CN109002994A - A kind of power grid project verification management method and system, computer equipment, medium - Google Patents
A kind of power grid project verification management method and system, computer equipment, medium Download PDFInfo
- Publication number
- CN109002994A CN109002994A CN201810827041.6A CN201810827041A CN109002994A CN 109002994 A CN109002994 A CN 109002994A CN 201810827041 A CN201810827041 A CN 201810827041A CN 109002994 A CN109002994 A CN 109002994A
- Authority
- CN
- China
- Prior art keywords
- project
- power grid
- score
- index
- evaluated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012795 verification Methods 0.000 title claims abstract description 59
- 238000007726 management method Methods 0.000 title claims abstract description 40
- 230000008901 benefit Effects 0.000 claims abstract description 25
- 238000011156 evaluation Methods 0.000 claims abstract description 17
- 238000000034 method Methods 0.000 claims description 30
- 238000004590 computer program Methods 0.000 claims description 15
- 238000003860 storage Methods 0.000 claims description 14
- 238000004519 manufacturing process Methods 0.000 claims description 10
- 230000006854 communication Effects 0.000 claims description 9
- 238000004891 communication Methods 0.000 claims description 8
- 230000005611 electricity Effects 0.000 claims description 8
- 208000027418 Wounds and injury Diseases 0.000 claims description 4
- 230000005540 biological transmission Effects 0.000 claims description 4
- 230000015556 catabolic process Effects 0.000 claims description 4
- 230000006378 damage Effects 0.000 claims description 4
- 208000014674 injury Diseases 0.000 claims description 4
- 230000009286 beneficial effect Effects 0.000 abstract description 5
- 230000008569 process Effects 0.000 description 11
- 238000010586 diagram Methods 0.000 description 10
- 238000009826 distribution Methods 0.000 description 7
- 230000006870 function Effects 0.000 description 7
- 238000004458 analytical method Methods 0.000 description 5
- 238000005457 optimization Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 239000011159 matrix material Substances 0.000 description 4
- 230000003287 optical effect Effects 0.000 description 3
- 230000009467 reduction Effects 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000011049 filling Methods 0.000 description 2
- 230000010354 integration Effects 0.000 description 2
- 230000000644 propagated effect Effects 0.000 description 2
- 238000011002 quantification Methods 0.000 description 2
- 239000004065 semiconductor Substances 0.000 description 2
- 238000003786 synthesis reaction Methods 0.000 description 2
- 230000009466 transformation Effects 0.000 description 2
- 238000013473 artificial intelligence Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000007405 data analysis Methods 0.000 description 1
- 238000013499 data model Methods 0.000 description 1
- 238000000354 decomposition reaction Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012854 evaluation process Methods 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 238000005194 fractionation Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000010606 normalization Methods 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000004445 quantitative analysis Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000012216 screening Methods 0.000 description 1
- 238000012549 training Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06393—Score-carding, benchmarking or key performance indicator [KPI] analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Data Mining & Analysis (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Game Theory and Decision Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention provides a kind of power grid project verification management method, comprising: obtains the project data of power grid project to be evaluated;Judge whether to meet in the project information sufficiently project verification information, if it is, the power grid project to be evaluated is assessed as highest level project;If it is not, then according to power grid security index and/or service efficiency index and/or economic benefits indicator evaluation rank in the project data.It can be after the project data for getting power grid project, according to existing abundant project verification information, and specific project data goes to judge the rank of the power grid project, and then can distinguish the rank of different power grid projects, select important power grid project, the reference as the project implementation.A kind of power grid project verification management system, computer equipment, medium provided by the invention, it may have above-mentioned beneficial effect, details are not described herein.
Description
Technical field
The present invention relates to power grid project management techniques field, in particular to a kind of power grid project verification management method and system, meter
Calculate machine equipment, medium.
Background technique
Power grid enterprises' project verification management is one and covers multidisciplinary, multi-field comprehension management work, from planning, feasibility study,
Design generates project library, and project management includes relevant work such as large project and Project Portfolio Management etc..Project is commonly invented
Scheme is to generate project based on full voltage grade to preferably generate library.This be also solve power grid enterprises Electric Power Network Planning project management ask
A kind of method of topic.In existing invention, project preference ordering system is initially set up, then according to the investment amount of each voltage class
With project preference ordering score, incidence relation between integration project, to project from voltage levels to low-voltage-grade successively
It is screened, ultimately generates the preferred library of full voltage grade planned project.This kind of invention is on the basis of being based on voltage class, mainly
It investigates engineering attribute index, establish project degree of urgency index and constructing emphases etc. to planned project scoring.This kind of invention pair
It is subjective in the selection of index, determined to further reduce so that examining or check range on the basis of voltage class, it is difficult to
Guarantee comprehensive.
As grid company life of assets reaches lifetime in the following concentration and what electricity changed gos deep into, grid company will face
The number of entry increases and the double challenge of fund tightening.Therefore, power grid enterprises how to make overall planning economic benefit and society effect
Benefit, optimization of investment ratio reinforce planned project management, promote the coordinated development of production intermediate item, become power grid enterprises' work weight
Point.
Therefore, how when power grid is approved and initiate a project, in the case where guaranteeing that comprehensive summation considers indices, to project into
The reasonable evaluation of row is those skilled in the art's technical problem urgently to be resolved.
Summary of the invention
In view of this, the purpose of the present invention is to provide a kind of power grid project verification management method and system, computer equipment, Jie
Matter, in the case where guaranteeing that comprehensive summation considers indices, can reasonably comment project when power grid is approved and initiate a project
Valence.Its concrete scheme is as follows:
In a first aspect, the present invention provides a kind of power grid project verification management method, comprising:
Obtain the project data of power grid project to be evaluated;
Judge whether to meet in the project information sufficiently project verification information,
If it is, the power grid project to be evaluated is assessed as highest level project;
If it is not, then according to power grid security index and/or service efficiency index and/or economic effect in the project data
Beneficial index evaluation rank.
Preferably,
The power grid security index specifically includes: electric power safety and equipment breakdown number, electric power safety and device events number, and hundred
Ten thousand working hour industrial injury accident digit rates, relay protection performance factor, production are implemented control service communication channel mean down time, are adjusted
Degree automation main station system be averaged failure number, pacifies from any one or more than one of combination in device performance factor.
Preferably,
The service efficiency index specifically includes: equipment state index, medium-voltage line failure rate, rate of qualified voltage, user
Be averaged power-off event rate, transformer forced outage rate, breaker forced outage rate, any one in transmission line of electricity forced outage rate
Item or more than one of combination.
Preferably,
The economic benefits indicator specifically includes: the net value rate of ten thousand yuan of fixed assets O&M expenses and/or write-off equipment.
Preferably,
The power grid security index and/or service efficiency index and/or economic benefit according in the project data refers to
Mark evaluation rank, comprising:
According to the power grid security index and corresponding first weight in the project data, the first score is obtained;
According to the service efficiency index and corresponding second weight in the project data, the second score is obtained;
According to the economic benefits indicator and corresponding third weight in the project data, third score is obtained;
And be added first score and/or the second score and/or third score to obtain overall merit score, with determination
The project level of power grid project to be evaluated.
Preferably,
After being added first score and/or the second score and/or third score to obtain overall merit score, also
Include:
All power grid projects to be evaluated are arranged according to overall merit score descending.
Second aspect, the present invention provide a kind of power grid project verification management system, comprising:
Project data obtains module, for obtaining the project data of power grid project to be evaluated;
Sufficiently project verification signal judgement module, for judging to whether there is in the project information sufficiently project verification information,
Highest level determination module is used for if it is determined that meet sufficiently project verification information in the project information, then will be described
Power grid project to be evaluated is assessed as highest level project;
Rank assessment module is used for if it is determined that meeting sufficiently project verification information in the project information, then according to the item
Power grid security index and/or service efficiency index and/or economic benefits indicator of the mesh number in evaluate rank.
Preferably, further includes:
Project arranges module, for arranging all power grid projects to be evaluated according to overall merit score descending.
The third aspect, the present invention provide a kind of computer equipment, comprising:
Memory, for storing computer program;
Processor realizes the step of any of the above-described kind of power grid project verification management method when for executing the computer program
Suddenly.
Fourth aspect, the present invention provide a kind of computer readable storage medium, deposit on the computer readable storage medium
Computer program is contained, the computer program realizes any of the above-described kind of power grid project verification management method when being executed by processor
Step.
The present invention provides a kind of power grid project verification management method, comprising: obtains the project data of power grid project to be evaluated;Judgement
Whether sufficiently project verification information is met in the project information, if it is, the power grid project to be evaluated is assessed as the superlative degree
Other project;If it is not, then according to power grid security index and/or service efficiency index and/or economic effect in the project data
Beneficial index evaluation rank.It can be and specific after the project data for getting power grid project, according to existing abundant project verification information
Project data go to judge the rank of the power grid project, and then the rank of different power grid projects can be distinguished, selected important
Power grid project, the reference as the project implementation.
A kind of power grid project verification management system, computer equipment, medium provided by the invention, it may have above-mentioned beneficial effect
Fruit, details are not described herein.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis
The attached drawing of offer obtains other attached drawings.
Fig. 1 is a kind of flow chart of power grid project verification management method provided by a kind of specific embodiment of the present invention;
Fig. 2 is the schematic diagram of the evaluation process of power grid project to be set up the project provided by a kind of specific embodiment of the present invention;
Fig. 3 is each index weights distribution map applied in a kind of specific embodiment of the present invention;
Fig. 4 is the flow diagram that indices are determined provided by another specific embodiment of the invention;
Fig. 5 is the composition schematic diagram of power grid project verification management system provided by a kind of specific embodiment of the present invention;
Fig. 6 is the structural schematic diagram of computer equipment provided by another specific embodiment of the invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Referring to FIG. 1, Fig. 1 is a kind of stream of power grid project verification management method provided by a kind of specific embodiment of the present invention
Cheng Tu.
In a kind of specific embodiment of the invention, the embodiment of the present invention provides a kind of power grid project verification management method, packet
It includes:
S11: the project data of power grid project to be evaluated is obtained;
Firstly, the project data of power grid project will be obtained according to actual demand, wherein should include abundant project verification
Information, that is to say, that, if met, can not include other projects comprising whether meeting the condition sufficiently set up the project
Information does not interfere assessment of this method to power grid project yet, but to be on the safe side, it can also include the letter of insufficient project verification
Breath, for example, power grid security index and/or service efficiency index and/or economic benefits indicator evaluate rank.
Specifically, the history item and actual demand data in electric power big data platform can be indexed and carry out dimensionality reduction point
Analysis, while effectively to accept the existing system standard of company, adequate condition determines the mainly standard according to company's project access.According to
These system standards need the project data of the power grid project to be evaluated obtained to specify.
S12: judge whether to meet in the project information sufficiently project verification information;
Generally, grid company repair entry criteria application detailed rules and regulations data include transformer class equipment, it is Switch equipment, defeated
Electric class, electrical distribution kind equipment, distribution line class, peace are repaired quasi- from class equipment, communication class equipment, comprehensive, administrative office class, warehouse
Enter condition application detailed rules and regulations;Technological transformation entry criteria application detailed rules and regulations include transformer class equipment, Switch equipment, transmission of electricity class, distribution class,
Pacify from class, relay protection class, automation class, communication class, jury rig class, administrative office class, warehouse class, teach training base class, comprehensive
Technological transformation entry criteria application detailed rules and regulations data.
Entry criteria application detailed rules and regulations data, by project data dimensionality reduction, be divided into I class (must implement), II class (preferential to ensure),
Group III (reasonable arrangement), four class of IV class (strict control), primarily determine the priority level of project.
Classification of the production project preference ordering model based on application detailed rules and regulations determines that I class (must implement) meets adequate condition,
Belong to guarantee and implements intermediate item;Determine that II class (preferential to ensure), Group III (reasonable arrangement), IV class (strict control) are unsatisfactory for filling
Slitting part belongs to elastic implementation of class.
Therefore, it is possible to judge that with the presence or absence of satisfaction sufficiently project verification in the project verification information of power grid project, that is, must implement
The information of condition.Abundant desirable information may relate to planning, examination & approval, policy change, natural situation or other be a series of
Situation, can according to the actual situation, increase or reduce sufficiently project verification information.
S13: if it is, the power grid project to be evaluated is assessed as highest level project;
Naturally, if a power grid project to be evaluated meets the condition sufficiently set up the project, which will be evaluated
Particularly, the project can also be marked for the project of highest level in order to remind staff to can be noted that this project
Why the foundation of highest level is assessed as.Specifically, if carrying out percentage scoring mechanism to divide power grid project to be evaluated
Grade, then highest level project can be made to 100 scores.
S14: if it is not, then according to power grid security index and/or service efficiency index and/or warp in the project data
Performance indicator of helping evaluates rank.
If power grid project to be evaluated is unsatisfactory for abundant project verification condition, if then then needing to be somebody's turn to do specifically according to implementation
The possible some efficiencies of project, income to carry out the power grid project marking item by item, are then classified.It specifically can be with
It is evaluated according to power grid security index and/or service efficiency index and/or economic benefits indicator evaluation rank.
Specifically, when implementing, power grid security index be can specifically include: electric power safety and equipment breakdown number, power ampere
Complete and device events number, million working hour industrial injury accident digit rates, relay protection performance factor, it is logical that control service communication is implemented in production
Road mean down time, dispatching automation main station system are averaged failure number, and peace is from any one in device performance factor
Or more than one of combination.
Service efficiency index can specifically include: equipment state index, medium-voltage line failure rate, rate of qualified voltage, user
Be averaged power-off event rate, transformer forced outage rate, breaker forced outage rate, any one in transmission line of electricity forced outage rate
Item or more than one of combination.
Economic benefits indicator can specifically include: the net value rate of ten thousand yuan of fixed assets O&M expenses and/or write-off equipment.
Certainly, power grid security index, service efficiency index, economic benefits indicator may further include other specific targets,
Here it no longer states one by one.
Based on declaring mark reference and company's off-the-shelf item, checking and approving status, analysis obtains three of final project appraisal
Data dimension and corresponding specific evaluation index.Three dimensions are respectively power grid security, service efficiency, economic benefit, Ge Gewei
It is as shown in table 1 below to spend corresponding specific evaluation index:
The specific evaluation index of table 1
Further, in order to enable every specific index can comprehensive quantification be the index that can be compared, Ke Yigen
According to the power grid security index and/or service efficiency index and/or economic benefits indicator evaluation rank in the project data, specifically
Ground, can be with
According to the power grid security index and corresponding first weight in the project data, the first score is obtained;
According to the service efficiency index and corresponding second weight in the project data, the second score is obtained;
According to the economic benefits indicator and corresponding third weight in the project data, third score is obtained;
And be added first score and/or the second score and/or third score to obtain overall merit score, with determination
The project level of power grid project to be evaluated.
That is, can will be included specific in power grid security index, service efficiency index, economic benefits indicator
Weight is set separately in indices, in the case where indices carry out quantification, can be calculated by way of weighting
To overall merit score, so that it is determined that the project level of power grid project to be evaluated.
Further, it after each power grid project to be evaluated is carried out the overall merit of fractionation, can be commented according to synthesis
Valence score arranges all power grid projects to be evaluated according to overall merit score descending.In order to which administrative staff can facilitate
Ground refers to the overall merit score, picks out important power grid project to be evaluated.
Specifically, in a specific embodiment, refer to when to power grid security index, service efficiency index, economic benefit
When every specific targets of target are scored, the following table 2 can be referred to:
The scoring formula of 2 indices of table
Fig. 2, Fig. 3 are please referred to, Fig. 2 is the assessment of power grid project to be set up the project provided by a kind of specific embodiment of the present invention
The schematic diagram of process;Fig. 3 is each index weights distribution map applied in a kind of specific embodiment of the present invention.
It in conjunction with Fig. 2, sees from left to right, the comprehensive guarantee for meeting sufficiently project verification condition is implemented intermediate item and is unsatisfactory for sufficiently
The elasticity of condition implements intermediate item appraisal result, is ranked up according to the principle of score value from high to low.With minimum score value or fund
Limit determines project optimization range as limit value.The comprehensive guarantee for meeting adequate condition implements intermediate item and is unsatisfactory for filling
The elasticity of slitting part implements intermediate item appraisal result, is ranked up according to the principle of score value from high to low.The high person of score value preferentially into
Row investment.The following figure illustrates the whole process to form ranking results.
It is possible, firstly, to first to included specific each in power grid security index, service efficiency index, economic benefits indicator
Item index, gives a mark according to the evaluation method in table 2, can be with reference to each index weights distribution in Fig. 3 after marking
Weight in figure, is weighted, and synthesis obtains three dimensionality comprehensive score (namely overall merit score), then presses to a project
It is ranked up according to the height of score.
In specific implementation, the index weights for reasonably determining assessment indicator system are production project preference ordering scoring moulds
Type establish basis, the science of index weights be it can objectively reflect the composition of the preferred evaluation factor of production project and
Its inner link.
Since contribution of each subsystem to overall merit target is different, each evaluation index of indicator layer is corresponding to its to realizing
A upper layer subsystem contribution it is also different, so needing first to determine each index phase before each sub-goal of overall merit
To the relative importance weights of one layer of target thereon, on the basis of comprehensive analysis and combination experience evaluation, with product side
Root method (geometrical mean method) and analytic hierarchy process (AHP) (AHP method) determine weighted value, specific steps are as follows:
Weight vector is calculated with product root method, that is, geometrical mean method and carries out consistency check, if m rank judgment matrix is
A first even multiplies and opens m power by being about to each element, that is, seeks the geometrical mean of each row element: bi, i=1,2 ... m, then bi
Normalization, that is, acquire the weight coefficient of index xj: ω j, the reasonability of product root method can be explained by the condition for consistence of A.
The quantitative index for measuring inconsistent degree is known as coincident indicator C.I., may be defined as: C.I=(λ max-m)/(m-
1) it, considers further that the relationship between consistency and matrix order, introduces Aver-age Random Consistency Index R.I. value.
3 coincident indicator R.I. value of table
m | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
R.I. | 0 | 0.5149 | 0.8931 | 1.1185 | 1.2494 | 1.345 | 1.42 |
m | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
R.I | 1.4616 | 1.4874 | 1.5156 | 1.5405 | 1.5583 | 1.5779 | 1.5894 |
Random consistency ratio is denoted as C.R., and as C.R.=C.I./R.I. < 0.10, it is believed that judgment matrix has and can connect
The inconsistency received, otherwise, the judgment matrix for being considered as tentatively establishing be it is unsatisfactory, need assignment again, carefully
Amendment, until consistency check passes through.
Each index weights are determined with analytic hierarchy process (AHP), it is top to be denoted as z if system decomposition is three levels, the
Two layers are denoted as Y={ y1, y2 ..., yn }, and third layer is denoted as X={ x1, x2 ..., xn }, are to the weight vector of z if having obtained Y
ω z (Y)=weight vector ω z (X)=(ω z (x1), ω z of (ω z (y1), ω z (y2) ..., ω z (the yn)) T, X about yi
(x2) ..., ω z (xm)) T, then the specific gravity that xj is accounted in z is ω z (Xj)=Σ ω yi (xj) ω z (yi).
With analytic hierarchy process (AHP), the weight of each evaluative dimension and evaluation index in setting item preference ordering score-system.
Please referring to Fig. 4, Fig. 4 is the process signal that indices are determined provided by another specific embodiment of the invention
Figure.
It should be noted that on the basis of above-mentioned specific embodiment, in present embodiment, emphasis to how
To the indices of power grid project to be evaluated, specifically, the history item and reality that can be indexed in electric power big data platform are needed
It seeks data and carries out Dimension Reduction Analysis, while effectively to accept the existing system standard of company, adequate condition determines mainly according to company
The standard of project access.That is, in various projects related with electric system, according to related audio-video, document, number
Data model is established according to library etc., also will be exactly the model of every specific targets, closed it is possible to further every specific targets
Connection, such as can be by electric power safety and the surprisingly rate unification of equipment breakdown number, electric power safety and device events number, million working hour industrial injuries
It is divided into power grid security index, similarly, other specific targets can be divided into service efficiency index, economic benefit
In index.To establish the level and data relationship of indices.To be used with the method provided in embodiments of the present invention
With these data.
The present invention provides a kind of power grid project verification management method, comprising: obtains the project data of power grid project to be evaluated;Judgement
Whether sufficiently project verification information is met in the project information, if it is, the power grid project to be evaluated is assessed as the superlative degree
Other project;If it is not, then according to power grid security index and/or service efficiency index and/or economic effect in the project data
Beneficial index evaluation rank.It can be and specific after the project data for getting power grid project, according to existing abundant project verification information
Project data go to judge the rank of the power grid project, and then the rank of different power grid projects can be distinguished, selected important
Power grid project, the reference as the project implementation.
Referring to FIG. 5, the composition that Fig. 5 is power grid project verification management system provided by a kind of specific embodiment of the present invention shows
It is intended to.
In a kind of specific embodiment of the invention, the embodiment of the present invention provides a kind of power grid project verification management system 500,
Include:
Project data obtains module 510, for obtaining the project data of power grid project to be evaluated;
Sufficiently project verification signal judgement module 520, for judging to whether there is in the project information sufficiently project verification information,
Highest level determination module 530 is used for if it is determined that meeting sufficiently project verification information in the project information, then by institute
It states power grid project to be evaluated and is assessed as highest level project;
Rank assessment module 540 is used for if it is determined that meeting sufficiently project verification information in the project information, then according to
Power grid security index and/or service efficiency index and/or economic benefits indicator in project data evaluate rank.
Preferably, power grid project verification management system 500 further include:
Project arranges module 550, for arranging all power grid projects to be evaluated according to overall merit score descending.
The embodiment of the present invention is then by based on electric power big data analysis platform, by collecting power grid in power generation, distribution, defeated
The mass data that the links such as electricity, marketing and management generate, in platform unified integration, screening, creativeness is to have used to be based on
Artificial intelligence, the optimization algorithm of uncertain quantitative analysis, and declare in conjunction with the existing production project of power grid enterprises, check and approve and written
It is required that obtain autonomous project verification optimization model, and it is horizontal to promote power grid intelligent decision, it formulates more scientific production plan and provides branch
Support.The present invention solves the problems such as production intermediate item project verification job requirement is high, and the project verification content that need to be considered is more, utilizes the big number of electric power
According to analysis platform, the index system that many factors set up electric grid investment project appraisal is comprehensively considered, construct power network construction project
The autonomous project verification optimization model of investment.
Referring to FIG. 6, Fig. 6 is the structural representation of computer equipment provided by another specific embodiment of the invention
Figure.
In another specific embodiment of the invention, the embodiment of the present invention provides a kind of computer equipment, comprising:
Memory, for storing computer program;
Processor realizes a kind of electricity described in any of the above-described kind of specific embodiment when for executing the computer program
The step of net project verification management method.
Below with reference to Fig. 6, it illustrates the structural schematic diagrams for the computer equipment for being suitable for being used to realize the embodiment of the present application.
Computer equipment shown in Fig. 6 is only an example, should not function to the embodiment of the present application and use scope bring it is any
Limitation.
As shown in fig. 6, computer system 600 includes processor (CPU) 601, it can be according to being stored in read-only memory
(ROM) it the program in 602 or is executed respectively from the program that storage section 608 is loaded into random access storage device (RAM) 603
Kind movement appropriate and processing.In RAM 603, also it is stored with system 600 and operates required various programs and data.
CPU 601, ROM 602 and RAM 603 are connected with each other by bus 604.Input/output (I/O) interface 603
It is connected to bus 604.
I/O interface 605 is connected to lower component: the importation 606 including keyboard, mouse etc.;It is penetrated including such as cathode
The output par, c 607 of spool (CRT), liquid crystal display (LCD) etc. and loudspeaker etc.;Storage section 608 including hard disk etc.;
And the communications portion 609 of the network interface card including LAN card, modem etc..Communications portion 609 via such as because
The network of spy's net executes communication process.Driver 610 is also connected to I/O interface 607 as needed.Detachable media 611, such as
Disk, CD, magneto-optic disk, semiconductor memory etc. are mounted on as needed on driver 610, in order to read from thereon
Computer program be mounted into storage section 608 as needed.
Particularly, in accordance with an embodiment of the present disclosure, it may be implemented as computer above with reference to the process of flow chart description
Software program.For example, embodiment of the disclosure includes a kind of computer program product comprising be carried on computer-readable medium
On computer program, which includes the program code for method shown in execution flow chart.In such reality
It applies in example, which can be downloaded and installed from network by communications portion 609, and/or from detachable media
611 are mounted.When the computer program is executed by processor (CPU) 601, the above-mentioned function limited in the present processes is executed
Energy.It should be noted that computer-readable medium described herein can be computer-readable signal media or computer
Readable medium either the two any combination.Computer-readable medium for example may be-but not limited to-electricity,
Magnetic, optical, electromagnetic, infrared ray or semiconductor system, device or device, or any above combination.Computer-readable medium
More specific example can include but is not limited to: there is the electrical connection of one or more conducting wires, portable computer diskette, hard
Disk, random access storage device (RAM), read-only memory (ROM), erasable programmable read only memory (EPROM or flash memory), light
Fibre, portable compact disc read-only memory (CD-ROM), light storage device, magnetic memory device or above-mentioned any appropriate
Combination.In this application, it includes or the tangible medium of storage program that the program can be with that computer-readable medium, which can be any,
It is commanded execution system, device or device use or in connection.And in this application, computer-readable signal
Medium may include in a base band or as the data-signal that carrier wave a part is propagated, wherein carrying computer-readable journey
Sequence code.The data-signal of this propagation can take various forms, including but not limited to electromagnetic signal, optical signal or above-mentioned
Any appropriate combination.Computer-readable signal media can also be any computer-readable other than computer-readable medium
Medium, the computer-readable medium can be sent, propagated or transmitted for being used by instruction execution system, device or device
Or program in connection.The program code for including on computer-readable medium can pass with any suitable medium
It is defeated, including but not limited to: wireless, electric wire, optical cable, RF etc. or above-mentioned any appropriate combination.
The calculating of the operation for executing the application can be write with one or more programming languages or combinations thereof
Machine program code, described program design language include object-oriented programming language-such as Java, Smalltalk, C+
+, further include conventional procedural programming language-such as " C " language or similar programming language.Program code can
Fully to execute, partly execute on the user computer on the user computer, be executed as an independent software package,
Part executes on the remote computer or executes on a remote computer or server completely on the user computer for part.
In situations involving remote computers, remote computer can pass through the network of any kind --- including local
Net (LAN) or wide area network (WAN)-are connected to subscriber computer, or, it may be connected to outer computer (such as using because of spy
Service provider is netted to connect by internet).
Flow chart and block diagram in attached drawing are illustrated according to the system of the various embodiments of the application, method and computer journey
The architecture, function and operation in the cards of sequence product.In this regard, each box in flowchart or block diagram can generation
A part of one module, program segment or code of table, a part of the module, program segment or code include one or more use
The executable instruction of the logic function as defined in realizing.It should also be noted that in some implementations as replacements, being marked in box
The function of note can also occur in a different order than that indicated in the drawings.For example, two boxes succeedingly indicated are actually
It can be basically executed in parallel, they can also be executed in the opposite order sometimes, and this depends on the function involved.Also it to infuse
Meaning, the combination of each box in block diagram and or flow chart and the box in block diagram and or flow chart can be with holding
The dedicated hardware based system of functions or operations as defined in row is realized, or can use specialized hardware and computer instruction
Combination realize.
As still another embodiment of the invention, the embodiment of the present invention provides a kind of computer readable storage medium institute
It states and is stored with computer program on computer readable storage medium, the computer program realizes above-mentioned when being executed by processor
The step of one of specific embodiment of anticipating power grid project verification management method.
The computer-readable medium can be included in computer or terminal device described in above-described embodiment;?
It can be individualism, and without in the supplying computer equipment.Above-mentioned computer-readable medium carries one or more
Program, when said one or multiple programs are executed by the computer equipment, so that the computer equipment: obtaining electricity to be evaluated
The project data of net project;Judge whether to meet in the project information sufficiently project verification information, if it is, by described to be evaluated
Power grid project is assessed as highest level project;If it is not, then according to power grid security index and/or service in the project data
Efficiency index and/or economic benefits indicator evaluate rank.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only storage
Device (Read-Only Memory, ROM), random access memory (Random Access Memory, RAM), magnetic disk or light
The various media that can store program code such as disk.
Finally, it is to be noted that, herein, relational terms such as first and second and the like be used merely to by
One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation
Between there are any actual relationship or orders.Moreover, the terms "include", "comprise" or its any other variant meaning
Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that
A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or
The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged
Except there is also other identical elements in the process, method, article or apparatus that includes the element.
A kind of power grid project verification management method provided by the present invention and system, computer equipment, medium are carried out above
It is discussed in detail, used herein a specific example illustrates the principle and implementation of the invention, above embodiments
Illustrate to be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, according to
According to thought of the invention, there will be changes in the specific implementation manner and application range, in conclusion the content of the present specification
It should not be construed as limiting the invention.
Claims (10)
- The management method 1. a kind of power grid is set up the project characterized by comprisingObtain the project data of power grid project to be evaluated;Judge whether to meet in the project information sufficiently project verification information;If it is, the power grid project to be evaluated is assessed as highest level project;If it is not, then according in the project data power grid security index and/or service efficiency index and/or economic benefit refer to Mark evaluation rank.
- The management method 2. power grid according to claim 1 is set up the project, which is characterized in thatThe power grid security index specifically includes: electric power safety and equipment breakdown number, electric power safety and device events number, Bai Wangong When industrial injury accident digit rate, relay protection performance factor, production implement control service communication channel mean down time, scheduling from Dynamicization main station system is averaged failure number, and peace is from any one or more than one of combination in device performance factor.
- The management method 3. power grid according to claim 1 is set up the project, which is characterized in thatThe service efficiency index specifically includes: equipment state index, medium-voltage line failure rate, rate of qualified voltage, user are average Power-off event rate, transformer forced outage rate, breaker forced outage rate, any one in transmission line of electricity forced outage rate or More than one of combination.
- The management method 4. power grid according to claim 1 is set up the project, which is characterized in thatThe economic benefits indicator specifically includes: the net value rate of ten thousand yuan of fixed assets O&M expenses and/or write-off equipment.
- The management method 5. power grid according to any one of claims 1 to 4 is set up the project, which is characterized in thatThe power grid security index and/or service efficiency index and/or economic benefits indicator according in the project data is commented Deciding grade and level is other, comprising:According to the power grid security index and corresponding first weight in the project data, the first score is obtained;According to the service efficiency index and corresponding second weight in the project data, the second score is obtained;According to the economic benefits indicator and corresponding third weight in the project data, third score is obtained;And be added first score and/or the second score and/or third score to obtain overall merit score, it is to be evaluated with determination The project level of valence power grid project.
- The management method 6. power grid according to claim 5 is set up the project, which is characterized in thatAfter being added first score and/or the second score and/or third score to obtain overall merit score, also wrap It includes:All power grid projects to be evaluated are arranged according to overall merit score descending.
- The management system 7. a kind of power grid is set up the project characterized by comprisingProject data obtains module, for obtaining the project data of power grid project to be evaluated;Sufficiently project verification signal judgement module, for judging to whether there is in the project information sufficiently project verification information,Highest level determination module, be used for if it is determined that in the project information meet sufficiently project verification information, then will be described to be evaluated Valence power grid project is assessed as highest level project;Rank assessment module is used for if it is determined that meeting sufficiently project verification information in the project information, then according to the item number Power grid security index and/or service efficiency index and/or economic benefits indicator in evaluate rank.
- The management system 8. power grid according to claim 7 is set up the project, which is characterized in that further include:Project arranges module, for arranging all power grid projects to be evaluated according to overall merit score descending.
- 9. a kind of computer equipment characterized by comprisingMemory, for storing computer program;Processor is realized when for executing the computer program such as power grid as claimed in any one of claims 1 to 6 project verification management The step of method.
- 10. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium Program is realized when the computer program is executed by processor such as power grid as claimed in any one of claims 1 to 6 project verification manager The step of method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810827041.6A CN109002994A (en) | 2018-07-25 | 2018-07-25 | A kind of power grid project verification management method and system, computer equipment, medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810827041.6A CN109002994A (en) | 2018-07-25 | 2018-07-25 | A kind of power grid project verification management method and system, computer equipment, medium |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109002994A true CN109002994A (en) | 2018-12-14 |
Family
ID=64597983
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810827041.6A Pending CN109002994A (en) | 2018-07-25 | 2018-07-25 | A kind of power grid project verification management method and system, computer equipment, medium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109002994A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110910013A (en) * | 2019-11-20 | 2020-03-24 | 南方电网能源发展研究院有限责任公司 | Method for establishing electric power system project evaluation model and evaluation method |
CN111598418A (en) * | 2020-04-29 | 2020-08-28 | 思创数码科技股份有限公司 | Balance-based item sorting method, balance-based item sorting device, balance-based item sorting equipment and storage medium |
CN112001629A (en) * | 2020-08-24 | 2020-11-27 | 北京鸿联九五信息产业有限公司 | Risk early warning method, device, system and storage medium |
CN113159537A (en) * | 2021-04-06 | 2021-07-23 | 南方电网能源发展研究院有限责任公司 | Evaluation method and device for new technical project of power grid and computer equipment |
-
2018
- 2018-07-25 CN CN201810827041.6A patent/CN109002994A/en active Pending
Non-Patent Citations (1)
Title |
---|
章玲玲 等: "关于农网中低压项目精益化管理思路的探讨", 《科技广场》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110910013A (en) * | 2019-11-20 | 2020-03-24 | 南方电网能源发展研究院有限责任公司 | Method for establishing electric power system project evaluation model and evaluation method |
CN111598418A (en) * | 2020-04-29 | 2020-08-28 | 思创数码科技股份有限公司 | Balance-based item sorting method, balance-based item sorting device, balance-based item sorting equipment and storage medium |
CN112001629A (en) * | 2020-08-24 | 2020-11-27 | 北京鸿联九五信息产业有限公司 | Risk early warning method, device, system and storage medium |
CN113159537A (en) * | 2021-04-06 | 2021-07-23 | 南方电网能源发展研究院有限责任公司 | Evaluation method and device for new technical project of power grid and computer equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Aliabadi et al. | An agent-based simulation of power generation company behavior in electricity markets under different market-clearing mechanisms | |
Sharifzadeh et al. | Multi-period stochastic security-constrained OPF considering the uncertainty sources of wind power, load demand and equipment unavailability | |
CN109002994A (en) | A kind of power grid project verification management method and system, computer equipment, medium | |
Miles et al. | Community of practice for modeling disaster recovery | |
Akbari et al. | A multi-stage stochastic transmission expansion planning method | |
Gomes et al. | A two-stage strategy for security-constrained AC dynamic transmission expansion planning | |
Talinli et al. | Comparative analysis for energy production processes (EPPs): Sustainable energy futures for Turkey | |
CN107453897B (en) | Node importance evaluation method and device, electronic equipment and storage medium | |
CN104715318A (en) | Multi-dimensional operational risk evaluating method for communication network | |
Eghbal et al. | Transmission expansion planning by meta-heuristic techniques: a comparison of shuffled frog leaping algorithm, PSO and GA | |
Pousinho et al. | A stochastic programming approach for the development of offering strategies for a wind power producer | |
Rodriguez-Calvo et al. | Scalability and replicability analysis of large-scale smart grid implementations: Approaches and proposals in Europe | |
Moreno et al. | Integrated reliability and cost–benefit-based standards for transmission network operation | |
CN109359277A (en) | Data monitoring method, equipment and computer storage medium | |
Moslemi et al. | Maintenance scheduling of transmission systems considering coordinated outages | |
Janjic et al. | Renewable energy integration in smart grids-multicriteria assessment using the fuzzy analytical hierarchy process | |
CN114548800A (en) | Future-state power grid maintenance risk identification method and device based on power grid knowledge graph | |
Cho et al. | Systematic Approach of TOPSIS Decision‐Making for Construction Method Based on Risk Reduction Feedback of Extended QFD‐FMEA | |
Huang et al. | A review of public safety power shutoffs (psps) for wildfire mitigation: Policies, practices, models and data sources | |
Yang et al. | Optimal investment decision of distribution network with investment ability and project correlation constraints | |
Birchfield | The creation, validation, and application of synthetic power grids | |
Moridi et al. | Prioritizing power outages causes in different scenarios of the global business network matrix by using Bwm and Topsis | |
Liu et al. | Study on construction safety management in megaprojects from the perspective of resilient governance | |
Khallaf et al. | A risk registry for renegotiation in public-private partnership (PPP) projects: ICRAM-PPP | |
Sergio et al. | Optimal subtransmission switching using a reliability simulation-based multi-objective optimization model |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181214 |