CN109024688A - A kind of assembled cable work well and component on site construction method - Google Patents

A kind of assembled cable work well and component on site construction method Download PDF

Info

Publication number
CN109024688A
CN109024688A CN201810996985.6A CN201810996985A CN109024688A CN 109024688 A CN109024688 A CN 109024688A CN 201810996985 A CN201810996985 A CN 201810996985A CN 109024688 A CN109024688 A CN 109024688A
Authority
CN
China
Prior art keywords
concrete
reinforced concrete
side plate
shaped steel
work well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810996985.6A
Other languages
Chinese (zh)
Inventor
刘洋
郑俊杰
付海平
赖汉江
崔明娟
严海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong University of Science and Technology
Original Assignee
Huazhong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong University of Science and Technology filed Critical Huazhong University of Science and Technology
Priority to CN201810996985.6A priority Critical patent/CN109024688A/en
Publication of CN109024688A publication Critical patent/CN109024688A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention belongs to cable work well fields, and specifically disclose a kind of assembled cable work well and component on site construction method, it includes plain concrete cushion layer, reinforced concrete floor, U-shaped steel reinforced concrete side plate and reinforced concrete cover plate, reinforced concrete floor is placed in plain concrete cushion layer after ground excavation, the lifting of armored concrete side plate is placed on stiffness bearer by stiffness bearer after being placed on reinforced concrete floor, formwork pours constructional column after U-shaped steel reinforced concrete side end distributing bar and longitudinal reinforcement are bound, reinforced concrete cover plate is shelved on the crossbeam of U-shaped steel reinforced concrete side plate when concrete strength reaches design value 75%.The present invention has many advantages, such as that structurally reasonable, barrier performance is good, assembly is simple, short time limit, low cost, environmental perturbation are small.

Description

A kind of assembled cable work well and component on site construction method
Technical field
The invention belongs to cable work well fields, more particularly, to a kind of assembled cable work well and site operation Method.
Background technique
Currently, mostly use cast-type construction method when building cable work well, the cable work well of cast-type exist with Under disadvantage: 1) it is long in time limit, cast-type cable work well need live assembling reinforcement, live formwork, poured in place concrete, after Phase demoulding etc., the duration is very long, and the curing age of single concrete just needs 28 days;2) costly, it is excavated from ground, binding steel Muscle, production mold, concreting, concrete curing, form removable just need to spend more expense;3) effect on environment is big, Municipal cable work well is often built in city, and the excavation of foundation soil unavoidably will affect urban environment, influence city image, The construction period of cast-type cable work well generally requires one month or more time, shadow larger for urban environmental impact Ring normal trip.
Then there are some prefabricated assembled cable active wells, but since assembly parts quantity is more, is only adopted between assembly parts With simple splicing and bolted mode, and there are certain deviations in assembly for prefabricated components, so that between assembly parts Rubber water-proof item cannot play good waterproof action, and underground water often penetrates into cable work well, threaten Electrical Safety With the personal safety of maintenance personnel, in addition, the process that assembly parts excessively make assembly construct becomes complicated, these unfavorable factors All limit the application and popularization of assembled cable work well.
Summary of the invention
Aiming at the above defects or improvement requirements of the prior art, the present invention provides a kind of assembled cable work well and now Construction method, by key component for example plain concrete cushion layer, reinforced concrete floor, U-shaped steel reinforced concrete side plate and The structure of reinforced concrete cover plate and the design of arrangement, obtain it is a kind of it is structurally reasonable, barrier performance is good, assembly is simple Assembled cable work well has the advantages that short time limit, low cost, environmental perturbation are small.
To achieve the above object, according to one aspect of the present invention, a kind of assembled cable work well is proposed comprising Plain concrete cushion layer, reinforced concrete floor, U-shaped steel reinforced concrete side plate and the reinforced concrete earth mulch set gradually from bottom to up Plate, in which:
The plain concrete cushion layer is poured by plain concrete, offers pull ring hole and catch pit thereon;
The reinforced concrete floor is arranged in plain concrete cushion layer, is poured by armored concrete, thereon together Sample offers pull ring hole and catch pit, and pull ring thereon is cheated and catch pit is cheated and catchmented with the pull ring in plain concrete cushion layer The position in hole is corresponding, is additionally provided with card slot on the reinforced concrete floor;
The U-shaped steel reinforced concrete side plate is poured by armored concrete, is provided with two pieces, two pieces of U-shaped steel muscle are mixed Solidifying soil side plate is horizontally disposed and opening is opposite, by the way that two blocks of U-shaped steel reinforced concrete side plates are inserted into reinforced concrete floor In card slot, and the casting concrete in card slot, realize the connection of U-shaped steel reinforced concrete side plate and reinforced concrete floor, two pieces of U It is linked together between the open end of steel bar concrete side plate by constructional column, is additionally provided on U-shaped steel reinforced concrete side plate Concrete beam, closed end are also provided with cable through-hole;
The reinforced concrete cover plate is poured by armored concrete, and the mixed of U-shaped steel reinforced concrete side plate is arranged in On solidifying soil crossbeam, it which is provided with for the manhole of people's discrepancy and for the pull ring of lifting.
As it is further preferred that being provided with stiffness bearer in the card slot of the reinforced concrete floor.
As it is further preferred that the end at armored concrete side plate openings end is projected with distributing bar, two blocks of steel The distributing bar at reinforced concrete side plate openings end is mutually lapped, and longitudinal reinforcement is banded on distributing bar;The constructional column passes through Early strong concrete acquisition is poured on the distributing bar for be banded with longitudinal reinforcement.
As it is further preferred that the concrete beam of the armored concrete side plate is equipped with water proof rubber.
As it is further preferred that between the reinforced concrete cover plate and armored concrete side plate and water proof rubber It is filled by early strong concrete in gap.
As it is further preferred that being provided with steel grating on the catch pit of the reinforced concrete floor, surrounding is arranged There is 5% gradient;Pull ring is provided in the pull ring hole of the reinforced concrete floor.
As it is further preferred that the concrete beam is equipped with the pull ring for lifting.
As it is further preferred that the distributing bar and longitudinal reinforcement are hot rolled ribbed bars, diameter 16mm.
As it is further preferred that the plain concrete cushion layer, reinforced concrete floor, U-shaped steel reinforced concrete side plate and Reinforced concrete cover plate by intensity be C40 or more than concrete pour in advance.
It is another aspect of this invention to provide that providing a kind of component on site construction method of assembled cable work well, feature It is, includes the following steps:
Previously prepared plain concrete cushion layer is lifted to designated position;
Previously prepared reinforced concrete floor is lifted to plain concrete cushion layer, it is made to be mounted on plain concrete pad On layer;
Stiffness bearer is placed in the card slot of reinforced concrete floor;
Previously prepared two blocks of armored concrete side plates are lifted respectively to reinforced concrete floor, steel is inserted it into In the card slot of reinforced concrete bottom plate;
In card slot and casting concrete is located relatively in two pieces of armored concrete side plate openings ends, to fill armored concrete side Gap between plate and reinforced concrete floor, and pour two blocks of armored concrete side plates and link together;
When concrete strength reaches the 75% of strength failure criterion, reinforced concrete cover plate is lifted to armored concrete side The top of plate is mounted on it on concrete beam of armored concrete side plate, and with Concrete Filled armored concrete cover board With the gap between armored concrete side plate, the assembled in situ of assembled cable work well is completed with this.
In general, through the invention it is contemplated above technical scheme is compared with the prior art, mainly have below Technological merit:
1. the present invention can greatly shorten cable work by pouring to the assembly of less assembly parts and small-scale formwork Construction time, influence when reducing urban construction pre-fabricated electric cables active well to environment reduce project cost, while in key node Place carries out small range concreting, solves the problems, such as that assembled cable work well barrier performance is poor, guarantees buried cable The personal safety of Electrical Safety and construction personnel.
2. cable work well assembly parts quantity of the invention is few, without assembling deviation between assembly parts, so that between assembly parts Water proof rubber play good waterproof action, underground water will not penetrate into cable work well, will not threaten Electrical Safety and The personal safety of maintenance personnel, assembly parts pour in advance and only there are four, when site operation need to only be aided with it is a small amount of pour, The site operation of cable shaft can be realized, assembly work progress is simple, and short time limit is conducive to the application and popularization of active well.
3. the present invention is between reinforced concrete floor and U-shaped steel reinforced concrete side plate, U-shaped steel reinforced concrete side plate and steel Early strong concrete is poured in hole between reinforced concrete cover board, to guarantee that pre-fabricated electric cables active well does not leak, two Constructional column is poured with early strong concrete between block U-shaped steel reinforced concrete side plate, to realize the connection of both side plate, prevents cable work Make well to leak, guarantees the overall structural strength and service life of active well.
4. assembled cable work well of the invention can mix plain concrete cushion layer, reinforced concrete floor, U-shaped steel muscle Solidifying soil four concrete components of side plate and reinforced concrete cover plate are prefabricated in the factory in advance, and when construction need to only spell assembly parts Dress, and pours a small amount of early strong concrete, can quickly come into operation, with small excellent of short time limit, low cost, environmental perturbation Point.
5. the present invention in the card slot of reinforced concrete floor by being arranged rigid pad, so that between side plate bottom and bottom plate There are gap, it is convenient for concrete floor when later period casting concrete to connect with concrete side plate bottom, to enhance concrete bottom The integraty of plate and side plate.
6. the present invention is by being provided with overhanging distributing bar in the end at U-shaped steel reinforced concrete side plate openings end, and Longitudinal reinforcement is overlapped on distributing bar, to prepare constructional column by pouring early strong concrete, with this realize two pieces it is U-shaped Effective connection of armored concrete side plate constitutes a complete rectangle cavity body structure, guarantees that the overall structure of active well is strong Degree and performance.
Detailed description of the invention
Fig. 1 is the three-dimensional axonometric schematic diagram of assembled cable work well of the invention;
Fig. 2 is the top view of reinforced concrete floor of the invention;
Fig. 3 is the part cut-away view of reinforced concrete floor of the invention;
Fig. 4 is the setting schematic diagram of water proof rubber of the invention;
Fig. 5 is the schematic diagram that U-shaped steel reinforced concrete side plate of the invention is caught in card slot;
Fig. 6 is the top view of constructional column of the invention;
Fig. 7 is the top view of U-shaped steel reinforced concrete side plate of the invention;
Fig. 8 is the top view of plain concrete cushion layer of the invention;
Fig. 9 is the top view of reinforced concrete cover plate of the invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.As long as in addition, technical characteristic involved in the various embodiments of the present invention described below Not constituting a conflict with each other can be combined with each other.
As shown in Figure 1, a kind of assembled cable work well provided in an embodiment of the present invention comprising successively set from bottom to up Plain concrete cushion layer 1, reinforced concrete floor 2, U-shaped steel reinforced concrete side plate 3 and the reinforced concrete cover plate 4 set, wherein element Concrete cushion 1 is used as mounting substrate, is poured by plain concrete, and reinforced concrete floor 2 is used as structural substrates, setting It in plain concrete cushion layer 1, is poured by armored concrete, mounting structure of the U-shaped steel reinforced concrete side plate 3 as cable, It is arranged on reinforced concrete floor 2, is poured by armored concrete, well lid of the reinforced concrete cover plate 4 as active well, It is arranged on U-shaped steel reinforced concrete side plate 3, is poured by armored concrete.
As shown in figs. 1 and 8, plain concrete cushion layer 1 is layer structure, is used to disperse the pressure of its top structure part, Having a size of 7200mm long × 3200mm wide × 100mm thickness, it is slightly larger than reinforced concrete floor 2, offers pull ring thereon and cheat 7 Hes Catch pit 8, pull ring cheats 7 and the top of catch pit 8 is groove structure, bottom is projective structure, and wherein the size of catch pit 8 is 520mm long × 520mm wide × 520mm is deep, and the size in pull ring hole 7 is 270mm long × 270mm wide × 170mm deep, and pull ring is cheated in 7 It is not provided with pull ring 16, is assemblied in plain concrete cushion layer 1 convenient for reinforced concrete floor 2.Specifically, the four of plain concrete cushion layer Pull ring 16 of a angle setting for lifting, pull ring uses HRB400, diameter 16mm, to meet the plain concrete pad of the size The lifting demand of layer.
As shown in Fig. 2, equally offering pull ring hole 7 and catch pit 8 on reinforced concrete floor 2, wherein catch pit is used for The a small amount of water that may be penetrated at disengaging cable through-hole is collected, and pull ring hole and catch pit and element on reinforced concrete floor 2 Pull ring hole on concrete cushion is corresponding with the position of catch pit, and structure is identical, as shown in figure 3, the top in pull ring hole and catch pit Portion is groove structure, bottom is projective structure, makes the bottom of the hole of the pull ring on reinforced concrete floor 2 and catch pit embedding with this Pull ring mounted in plain concrete cushion layer 1 is cheated on 7 and catch pit 8, and that realizes reinforced concrete floor 2 and plain concrete cushion layer 1 can By assembly.The card slot 10 placed for U-shaped steel reinforced concrete side plate 3 is additionally provided on the reinforced concrete floor 2.Specifically, steel The size of the pull ring hole of reinforced concrete bottom plate 2 and catch pit than the pull ring hole and catch pit that are arranged on plain concrete bottom plate 1 is small, To realize the reliable assembling of reinforced concrete floor 2 and plain concrete cushion layer 1, the size in pull ring hole on reinforced concrete floor 2 Deep for 250mm long × 250mm wide × 150mm, the size of catch pit is 500mm long × 500mm wide × 500mm deep, guarantees reinforcing bar Effective assembly of concrete floor 2 and plain concrete cushion layer 1.The catch pit surrounding of reinforced concrete floor 2 is provided with to catchmenting 8 inclined 5% gradients are cheated, to catchment.Pull ring 16, reinforced concrete floor 2 are provided on the side wall of reinforced concrete floor 2 Size be 7000mm long × 3000mm wide × 200mm thick, the reinforced concrete floor of the size is C40 (40MPa) by intensity Or above concreting forms, so that the intensity of reinforced concrete floor reaches C40 (40MPa) or more, in the ruler It aloows active well to resist the load of -20 or more vapour under very little and intensity, that is, allows 20 tons or more of vehicle in cable work Make to pass through above well, guarantees the service life of active well.
As shown in figure 3, being provided with steel grating 5 in catch pit 8 on reinforced concrete floor 2, stepped on when worker being avoided to overhaul Into catch pit, steel grating 5 with a thickness of 20mm, use when being provided with pull ring 16 in pull ring hole 7 for lifting, pull ring 16 uses HRB400, bar diameter 16mm.Specifically, 10 cross section of card slot is small big trapezoidal under being, which is 400mm, bottom 350mm, a height of 350mm.
As shown in figs. 1 and 4, U-shaped steel reinforced concrete side plate 3 is provided with two pieces, and two blocks of U-shaped steel reinforced concrete side plates 3 are horizontal It arranges and opening is opposite, by being inserted into two blocks of U-shaped steel reinforced concrete side plates 3 in the card slot 10 of reinforced concrete floor 2 simultaneously The casting concrete in card slot 10, preferably early strong concrete realize U-shaped steel reinforced concrete side plate 3 and reinforced concrete floor 2 Connection, higher intensity can be reached using early strength concrete in a relatively short period of time, can be obviously shortened period of construction from And it improves benefit.It is linked together between the open end of two blocks of U-shaped steel reinforced concrete side plates 3 by constructional column 12, U-shaped steel muscle is mixed Concrete beam 13 is provided on solidifying soil side plate 3, concrete beam 13 is to choose crossbeam, the closing of U-shaped steel reinforced concrete side plate 3 outside End offers cable through-hole 6.Specifically, the width of concrete beam 13 is identical as the thickness of U-shaped steel reinforced concrete side plate 3, For 250mm, the overall structural strength and reinforced concrete cover plate of U-shaped steel reinforced concrete side plate can effectively ensure that under the size Stability of strutting system.
As shown in figure 4, being provided with pull ring 16 in the concrete beam 13 of armored concrete side plate 3, pull ring 16 is used HRB400, diameter 16mm, the top of armored concrete side plate 3 and the upper surface of concrete beam 13 are provided with water proof rubber 14, water proof rubber 14 is with a thickness of 20mm, to guarantee waterproof reliability.
As shown in figure 5, stiffness bearer 11 is shelved in the card slot 10 of reinforced concrete floor 2, U-shaped steel reinforced concrete side plate 3 be placed on stiffness bearer 11 after to the gap of card slot 10 pour early strong concrete 15 to complete U-shaped steel reinforced concrete side plate 3 The connection at 2 top of bottom and reinforced concrete floor, the barrier performance of reinforced assembly formula cable work well.As shown in Fig. 2, U-shaped It is correspondingly arranged a stiffness bearer 11 below each side of armored concrete side plate 3, stiffness bearer 11 is located at U-shaped steel reinforced concrete The midpoint of 3 each edge of side plate, the size of stiffness bearer 11 are 200mm long × 200mm wide × 50mm high, guarantee that cushion block can be placed on In card slot and the card slot of concrete floor and side plate bottom surface is enable to have gap for rear pouring concrete connecting bottom board and side plate.
As shown in Figures 6 and 7, the end of 3 open end of armored concrete side plate is projected with distributing bar 17, two pieces of reinforced concretes Distributing bar between native side plate 3 is mutually lapped, and longitudinal reinforcement 18, longitudinal reinforcement are then bound on distributing bar 17 with steel wire 18 is vertical with distributing bar 17, wherein the horizontal left and right arrangement of distributing bar 17, the horizontal front and back arrangement of longitudinal reinforcement 18.Specifically, Distributing bar 17 uses HRB400, a diameter of 16mm, to meet bonding strength demand, by by distributing bar 17 and longitudinal steel Muscle 18 overlaps, and then formwork pours early strong concrete 15 to prepare constructional column 12, i.e., by live formwork then in structure Make casting concrete on reinforcing bar 17 and longitudinal reinforcement 18 obtain constructional column 12 with complete two blocks of armored concrete side plates 3 connection, Two blocks of armored concrete side plates 3 are made to constitute a complete cuboid cavity body structure, the entirety of reinforced assembly formula cable work well Property, the reinforced concrete floor 2 of the reinforced concrete cover plate 4 and lower section of the cuboid cavity body structure and top collectively constitutes closing Installation cavity, to install cable, cable pierces into active well from another piece of U from the cable through-hole of one block of U-shaped steel reinforced concrete side plate The cable through-hole of steel bar concrete side plate is pierced by active well.
As illustrated in figs 1 and 9, reinforced concrete cover plate 4 is arranged on the concrete beam 13 of U-shaped steel reinforced concrete side plate 3, It which is provided with for worker's disengaging maintenance and the manhole 9 safeguarded and for the pull ring 16 of lifting, 9 height of manhole is 450mm, outer diameter For 1500mm, internal diameter 1000mm;Pull ring 16 when be provided on four corners of reinforced concrete cover plate 4 for lifting, draws Ring uses HRB400, diameter 16mm, and the size of reinforced concrete cover plate 4 is 5000mm long × 2160mm wide × 200mm thickness, The reinforced concrete cover plate of the size is that C40 (40MPa) or above concreting form by intensity, so that reinforced concrete The intensity of earth mulch plate reaches C40 (40MPa) or more, aloowed under the size and intensity active well resist vapour -20 with On load, that is, allow 20 tons or more of vehicle current above cable work well, guarantee the service life of active well.Reinforcing bar After concrete cover 4 lifts in place, the gap between reinforced concrete cover plate 4 and armored concrete side plate 3 and water proof rubber 14 It is filled by early strong concrete.Specifically, plain concrete cushion layer 1 and U-shaped steel reinforced concrete side plate 3 are equally C40 with intensity Or above concreting forms, to guarantee the overall structural strength of active well.
Assembled cable work well of the invention specifically uses following steps to carry out site operation:
Be prepared before construction: surveying setting-out excavates foundation soil, and foundation soil leveling, crane is in place, determines that element is mixed The Hoisting Position of solidifying soil padding;
Crane is lifted plain concrete cushion layer 1 to designated position by 4 pull rings that cable wire connects plain concrete cushion layer 1, It unloads cable wire and is installed on the pull ring of reinforced concrete floor 2 and reinforced concrete floor is lifted, by armored concrete bottom Cable wire is unloaded after the lifting to designated position of plate 2, determines the placement position of stiffness bearer 11, wherein stiffness bearer 11 is placed in U-shaped The midpoint on the every bottom edge of armored concrete side plate 3;First left side U-shaped steel reinforced concrete side plate is lifted in place with crane, and is protected The position for demonstrate,proving U-shaped steel reinforced concrete side plate is correct;Lifting the right U-shaped steel reinforced concrete side plate after the same method;To U-shaped steel After the completion of the lifting of reinforced concrete side plate, early strong concrete is poured, to fill the gap between two blocks of U-shaped steel reinforced concrete side plates And the gap between U-shaped steel reinforced concrete side plate and reinforced concrete floor, for connecting two pieces of U-shaped reinforced concrete floors And U-shaped steel reinforced concrete side plate and reinforced concrete floor;
After pouring completion 2 days, so that early strong concrete is reached 75% or more strength failure criterion, then mixed reinforcing bar with crane Solidifying earth mulch plate 4 is lifted on the concrete beam chosen outside U-shaped steel reinforced concrete side plate, fills reinforced concrete with early strong concrete Gap between earth mulch plate and armored concrete side plate is made by making early strong concrete reach 75% or more strength failure criterion It will not make concrete cracking because of strength problem after obtaining in cover plate lid, and can shorten the construction period, improve benefit;
Foundation soil directly can be backfilled to former base hole position after populated early strong concrete, complete a cable work well Whole constructions.
The present invention had not only given full play to the small advantage of fabricated construction short time limit, low cost, environmental perturbation, but also puted forth effort to solve dress Problem with formula component barrier performance difference, can be applicable on a large scale.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, not to The limitation present invention, any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should all include Within protection scope of the present invention.

Claims (10)

1. a kind of assembled cable work well, which is characterized in that including set gradually from bottom to up plain concrete cushion layer (1), Reinforced concrete floor (2), U-shaped steel reinforced concrete side plate (3) and reinforced concrete cover plate (4), in which:
The plain concrete cushion layer (1) is poured by plain concrete, offers pull ring hole and catch pit thereon;
The reinforced concrete floor (2) is arranged on plain concrete cushion layer (1), is poured by armored concrete, thereon Pull ring hole and catch pit are equally offered, and the pull ring on pull ring hole and catch pit and plain concrete cushion layer thereon cheats sum aggregate The position in puddle is corresponding, is additionally provided with card slot (10) on the reinforced concrete floor (2);
The U-shaped steel reinforced concrete side plate (3) is poured by armored concrete, is provided with two pieces, two pieces of U-shaped reinforced concretes Native side plate (3) is horizontally disposed and opening is opposite, by the way that two pieces of U-shaped steel reinforced concrete side plates (3) are inserted into armored concrete bottom In the card slot (10) of plate (2), and in card slot (10) interior casting concrete, U-shaped steel reinforced concrete side plate (3) and reinforced concrete are realized The connection of native bottom plate (2) is linked together by constructional column (12) between the open end of two pieces of U-shaped steel reinforced concrete side plates (3), It is additionally provided on U-shaped steel reinforced concrete side plate (3) concrete beam (13), closed end is also provided with cable through-hole (6);
The reinforced concrete cover plate (4) is poured by armored concrete, is arranged in U-shaped steel reinforced concrete side plate (3) On concrete beam (13), it which is provided with for the manhole (9) of people's discrepancy and for the pull ring (16) of lifting.
2. assembled cable work well as described in claim 1, which is characterized in that the card of the reinforced concrete floor (2) Stiffness bearer (11) are provided in slot.
3. assembled cable work well as described in claim 1, which is characterized in that armored concrete side plate (3) opening The end at end is projected with distributing bar (17), and the distributing bar (17) of two pieces of armored concrete side plate (3) open ends is mutually lapped, Longitudinal reinforcement (18) are banded on distributing bar (17);The constructional column (12) passes through in the construction for being banded with longitudinal reinforcement (18) Early strong concrete acquisition is poured on reinforcing bar (17).
4. assembled cable work well as described in claim 1, which is characterized in that the armored concrete side plate (3) is mixed Solidifying soil crossbeam (13) is equipped with water proof rubber (14).
5. assembled cable work well as claimed in claim 4, which is characterized in that the reinforced concrete cover plate (4) and steel It is filled by early strong concrete in gap between reinforced concrete side plate (3) and water proof rubber (14).
6. assembled cable work well as described in claim 1, which is characterized in that the collection of the reinforced concrete floor (2) Steel grating (5) are provided on puddle, surrounding is provided with 5% gradient;It is set in the pull ring hole of the reinforced concrete floor (2) It is equipped with pull ring.
7. assembled cable work well as claimed in any one of claims 1 to 6, which is characterized in that the concrete beam (13) It is equipped with the pull ring for lifting.
8. assembled cable work well as claimed in claim 3, which is characterized in that the distributing bar (17) and longitudinal reinforcement It (18) is hot rolled ribbed bars, diameter 16mm.
9. such as the described in any item assembled cable work wells of claim 1-8, which is characterized in that the plain concrete cushion layer (1), reinforced concrete floor (2), U-shaped steel reinforced concrete side plate (3) and reinforced concrete cover plate (4) by intensity be C40 or Above concrete pours in advance.
10. a kind of component on site construction method of assembled cable work well, which comprises the steps of:
By previously prepared plain concrete cushion layer (1) lifting to designated position;
Above previously prepared reinforced concrete floor (2) lifting to plain concrete cushion layer (1), it is made to be mounted on plain concrete On bed course (1);
Stiffness bearer (11) are placed in the card slot (10) of reinforced concrete floor (2);
Previously prepared two blocks of armored concrete side plates (3) are lifted respectively to reinforced concrete floor (2), are inserted it into In the card slot (10) of reinforced concrete floor (2);
In card slot and two pieces of armored concrete side plate openings ends are opposite locates casting concrete, with fill armored concrete side plate with Gap between reinforced concrete floor, and pour two blocks of armored concrete side plates and link together;
When concrete strength reaches the 75% of strength failure criterion, by reinforced concrete cover plate (4) lifting to armored concrete side The top of plate (3), is mounted on it on concrete beam of armored concrete side plate, and with Concrete Filled armored concrete lid The assembled in situ of assembled cable work well is completed in gap between plate and armored concrete side plate with this.
CN201810996985.6A 2018-08-29 2018-08-29 A kind of assembled cable work well and component on site construction method Pending CN109024688A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810996985.6A CN109024688A (en) 2018-08-29 2018-08-29 A kind of assembled cable work well and component on site construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810996985.6A CN109024688A (en) 2018-08-29 2018-08-29 A kind of assembled cable work well and component on site construction method

Publications (1)

Publication Number Publication Date
CN109024688A true CN109024688A (en) 2018-12-18

Family

ID=64625385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810996985.6A Pending CN109024688A (en) 2018-08-29 2018-08-29 A kind of assembled cable work well and component on site construction method

Country Status (1)

Country Link
CN (1) CN109024688A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847239A (en) * 2019-11-26 2020-02-28 河北建设集团安装工程有限公司 Assembled large reinforced concrete prefabricated inspection well and construction method thereof
CN111560982A (en) * 2020-04-21 2020-08-21 杭州冠通新型材料有限公司 Installation method of cable prefabricated well
CN111719589A (en) * 2020-06-10 2020-09-29 江苏万年达杭萧钢构有限公司 Prefabricated assembled square shaft
CN111719584A (en) * 2020-07-09 2020-09-29 广西缘晟建设有限公司 Tower crane assembled retaining wall subassembly
CN113482055A (en) * 2021-08-05 2021-10-08 湖北欣山新材料科技有限公司 Prefabricated cable working well with multiple turning angles

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042376A (en) * 2003-07-28 2005-02-17 Sumiken Concrete Kogyo Kk Manhole structure and its construction method
CN202500143U (en) * 2012-03-20 2012-10-24 叶小钗 Built-in dewatering well structure of sump
CN105369828A (en) * 2015-10-30 2016-03-02 国网浙江省电力公司台州供电公司 Prefabricated assembly type cable working well
CN206477362U (en) * 2016-11-15 2017-09-08 福建金固建材有限公司 A kind of pre-fabricated electric cables well
CN208857844U (en) * 2018-08-29 2019-05-14 华中科技大学 A kind of assembled cable work well

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005042376A (en) * 2003-07-28 2005-02-17 Sumiken Concrete Kogyo Kk Manhole structure and its construction method
CN202500143U (en) * 2012-03-20 2012-10-24 叶小钗 Built-in dewatering well structure of sump
CN105369828A (en) * 2015-10-30 2016-03-02 国网浙江省电力公司台州供电公司 Prefabricated assembly type cable working well
CN206477362U (en) * 2016-11-15 2017-09-08 福建金固建材有限公司 A kind of pre-fabricated electric cables well
CN208857844U (en) * 2018-08-29 2019-05-14 华中科技大学 A kind of assembled cable work well

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847239A (en) * 2019-11-26 2020-02-28 河北建设集团安装工程有限公司 Assembled large reinforced concrete prefabricated inspection well and construction method thereof
CN111560982A (en) * 2020-04-21 2020-08-21 杭州冠通新型材料有限公司 Installation method of cable prefabricated well
CN111719589A (en) * 2020-06-10 2020-09-29 江苏万年达杭萧钢构有限公司 Prefabricated assembled square shaft
CN111719589B (en) * 2020-06-10 2021-03-09 江苏万年达杭萧钢构有限公司 Prefabricated assembled square shaft
CN111719584A (en) * 2020-07-09 2020-09-29 广西缘晟建设有限公司 Tower crane assembled retaining wall subassembly
CN113482055A (en) * 2021-08-05 2021-10-08 湖北欣山新材料科技有限公司 Prefabricated cable working well with multiple turning angles

Similar Documents

Publication Publication Date Title
CN109024688A (en) A kind of assembled cable work well and component on site construction method
CN106854873A (en) A kind of engineering method and garage parking in precast spliced sinking type garage parking
CN206545215U (en) A kind of precast spliced sinking type garage parking
CN105696622B (en) A kind of prefabricated city piping lane and its construction method
CN110318776A (en) Method for tunnel construction based on inverted arch and inverted arch filled layer substitution steel-concrete combined structure
CN105201012B (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN109555112A (en) A kind of structure superposition formula diaphram wall and construction method
CN109372018A (en) Soft base Self-sinking type underground space structure construction and construction technology
CN101418569A (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN109457720A (en) The foundation precast elements and its construction method of assembled elevator
CN110219667A (en) Tunnel inverted arch and inverted arch filled layer substitution steel-concrete combined structure and construction technology
CN110397148A (en) A kind of prefabricated assembled catch pit structure and construction method
CN208857844U (en) A kind of assembled cable work well
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN206956949U (en) Overlap wall and intermediate layer laminated floor slab connecting node
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN209082558U (en) A kind of overlapping fabricated construction pipe gallery
CN106193081A (en) A kind of from draining assembled basic structure for moving house
CN207891904U (en) A kind of prefabricated basic component of additional elevator of existing building
CN115324104A (en) Permanent and temporary combined assembly type station and construction method thereof
CN209636573U (en) A kind of assembled self-balancing channel design system
CN209293069U (en) Soft base Self-sinking type underground space structure construction
CN110306534B (en) Construction method of three-in-one underground continuous wall
KR102202598B1 (en) Double wall structure for top-down construction and top-down structure construction method therewith
CN209619998U (en) A kind of superposed type continuous underground wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218