CN108999209A - A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering - Google Patents

A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering Download PDF

Info

Publication number
CN108999209A
CN108999209A CN201811143484.XA CN201811143484A CN108999209A CN 108999209 A CN108999209 A CN 108999209A CN 201811143484 A CN201811143484 A CN 201811143484A CN 108999209 A CN108999209 A CN 108999209A
Authority
CN
China
Prior art keywords
steel
oblique angle
rim
cup
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811143484.XA
Other languages
Chinese (zh)
Inventor
姜兆双
张辉
徐忠梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201811143484.XA priority Critical patent/CN108999209A/en
Publication of CN108999209A publication Critical patent/CN108999209A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Abstract

A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering, belongs to rim of a cup basis steel column mounting technique field.Step: according to rim of a cup basic (3) and steel column (2) sectional dimension processing oblique angle I-steel (1);When steel column (2) is installed, fixed using oblique angle I-steel (1) in steel column (2) root surrounding centering;To rim of a cup basic (3) perfusion concrete (4) for the first time, guarantee that first time concrete perfusion (4) are lower than oblique angle I-steel (1) lower end above;Oblique angle I-steel (1) is removed after concrete solidification, then to basic (3) second of the concrete perfusion (5) of rim of a cup, until rim of a cup basis (3) concrete pouring is complete.The advantage is that not only reusing oblique angle I-steel, section has remained material, and the centering set time shortens, and saves a large amount of adjustment times, greatly reduces construction cost, achieves good economic benefit for company.

Description

A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering
Technical field
The invention belongs to rim of a cup basis steel column installing area, in particular, provides and a kind of fixed using oblique angle I-steel centering The method of rim of a cup basis steel column installation.
Background technique
When steel column with rim of a cup basis is installed, the steel column centering before rim of a cup concrete perfusion is fixed, general using not Regular fashioned iron and steel plate are filled from steel column foot surrounding, are fixed temporarily again after measurement correction, later according to field condition to steel Column rim of a cup basis carries out filling concrete, using this method generation as a result, first is that fashioned iron and steel plate that centering is fixed can be mixed Solidifying soil is filled into rim of a cup basis, cannot be recycled;Second is that after centering is fixed, such as concrete perfusion not in time, steel plate deformed meeting Steel column installation deviation is caused, the later period adjusts steel column and increases expense.
Summary of the invention
The purpose of the present invention is to provide a kind of methods using the fixed rim of a cup basis steel column installation of oblique angle I-steel centering. The installation method not only reuses oblique angle I-steel, and section has remained material, and the centering set time shortens, and saves A large amount of adjustment times, greatly reduce construction cost.Installation smoothly success has accumulated invaluable experience for similar construction later.
The present invention processes oblique angle I-steel when steel column is installed according to rim of a cup basis and steel column sectional dimension and utilizes oblique angle work Word steel is fixed in steel column root surrounding centering, then to the basic first time concrete perfusion of rim of a cup, guarantees to be lower than oblique angle above concrete Oblique angle I-steel is removed in I-steel lower end after concrete solidification, then to basic second of the concrete perfusion of rim of a cup, until rim of a cup basis is mixed Solidifying soil has been perfused.Specific step is as follows:
The first step, according to rim of a cup basis 3 and 2 sectional dimension of steel column processing oblique angle I-steel 1 (Fig. 1);
Second step fixes (Fig. 2) in 2 root surrounding centering of steel column using oblique angle I-steel 1 when steel column 2 is installed;
Third step, to rim of a cup basis 3, perfusion concrete 4, guarantee first time concrete perfusion 4 are lower than oblique angle I-shaped above for the first time 1 lower end of steel (Fig. 3);
4th step removes oblique angle I-steel 1 after concrete solidification, then to basic 3 second of the concrete perfusion 5 of rim of a cup, until cup Basic 3 concrete pourings of mouth are complete (Fig. 4).
The installation method not only reuses oblique angle I-steel, and section has remained material, and the centering set time contracts It is short, a large amount of adjustment times are saved, construction cost is greatly reduced, achieve good economic benefit for company.
Detailed description of the invention
Fig. 1 is oblique angle I-steel manuscript.
Fig. 2 installs the fixed figure (cross-section diagram) of centering to steel column on rim of a cup basis for oblique angle I-steel.
Fig. 3 is the basic first time concrete perfusion figure (cross-section diagram) of rim of a cup.
Fig. 4 is second of the concrete perfusion figure (cross-section diagram) in rim of a cup basis after removing oblique angle I-steel.
In figure, oblique angle I-steel 1, steel column 2, rim of a cup basis 3, first time concrete perfusion 4, second of concrete perfusion 5.
Specific embodiment
Fig. 1-Fig. 4 is a kind of specific embodiment of the invention.Specific embodiment is as follows:
The first step processes oblique angle I-steel 1 according to rim of a cup basis 3 and 2 sectional dimension of steel column;
Second step is fixed using oblique angle I-steel 1 in 2 root surrounding centering of steel column when steel column 2 is installed;
Third step, to rim of a cup basis 3, perfusion concrete 4, guarantee first time concrete perfusion 4 are lower than oblique angle I-shaped above for the first time 1 lower end of steel;
4th step removes oblique angle I-steel 1 after concrete solidification, then to basic 3 second of the concrete perfusion 5 of rim of a cup, until cup Basic 3 concrete pourings of mouth are complete.

Claims (1)

1. a kind of method using the fixed rim of a cup basis steel column installation of oblique angle I-steel centering, which is characterized in that steps are as follows:
The first step, according to rim of a cup basic (3) and steel column (2) sectional dimension processing oblique angle I-steel (1);
Second step is fixed using oblique angle I-steel (1) in steel column (2) root surrounding centering when steel column (2) is installed;
Third step guarantees that first time concrete perfusion (4) are lower than oblique angle work above to rim of a cup basic (3) perfusion concrete (4) for the first time Word steel (1) lower end;
4th step removes oblique angle I-steel (1) after concrete solidification, then to basic (3) second of the concrete perfusion (5) of rim of a cup, until Rim of a cup basis (3) concrete pouring is complete.
CN201811143484.XA 2018-09-28 2018-09-28 A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering Pending CN108999209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811143484.XA CN108999209A (en) 2018-09-28 2018-09-28 A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811143484.XA CN108999209A (en) 2018-09-28 2018-09-28 A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering

Publications (1)

Publication Number Publication Date
CN108999209A true CN108999209A (en) 2018-12-14

Family

ID=64589764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811143484.XA Pending CN108999209A (en) 2018-09-28 2018-09-28 A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering

Country Status (1)

Country Link
CN (1) CN108999209A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU387087A1 (en) * 1971-01-12 1973-06-21 FOUNDATION OF GLASS TYPE FOR COLUMNS
CN202170645U (en) * 2011-07-15 2012-03-21 中国十七冶集团有限公司 Aligning positioner for cup-rim steel column
CN203080546U (en) * 2013-02-06 2013-07-24 陕西建工集团机械施工有限公司 Prefabricated column concrete cup opening base double-layer limiting fixed structure
CN104265000A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Column mounting method for cup foundation
CN205476528U (en) * 2016-03-01 2016-08-17 中国十七冶集团有限公司 Precast pile device of taking one's place fast
CN106368234A (en) * 2016-09-08 2017-02-01 中国航天建设集团有限公司 Novel cup foundation box-shaped steel column installation constructing technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU387087A1 (en) * 1971-01-12 1973-06-21 FOUNDATION OF GLASS TYPE FOR COLUMNS
CN202170645U (en) * 2011-07-15 2012-03-21 中国十七冶集团有限公司 Aligning positioner for cup-rim steel column
CN203080546U (en) * 2013-02-06 2013-07-24 陕西建工集团机械施工有限公司 Prefabricated column concrete cup opening base double-layer limiting fixed structure
CN104265000A (en) * 2014-09-12 2015-01-07 北京首钢建设集团有限公司 Column mounting method for cup foundation
CN205476528U (en) * 2016-03-01 2016-08-17 中国十七冶集团有限公司 Precast pile device of taking one's place fast
CN106368234A (en) * 2016-09-08 2017-02-01 中国航天建设集团有限公司 Novel cup foundation box-shaped steel column installation constructing technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
江正荣: "工业厂房柱子采用钢垫板找平的安装工艺", 《建筑技术》 *

Similar Documents

Publication Publication Date Title
CN104727223B (en) A kind of hoop platform for bridge pier column construction and construction method
CN102444285A (en) Method for manufacturing reinforced concrete basement external wall
CN105464216A (en) Construction method for ultrahigh oblique post with super-large cross section based on integral lifting formwork reinforcing system
CN108999209A (en) A method of it is installed using the fixed rim of a cup basis steel column of oblique angle I-steel centering
CN104727339B (en) Power equipment basis two-step construction method
CN110293622A (en) A kind of tunnel reinforced concrete lining cutting test model pours device and casting method
CN208966022U (en) A kind of template poured for large-scale beam column
CN102518046B (en) Method for eliminating secondary internal force of sinking of support saddle of continuous beam during cantilever construction
CN106284428A (en) A kind of concrete column method for supporting of building structure post-cast strip
CN105155843A (en) Construction method and construction device of constructional columns
CN105908752B (en) Formwork supporting and stripping system for pouring concrete on side wall and working process of formwork supporting and stripping system
CN104265000A (en) Column mounting method for cup foundation
CN204098488U (en) A kind of fixed structure of end bay beam forms
CN109853948A (en) The integrated template system and mold method of the cast-in-place overhanging windowsill of secondary structure
CN103015328B (en) Continuous splicing construction method of pier column for jacking broken beam of bridge
CN205296201U (en) Positioner suitable for post installation of rim of a cup basis
CN104775831B (en) A kind of tunnel double-lining inverted arch exempts from short abutment wall arcing construction method with arch wall joint portion
KR101099689B1 (en) Mounting method for structure for vessel
CN208662509U (en) Chassis mould
CN107338811B (en) Construction method that is a kind of while pouring two structural columns of deformation joint
CN107642240B (en) A method of strengthening concrete girder steel is installed in concrete bearing
CN105755943A (en) Arch bridge arch ring block section and construction method thereof
JP6345328B1 (en) Original position building method and original position structure
CN206681375U (en) Thrust block installation system
CN109098438A (en) A kind of template poured for large-scale beam column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181214

WD01 Invention patent application deemed withdrawn after publication