air pump and completes the inflation of hose to form the air column for playing the role of side form;
(5) concreting: the concreting at position other than slab post-cast strip region is completed;
(6) demoulding, hose are deflated, are extracted out;
(7) hose cleaning, recycling.
Further, in the step (3), when slab plate thickness is first laid with lower template in 300 ~ 500mm, and in lower die
Bottom muscle is bound on the upside of plate, and a pair of of wood is provided between bottom muscle and lower template and on the downside of the region for being used to form post-cast strip
Item;Steel bar rack is installed on the muscle of bottom and positioned at the upside of a pair of of batten, and in the setting of the outside of Steel bar rack and Steel bar rack
Between formed air column installation cavity limit steel bar;Hose is mounted on from bottom to top in air column installation cavity;Gluten is bound, and in face
The upside of muscle and be located at air column installation cavity above flitch is respectively set.
Further, the Steel bar rack is arranged by the reinforcing bar of diameter 14mm by 500mm spacing;The limit steel bar
It is arranged by the reinforcing bar that diameter is 10mm by 1000mm spacing.
Further, in the step (3), when in slab have steel plate for sealing water: preset bed course recess portion be laid with waterproof
Coiled material, bed course upside bind bottom muscle, and between waterproof roll and bottom muscle and be located at be used to form under the region of post-cast strip
Side is provided with a pair of of concrete item;One Steel bar rack is set on the muscle of bottom and positioned at the upside of a pair of of concrete item, and in Steel bar rack two sides
The upper end in portion is respectively arranged with the steel plate for sealing water of a cantilever position;The lower end of steel plate for sealing water and a U-shaped steel muscle anchor ear is mutually welded,
And two superimposed hoses are installed respectively in the downside of steel plate for sealing water and U-shaped steel muscle anchor ear;Gluten is bound, and on gluten
And it is located above U-shaped steel muscle anchor ear and is respectively arranged with flitch.
Further, the Steel bar rack is arranged by the reinforcing bar of diameter 14mm by 500mm spacing, the U-shaped steel muscle
Anchor ear is arranged by the U-shaped steel muscle of diameter 10mm by 500mm spacing.
Further, described when seal plate is more than 300mm with the height of lower portion, it heads in the concrete of steel plate for sealing water
Side need to add concrete side Steel bar rack, and the concrete side Steel bar rack is arranged by the reinforcing bar of diameter 10mm by 500mm spacing
It forms.
Further, the hose is containing double-layer polyester fiber reinforcing mat and surface has the hose of PVC coating, institute
The diameter for stating hose is 50mm, 80mm or 100mm;Number three or more of the hose;The blowing pressure of the hose is less than
Or it is equal to 0.6 Mpa.
Further, in the step (6), demoulding is carried out after concrete reaches initial setting strength, hose can not when demoulding
Brute-force pulls out, and after hose need to be deflated, first moves the hose to post-cast strip middle position and extracts out again.
Further, in the step (7), the hose removed after taking out is cleaned up with clear water, is returned after drying
It receives.
Compared with prior art, the invention has the following advantages that hose is inflated after being installed with air pump, inflation
When extrusion packing reinforcing bar of the hose by upper and lower reinforcing bar caused by gap, the air column formed after being inflated using hose carries out concrete
Barrier, has haved the function that side form, the frame structure, frame instead of traditional steel wire, wooden model, suitable for plate thickness 300-500mm
The designs such as frame shear wall structure, shear wall structure have in the engineering construction of post-cast strip.And when disturbing concrete, it is less prone to drum
Phenomena such as packet, spillage, good forming effect are not required to manually to chisel cleaning bulge and spillage, time saving and energy saving, save cost advantages in applying
The raising of working medium amount;The usual comparatively dense of reinforcing bar especially at post-cast strip is met at reinforcing bar, does not need to punch or small with fixation
Batten form is in one line, as long as hose is filled with to gas after passing through between post-cast strip bottom muscle and gluten can complete to pacify
Dress, installation is simple, and it is convenient to construct, and saves the duration;Concreting completion bleeds off gas in hose after reaching initial setting strength, extracts out
Hose completes demoulding, removes and is easy;It can reuse, improve the number of turnover, reduce construction cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the embodiment of the present invention one;
Fig. 2 is the structural schematic diagram of the embodiment of the present invention two.
Specific embodiment
To make the foregoing features and advantages of the present invention clearer and more comprehensible, special embodiment below, and cooperate attached drawing, make detailed
It is carefully described as follows, but the present invention is not limited thereto.
Embodiment one refers to Fig. 1
A kind of slab side form post-cast strip erection method, comprising the following steps:
(1) alter-pouring strips mould plate construction drawing of the design plank thickness in 300mm or more;
(2) preparation of construction: preparation hose, flitch, multi-layer board, inflator pump, air inflation nozzle and hose clamp;
(3) reinforcing bar binds and installs hose: carrying out binding gluten and bottom muscle according to the alter-pouring strips mould plate construction drawing of design, and will be soft
Pipe is mounted in the air column installation cavity bound out between bottom muscle and gluten;
(4) hose is fixed, is inflated: hose being fixed, and completes to block with air inflation nozzle by the both ends of hose by hose clamp, is led to
It overcharges air pump and completes the inflation of hose to form the air column for playing the role of side form, it is ensured that is existing without spillage and race mould when concreting
As;
(5) concreting: the concreting at position other than slab post-cast strip region is completed;
(6) demoulding, hose are deflated, are extracted out;
(7) hose cleaning, recycling.
In the present embodiment, in the step (3), when slab plate thickness a is in 300 ~ 500mm, it is first laid with lower template 1, and
Bottom muscle 2 is bound on the upside of lower template, is provided between bottom muscle and lower template and positioned at being used to form on the downside of the region of post-cast strip 20
A pair of of batten 3, for use in stuff up a crack;Steel bar rack 4 is installed on the muscle of bottom and positioned at the upside of a pair of of batten, and in Steel bar rack
Outside setting Steel bar rack between formed air column installation cavity limit steel bar 5;4 hoses 6 are mounted on gas from bottom to top
In column installation cavity;Gluten 7 is bound, and flitch 8 is respectively set in the upside of gluten and above air column installation cavity, with after an action of the bowels
For intercepting concrete when phase concreting.Post-cast strip is formed between two limit steel bars, reinforcing bar penetrates through in the plate of post-cast strip.
In the present embodiment, the Steel bar rack is arranged by the reinforcing bar of diameter 14mm by 500mm spacing, thus to air column
It is reinforced;The limit steel bar is arranged by the reinforcing bar that diameter is 10mm by 1000mm spacing, prevents air column in concrete
It is fallen before pouring.
In the present embodiment, the hose is containing double-layer polyester fiber reinforcing mat and surface has the hose of PVC coating,
The diameter of the hose is 50mm, 80mm or 100mm, wall thickness 1.0mm;The blowing pressure of the hose is less than or equal to 0.6
Mpa prevents the excessive hose explosion of pressure.
In the present embodiment, in the step (4), it need to be inflated and fix again after the completion of gluten is bound.
In the present embodiment, in the step (6), demoulding is carried out after concrete reaches initial setting strength, hose is not when demoulding
Can brute-force pull out, after hose need to be deflated, first move the hose to post-cast strip middle position and extract out again, two limits are located in slab
Region between reinforcing bar is post-cast strip.
In the present embodiment, in the step (7), the hose removed after taking out is cleaned up with clear water, after drying
Recycling, to reuse.
Embodiment two refers to Fig. 2
A kind of slab side form post-cast strip erection method, comprising the following steps:
(1) alter-pouring strips mould plate construction drawing of the design plank thickness in 300mm or more;
(2) preparation of construction: preparation hose, flitch, multi-layer board, inflator pump, air inflation nozzle and hose clamp;
(3) reinforcing bar binds and installs hose: carrying out binding gluten and bottom muscle according to the alter-pouring strips mould plate construction drawing of design, and will be soft
Pipe is mounted in the air column installation cavity bound out between bottom muscle and gluten;
(4) hose is fixed, is inflated: hose being fixed, and completes to block with air inflation nozzle by the both ends of hose by hose clamp, is led to
It overcharges air pump and completes the inflation of hose to form the air column for playing the role of side form, it is ensured that is existing without spillage and race mould when concreting
As;
(5) concreting: the concreting at position other than slab post-cast strip region is completed;
(6) demoulding, hose are deflated, are extracted out;
(7) hose cleaning, recycling.
In the present embodiment, in the step (3), when in slab have steel plate for sealing water 10: in preset 11 recess portion 12 of bed course
Laying water-proof coiled material 13 binds bottom muscle 2 in the upside of bed course, and pours between waterproof roll and bottom muscle and after being used to form
A pair of of concrete item 14 is provided on the downside of the region of band;One Steel bar rack 4 of upside setting on the muscle of bottom and positioned at a pair of of concrete item, and
The upper end of Steel bar rack both sides is respectively arranged with the steel plate for sealing water of a cantilever position;By steel plate for sealing water and a U-shaped steel muscle anchor ear
15 lower end is mutually welded, and installs two superimposed hoses 6 respectively in the downside of steel plate for sealing water and U-shaped steel muscle anchor ear;It ties up
Gluten 7 is pricked, and is respectively arranged with flitch 8 on gluten and above U-shaped steel muscle anchor ear, when so as to later period concreting
For intercepting concrete.To form post-cast strip, reinforcing bar is penetrated through in the plate of post-cast strip.
In the present embodiment, the installation of hose is completed during need to being interspersed in reinforcement installation, can not before steel plate for sealing water installation
Air column is transferred, the electroslag and spark of steel plate welding are easily scorched.
In the present embodiment, the size of U-shaped steel muscle anchor ear should be suitably larger than the diameter of hose because hose inflation after by
It squeezes, actual size can be greater than former design size, the U-shaped steel muscle anchor ear with diameter such as be installed, after hose is completely sufficient
It can be squeezed askew, influence fixed effect.
In the present embodiment, the Steel bar rack is arranged by the reinforcing bar of diameter 14mm by 500mm spacing, the U-shaped steel
Muscle anchor ear is arranged by the U-shaped steel muscle of diameter 10mm by 500mm spacing.
It is described when seal plate is more than 300mm with the height of lower portion in the present embodiment, it is met in the concrete of steel plate for sealing water
Surface side need to add concrete side Steel bar rack described in concrete side Steel bar rack 16 by the reinforcing bar of diameter 10mm by 500mm spacing cloth
It sets.
In the present embodiment, the hose is containing double-layer polyester fiber reinforcing mat and surface has the hose of PVC coating,
The diameter of the hose is 80mm, wall thickness 1.0mm;The blowing pressure of the hose is less than or equal to 0.6 Mpa, prevents pressure mistake
Big hose explosion.
In the present embodiment, in the step (4), it need to be inflated and fix again after the completion of gluten is bound.
In the present embodiment, in the step (6), demoulding is carried out after concrete reaches initial setting strength, hose is not when demoulding
Can brute-force pull out, after hose need to be deflated, first move the hose to post-cast strip middle position and extract out again, two coagulations are located in slab
The region formed between native side Steel bar rack and U-shaped steel muscle anchor ear is post-cast strip.
In the present embodiment, in the step (7), the hose removed after taking out is cleaned up with clear water, after drying
Recycling, to reuse.
The foregoing is merely presently preferred embodiments of the present invention, for the ordinary skill in the art, according to this hair
Bright introduction designs a kind of various forms of slab side form post-cast strips erection method and does not need creative labor, not
The case where being detached from the principle and spirit of the invention is descended to the mortal world the equivalent change made according to scope of the present invention patent, modification, replacement
And modification, it is all covered by the present invention.
Claims (9)
1. a kind of slab side form post-cast strip erection method, which comprises the following steps:
(1) alter-pouring strips mould plate construction drawing of the design plank thickness in 300mm or more;
(2) preparation of construction: preparation hose, flitch, multi-layer board, inflator pump, air inflation nozzle and hose clamp;
(3) reinforcing bar binds and installs hose: carrying out binding gluten and bottom muscle according to the alter-pouring strips mould plate construction drawing of design, and will be soft
Pipe is mounted in the air column installation cavity bound out between bottom muscle and gluten;
(4) hose is fixed, is inflated: hose being fixed, and completes to block with air inflation nozzle by the both ends of hose by hose clamp, is led to
It overcharges air pump and completes the inflation of hose to form the air column for playing the role of side form;
(5) concreting: the concreting at position other than slab post-cast strip region is completed;
(6) demoulding, hose are deflated, are extracted out;
(7) hose cleaning, recycling.
2. a kind of slab side form post-cast strip according to claim 1 erection method, which is characterized in that in the step (3),
When slab plate thickness is in 300 ~ 500mm, be first laid with lower template, and bind bottom muscle on the upside of lower template, the bottom of at muscle and lower template it
Between and be located to be used to form on the downside of the region of post-cast strip and be provided with a pair of of batten;Upside peace on the muscle of bottom and positioned at a pair of of batten
Steel bar rack is filled, and forms the limit steel bar of air column installation cavity between the setting of the outside of Steel bar rack and Steel bar rack;It will be soft
Pipe is mounted on from bottom to top in air column installation cavity;Gluten is bound, and in the upside of gluten and positioned at the top of air column installation cavity point
It She Zhi not flitch.
3. a kind of slab side form post-cast strip according to claim 2 erection method, which is characterized in that the Steel bar rack by
The reinforcing bar of diameter 14mm is arranged by 500mm spacing;The limit steel bar presses 1000mm spacing by the reinforcing bar that diameter is 10mm
It arranges.
4. a kind of slab side form post-cast strip according to claim 1 erection method, which is characterized in that in the step (3),
When having steel plate for sealing water in slab: in preset bed course recess portion laying water-proof coiled material, binding bottom muscle in the upside of bed course, and anti-
A pair of of concrete item is provided between water coiled material and bottom muscle and positioned at being used to form on the downside of the region of post-cast strip;On the muscle of bottom and it is located at one
One Steel bar rack is arranged to the upside of concrete item, and is respectively arranged with the sealing of a cantilever position in the upper end of Steel bar rack both sides
Steel plate;The lower end of steel plate for sealing water and a U-shaped steel muscle anchor ear is mutually welded, and in the downside of steel plate for sealing water and U-shaped steel muscle anchor ear
Two superimposed hoses are installed respectively;Gluten is bound, and is respectively arranged on gluten and above U-shaped steel muscle anchor ear
Flitch.
5. a kind of slab side form post-cast strip according to claim 4 erection method, which is characterized in that the Steel bar rack by
The reinforcing bar of diameter 14mm is arranged that the U-shaped steel muscle anchor ear is by the U-shaped steel muscle of diameter 10mm by between 500mm by 500mm spacing
Away from arranging.
6. a kind of slab side form post-cast strip according to claim 4 or 5 erection method, which is characterized in that described to work as sealing
When plate is more than 300mm with the height of lower portion, concrete side Steel bar rack, institute need to be added in the concrete of steel plate for sealing water side of heading on
Concrete side Steel bar rack is stated to be arranged by the reinforcing bar of diameter 10mm by 500mm spacing.
7. a kind of according to claim 1, slab side form post-cast strip erection method described in 2,3,4 or 5, which is characterized in that described
Hose is containing double-layer polyester fiber reinforcing mat and surface has a hose of PVC coating, the diameter of the hose be 50mm,
80mm or 100mm;Number three or more of the hose;The blowing pressure of the hose is less than or equal to 0.6 Mpa.
8. a kind of according to claim 1, slab side form post-cast strip erection method described in 2,3,4 or 5, which is characterized in that described
In step (6), carry out demoulding after concrete reaches initial setting strength, when demoulding hose can not brute-force pull out, hose need to be deflated
Later, post-cast strip middle position is first moved the hose to extract out again.
9. a kind of according to claim 1, slab side form post-cast strip erection method described in 2,3,4 or 5, which is characterized in that described
In step (7), the hose removed after taking out is cleaned up with clear water, is recycled after drying.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810849209.3A CN109025293B (en) | 2018-07-28 | 2018-07-28 | Thick plate side mold post-cast strip supporting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810849209.3A CN109025293B (en) | 2018-07-28 | 2018-07-28 | Thick plate side mold post-cast strip supporting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109025293A true CN109025293A (en) | 2018-12-18 |
CN109025293B CN109025293B (en) | 2020-11-06 |
Family
ID=64646510
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810849209.3A Active CN109025293B (en) | 2018-07-28 | 2018-07-28 | Thick plate side mold post-cast strip supporting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109025293B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110374234A (en) * | 2019-07-19 | 2019-10-25 | 杭州三丰装配式建筑科技有限公司 | A kind of the cavity node structure and construction method of assembled wall and building frame |
CN111441576A (en) * | 2020-04-14 | 2020-07-24 | 中建四局第一建筑工程有限公司 | Method and structure for pouring concrete beam post-cast strip by adopting inflatable template |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102635128A (en) * | 2012-04-27 | 2012-08-15 | 天津二十冶建设有限公司 | Foundation slab post-cast strip waterproof steel plate combined structure and bracing method thereof |
CN106284427A (en) * | 2016-08-31 | 2017-01-04 | 中国冶集团有限公司 | A kind of basement post-pouring zone temporary leaking water gear soil construction method |
CN206128631U (en) * | 2016-10-10 | 2017-04-26 | 启东建筑集团有限公司 | Inflatable post -cast strip side form props up establishes structure |
KR20170138603A (en) * | 2016-06-07 | 2017-12-18 | 경희대학교 산학협력단 | the form unit of precast concrete joint and the construction method of form installing between column and girder using the same |
CN207484964U (en) * | 2017-11-03 | 2018-06-12 | 重庆建工第四建设有限责任公司 | Side form structure at post-cast strip in concrete pouring construction |
-
2018
- 2018-07-28 CN CN201810849209.3A patent/CN109025293B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102635128A (en) * | 2012-04-27 | 2012-08-15 | 天津二十冶建设有限公司 | Foundation slab post-cast strip waterproof steel plate combined structure and bracing method thereof |
KR20170138603A (en) * | 2016-06-07 | 2017-12-18 | 경희대학교 산학협력단 | the form unit of precast concrete joint and the construction method of form installing between column and girder using the same |
CN106284427A (en) * | 2016-08-31 | 2017-01-04 | 中国冶集团有限公司 | A kind of basement post-pouring zone temporary leaking water gear soil construction method |
CN206128631U (en) * | 2016-10-10 | 2017-04-26 | 启东建筑集团有限公司 | Inflatable post -cast strip side form props up establishes structure |
CN207484964U (en) * | 2017-11-03 | 2018-06-12 | 重庆建工第四建设有限责任公司 | Side form structure at post-cast strip in concrete pouring construction |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110374234A (en) * | 2019-07-19 | 2019-10-25 | 杭州三丰装配式建筑科技有限公司 | A kind of the cavity node structure and construction method of assembled wall and building frame |
CN110374234B (en) * | 2019-07-19 | 2024-04-09 | 杭州三丰装配式建筑科技有限公司 | Cavity node structure of assembled wall body and building frame and construction method |
CN111441576A (en) * | 2020-04-14 | 2020-07-24 | 中建四局第一建筑工程有限公司 | Method and structure for pouring concrete beam post-cast strip by adopting inflatable template |
Also Published As
Publication number | Publication date |
---|---|
CN109025293B (en) | 2020-11-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207484964U (en) | Side form structure at post-cast strip in concrete pouring construction | |
CN101832026B (en) | Construction method of sole plate post-poured strip form bracing system | |
CN204703498U (en) | Wall of High-building deformation joint template construction structure | |
CN103938870B (en) | The synchronous pouring construction method of a kind of light weight concrete construction and ordinary concrete | |
CN208220197U (en) | A kind of adjustable type assembled hoard strip hangs mold device | |
CN106760496A (en) | A kind of floor beam plate post-cast strip template support system and its construction method | |
CN109025293A (en) | A kind of slab side form post-cast strip erection method | |
CN201486133U (en) | Reinforced concrete double-shear wall template | |
CN110284704A (en) | A kind of Assembled Building board post poured band formwork edge joint structure and its construction method | |
CN107905424A (en) | Full prefabricated band splicing groove unidirectional harden structure, making and assembly method | |
CN204781960U (en) | High -rise building shear force wall movement joint department template is propped up and is established and reinforcement system | |
CN207619807U (en) | Cast-in-situ concrete hollow slab beam and its core model supporting construction | |
CN206888509U (en) | A kind of box culvert plate outer side template reinforcing device | |
CN106049704B (en) | Prefabrication cast-in-place combined type fair-faced concrete outer wall structure and construction method | |
CN114704112A (en) | Disassembly-free anti-seepage plugging method for cantilever type scaffold steel beam through-wall opening | |
CN202483061U (en) | Post-cast strip supporting formwork | |
CN109025294A (en) | A kind of post-cast strip inflatable arc angle rectangular section hose side form installs construction method | |
CN208792764U (en) | A kind of stock mould for concrete-constituted pile | |
CN203640278U (en) | Stair construction die shelf | |
CN109025265A (en) | A kind of thin plate side form post-cast strip erection method | |
CN103882992A (en) | Connection piece with annular steel bar | |
CN207211440U (en) | Overlaid plate type Combined concrete prefabricated components | |
CN206873731U (en) | A kind of concrete hollow double-storied floor | |
CN214144725U (en) | UHPC (ultra high performance polycarbonate) disassembly-free hollow template and superposed hollow floor slab | |
CN212406109U (en) | Structure for pouring concrete floor post-cast strip by adopting inflatable template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |