CN108979296A - A kind of building waste is used for the construction method of environmentally friendly enclosure wall - Google Patents

A kind of building waste is used for the construction method of environmentally friendly enclosure wall Download PDF

Info

Publication number
CN108979296A
CN108979296A CN201810866699.8A CN201810866699A CN108979296A CN 108979296 A CN108979296 A CN 108979296A CN 201810866699 A CN201810866699 A CN 201810866699A CN 108979296 A CN108979296 A CN 108979296A
Authority
CN
China
Prior art keywords
wall
building waste
environmentally friendly
base station
class
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810866699.8A
Other languages
Chinese (zh)
Other versions
CN108979296B (en
Inventor
李德建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Xing Chang Construction Engineering Co Ltd
Original Assignee
Sichuan Xing Chang Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Xing Chang Construction Engineering Co Ltd filed Critical Sichuan Xing Chang Construction Engineering Co Ltd
Priority to CN201810866699.8A priority Critical patent/CN108979296B/en
Publication of CN108979296A publication Critical patent/CN108979296A/en
Application granted granted Critical
Publication of CN108979296B publication Critical patent/CN108979296B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B18/00Use of agglomerated or waste materials or refuse as fillers for mortars, concrete or artificial stone; Treatment of agglomerated or waste materials or refuse, specially adapted to enhance their filling properties in mortars, concrete or artificial stone
    • C04B18/04Waste materials; Refuse
    • C04B18/16Waste materials; Refuse from building or ceramic industry
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Abstract

The present invention provides the construction methods that a kind of building waste is used for environmentally friendly enclosure wall, are related to building waste utilization technology field, it is intended to solve the problems, such as that building waste recycling and reusing is at high cost in the prior art comprising following steps: S1: sifting sort;S2: broken apart;S3: reinforcing bar shaping;S4: foundation stabilization;S5: base station construction;S6: reinforcing steel bar frame is placed;S7: wall filling.The present invention is built by foundation stabilization, base station, wall pours the setting with wall skeleton, the quantity for recycling the scene of fractionation to generate most construction main body material and reinforcing bar, and its reprocessing difficulty is low, return period is short, recycles at low cost.

Description

A kind of building waste is used for the construction method of environmentally friendly enclosure wall
Technical field
The present invention relates to building waste utilization technology fields more particularly to a kind of building waste to be used for environmentally friendly enclosure wall Construction method.
Background technique
Building waste refers to that construction, all kinds of buildings of unit in charge of construction or personal team, structures, pipe network etc. are built, spread If or removing, generated dregs, spoir, rejected material, remaining mud and other wastes in reparative processes;However, overwhelming majority building Rubbish just transports countryside or rural area, air storage or landfill to by unit in charge of construction without any processing, consumes a large amount of land acquisition Take, the pork barrels such as refuse collection expense, meanwhile, it clears and is made again with the problems such as being flown upward with dust, sand-lime of dropping in stacking process At serious environmental pollution.
To solve the above-mentioned problems, the Chinese invention patent of notification number CN107377584A discloses a kind of building waste time Regeneration method is received, after construction waste crushing, magnetic separation removes iron refuse, washing removal soil and light materials, screening Obtain the rubbish of tri- kinds of particle size ranges of granulated garbage fines and 5-8mm, 8-12mm and 12-25mm of 0-5mm particle size range Grain coarse fodder, being collected simultaneously the dust generated during refuse breaking and obtaining partial size is 0.3mm granulated garbage powder below;It will The coarse fodder of powder, fines and corresponding type adds cement and water as brick-making raw material, according still further to proportion requirement, makes after being stirred It is standby to obtain the cement brick made from raw material based on building waste.
Although this building waste recovery and reusing and recycling method is by crushing and screening, by the powder of different-grain diameter in building waste Last particle distinguishes, to be used for being prepared for for cement brick;But this building waste recovery and reusing and recycling method is not Only need the broken classification in scene, it is also necessary to the granulated garbage of broken generation be transported to brickmaking place and reprocess and can make With return period is long, recycles at high cost.
Summary of the invention
In view of the deficiencies of the prior art, the present invention provides the construction parties that a kind of building waste is used for environmentally friendly enclosure wall Method has processing convenience, return period short, recycles advantage at low cost.
To realize the above-mentioned technical purpose, a kind of building waste provided by the invention is used for the construction method of environmentally friendly enclosure wall, packet Include following steps:
S1: sifting sort splits resulting material type according to construction site and manually classifies;
Wherein, classify according to following standard:
The first kind: plant material, plant material include woodwork and bamboo product;
Second class: textile material;
Third class: resinous material;
4th class: construction main body material comprising soil, brick, concrete block, reinforced concrete block;
5th class: glass;
6th class: other materials;
S2: it is broken apart, the reinforced concrete block containing reinforcing bar be tentatively crushed, screens out reinforcing bar part, and will screening Remaining the 4th class material of clout afterwards is used as object is built;
S3: reinforcing bar shaping, the reinforcing bar that will be singled out carry out shaping, it is made to keep linear state substantially, and by bending, cut and Welding manner is made into reinforcing steel bar frame, using as wall skeleton;
S4: average grain diameter is greater than the masonry of 100mm on ground along the pre- masonry position excavation and reinforcement slot of enclosure wall by foundation stabilization Object is filled into reinforcement tank, and is handled using machine compacting, the gap built between object after ramming, in reinforcement tank Average grain diameter is less than the masonry object of 10mm in middle filling, then carry out it is secondary ram, and pour at the top of filler by average grain Mortar made of masonry object mixing of the diameter less than 10mm forms until flushing with the ground around reinforcement tank and reinforces platform;
S5: base station construction sets up the two rows of templates being oppositely arranged, the cavity surrounded between two rows of templates on reinforcing platform In pour into the mortar as made of masonrys object mixing of the average grain diameter less than 10mm to the position of template half height, then the grain that will be averaged In the mortar built between object indentation template of the diameter greater than 100mm, and back-grouting is carried out until forming base station;
S6: placing reinforcing steel bar frame, the demoulding after the firm molding of base station, and reinforcing steel bar frame is fixed on base station;
S7: wall filling will build object and be sequentially filled by the sequence of average grain diameter from big to small in the affixed baffle in reinforcing steel bar frame two sides Into in the reinforcing steel bar frame between baffle, and leaching sand as made of masonry object mixing of the average grain diameter less than 10mm is poured from upper opening Slurry, wait build bonded between object it is firm after remove baffle and form wall body structure.
By using above-mentioned technical proposal, all kinds of building wastes mixed in construction site are classified first, after convenient Continuous broken and recycling, then the reinforcing bar in construction main body material is separated, to facilitate subsequent processing, and separate Reinforcing bar the skeleton of environmentally friendly enclosure wall can be constituted by way of bending, cutting and welding, wall body structure is reinforced, is improved Its stress intensity, and remove the construction main body material after reinforcing bar and can be used in consolidated subsoil, build base station and wall;In addition, applying The filler and mortar used in work are all a part in construction main body material, to consume a large amount of building waste;It tears open Resulting quantity mega structure material of main part part the most can be used for the masonry of environmentally friendly enclosure wall after point, without adding at the scene After work, also needs finish and can use, but can transport after the scene of fractionation carries out preliminary treatment to environmentally friendly enclosure wall Job location is recycled, and return period is short, is recycled at low cost.
In some embodiments, in the step S3, in framework reinforcing steel bar frame, polishing derusting is carried out to reinforcing bar.
By adopting the above technical scheme, when recycling reinforcing bar framework reinforcing steel bar frame, rebar surface of being gone out by way of polishing Iron rust, can not only check whether reinforcing bar actual state meets requirement, moreover it is possible to avoid the further Corrosion Reinforcement frame of iron rust.
In some embodiments, in the step S3, the reinforcing bar periphery of the reinforcing steel bar frame is painted with antirust paint.
By using above-mentioned technical proposal, it is brushed on antirust paint in the reinforcing bar periphery for removing iron rust, avoids reinforcing steel bar frame certainly It is corroded in right environment, and loses the support to environmentally friendly enclosure wall, blocks shield effect.
In some embodiments, in the step S4, separating reinforcement tank from bottom to top is multilayer, is filled using layer-by-layer, The mode successively rammed is constructed.
By using above-mentioned technical proposal, multilayer filling, the multiple mode rammed can be reinforced and be filled in reinforcement tank The compactness of construction main body material occurs significantly when wall part being avoided to be set on ground to improve its weight bearing power Sedimentation or offset, and influence the stability of environmentally friendly enclosure wall.
In some embodiments, in the step S5, when building base station, upper several are plugged vertically between template Fixed steel bars, and fixed steel bars top is made to stretch out base station setting, and reinforcing bar frame bottom is welded in setting at the top of fixed steel bars.
By adopting the above technical scheme, by the way that when base station is built, fixed steel bars are plugged between template in advance, thus After base station forming, fixed steel bars can form an entirety with base station, can not only facilitate construction personnel that reinforcing steel bar frame is affixed Onto base station, moreover it is possible to the connection structure of firm reinforcing steel bar frame and base station.
In some embodiments, in the step S5, when building base station, base station width is greater than reinforcing bar width of frame and sets It sets, and in the reserved groove being adapted to reinforcing bar frame bottom in base station top, and stretches out and be arranged from groove at the top of fixed steel bars.
By using above-mentioned technical proposal, the groove of upper and reinforcing bar frame bottom cooperation is set at the top of base station, and will be fixed In base station part below steel-bar arrangement and groove, so that reinforcing steel bar frame is installed in groove in construction personnel's installation, cooperate The stability of the further stabilization wall of fixed steel bars.
In some embodiments, in the step S1, for first kind material, intact plant material can lead to Cutting, assembled formation ornament or vegetation box are crossed, and is positioned on environmentally friendly enclosure wall;And more scrappy plant material can Carry out pulverization process.
By using above-mentioned technical proposal, will there is the plant material of reprocessing value to process to form ornament or plant Case, and will be secured on environmentally friendly enclosure wall, to beautify environmentally friendly enclosure wall while recycling plant material;And it is corresponding compared with Low plant material is worth for scrappy, reprocessing and carries out pulverization process, be can be used for the compound preparation of Wood-plastic material, is realized it It recycles.
In some embodiments, in the step S7, direction is extended along at the top of the wall and is provided with planting groove, will be spun It knits class material cushion to be placed in planting groove, then transplants green plants in planting groove.
By adopting the above technical scheme, by extending along the root that the planting groove of direction setting is green plants at the top of wall Portion provides embedded space, and the textile material cushion that fractionation scene obtains is set to the bottom of planting groove, can not only avoid planting The planting soil planted in slot is largely lost under rainwater effect, moreover it is possible to be avoided the root growth of green plants into wall, be destroyed wall Body structure, to realize the recycling of textile material.
In some embodiments, in the step S7, resinous material is divided into thermoplastic class and thermosetting class, thermoplastic class Expect that material recovery recycles, thermosetting class material is processed as ornament according to its own characteristic, and is fixed in wall side wall.
By using above-mentioned technical proposal, the thermoplastic material that can be shaped again after recycling heating is recycled, and is added The thermosetting class material for being difficult to shape again after heat can be reprocessed according to its own characteristic, and be secured to wall side wall On, beautify wall.
In some embodiments, in the step S7, glass is cut, is spliced and reprocessing forms ornament, And ornament is secured on wall side wall.
By using above-mentioned technical proposal, the glass after reprocessing is secured on wall side wall, is cooperated on wall side wall Plant material, ornament made of resinous material beautify wall, improve its ornamental value.
In conclusion compared with prior art, the present invention having the advantage that
1. pouring the setting with wall skeleton by foundation stabilization, base station construction, wall, the quantity for recycling the scene of fractionation to generate Most construction main body materials and reinforcing bar, and reprocessing difficulty is low, return period is short, recycles at low cost;
2. facilitate construction personnel that the textile material cushion that the scene of fractionation generates is located in planting groove by the setting of planting groove, Realize the recycling of textile material;
3. by the way that plant material, resinous material and glass are reprocessed, realize plant material, resinous material and The recycling of glass.
Specific embodiment
Embodiment:
A kind of building waste is used for the construction method of environmentally friendly enclosure wall, comprising the following steps:
S1: sifting sort splits resulting material type according to construction site and manually classifies, construction personnel is facilitated to divide Class management, recycling and transport.
Wherein, classify according to following standard:
The first kind: plant material, plant material include woodwork and bamboo product;
Second class: textile material;
Third class: resinous material;
4th class: construction main body material comprising soil, brick, concrete block, reinforced concrete block;
5th class: glass;
6th class: other materials.
Wherein, the other materials of the 6th class is all kinds of composite articles of negligible amounts, battery and other items, is collected separately this kind of Article, and classification processing is carried out according to its characteristic.
S2: it is broken apart, tentatively broken, recycling iron remover screening tapping is carried out to the reinforced concrete block containing reinforcing bar Muscle portion point, had both been avoided that the waste of steel material, moreover it is possible to the presence of reinforcing bar be avoided to influence the subsequent processing of construction main body material; Meanwhile it being used using remaining the 4th class material of the clout after screening as object is built.
S3: reinforcing bar shaping, the reinforcing bar that will be singled out carry out shaping by modes such as stretching, weight, reach basic guarantor The state of straight line is held, then the reinforcing bar after shaping is made into reinforcing steel bar frame by bending, cutting and welding manner, here, setting There is several segments reinforcing steel bar frame, wall skeleton is capable of forming by the splicing of reinforcing steel bar frame, realizes the recycling and reusing of reinforcing bar;
Wherein, after to reinforcing bar shaping, grinding process is carried out to reinforcing bar one by one, removes the iron rust of rebar surface, remove de-iron It observes whether reinforcing bar meets requirement after rust, and the presence of iron rust is avoided to influence the subsequent processing to reinforcing bar;
In addition, using antirust paint brushing rebar surface, reinforcing steel bar frame is avoided to get rusty and shadow in the natural environment after reinforcing steel bar frame molding The structural strength for arriving reinforcing steel bar frame is rung, to guarantee the service life of environmentally friendly enclosure wall.
S4: foundation stabilization is excavated with the reinforcement tank of the trapezoidal setting in section along the pre- masonry position of enclosure wall on ground, will put down Equal masonry object of the partial size greater than 100mm is filled into reinforcement tank, and is handled using machine compacting, after ramming, in reinforcing The masonry object that upper average grain diameter is less than 10mm is filled in the gap built between object in slot, then carry out it is secondary ram, and filling out It fills and pours the mortar as made of masonry object mixing of the average grain diameter less than 10mm at the top of object, until with the ground around reinforcement tank It flushes, is formed and reinforce platform;
Wherein, reinforcement tank is divided into multilayer from bottom to up, is filled in every layer and builds object, and carry out compacting processing, upper One layer of compacting finishes the filling construction that rear carries out next layer, after successively tamping, pours mortar on reinforcement tank top and forms reinforcing Platform forms firm supporting plane.
S5: base station construction sets up the two rows of templates being oppositely arranged on reinforcing platform, surrounds between two rows of templates The mortar as made of masonry object mixing of the average grain diameter less than 10mm is poured into cavity to the position of template half height, then will be put down In the mortar built between object indentation template of the equal partial size greater than 100mm, and back-grouting is carried out, it can shape after mortar solidification At base station;
Wherein, the steel reinforcement cage bound in advance, and opening between steel reinforcement cage corresponding templates can be put into the cavity between template Open setting at mouthful, while reinforcing base station, to avoid the pre-placing of steel reinforcement cage from influencing the dispensing of masonry object.
S601: when base station pours, setting groove template in two rows of die head lids, thus can be in base after forming base station Countertop postpone its length direction formed groove;Wherein, before base station molding, interval is inserted along its length in two rows of templates Fixed steel bars are set in the base station part immediately below groove, and make reinforced steel top by the fixed steel bars being vertically arranged on if Groove setting is stretched out at end;
S602: reinforcing steel bar frame is clamped into groove, and reinforcing bar frame bottom is welded in fixed steel by the demoulding after the firm molding of base station On muscle.
S701: wall filling, in the affixed baffle in reinforcing steel bar frame two sides, will build object by the sequence of average grain diameter from big to small according to In the secondary reinforcing steel bar frame being filled between baffle, and pour from upper opening masonry object mixing of the leaching by average grain diameter less than 10mm and At mortar, wait build bonded between object it is firm after remove baffle and form wall body structure;
S702: for first kind material, intact plant material forms ornament or vegetation box by cutting, assembly, It is fixed on the side wall of wall, and plants upper green plants in vegetation box, beautify wall;And in first kind material More scrappy plant material part is crushed, and the preparation of Wood-plastic material is carried out, and realizes that the recycling of first kind material is sharp again With;
S703: for the second class material, direction is extended along at the top of wall and is provided with planting groove, and textile material cushion is being planted Trench bottom is planted, to planting groove filling planting soil, and transplants upper green plants, on the one hand, the setting of textile material can encase Planting soil avoids it from being lost under rainwater effect, and on the other hand, the setting of textile material can prevent the root system of green plants It grows into wall, and destroys wall body structure, while further beautification wall, realize that the recycling of the second class material is sharp again With;
S704: for third class material, resinous material is divided into thermoplastic class and thermosetting class, thermoplastic class material can be in high temperature Again it is formed, realizes its recycling, and thermosetting class material is passed through according to its own characteristic (size, shape, color etc.) It cuts, the mode of splicing is processed to form ornament, and is fixed on wall side wall, beautification wall side wall, realization third class The recycling and reusing of material;
S705: for the 5th class material, glass being cut, is spliced, and reprocessing forms ornament, and is fixed in wall On side wall, beautify wall side wall, realizes the recycling and reusing of the 5th class material.
In conclusion the main part (the five class material of the first kind-the) in building waste is used for ring by the above method It protects in the construction of enclosure wall, building can be converted by building waste rapidly, return period is short, recycles cost compared to secondary Recycling after processing is more cheap.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

1. the construction method that a kind of building waste is used for environmentally friendly enclosure wall, which comprises the following steps:
S1: sifting sort splits resulting material type according to construction site and manually classifies;
Wherein, classify according to following standard:
The first kind: plant material, plant material include woodwork and bamboo product;
Second class: textile material;
Third class: resinous material;
4th class: construction main body material comprising soil, brick, concrete block, reinforced concrete block;
5th class: glass;
6th class: other materials;
S2: it is broken apart, the reinforced concrete block containing reinforcing bar be tentatively crushed, screens out reinforcing bar part, and will screening Remaining the 4th class material of clout afterwards is used as object is built;
S3: reinforcing bar shaping, the reinforcing bar that will be singled out carry out shaping, it is made to keep linear state substantially, and by bending, cut and Welding manner is made into reinforcing steel bar frame, using as wall skeleton;
S4: average grain diameter is greater than the masonry of 100mm on ground along the pre- masonry position excavation and reinforcement slot of enclosure wall by foundation stabilization Object is filled into reinforcement tank, and is handled using machine compacting, the gap built between object after ramming, in reinforcement tank Average grain diameter is less than the masonry object of 10mm in middle filling, then carry out it is secondary ram, and pour at the top of filler by average grain Mortar made of masonry object mixing of the diameter less than 10mm forms until flushing with the ground around reinforcement tank and reinforces platform;
S5: base station construction sets up the two rows of templates being oppositely arranged, the cavity surrounded between two rows of templates on reinforcing platform In pour into the mortar as made of masonrys object mixing of the average grain diameter less than 10mm to the position of template half height, then the grain that will be averaged In the mortar built between object indentation template of the diameter greater than 100mm, and back-grouting is carried out until forming base station;
S6: placing reinforcing steel bar frame, the demoulding after the firm molding of base station, and reinforcing steel bar frame is fixed on base station;
S7: wall filling will build object and be sequentially filled by the sequence of average grain diameter from big to small in the affixed baffle in reinforcing steel bar frame two sides Into in the reinforcing steel bar frame between baffle, and leaching sand as made of masonry object mixing of the average grain diameter less than 10mm is poured from upper opening Slurry, wait build bonded between object it is firm after remove baffle and form wall body structure.
2. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S3, in framework reinforcing steel bar frame, polishing derusting is carried out to reinforcing bar.
3. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S3, the reinforcing bar periphery of the reinforcing steel bar frame is painted with antirust paint.
4. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S4, separating reinforcement tank from bottom to top is multilayer, and using layer-by-layer filling, the mode successively rammed is constructed.
5. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S5, when building base station, upper several fixed steel bars are plugged vertically between template, and fixed steel bars top is made to stretch out base Platform setting, and reinforcing bar frame bottom is welded in setting at the top of fixed steel bars.
6. the construction method that a kind of building waste according to claim 5 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S5, when building base station, base station width is arranged greater than reinforcing bar width of frame, and reserved suitable with reinforcing bar frame bottom on base station top The groove matched, and stretch out and be arranged from groove at the top of fixed steel bars.
7. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S7, for first kind material, intact plant material can form ornament or vegetation box by cutting, assembly, And it is positioned on wall;And more scrappy plant material can carry out pulverization process.
8. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S7, direction is extended along at the top of the wall and is provided with planting groove, textile material cushion is placed in planting groove, then is transplanted green Change plant in planting groove.
9. the construction method that a kind of building waste according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S7, resinous material is divided into thermoplastic class and thermosetting class, thermal plastic material's recycling and reusing, thermosetting class material is according to it Self-characteristic is processed as ornament, and is fixed in wall side wall.
10. the construction method that a kind of building waste stated according to claim 1 is used for environmentally friendly enclosure wall, which is characterized in that the step In rapid S7, glass is cut, is spliced and reprocessing forms ornament, and is secured on wall side wall.
CN201810866699.8A 2018-08-01 2018-08-01 Construction method for using construction waste for environment-friendly enclosing wall Expired - Fee Related CN108979296B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810866699.8A CN108979296B (en) 2018-08-01 2018-08-01 Construction method for using construction waste for environment-friendly enclosing wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810866699.8A CN108979296B (en) 2018-08-01 2018-08-01 Construction method for using construction waste for environment-friendly enclosing wall

Publications (2)

Publication Number Publication Date
CN108979296A true CN108979296A (en) 2018-12-11
CN108979296B CN108979296B (en) 2020-01-24

Family

ID=64554891

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810866699.8A Expired - Fee Related CN108979296B (en) 2018-08-01 2018-08-01 Construction method for using construction waste for environment-friendly enclosing wall

Country Status (1)

Country Link
CN (1) CN108979296B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113530235A (en) * 2021-07-19 2021-10-22 屈志斌 Clean and environment-friendly building construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4602765A (en) * 1984-04-23 1986-07-29 Loper Karl J Fencing assembly and process
CN101892764A (en) * 2010-06-19 2010-11-24 张培霞 Method for building enclosing wall
CN102587542A (en) * 2011-01-13 2012-07-18 谢兆坤 Method for producing wall with building waste
CN105198257A (en) * 2015-09-06 2015-12-30 越艳 Construction waste crushing and screening line method
CN206385903U (en) * 2017-01-16 2017-08-08 上海大越人居环境科技发展有限公司 A kind of green building enclosure wall for recycling timber
CN107143204A (en) * 2017-05-31 2017-09-08 中国十九冶集团有限公司 Detachable assembling enclosure construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4602765A (en) * 1984-04-23 1986-07-29 Loper Karl J Fencing assembly and process
CN101892764A (en) * 2010-06-19 2010-11-24 张培霞 Method for building enclosing wall
CN102587542A (en) * 2011-01-13 2012-07-18 谢兆坤 Method for producing wall with building waste
CN105198257A (en) * 2015-09-06 2015-12-30 越艳 Construction waste crushing and screening line method
CN206385903U (en) * 2017-01-16 2017-08-08 上海大越人居环境科技发展有限公司 A kind of green building enclosure wall for recycling timber
CN107143204A (en) * 2017-05-31 2017-09-08 中国十九冶集团有限公司 Detachable assembling enclosure construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113530235A (en) * 2021-07-19 2021-10-22 屈志斌 Clean and environment-friendly building construction method

Also Published As

Publication number Publication date
CN108979296B (en) 2020-01-24

Similar Documents

Publication Publication Date Title
CN105198257A (en) Construction waste crushing and screening line method
CN201442005U (en) Construction waste comprehensive treatment equipment
CN101913788A (en) Method for comprehensively treating construction waste
CN105776930B (en) A kind of microwave radiation technology picks the method for selecting recycled concrete coarse aggregate
CN102974420B (en) Cut roll crusher and construction waste roll-in crushing station based on same
CN104711974B (en) A kind of steel tube regeneration concrete complex carrier stake and preparation method thereof
CN209848991U (en) Environment-friendly building solid waste treatment device
CN108188149A (en) A kind of urban building waste treatment process and resource utilization process
CN102974596B (en) Construction waste co-extrusion harmless treatment system and method thereof
CN203076009U (en) Cutting roller crushing equipment and construction waste rolling crushing station based on same
CN102744236A (en) Comprehensive processing method of construction wastes
CN109095826A (en) A kind of production method of construction garbage brick
CN202410796U (en) System for recycling building rubbish
CN108409287A (en) A kind of Wetland ecological made using building waste is laid bricks and preparation method thereof
CN108979296A (en) A kind of building waste is used for the construction method of environmentally friendly enclosure wall
CN208786539U (en) A kind of building waste grinding device
CN104164822A (en) Process for paving pedestrian pavement by utilizing building debris
CN201940415U (en) Building rubbish disposal device
CN202280077U (en) Novel retaining wall
KR101601611B1 (en) Equipment for producing recycling aggrete using waste concrete
CN211597609U (en) Gap plugging device for building decoration
CN201073653Y (en) Recovery system of building recycled aggregate for construction site
CN212795371U (en) Clout cleaning device of production cement pole
CN103936316A (en) Waste-concrete regeneration system
CN113171865A (en) Preparation method of high-quality machine-made sand

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200124

Termination date: 20210801