CN109000094A - A kind of small towns river water treatment facilities secure mounting arrangements - Google Patents

A kind of small towns river water treatment facilities secure mounting arrangements Download PDF

Info

Publication number
CN109000094A
CN109000094A CN201810716193.9A CN201810716193A CN109000094A CN 109000094 A CN109000094 A CN 109000094A CN 201810716193 A CN201810716193 A CN 201810716193A CN 109000094 A CN109000094 A CN 109000094A
Authority
CN
China
Prior art keywords
water treatment
treatment facilities
pedestal
welded
box body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810716193.9A
Other languages
Chinese (zh)
Other versions
CN109000094B (en
Inventor
冯皓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaoxing Jiayue Textile Machinery Co., Ltd
Original Assignee
Huzhou Yi Chuang Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huzhou Yi Chuang Environmental Engineering Co Ltd filed Critical Huzhou Yi Chuang Environmental Engineering Co Ltd
Priority to CN201810716193.9A priority Critical patent/CN109000094B/en
Publication of CN109000094A publication Critical patent/CN109000094A/en
Application granted granted Critical
Publication of CN109000094B publication Critical patent/CN109000094B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16MFRAMES, CASINGS OR BEDS OF ENGINES, MACHINES OR APPARATUS, NOT SPECIFIC TO ENGINES, MACHINES OR APPARATUS PROVIDED FOR ELSEWHERE; STANDS; SUPPORTS
    • F16M7/00Details of attaching or adjusting engine beds, frames, or supporting-legs on foundation or base; Attaching non-moving engine parts, e.g. cylinder blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Biological Treatment Of Waste Water (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of small towns river water treatment facilities secure mounting arrangements, including pedestal, deck is welded at the top of the pedestal, water treatment facilities ontology is connected at the top of the deck, the first tooth set is mounted at left and right sides of the base intracavity, the first tooth set internal screw thread is equipped with adjustable column, the bottom of the pedestal is installed by rack gear, the bottom of the gear ring is movably installed with externally threaded thread bush, the inside thread of the thread bush is connected on the outer wall of adjustable column, bearing (ball) cover is socketed on the outer wall of the thread bush, fixed frame is welded on the outside of the bearing (ball) cover, it is socketed on the outer wall of pedestal at the top of the fixed frame.The small towns river water treatment facilities secure mounting arrangements, by the way that height adjustment mechanism is arranged, water treatment facilities ontology can be installed on the river of precipitous injustice and be rectified, making water treatment facilities ontology is not in the phenomenon of skew, to guarantee normally coming into operation for water treatment facilities ontology later period.

Description

A kind of small towns river water treatment facilities secure mounting arrangements
Technical field
The present invention relates to water treatment facilities mounting technique field, specially a kind of small towns river water treatment facilities are fixedly mounted Device.
Background technique
With gradually going deep into for environmental consciousness, sewage treatment has gradually obtained benign development, especially at the water in river Reason aspect generally installs water treatment facilities in river two sides on the spot, to be carried out in situ sewage treatment.
For some small towns rivers, river is precipitous and narrow, thus the installation bring of water-suppling treatment equipment compared with Skew state is presented in big inconvenience, many times, the installation of water treatment facilities, to influence its normal use.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the present invention provides a kind of small towns river water treatment facilities secure mounting arrangements, solutions The inconvenient problem of existing small towns river water treatment facilities of having determined installation.
(2) technical solution
To achieve the above object, the invention provides the following technical scheme: a kind of small towns river water treatment facilities are fixedly mounted Device, including pedestal are welded with deck at the top of the pedestal, water treatment facilities ontology, institute are connected at the top of the deck It states and is mounted on the first tooth set at left and right sides of base intracavity, the first tooth set internal screw thread is equipped with adjustable column, the pedestal Bottom install rack gear, the bottom of the gear ring is movably installed with externally threaded thread bush, the inside spiral shell of the thread bush Line is connected on the outer wall of adjustable column, and bearing (ball) cover, the outside weldering of the bearing (ball) cover are socketed on the outer wall of the thread bush It is connected to fixed frame, is socketed on the outer wall of pedestal at the top of the fixed frame, the center of the base bottom is equipped with box body, institute The inner cavity for stating box body is equipped with fixing head, and the bottom of the fixing head is connected with lifting rope, and the bottom of the box body offers through slot, The bottom of the lifting rope runs through through slot and extends to the outside of box body, and the lifting rope part of the box portion outside is equipped with clump weight, The front-side etch of the box body angled line is welded with indicator, the left and right two of the base top at the center of the box body Side is welded with slide-bar, and movable sleeve is connected to fixing clamp on the outer wall of the slide-bar, and the top and bottom of the fixing clamp are welded It is connected to the trapezoidal swivel nut of plastics, the outside screw of the trapezoidal swivel nut of plastics is equipped with lock sleeve, the water treatment facilities ontology Top is symmetrically installed with non-slip mat, and the side of the fixing clamp and the top of non-slip mat are mutually clamped.
Preferably, the lock sleeve is trapezium structure, and the Poisson's ratio of the trapezoidal swivel nut of plastics is 0.25-0.3.
Preferably, anti-drop head is welded at the top of the adjustable column, and the diameter of anti-drop head is adjust column diameter 1.2 Times.
Preferably, the left and right sides of the through slot is welded with neonychium, the inside of the neonychium and the outside of lifting rope It contacts with each other.
Preferably, the bottom of the adjustable column is equipped with slip preventing fringe.
(3) beneficial effect
The present invention provides a kind of small towns river water treatment facilities secure mounting arrangements.Have it is following the utility model has the advantages that
(1), the small towns river water treatment facilities secure mounting arrangements can be precipitous by the way that height adjustment mechanism is arranged Water treatment facilities ontology is installed on uneven river and is rectified, making water treatment facilities ontology is not in the phenomenon of skew, thus Guarantee normally coming into operation for water treatment facilities ontology later period, by rotating thread bush, drive adjustable column is moved up and down, and by In the setting of gear ring and bearing (ball) cover, it is ensured that in rotation, it (is not in move up and down that the position of thread bush, which remains unchanged, Phenomenon), the setting covered by the first tooth, it is ensured that the phenomenon that dallies will not occur for adjustable column, pass through individual adjustment base or so two The height on side, so that even if on jiggly river, by individually adjusting height, pedestal or so two is also may be implemented in base position The balance of side guarantees that the water treatment facilities ontology of base top is steady.
(2), the small towns river water treatment facilities secure mounting arrangements can be timely by the way that accuracy correction mechanism is arranged It was found that whether pedestal is in steady state, if unstable, so as to rapidly be modified, it is ensured that pedestal is steadily installed, and is hung The bottom of rope be equipped with clump weight, the vertical direction of clump weight, as steady direction, when clump weight is overlapped with indicator, surface Pedestal is in steady state, if not being overlapped, show pedestal occur skew (clump weight is perpendicularly oriented to as abswolute level state, Indicator is oriented to relative level state), at this time by continuing the adjustable column at left and right sides of adjustment base, make at the top of clump weight Lifting rope be overlapped with indicator.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention;
Fig. 2 is pedestal partial structure sectional view of the present invention;
Fig. 3 is pedestal partial structural diagram of the present invention;
Fig. 4 is box body structure cross-sectional view of the present invention;
Fig. 5 is locking sleeve structure cross-sectional view of the present invention.
In figure: 1, pedestal;2, deck;3, water treatment facilities ontology;4, the first tooth set;5, adjustable column;6, gear ring;7, screw thread Set;8, bearing (ball) cover;9, fixed frame;10, box body;11, fixing head;12, through slot;13, lifting rope;14, clump weight;15, angle line; 16, indicator;17, slide-bar;18, fixing clamp;19, the trapezoidal swivel nut of plastics;20, lock sleeve;21, non-slip mat;22, anti-drop head;23, Neonychium;24, slip preventing fringe.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figs. 1-5, the present invention provides a kind of technical solution: dress is fixedly mounted in a kind of small towns river water treatment facilities It sets, by the way that height adjustment mechanism is arranged, water treatment facilities ontology 3 can be installed on the river of precipitous injustice and be rectified, make water Processing equipment ontology 3 is not in the phenomenon of skew, to guarantee normally coming into operation for 3 later period of water treatment facilities ontology, leads to Setting accuracy correction mechanism is crossed, can timely find pedestal 1 whether in steady state, if unstable, so as to quick Ground is modified, it is ensured that pedestal 1 is steadily installed, including pedestal 1, and the top of pedestal 1 is welded with deck 2, the top clamping of deck 2 Water position manage apparatus body 3, by the height of individual 1 the right and left of adjustment base, thus even if pedestal 1 be in it is jiggly On river, by individually adjusting height, the balance of 1 left and right sides of pedestal also may be implemented, guarantee that the water process at 1 top of pedestal is set Standby ontology 3 is steady, and the first tooth set 4 is mounted at left and right sides of 1 inner cavity of pedestal, and the first tooth covers 4 internal screw threads and is equipped with adjustable column 5, pass through the setting of the first tooth set 4, it is ensured that the phenomenon that dallies will not occur for adjustable column 5, and the bottom of adjustable column 5 is equipped with slip preventing fringe 24, the top of adjustable column 5 is welded with anti-drop head 22, and the diameter of anti-drop head 22 is 1.2 times of 5 diameter of adjustable column, the bottom of pedestal 1 Rack gear 6 is installed in portion, and the bottom of gear ring 6 is movably installed with externally threaded thread bush 7, and the inside thread of thread bush 7 is connected to On the outer wall of adjustable column 5, bearing (ball) cover 8 is socketed on the outer wall of thread bush 7, the outside of bearing (ball) cover 8 is welded with fixed frame 9, By rotating thread bush 7, adjustable column 5 is driven to move up and down, and due to the setting of gear ring 6 and bearing (ball) cover 8, it is ensured that turning When dynamic, the position of thread bush 7 remains unchanged (being not in the phenomenon that moving up and down), and the top of fixed frame 9 is socketed in pedestal 1 On outer wall, the center of 1 bottom of pedestal is equipped with box body 10, and the inner cavity of box body 10 is equipped with fixing head 11, the bottom of fixing head 11 It is connected with lifting rope 13, the bottom of box body 10 offers through slot 12, and the left and right sides of through slot 12 is welded with neonychium 23, neonychium 23 inside and the outside of lifting rope 13 contact with each other, and the bottom of lifting rope 13 runs through through slot 12 and extends to the outside of box body 10, box 13 part of lifting rope outside body 10 is equipped with clump weight 14, the angled line 15 of the front-side etch of box body 10, at the center of box body 10 It is welded with indicator 16, the bottom of lifting rope 13 is equipped with clump weight 14, the vertical direction of clump weight 14, as steady direction, when matching When pouring weight 14 is overlapped with indicator 16, surface mounts 1 are in steady state, if not being overlapped, show that pedestal 1 skew occurs and (matches Pouring weight 14 is perpendicularly oriented to as abswolute level state, and indicator 16 is oriented to relative level state), at this time by continuing to adjust The adjustable column 5 of 1 left and right sides of pedestal is overlapped the lifting rope 13 at 14 top of clump weight with indicator 16, the left side at 1 top of pedestal Right two sides are welded with slide-bar 17, and movable sleeve is connected to fixing clamp 18, the top and bottom of fixing clamp 18 on the outer wall of slide-bar 17 It is welded with the trapezoidal swivel nut 19 of plastics, the outside screw of the trapezoidal swivel nut 19 of plastics is equipped with lock sleeve 20, and lock sleeve 20 is trapezoidal The Poisson's ratio of structure, the trapezoidal swivel nut 19 of plastics is 0.25-0.3, and the top of water treatment facilities ontology 3 is symmetrically installed with non-slip mat 21, the side of fixing clamp 18 is mutually clamped with the top of non-slip mat 21, when fixing water treatment facilities ontology 3, first by fixing clamp 18 slide into the top of water treatment facilities ontology 3, and with 21 clamping of non-slip mat, then rotation lock fixed 20, make it screw plastics Trapezoidal swivel nut 19, due to itself trapezium structure of the trapezoidal swivel nut 19 of plastics, along with the Poisson's ratio of the trapezoidal swivel nut 19 of plastics is 0.25-0.3 (the trapezoidal swivel nut 19 of plastics has certain elasticity), therefore lock sleeve 20 is in the process for screwing the trapezoidal swivel nut 19 of plastics In, it can gradually make the trapezoidal 19 locking slide-bar 17 of swivel nut of plastics, so that the position of fixed fixing clamp 18, then locks water treatment facilities Ontology 3.
In use, driving adjustable column 5 to move up and down, and due to gear ring 6 and bearing (ball) cover 8 by rotation thread bush 7 Setting, it is ensured that rotation when, the position of thread bush 7 remains unchanged (being not in the phenomenon that moving up and down), passes through the first tooth The setting of set 4, it is ensured that the phenomenon that dallies will not occur for adjustable column 5, by the height of individual 1 the right and left of adjustment base, thus Even if pedestal 1 is on jiggly river, by individually adjusting height, the balance of 1 left and right sides of pedestal also may be implemented, protect The water treatment facilities ontology 3 for demonstrate,proving 1 top of pedestal is steady;The bottom of lifting rope 13 be equipped with clump weight 14, the vertical direction of clump weight 14, As steady direction, when clump weight 14 is overlapped with indicator 16, surface mounts 1 are in steady state and show if not being overlapped There is skew (clump weight 14 be perpendicularly oriented to as abswolute level state, indicator 16 is oriented to relative level state) in pedestal 1, At this time by continuing the adjustable column 5 of 1 left and right sides of adjustment base, it is overlapped the lifting rope 13 at 14 top of clump weight i.e. with indicator 16 It can.
In conclusion the small towns river water treatment facilities secure mounting arrangements, by the way that height adjustment mechanism, Neng Gou is arranged Water treatment facilities ontology 3 is installed on the river of precipitous injustice and is rectified, making water treatment facilities ontology 3 is not in showing for skew As, thus guarantee normally coming into operation for 3 later period of water treatment facilities ontology, it, can be timely by the way that accuracy correction mechanism is arranged It was found that whether pedestal 1 is in steady state, if unstable, so as to rapidly be modified, it is ensured that pedestal 1 is steadily installed.
It should be noted that the electric elements occurred in this article are electrically connected with extraneous main controller and 220V alternating current, and And main controller can play the conventionally known equipment of control, herein, such as first and second or the like pass for computer etc. It is that term is only used to distinguish one entity or operation from another entity or operation, and not necessarily requires or secretly Show that there are any actual relationship or orders between these entities or operation.Moreover, the terms "include", "comprise" or Any other variant thereof is intended to cover non-exclusive inclusion so that include the process, methods of a series of elements, article or Person's equipment not only includes those elements, but also including other elements that are not explicitly listed, or further includes for this mistake Journey, method, article or the intrinsic element of equipment.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of small towns river water treatment facilities secure mounting arrangements, including pedestal (1), it is characterised in that: the pedestal (1) Top is welded with deck (2), is connected with water treatment facilities ontology (3) at the top of the deck (2), pedestal (1) inner cavity The left and right sides is mounted on the first tooth set (4), and the first tooth set (4) internal screw thread is equipped with adjustable column (5), the pedestal (1) Bottom install rack gear (6), the bottom of the gear ring (6) is movably installed with externally threaded thread bush (7), the thread bush (7) inside thread is connected on the outer wall of adjustable column (5), is socketed with bearing (ball) cover (8) on the outer wall of the thread bush (7), It is welded with fixed frame (9) on the outside of the bearing (ball) cover (8), the outer wall of pedestal (1) is socketed at the top of the fixed frame (9) On, the center of pedestal (1) bottom is equipped with box body (10), and the inner cavity of the box body (10) is equipped with fixing head (11), institute The bottom for stating fixing head (11) is connected with lifting rope (13), and the bottom of the box body (10) offers through slot (12), the lifting rope (13) bottom runs through through slot (12) and extends to the outside of box body (10), and external lifting rope (13) part of the box body (10) is pacified Equipped with clump weight (14), the angled line of front-side etch (15) of the box body (10) is welded at the center of the box body (10) Indicator (16), the left and right sides at the top of the pedestal (1) are welded with slide-bar (17), movable on the outer wall of the slide-bar (17) It is socketed with fixing clamp (18), the top and bottom of the fixing clamp (18) are welded with the trapezoidal swivel nut of plastics (19), the modeling Expect that the outside screw of trapezoidal swivel nut (19) is equipped with lock sleeve (20), is symmetrically installed at the top of the water treatment facilities ontology (3) Have non-slip mat (21), the side of the fixing clamp (18) and the top of non-slip mat (21) are mutually clamped.
2. a kind of small towns river water treatment facilities secure mounting arrangements according to claim 1, it is characterised in that: the lock Fixed (20) are trapezium structure, and the Poisson's ratio of the trapezoidal swivel nut of plastics (19) is 0.25-0.3.
3. a kind of small towns river water treatment facilities secure mounting arrangements according to claim 1, it is characterised in that: the tune It is welded at the top of segmented column (5) anti-drop head (22), and the diameter of anti-drop head (22) is 1.2 times of adjustable column (5) diameter.
4. a kind of small towns river water treatment facilities secure mounting arrangements according to claim 1, it is characterised in that: described logical The left and right sides of slot (12) is welded with neonychium (23), the inside of the neonychium (23) and the outside phase mutual connection of lifting rope (13) Touching.
5. a kind of small towns river water treatment facilities secure mounting arrangements according to claim 1, it is characterised in that: the tune The bottom of segmented column (5) is equipped with slip preventing fringe (24).
CN201810716193.9A 2018-06-30 2018-06-30 Fixed mounting device for riverway water treatment equipment in villages and towns Active CN109000094B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810716193.9A CN109000094B (en) 2018-06-30 2018-06-30 Fixed mounting device for riverway water treatment equipment in villages and towns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810716193.9A CN109000094B (en) 2018-06-30 2018-06-30 Fixed mounting device for riverway water treatment equipment in villages and towns

Publications (2)

Publication Number Publication Date
CN109000094A true CN109000094A (en) 2018-12-14
CN109000094B CN109000094B (en) 2020-08-07

Family

ID=64599670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810716193.9A Active CN109000094B (en) 2018-06-30 2018-06-30 Fixed mounting device for riverway water treatment equipment in villages and towns

Country Status (1)

Country Link
CN (1) CN109000094B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617851A (en) * 2019-07-25 2019-12-27 滨州学院 Mobile and portable marine data acquisition device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150338019A1 (en) * 2012-12-21 2015-11-26 H. Schinkel Holding B.V. Spring balanced support device
CN106647115A (en) * 2016-11-22 2017-05-10 魏承赟 Panoramic camera stabilizer
CN206555673U (en) * 2017-02-24 2017-10-13 安徽艾美人体工学科技有限公司 Display bracket wallboard
CN107795825A (en) * 2017-11-13 2018-03-13 梁兆寇 Placing frame of dehydrator

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150338019A1 (en) * 2012-12-21 2015-11-26 H. Schinkel Holding B.V. Spring balanced support device
CN106647115A (en) * 2016-11-22 2017-05-10 魏承赟 Panoramic camera stabilizer
CN206555673U (en) * 2017-02-24 2017-10-13 安徽艾美人体工学科技有限公司 Display bracket wallboard
CN107795825A (en) * 2017-11-13 2018-03-13 梁兆寇 Placing frame of dehydrator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617851A (en) * 2019-07-25 2019-12-27 滨州学院 Mobile and portable marine data acquisition device
CN110617851B (en) * 2019-07-25 2021-05-18 滨州学院 Mobile and portable marine data acquisition device

Also Published As

Publication number Publication date
CN109000094B (en) 2020-08-07

Similar Documents

Publication Publication Date Title
CN109000094A (en) A kind of small towns river water treatment facilities secure mounting arrangements
CN208735194U (en) A kind of geological hazard detection apparatus fixed frame
CN109878081A (en) A kind of 3D printing equipment with levelling function
CN206894046U (en) A kind of secure mounting arrangements for regulator cubicle
CN206447061U (en) Aggregate material-level detecting device and mixing plant
CN207122732U (en) Pump motor installation levelling device
CN210975579U (en) Temporary support device for bridge construction
CN207739568U (en) A kind of high abrasion antistatic floor
CN206942205U (en) A kind of support frame for building
CN104477364B (en) A kind of mechanical and electric equipment installation pedestal and ship
CN214893813U (en) Torque tester for preset torque wrench
CN209214528U (en) A kind of mobile phone shell deformation degree detecting device
CN214374024U (en) Civil engineering material sample detection device
CN214248757U (en) Balancing equipment for mounting electromechanical equipment
CN108413931A (en) A kind of monitoring device for building
CN204165992U (en) A kind of two eccentric structures increasing sensing range
CN210341670U (en) Steel support with adjustable height and angle
CN210487541U (en) Multifunctional raise dust monitoring device
CN210857949U (en) Novel external protection scaffold for building
CN207946097U (en) A kind of automatic monitoring mark for road level displacement, sedimentation
CN213632052U (en) Hydraulic engineering measuring device
CN206971286U (en) A kind of novel and multifunctional inspection well cover for urban construction
CN216309157U (en) Water level monitoring device for hydraulic engineering
CN213136341U (en) Special wheel of polishing of high stability glass
CN208029865U (en) A kind of slurry scraper corner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200629

Address after: 312030 room 309-16, Fuquan science and Innovation Industrial Park, Fuquan street, Keqiao District, Shaoxing City, Zhejiang Province

Applicant after: Shaoxing Jiayue Textile Machinery Co., Ltd

Address before: 313021 south of Baoge Highway, Donglin Town, Wuxing District, Huzhou City, Zhejiang Province

Applicant before: HUZHOU YICHUANG ENVIRONMENT ENGINEERING Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant