CN108978665A - One kind is cast-in-place to build concrete curing method - Google Patents

One kind is cast-in-place to build concrete curing method Download PDF

Info

Publication number
CN108978665A
CN108978665A CN201810939423.8A CN201810939423A CN108978665A CN 108978665 A CN108978665 A CN 108978665A CN 201810939423 A CN201810939423 A CN 201810939423A CN 108978665 A CN108978665 A CN 108978665A
Authority
CN
China
Prior art keywords
layer
gunnysack
concrete
foundation pit
laid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810939423.8A
Other languages
Chinese (zh)
Inventor
江玲
叶兴国
吕俊杰
吕宗霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hui Du Construction Co Ltd
Original Assignee
Hui Du Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hui Du Construction Co Ltd filed Critical Hui Du Construction Co Ltd
Priority to CN201810939423.8A priority Critical patent/CN108978665A/en
Publication of CN108978665A publication Critical patent/CN108978665A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/246Safety or protective measures preventing damage to building parts or finishing work during construction specially adapted for curing concrete in situ, e.g. by covering it with protective sheets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

Cast-in-place concrete curing method is built the invention discloses a kind of, after concrete final set in pouring area inside foundation pit, at least 2 layers of gunnysack being sufficiently humidified so as to are covered on its surface, before foundation pit inner concrete will enter temperature-fall period, at least one layer of plastic film is covered on the gunnysack surface for being located at top layer, it is then laid at least one layer of gunnysack layer, at least two layers of gunnysack is laid on to the side of foundation pit inner concrete bottom plate, is fixed at template and the support section space of concrete floor;Conservation layer is built on the outside of concrete floor side, conservation layer is made of heating layer and insulating layer, and heating layer is located at the inside of insulating layer;The present invention conserves the cast-in-place concrete built by being laid with gunnysack, plastic film and geotextiles in the outside of foundation pit inner concrete, while building conservation layer and brooder and further being conserved to concrete, and maintenance effect is excellent.

Description

One kind is cast-in-place to build concrete curing method
Technical field
It is specifically a kind of cast-in-place to build concrete curing method the present invention relates to technical field of concrete.
Background technique
Concrete, referred to as " concrete ": refer to the general designation for the cementing integral engineered composite material that gathers materials by cementitious material. One word of concrete usually said, which refers to, makees cementitious material with cement, and sand, masonry gather materials;It is pressed with water (additive and admixture can be contained) Certain proportion cooperation, it is agitated obtained by cement concrete, also referred to as normal concrete, it is widely used in civil engineering.
After casting and compacting of concrete, why can gradually condense hardening, be primarily due to cement aquation as a result, and aquation Effect then needs temperature and humidity condition appropriate, therefore in order to guarantee that concrete has suitable curing condition, makes its intensity not It is disconnected to increase, it is necessary to which that concrete is conserved.
Existing concrete curing method is excessively single, is unable to satisfy requirement of the concrete to temperature and humidity, influences to mix Coagulate the hardening of soil.
Summary of the invention
The purpose of the present invention is to provide it is a kind of it is cast-in-place build concrete curing method, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the invention provides the following technical scheme:
One kind is cast-in-place to build concrete curing method, comprising the following steps:
1), after the concrete final set in pouring area 1 inside foundation pit, at least 2 layers of gunnysack being sufficiently humidified so as to is covered on its surface, are continued 3-5 days, in the process, remain the wet of gunnysack;
2) before, foundation pit inner concrete will enter temperature-fall period, in at least one layer of modeling of gunnysack surface covering for being located at top layer Expect film, is then laid at least one layer of gunnysack layer, at least one layer of geotextiles are covered on gunnysack layer, re-lay at least three layers on it Then gunnysack is laid at least one layer of plastic film, is finally laid at least two layers of gunnysack;
3), when the central temperature of foundation pit inner concrete bottom plate and the difference of environment temperature tend to 20 DEG C or falling temperature gradient tends to be greater than At 1.1 DEG C, it is laid with geotextiles and is kept the temperature;
4), at least two layers of gunnysack is laid on to the side of foundation pit inner concrete bottom plate, be fixed on the template and branch of concrete floor It supports at segment space, gunnysack edge fastens, and is pegged using flitch and nail, prevents gunnysack from falling;
5) conservation layer, is built on the outside of concrete floor side, conservation layer is made of heating layer and insulating layer, and heating layer is located at The inside of insulating layer, and heating layer is hollow structure;
6) brooder, is built above foundation pit after the completion of basis pours;It is arranged while providing the heating installation of heating in foundation pit, Heating installation is located at the four corners of foundation pit, and heating installation is connected to by air duct with the inside of heating layer, so as to heating layer Inside is passed through heating, conserves to concrete;
7), brooder is supported with the precast concrete column of 15 × 15cm of high 5.0~6.0m, and canopy lid is bound using round log scene, The concrete discharging mouth of ceiling sets movable material lid and is kept the temperature with piece of sack packet straw mattress;
8), the canopy lid is assembled using monolithic steel truss, and ceiling sets concrete discharging mouth and movable material lid;
As a further solution of the present invention: the gunnysack layer includes at least two layers of gunnysack, and at least two layers of gunnysack is using one vertical one Horizontal mode is laid with;
As further scheme of the invention: the inside of the insulating layer is filled with asbestos;
As further scheme of the invention: the brooder is by steel truss combination beam, sizing heat preservation supporting structure, hoisting structure And building enclosure assembles, entire canopy lid is integral lifting elements;
As further scheme of the invention: within the scope of 5~15 DEG C of temperature in the brooder.
Compared with prior art, the beneficial effects of the present invention are: the present invention in the outside of foundation pit inner concrete by spreading If gunnysack, plastic film and geotextiles conserve the cast-in-place concrete built, while building conservation layer and brooder to concrete It is further conserved, maintenance effect is excellent.
Detailed description of the invention
Fig. 1 is the cast-in-place structural schematic diagram for building concrete curing method.
In figure: the pouring area 1-, 2- heating installation, 3- conservation layer, 4- insulating layer, 5- heating layer, the air duct 6-.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, one kind is cast-in-place to build concrete curing method in the embodiment of the present invention, comprising the following steps:
1), after the concrete final set in pouring area 1 inside foundation pit, at least 2 layers of gunnysack being sufficiently humidified so as to is covered on its surface, are continued 3-5 days, in the process, remain the wet of gunnysack;
2) before, foundation pit inner concrete will enter temperature-fall period, in at least one layer of modeling of gunnysack surface covering for being located at top layer Expect film, is then laid at least one layer of gunnysack layer, at least one layer of geotextiles are covered on gunnysack layer, re-lay at least three layers on it Then gunnysack is laid at least one layer of plastic film, is finally laid at least two layers of gunnysack;
3), when the central temperature of foundation pit inner concrete bottom plate and the difference of environment temperature tend to 20 DEG C or falling temperature gradient tends to be greater than At 1.1 DEG C, it is laid with geotextiles and is kept the temperature;
4), at least two layers of gunnysack is laid on to the side of foundation pit inner concrete bottom plate, be fixed on the template and branch of concrete floor It supports at segment space, gunnysack edge fastens, and is pegged using flitch and nail, prevents gunnysack from falling;
5) conservation layer 3, is built on the outside of concrete floor side, conservation layer 3 is made of heating layer 5 and insulating layer 4, heating layer 5 are located at the inside of insulating layer 4, and heating layer 5 is hollow structure;
6) brooder, is built above foundation pit after the completion of basis pours;It is arranged in foundation pit while the heating installation of heating is provided 2, heating installation 2 is located at the four corners of foundation pit, and heating installation 2 is connected to by air duct with the inside of heating layer, so as to heating The inside of layer is passed through heating, conserves to concrete;
7), brooder is supported with the precast concrete column of 15 × 15cm of high 5.0~6.0m, and canopy lid is bound using round log scene, The concrete discharging mouth of ceiling sets movable material lid and is kept the temperature with piece of sack packet straw mattress;
8), the canopy lid is assembled using monolithic steel truss, and ceiling sets concrete discharging mouth and movable material lid;
Preferably, in the present embodiment, the gunnysack layer includes at least two layers of gunnysack, the side that at least two layers of gunnysack uses a vertical and one horizontal Formula is laid with;
Preferably, in the present embodiment, the inside of the insulating layer 4 is filled with asbestos;
Preferably, in the present embodiment, the brooder is by steel truss combination beam, sizing heat preservation supporting structure, hoisting structure and goes along with sb. to guard him Structure assembles, and entire canopy lid is integral lifting elements;
Preferably, in the present embodiment, within the scope of 5~15 DEG C of temperature in the brooder.
The present invention by the outside of foundation pit inner concrete be laid with gunnysack, plastic film and geotextiles to it is cast-in-place build it is mixed Solidifying soil is conserved, while being built conservation layer and brooder and further being conserved to concrete, and maintenance effect is excellent.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (5)

1. one kind is cast-in-place to build concrete curing method, which comprises the following steps:
1), after the concrete final set in pouring area 1 inside foundation pit, at least 2 layers of gunnysack being sufficiently humidified so as to is covered on its surface, are continued 3-5 days, in the process, remain the wet of gunnysack;
2) before, foundation pit inner concrete will enter temperature-fall period, in at least one layer of modeling of gunnysack surface covering for being located at top layer Expect film, is then laid at least one layer of gunnysack layer, at least one layer of geotextiles are covered on gunnysack layer, re-lay at least three layers on it Then gunnysack is laid at least one layer of plastic film, is finally laid at least two layers of gunnysack;
3), when the central temperature of foundation pit inner concrete bottom plate and the difference of environment temperature tend to 20 DEG C or falling temperature gradient tends to be greater than At 1.1 DEG C, it is laid with geotextiles and is kept the temperature;
4), at least two layers of gunnysack is laid on to the side of foundation pit inner concrete bottom plate, be fixed on the template and branch of concrete floor It supports at segment space, gunnysack edge fastens, and is pegged using flitch and nail, prevents gunnysack from falling;
5) it, is built on the outside of concrete floor side conservation layer (3), conservation layer (3) is by heating layer (5) and insulating layer (4) group At heating layer (5) is located at the inside of insulating layer (4), and heating layer (5) is hollow structure;
6) brooder, is built above foundation pit after the completion of basis pours;It is arranged in foundation pit while the heating installation of heating is provided (2), heating installation (2) is located at the four corners of foundation pit, and heating installation (2) is connected to by air duct with the inside of heating layer;
7), brooder is supported with the precast concrete column of 15 × 15cm of high 5.0~6.0m, and canopy lid is bound using round log scene, The concrete discharging mouth of ceiling sets movable material lid and is kept the temperature with piece of sack packet straw mattress;
8), the canopy lid is assembled using monolithic steel truss, and ceiling sets concrete discharging mouth and movable material lid.
2. cast-in-place concrete curing method is built according to claim 1, which is characterized in that the gunnysack layer includes at least two Layer gunnysack, at least two layers of gunnysack are laid with by the way of a vertical and one horizontal.
3. cast-in-place concrete curing method is built according to claim 1, which is characterized in that the inside of the insulating layer (4) Filled with asbestos.
4. cast-in-place concrete curing method is built according to claim 1, which is characterized in that the brooder is combined by steel truss Beam, sizing heat preservation supporting structure, hoisting structure and building enclosure assemble, and entire canopy lid is integral lifting elements.
5. cast-in-place concrete curing method is built according to claim 1, which is characterized in that temperature 5 in the brooder~ Within the scope of 15 DEG C.
CN201810939423.8A 2018-08-17 2018-08-17 One kind is cast-in-place to build concrete curing method Pending CN108978665A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810939423.8A CN108978665A (en) 2018-08-17 2018-08-17 One kind is cast-in-place to build concrete curing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810939423.8A CN108978665A (en) 2018-08-17 2018-08-17 One kind is cast-in-place to build concrete curing method

Publications (1)

Publication Number Publication Date
CN108978665A true CN108978665A (en) 2018-12-11

Family

ID=64553928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810939423.8A Pending CN108978665A (en) 2018-08-17 2018-08-17 One kind is cast-in-place to build concrete curing method

Country Status (1)

Country Link
CN (1) CN108978665A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041994A (en) * 2019-12-24 2020-04-21 中交隧道工程局有限公司 Pier stud wraps up in mould device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102501311A (en) * 2011-11-23 2012-06-20 国核工程有限公司 Method for curing bottom plate concrete of nuclear island
CN103410164A (en) * 2013-08-07 2013-11-27 国家电网公司 Concrete curing method for power transmission and transformation line foundations in winter
CN104109989A (en) * 2013-04-18 2014-10-22 中铁十一局集团第一工程有限公司 Method for curing double-block ballastless tracks in extreme environments
CN104369262A (en) * 2013-08-12 2015-02-25 中铁二局股份有限公司 Concrete curing method for Gobi environments
CN204850505U (en) * 2015-07-20 2015-12-09 中国建筑第八工程局有限公司 Concrete heat preservation maintenance brooder
CN206957250U (en) * 2017-06-06 2018-02-02 中国建筑第六工程局有限公司 A kind of brooder for the freeze proof heat preservation construction of severe cold area cold weather concrete

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102501311A (en) * 2011-11-23 2012-06-20 国核工程有限公司 Method for curing bottom plate concrete of nuclear island
CN104109989A (en) * 2013-04-18 2014-10-22 中铁十一局集团第一工程有限公司 Method for curing double-block ballastless tracks in extreme environments
CN103410164A (en) * 2013-08-07 2013-11-27 国家电网公司 Concrete curing method for power transmission and transformation line foundations in winter
CN104369262A (en) * 2013-08-12 2015-02-25 中铁二局股份有限公司 Concrete curing method for Gobi environments
CN204850505U (en) * 2015-07-20 2015-12-09 中国建筑第八工程局有限公司 Concrete heat preservation maintenance brooder
CN206957250U (en) * 2017-06-06 2018-02-02 中国建筑第六工程局有限公司 A kind of brooder for the freeze proof heat preservation construction of severe cold area cold weather concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111041994A (en) * 2019-12-24 2020-04-21 中交隧道工程局有限公司 Pier stud wraps up in mould device

Similar Documents

Publication Publication Date Title
CN106013811B (en) A kind of installation method of assembled architecture
CN102245529B (en) Lightweight house structure built by mortar and production method thereof
CN102677898A (en) Sequence construction method for large area reinforced concrete floors
CN108343173A (en) High-strength foam concrete self-heat conserving shear wall and high-strength foam concrete self-heat conserving shear wall structure system
CN102747807A (en) Novel building wallboard, building wall body structure and manufacturing method thereof
CN110469138B (en) Traditional rammed earth building repairing method and structure
CN106284653B (en) A kind of construction method that balcony construct capital interspaces in advance
CN103821263A (en) Precast assembly self-heat preservation concrete shear wall system and construction method thereof
CN108978665A (en) One kind is cast-in-place to build concrete curing method
CN205776349U (en) A kind of stand alone type brick setting antidetonation cave dwelling
CN208415928U (en) A kind of prefabricated lining being used in combination with aluminum dipping form
CN111101594A (en) Cold-formed thin-wall light steel structure building
CN105967631A (en) Prefabricated housing made from straw composite material
CN207110035U (en) Assembled steel tendon concrete frame structure based on steel plate connection joint
CN108018986A (en) A kind of structure and half prefabricated Side fascia of energy saving integrated and its construction method
CN108625590A (en) A kind of prefabricated lining being used in combination with aluminum dipping form
CN107473656A (en) A kind of foaming concrete lightweight material and the traditional rowlock wall body construction method of filling
JPH02164755A (en) Concrete improver and improvement of concrete
CN211690738U (en) Cold-formed thin-wall light steel structure building
CN106639089A (en) Novel assembled I-shaped prefabricated composite floor supporting plate and preparing method thereof
CN105731904A (en) High-quality building pile and preparation method thereof
CN206418642U (en) A kind of I-shaped prefabricated compound floor support plate of novel fabricated
CN106284720A (en) A kind of building flooring with heat-and sound-insulating function and constructing structure thereof
CN207211805U (en) A kind of existing building adds the shockproof ruggedized construction of layer
CN206570973U (en) Building flooring and its constructing structure with heat-and sound-insulating function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211

RJ01 Rejection of invention patent application after publication