CN109024927A - A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll - Google Patents
A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll Download PDFInfo
- Publication number
- CN109024927A CN109024927A CN201810897477.2A CN201810897477A CN109024927A CN 109024927 A CN109024927 A CN 109024927A CN 201810897477 A CN201810897477 A CN 201810897477A CN 109024927 A CN109024927 A CN 109024927A
- Authority
- CN
- China
- Prior art keywords
- coiled material
- layer
- short side
- facade
- self
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
Abstract
The present invention relates to a kind of construction methods of the waterproof of prespreading self-adhesion glue film waterproof roll, the waterproof roll has long side, short side after cutting, short side is coiled material wide cut, the self-adhesive glue layer for being wherein 5 ~ 20 centimetres with width at the long side edge of side above the coiled material is pasted with release film layer above self-adhesive glue layer;The construction method is laid with overlap joint the following steps are included: overlaying coiled material, long edge lap, short side overlap joint, facade coiled material on cleaning basal plane, bottom surface.The present invention reduces the fault during coiled material lapping by way of overlaying coiled material and causes leakage point of doing over again or generate;Upper one layer of long side is carried out again after overlapping using the short side for carrying out next layer first overlapped overlapping mode, then can reduce by three width coiled material confluces overlapped gap;Three width coiled materials overlapping intersection region is located at the coiled material excision corner of middle layer, makes the length of overlapping the slot, reduces the probability for generating leakage point.
Description
Technical field
The present invention relates to buildings waterproof construction field, in particular to a kind of waterproof of prespreading self-adhesion glue film waterproof roll
Construction method.
Background technique
In life, from house to workshop, the phenomenon that water penetration, is commonplace, not only comes to people's lives, work belt
It is inconvenient and difficult, while security risk is caused to the building body of leak;Waterproofing work exactly occurs for drainage
's.In different places, the requirement to buildings waterproof performance is different, such as the underground engineering of basement etc, it is necessary to build
If waterproofing work is carried out during.
Existing waterproof material mainly has water-repellent paint and waterproof roll, and since the execution conditions of water-repellent paint are more multiple
It is miscellaneous, construction period longer the disadvantages of more demanding to construction environment, in recent years, waterproof roll due to its construction period is short, to applying
The breakthrough of the low feature of work environmental requirement and web material and coiled material are greatly improved with building basal plane adhesive property, and are obtained
To being widely applied.
When using waterproof roll, it usually needs the coiled material of muti-piece smaller size is mutually overlapped to form to the waterproof of large area
Coiled material, however, certain buildings used after waterproof roll, especially basement, also frequent occurrence leak the phenomenon that, waterproof
Coiled material, which does not play the role of this, to be had, to find out its cause, being due to during overlapped, due to stress, gap, gauffer at overlap edge
Or other reasons cause to overlap it is bad, to leakage point occur;And at present in the market, the quality of construction effect, depending on applying
The consummate degree of Gongshi Fu's handicraft and the abundant degree of construction experience, fail to form effective technical solution to avoid leakage point
It generates;Also therefore cause work progress complex, inconvenient.
Summary of the invention
A kind of prespreading self-adhesion is provided it is an object of the invention to overcome at least one of the prior art insufficient based on this
The construction method of the waterproof of glue film waterproof roll.Using this method to waterproof construction is carried out, convenient, fast, coiled material lapping is good,
Waterproof effect is excellent.
In order to achieve the above objectives, the technical solution adopted by the present invention is that:
A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll, the waterproof roll have long side, short after cutting
Side, short side are coiled material wide cut, the self-adhesive glue layer for being wherein 5 ~ 20 centimetres with width at the long side edge of side above the coiled material, from
Release film layer is pasted with above adhesive-layer;It is characterized in that, the construction method the following steps are included:
S1, cleaning basal plane, the bottom surface for object of constructing, facade is clean;
Coiled material is overlay on S2, bottom surface, the waterproof roll after cutting is laid with since one edge of bottom surface, until corresponding thereto another
On one side;
Firstly, the first width waterproof roll long edge size matches with the marginal dimension when being laid with, the side with self-adhesive glue layer is long
Outlying from the edge, and self-adhesive glue layer is upward, if long edge size is less than the marginal dimension, by the side of the second width waterproof roll
Short side is laid with after intersecting with the side short side of the first width waterproof roll extremely to match with the marginal dimension;Secondly, being successively laid with anti-
For water coiled material until being paved with bottom surface, coiled material long side intersects overlapping two-by-two, and intersects at the self-adhesive glue layer of lower layer coiled material;
S3, it overlaps by width since the first width waterproof roll;
A1, long edge lap;Release film by long side confluce positioned at the self-adhesive glue layer of next layer of coiled material removes, while using pressure
Roller is rolled in the long side confluce of a upper layer coiled material, and the long side of upper layer and lower layer coiled material is overlapped;
A2, short side overlap joint;When next layer of waterproof roll has the short side of intersection, walked again after progress short side overlap joint first
Rapid a1;The release film of short side overlap joint auxiliary material is removed, together after one layer of upper patch short side overlap joint auxiliary material under short side confluce when overlap joint
When using pressure roller a upper layer coiled material short side confluce roll, the short side of upper layer and lower layer coiled material is overlapped;It is described short
Edge lap auxiliary material is wet-laying waterproof roll or double-sided adhesive, for the short side of two width coiled materials to overlap;
S4, S3 is repeated, until flooring sheet overlap joint finishes;
S5, facade coiled material are laid with overlap joint.
In above scheme, the self-adhesive waterproof roll material and being bonded for basal plane after cleaning basal plane are closer, avoid because of basal plane not
It is smooth and form water storage point;It overlays and carries out long side or short side overlap joint after coiled material, then the position of coiled material is relatively fixed, avoids that overlapped
The position for needing to change coiled material when being laid with coiled material in the process because of fault, that is, reduce the probability of leakage point generation;Mistake that overlapped
The long side of Cheng Zhong, coiled material are stacked from level to level, are limited to the size of coiled material, when the long edge size of coiled material is less than basement bottom surface one side
It when size, needs to splice the coiled material of this layer to the size on one side corresponding to bottom surface and matches, and use and carry out next layer first
Short side overlap joint after carry out one layer of long side again overlapped overlapping mode, then can reduce by three width coiled material confluces overlapped seam
The probability that gap, i.e. reduction leakage point generate, improves waterproof construction effect;Lap-joint is rolled using pressure roller when overlap joint, keeps coiled material good
It overlaps well.
Further, the facade has inner corner trim, external corner, and step S5 includes:
B1, short side overlap joint auxiliary material is pasted with the junction of facade on bottom surface;
B2, facade overlay coiled material, by the waterproof roll after cutting from facade inner corner trim or external corner be laid with, it is solid using top
Fixed, coiled material long side is perpendicular to bottom surface when laying;Successively for laying water-proof coiled material until being paved with facade, coiled material long side intersects weight two-by-two
It is folded, and intersect at the self-adhesive glue layer of lower layer coiled material;
B3, since at inner corner trim or external corner carry out facade coiled material by width overlap;
B31, facade coiled material short side overlap joint, the short side by the coiled material for being laid on facade in advance close to junction are overlapped by junction short side
Auxiliary material is overlapped with bottom surface coiled material;
The coiled material long side confluce for being laid on facade in advance is located at the self-adhesive of next layer of coiled material by b32, the long edge lap of facade coiled material
The release film of layer removes, while being rolled using pressure roller in the long side confluce of a upper layer coiled material, by the long side of upper layer and lower layer coiled material
It overlaps;
B33, alternately step b31, b32 is repeated, until facade coiled material lapping finishes.
In the present solution, auxiliary material is overlapped by pasting short side with the junction of facade on bottom surface, it is anti-on facade by being laid in advance
Water coiled material overlaps with the waterproof roll on bottom surface, forms whole waterproof layer, due to the structure at inner corner trim, external corner, is
Prevent the coiled material lapping after overlaying inconvenient, from this overlay;And the short side for overlapping facade coiled material first is used, then overlap
The mode of the long side of facade coiled material, avoids during overlap joint that coiled material is unsceptered leads to leakage point of doing over again or occur.
Further, fixed adopt in the top nails, and fixed area is located in the short side overlapping regions of top, long side
Outside overlapping regions.In the present solution, being fixed on the pre- coiled material being laid on facade using nail, consolidate, it is not easily to fall off;The position of nail
The position of coiled material is limited, is more convenient the overlap joint of facade coiled material long side and bottom short side, and the hole as caused by nail is due to rear
When the continuous short side and ceiling coiled material lapping carried out at the top of facade coiled material, need to attach short side overlap joint auxiliary material, hole it is capped and
It is easy for construction, quick there is no leakage point.
Further, the long edge size for being laid on the coiled material of facade in advance matches with elevation.Due to the coiled material at facade
Overlap joint is inconvenient, and its lap-joint is easier to be influenced by external force and generate leakage point, therefore, upper to use long edge size in facade height
The coiled material to match is spent to be laid on facade in advance.
Further, the distance that long back gauge inner corner trim/external corner of coiled material is overlay at the inner corner trim/external corner is greater than 20cm.By
Structure at inner corner trim, external corner, to prevent the coiled material lapping after overlaying inconvenient, and after overlap joint the position coiled material due to answering
The influence of power causes to overlap bad and generate leakage point, and the distance of its long back gauge inner corner trim/external corner is made to be greater than 20cm.
Further, the overlapping intersection region formed is intersected by three width coiled materials, and there is three-layer coil material structure, be located in the middle
One layer coiled material cuts corner, and cutting part is located in overlapping intersection region.Since there are differences in height at the coil edge of overlapping, i.e.,
There are overlapping the slot, are easy to produce leakage point, and when corner is not cut off, the length of overlapping the slot is lap width, i.e. coiled material long side is handed over
The width that can be overlapped;And cut off and be located at after the corner of intermediate layer coiled material, the length of overlapping the slot, then the overlapping the slot leak
Possibility is just lower.
Further, removal corner is cut along the diagonal line in overlapping region.Due to cornerwise length longest,
After the corner for diagonally cutting intermediate layer coiled material, the probability of leak can be effectively reduced.
Further, the distance between adjacent overlapping intersection region is not less than 15 centimetres.Since overlapping intersection region is
The multiple area of leakage point is easy to influence each other and the probability for generating leakage point is caused to increase if spacing distance is too small, therefore, phase
The distance between adjacent overlapping intersection region should be not less than 15cm.
Further, the short side overlap joint auxiliary material wide cut is alignment overlap joint between 5 ~ 20cm and/or auxiliary material.This programme
In, coiled material can overlap well, while being avoided that overlapping region is excessive again causes cost to increase.
Further, between step S1 and S2, further include the steps that placing inner corner trim/external corner prefabricated component, the prefabricated component
Surface has adhesive layer, is used for inner corner trim/external corner angle bottom, makes inner corner trim/external corner surfacing;In S2 step, coiled material is layed in yin
Above angle/external corner prefabricated component.When the position out-of-flatness of basement inner corner trim/external corner bottom, the coiled material being laid with thereon is easily deformed
Cause to overlap bad, and the position is easy water storage and reduces the service life of coiled material, generates leakage point;Use corresponding prefabricated component
Later, the surface of position is smooth, and coiled material will not be unsceptered because of deformation, the waterproof effect after improving coiled material lapping.
Compared with prior art, the beneficial effects of the present invention are:
A kind of construction method (1) of the waterproof of prespreading self-adhesion glue film waterproof roll of the present invention is reduced by way of overlaying coiled material
Fault during coiled material lapping causes leakage point of doing over again or generate;(2) after being overlapped using the short side for carrying out next layer first
One layer of long side is carried out again overlapped overlapping mode, then can reduce by three width coiled material confluces overlapped gap, i.e. reduction leak
The probability that point generates improves waterproof construction effect;(3) three width coiled materials overlapping intersection region is located at the coiled material excision angle of middle layer
Portion makes the length of overlapping the slot, reduces the probability for generating leakage point;(4) adjacent overlapping intersects the distance between region no
Less than 15 centimetres, the probability that the region generates leakage point is reduced.
Detailed description of the invention
Fig. 1 is prespreading self-adhesion glue film waterproof roll structure schematic diagram of the present invention;
Fig. 2 is prespreading self-adhesion glue film waterproof roll cross section structure schematic diagram;
Fig. 3, which attaches most importance to, overlaps meeting regional structure schematic diagram;
Fig. 4 is inner corner trim coiled material lapping structural schematic diagram.
Specific embodiment
The present invention is further illustrated With reference to embodiment.Wherein, attached drawing only for illustration,
What is indicated is only schematic diagram, rather than pictorial diagram, should not be understood as the limitation to this patent;
Embodiment 1
A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll of the present embodiment, as shown in Figure 1, the waterproof roll
There is long side 11, short side 12, short side is coiled material wide cut, and wherein long side 11 edge in side has width on coiled material after 1 cutting
The self-adhesive glue layer 2 that degree is 5 ~ 20 centimetres, self-adhesive glue layer top are pasted with release film layer 3, see Fig. 2;It is characterized in that, the construction
Method the following steps are included:
S1, cleaning basal plane, the bottom surface for object of constructing, facade is clean;
Coiled material is overlay on S2, bottom surface, the waterproof roll after cutting is laid with since one edge of bottom surface, until corresponding thereto another
On one side;
Firstly, the first width waterproof roll long edge size matches with the marginal dimension when being laid with, the side with self-adhesive glue layer is long
Outlying from the edge, and self-adhesive glue layer is upward, if long edge size is less than the marginal dimension, by the side of the second width waterproof roll
Short side is laid with after intersecting with the side short side of the first width waterproof roll extremely to match with the marginal dimension;Secondly, being successively laid with anti-
For water coiled material until being paved with bottom surface, coiled material long side intersects overlapping two-by-two, and intersects at the self-adhesive glue layer of lower layer coiled material;
S3, it overlaps by width since the first width waterproof roll;
A1, long edge lap;Release film by long side confluce positioned at the self-adhesive glue layer of next layer of coiled material removes, while using pressure
Roller is rolled in the long side confluce of a upper layer coiled material, and the long side of upper layer and lower layer coiled material is overlapped;
A2, short side overlap joint;When next layer of waterproof roll has the short side of intersection, walked again after progress short side overlap joint first
Rapid a1;The release film of short side overlap joint auxiliary material is removed, together after one layer of upper patch short side overlap joint auxiliary material under short side confluce when overlap joint
When using pressure roller a upper layer coiled material short side confluce roll, the short side of upper layer and lower layer coiled material is overlapped;It is described short
Edge lap auxiliary material is wet-laying waterproof roll or double-sided adhesive, for the short side of two width coiled materials to overlap;
S4, S3 is repeated, until flooring sheet overlap joint finishes;
S5, facade coiled material are laid with overlap joint.
In above scheme, the self-adhesive waterproof roll material and being bonded for basal plane after cleaning basal plane are closer, avoid because of basal plane not
It is smooth and form water storage point;It overlays and carries out long side or short side overlap joint after coiled material, then the position of coiled material is relatively fixed, avoids that overlapped
The position for needing to change coiled material when being laid with coiled material in the process because of fault, that is, reduce the probability of leakage point generation;Mistake that overlapped
The long side of Cheng Zhong, coiled material are stacked from level to level, are limited to the size of coiled material, when the long edge size of coiled material is less than basement bottom surface one side
It when size, needs to splice the coiled material of this layer to the size on one side corresponding to bottom surface and matches, and use and carry out next layer first
Short side overlap joint after carry out one layer of long side again overlapped overlapping mode, then can reduce by three width coiled material confluces overlapped seam
The probability that gap, i.e. reduction leakage point generate, improves waterproof construction effect;Lap-joint is rolled using pressure roller when overlap joint, keeps coiled material good
It overlaps well.
Further, the facade has inner corner trim, external corner, and step S5 includes:
B1, short side overlap joint auxiliary material is pasted with the junction of facade on bottom surface;
B2, facade overlay coiled material, by the waterproof roll after cutting from facade inner corner trim or external corner be laid with, it is solid using top
Fixed, coiled material long side is perpendicular to bottom surface when laying;Successively for laying water-proof coiled material until being paved with facade, coiled material long side intersects weight two-by-two
It is folded, and intersect at the self-adhesive glue layer of lower layer coiled material;
B3, since at inner corner trim or external corner carry out facade coiled material by width overlap;
B31, facade coiled material short side overlap joint, the short side by the coiled material for being laid on facade in advance close to junction are overlapped by junction short side
Auxiliary material is overlapped with bottom surface coiled material;
The coiled material long side confluce for being laid on facade in advance is located at the self-adhesive of next layer of coiled material by b32, the long edge lap of facade coiled material
The release film of layer removes, while being rolled using pressure roller in the long side confluce of a upper layer coiled material, by the long side of upper layer and lower layer coiled material
It overlaps;
B33, alternately step b31, b32 is repeated, until facade coiled material lapping finishes.
In the present solution, auxiliary material is overlapped by pasting short side with the junction of facade on bottom surface, it is anti-on facade by being laid in advance
Water coiled material overlaps with the waterproof roll on bottom surface, forms whole waterproof layer, due to the structure at inner corner trim, external corner, is
Prevent the coiled material lapping after overlaying inconvenient, from this overlay;And the short side for overlapping facade coiled material first is used, then overlap
The mode of the long side of facade coiled material, avoids during overlap joint that coiled material is unsceptered leads to leakage point of doing over again or occur.
Further, fixed adopt in the top nails, and fixed area is located in the short side overlapping regions of top, long side
Outside overlapping regions.In the present solution, being fixed on the pre- coiled material being laid on facade using nail, consolidate, it is not easily to fall off;The position of nail
The position of coiled material is limited, is more convenient the overlap joint of facade coiled material long side and bottom short side, and the hole as caused by nail is due to rear
When the continuous short side and ceiling coiled material lapping carried out at the top of facade coiled material, need to attach short side overlap joint auxiliary material, hole it is capped and
It is easy for construction, quick there is no leakage point.
Further, the long edge size for being laid on the coiled material of facade in advance matches with elevation.Due to the coiled material at facade
Overlap joint is inconvenient, and its lap-joint is easier to be influenced by external force and generate leakage point, therefore, upper to use long edge size in facade height
The coiled material to match is spent to be laid on facade in advance.
Further, the distance that long back gauge inner corner trim/external corner of coiled material is overlay at the inner corner trim/external corner is greater than 20cm.By
Structure at inner corner trim, external corner, to prevent the coiled material lapping after overlaying inconvenient, and after overlap joint the position coiled material due to answering
The influence of power causes to overlap bad and generate leakage point, and the distance of its long back gauge inner corner trim/external corner is made to be greater than 20cm.
As shown in figure 3, intersecting the overlapping intersection region 4 formed by three width coiled materials, there is three-layer coil material structure, be located at centre
A layer coiled material cut corner, cutting part is located in overlapping intersection region 4.Due to there is height at the coil edge of overlapping
That is, there is overlapping the slot in difference, be easy to produce leakage point, and when corner is not cut off, the length of overlapping the slot is lap width, i.e. coiled material is long
The width of side intersection overlapping;And cut off and be located at after the corner of intermediate layer coiled material, the length of overlapping the slot, then the overlapping the slot is leaked
A possibility that water, is just lower.
Further, removal corner is cut along the diagonal line in overlapping intersection region.Due to cornerwise length longest,
Therefore after diagonally cutting the corner of intermediate layer coiled material, the probability of leak can be effectively reduced.
Further, the distance between adjacent overlapping intersection region is not less than 15 centimetres.Since overlapping intersection region is
The multiple area of leakage point is easy to influence each other and the probability for generating leakage point is caused to increase if spacing distance is too small, therefore, phase
The distance between adjacent overlapping intersection region should be not less than 15cm.
Further, the short side overlap joint auxiliary material wide cut is alignment overlap joint between 5 ~ 20cm and/or auxiliary material.This programme
In, coiled material can overlap well, while being avoided that overlapping region is excessive again causes cost to increase.
Further, between step S1 and S2, further include the steps that placing inner corner trim/external corner prefabricated component, the prefabricated component
Surface has adhesive layer, is used for inner corner trim/external corner angle bottom, makes inner corner trim/external corner surfacing;In S2 step, coiled material is layed in yin
Above angle/external corner prefabricated component.When the position out-of-flatness of basement inner corner trim/external corner bottom, the coiled material being laid with thereon is easily deformed
Cause to overlap bad, and the position is easy water storage and reduces the service life of coiled material, generates leakage point;Use corresponding prefabricated component
Later, the surface of position is smooth, and coiled material will not be unsceptered because of deformation, the waterproof effect after improving coiled material lapping.
As shown in figure 4, the coiled material for overlaying on it is divided into left-hand component and right-hand component by inner corner trim, carries out bottom short side and take
When connecing, first by the coiled material of left/right part since far from one section of inner corner trim start with short side overlap joint auxiliary material overlap joint, until the right side
Side/left side facade;Then by the right/left-hand component coiled material push and in corresponding short side overlap joint auxiliary material to its, then left lateral
Divide and the coiled material of right-hand component forms fold domain 5, cuts removal for a layer coiled material is located in the middle in fold domain 5, then,
Short side is attached on the coiled material of left/right part in fold domain 5 and overlaps auxiliary material, by the right, left-hand component in fold domain 5
Coiled material lapping together.This method treated inner corner trim, waterproof effect is good, convenient and quick construction.
Further, it needs to cut out at intermediate position when coiled material bottom short side overlaps at external corner, coiled material at this is laid on bottom
The part in face is divided into left and right two parts, cuts out wide cut of the width less than short side overlap joint auxiliary material, and the coiled material after cutting is folded into and sun
After the shape that angle matches, the two-part coiled material of left/right is overlapped with junction short side overlap joint auxiliary material respectively;And due to external corner at
Particularity, be easy to produce leakage point at this, therefore repairing coiled material is sticked in bottom at this, reduce and generate the general of leakage point at this
Rate.
Further, ceiling surface is similar with bottom surface, differs only in when overlaying waterproof roll, adopts the waterproof that nails
After coiled material, then carry out block-by-block lap works.
Obviously, the above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be pair
The restriction of embodiments of the present invention.For those of ordinary skill in the art, may be used also on the basis of the above description
To make other variations or changes in different ways.There is no necessity and possibility to exhaust all the enbodiments.It is all this
Made any modifications, equivalent replacements, and improvements etc., should be included in the claims in the present invention within the spirit and principle of invention
Protection scope within.
Claims (10)
1. a kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll, the waterproof roll have after cutting long side,
Short side, short side are coiled material wide cut, the self-adhesive glue layer for being wherein 5 ~ 20 centimetres with width at the long side edge of side above the coiled material,
Release film layer is pasted with above self-adhesive glue layer;It is characterized in that, the construction method the following steps are included:
S1, cleaning basal plane, the bottom surface for object of constructing, facade is clean;
Coiled material is overlay on S2, bottom surface, the waterproof roll after cutting is laid with since one edge of bottom surface, until corresponding thereto another
On one side;
Firstly, the first width waterproof roll long edge size matches with the marginal dimension when being laid with, the side with self-adhesive glue layer is long
Outlying from the edge, and self-adhesive glue layer is upward, if long edge size is less than the marginal dimension, by the side of the second width waterproof roll
Short side is laid with after intersecting with the side short side of the first width waterproof roll extremely to match with the marginal dimension;Secondly, being successively laid with anti-
For water coiled material until being paved with bottom surface, coiled material long side intersects overlapping two-by-two, and intersects at the self-adhesive glue layer of lower layer coiled material;
S3, it overlaps by width since the first width waterproof roll;
A1, long edge lap;Release film by long side confluce positioned at the self-adhesive glue layer of next layer of coiled material removes, while using pressure
Roller is rolled in the long side confluce of a upper layer coiled material, and the long side of upper layer and lower layer coiled material is overlapped;
A2, short side overlap joint;When next layer of waterproof roll has the short side of intersection, walked again after progress short side overlap joint first
Rapid a1;The release film of short side overlap joint auxiliary material is removed, together after one layer of upper patch short side overlap joint auxiliary material under short side confluce when overlap joint
When using pressure roller a upper layer coiled material short side confluce roll, the short side of upper layer and lower layer coiled material is overlapped;It is described short
Edge lap auxiliary material is wet-laying waterproof roll or double-sided adhesive, for the short side of two width coiled materials to overlap;
S4, S3 is repeated, until flooring sheet overlap joint finishes;
S5, facade coiled material are laid with overlap joint.
2. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 1, which is characterized in that described
Facade has inner corner trim, external corner, and step S5 includes:
B1, short side overlap joint auxiliary material is pasted with the junction of facade on bottom surface;
B2, facade overlay coiled material, by the waterproof roll after cutting from facade inner corner trim or external corner be laid with, it is solid using top
Fixed, coiled material long side is perpendicular to bottom surface when laying;Successively for laying water-proof coiled material until being paved with facade, coiled material long side intersects weight two-by-two
It is folded, and intersect at the self-adhesive glue layer of lower layer coiled material;
B3, since at inner corner trim or external corner carry out facade coiled material by width overlap;
B31, facade coiled material short side overlap joint, the short side by the coiled material for being laid on facade in advance close to junction are overlapped by junction short side
Auxiliary material is overlapped with bottom surface coiled material;
The coiled material long side confluce for being laid on facade in advance is located at the self-adhesive of next layer of coiled material by b32, the long edge lap of facade coiled material
The release film of layer removes, while being rolled using pressure roller in the long side confluce of a upper layer coiled material, by the long side of upper layer and lower layer coiled material
It overlaps;
B33, alternately step b31, b32 is repeated, until facade coiled material lapping finishes.
3. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 2, which is characterized in that described
Fixed adopt in top nails, and fixed area is located in the short side overlapping regions of top, outside long side overlapping regions.
4. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 2, which is characterized in that overlay
Match in the long edge size of the coiled material of facade with elevation.
5. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 2, which is characterized in that described
The distance that long back gauge inner corner trim/external corner of coiled material is overlay at inner corner trim/external corner is greater than 20cm.
6. the construction method of the waterproof of any one of claims 1 or 2 prespreading self-adhesion glue film waterproof roll, feature exist
In, intersected by three width coiled materials formed overlapping intersection region, have three-layer coil material structure, be located in the middle a layer coiled material cutting angle
Portion, cutting part are located in overlapping intersection region.
7. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 6, which is characterized in that along
Diagonal line in overlapping intersection region cuts removal corner.
8. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 6, which is characterized in that adjacent
Overlapping intersection the distance between region be not less than 15 centimetres.
9. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 1, which is characterized in that described
It is alignment overlap joint that short side, which overlaps auxiliary material wide cut between 5 ~ 20cm and/or auxiliary material,.
10. the construction method of the waterproof of prespreading self-adhesion glue film waterproof roll according to claim 1, which is characterized in that institute
Facade is stated with inner corner trim, external corner, between step S1 and S2, further includes the steps that placing inner corner trim/external corner prefabricated component, it is described prefabricated
Part surface has adhesive layer, is used for inner corner trim/external corner angle bottom, makes inner corner trim/external corner surfacing;In S2 step, coiled material is layed in
Above inner corner trim/external corner prefabricated component.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810278802 | 2018-03-31 | ||
CN2018102788027 | 2018-03-31 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109024927A true CN109024927A (en) | 2018-12-18 |
Family
ID=64632346
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810897477.2A Pending CN109024927A (en) | 2018-03-31 | 2018-08-08 | A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109024927A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306732A (en) * | 2019-07-31 | 2019-10-08 | 宁波瑞凌新能源科技有限公司 | A kind of radiation refrigeration building materials and preparation method thereof |
CN112726844A (en) * | 2020-12-25 | 2021-04-30 | 北京市腾美骐科技发展有限公司 | Application method of waterproof and steam-proof membrane for building |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2709552Y (en) * | 2004-04-02 | 2005-07-13 | 深圳市卓宝科技股份有限公司 | Pre-spread self-adhesive water-proof coiled material |
CN2734877Y (en) * | 2004-06-02 | 2005-10-19 | 苏翠燕 | Rubber-combined self-adhesive waterproof roll |
CN102409813A (en) * | 2011-09-08 | 2012-04-11 | 中国核工业华兴建设有限公司 | Whole blanking waterproof construction method |
US20130295295A1 (en) * | 2009-02-12 | 2013-11-07 | Firestone Building Products Co., LLC | Membrane having a cured coating layer |
CN204282657U (en) * | 2014-11-28 | 2015-04-22 | 青岛科化高分子科技股份有限公司 | Two overlap edge polymer membranes |
-
2018
- 2018-08-08 CN CN201810897477.2A patent/CN109024927A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2709552Y (en) * | 2004-04-02 | 2005-07-13 | 深圳市卓宝科技股份有限公司 | Pre-spread self-adhesive water-proof coiled material |
CN2734877Y (en) * | 2004-06-02 | 2005-10-19 | 苏翠燕 | Rubber-combined self-adhesive waterproof roll |
US20130295295A1 (en) * | 2009-02-12 | 2013-11-07 | Firestone Building Products Co., LLC | Membrane having a cured coating layer |
CN102409813A (en) * | 2011-09-08 | 2012-04-11 | 中国核工业华兴建设有限公司 | Whole blanking waterproof construction method |
CN204282657U (en) * | 2014-11-28 | 2015-04-22 | 青岛科化高分子科技股份有限公司 | Two overlap edge polymer membranes |
Non-Patent Citations (3)
Title |
---|
中国二十冶集团有限公司: "《宝钢股份不锈钢事业部冷IV标工程施工技术》", 31 August 2010, 同济大学出版社 * |
叶军: "地下工程预铺反粘防水技术", 《建设科技》 * |
陈春荣: "大型种植屋面系统的防水做法", 《建筑施工》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306732A (en) * | 2019-07-31 | 2019-10-08 | 宁波瑞凌新能源科技有限公司 | A kind of radiation refrigeration building materials and preparation method thereof |
CN112726844A (en) * | 2020-12-25 | 2021-04-30 | 北京市腾美骐科技发展有限公司 | Application method of waterproof and steam-proof membrane for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207775945U (en) | A kind of bridging arrangement of Novel underground room bottom plate and side wall difference waterproof material | |
CN105544617B (en) | A kind of basement bottom board and waterproof roll integral construction method and waterproof construction | |
CN104912119A (en) | Close jointing method for pre-paving macromolecular self-adhesion film waterproof roll | |
CN110735499B (en) | Parapet waterproof structure and construction method thereof | |
CN108999346A (en) | A kind of prespreading self-adhesion glue film waterproof roll is applied to the construction method of plane waterproof | |
CN109024927A (en) | A kind of construction method of the waterproof of prespreading self-adhesion glue film waterproof roll | |
CN111173166A (en) | Basement outer wall waterproof protection structure and construction method | |
CN107165290A (en) | Basement bottom board prespreading Macromolecular self-adhesive membrane waterproof roll non-bituminous base construction | |
CN111395410B (en) | Construction method for pre-paving asphalt-based waterproof coiled material through welding and bonding combined construction | |
CN105150622A (en) | Self-adhesive modified asphalt waterproof roll | |
CN105780816B (en) | A kind of water-proofing treatment mode for solving underground position subsiding crack in existed building enlarging construction | |
US2144168A (en) | Roof construction and method of laying roll roofing | |
CN207419541U (en) | A kind of composite light lumber convenient for splicing | |
CN108979016A (en) | A kind of prespreading self-adhesion glue film waterproof roll is applied to the construction method of facade waterproof | |
CN109881864A (en) | A kind of joining method and structure on floor and stone material or ceramic tile | |
CN204982977U (en) | Basement bottom plate and waterproofing membrane integration waterproof construction | |
CN102505947A (en) | Construction method for butt-jointing and sealing waterproof rolls | |
CN213868357U (en) | Waterproofing membrane of easily splicing | |
CN211764009U (en) | Thermoplastic polyolefin waterproofing membrane is used in maintenance | |
CN210151967U (en) | Waterproof type building indoor floor deformation joint structure | |
CN219622268U (en) | Waterproof splicing structure | |
CN207727781U (en) | A kind of deformation joint of roof connecting structure | |
KR20050015091A (en) | A waterproofing method and method for connecting waterproofing sheets | |
CN212827206U (en) | Wet anti-waterproofing membrane that glues of shop PVC in advance that paves | |
CN215518901U (en) | Composite structure underground high-side wall waterproof structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181218 |