CN108978650A - A kind of retarded adhesive prestressed single-pile foundation - Google Patents

A kind of retarded adhesive prestressed single-pile foundation Download PDF

Info

Publication number
CN108978650A
CN108978650A CN201810965260.0A CN201810965260A CN108978650A CN 108978650 A CN108978650 A CN 108978650A CN 201810965260 A CN201810965260 A CN 201810965260A CN 108978650 A CN108978650 A CN 108978650A
Authority
CN
China
Prior art keywords
ontology
pile foundation
delayed bonding
retarded adhesive
bonding prestressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810965260.0A
Other languages
Chinese (zh)
Inventor
曾永平
陶奇
郑晓龙
庞林
杨国静
素延文
董俊
徐昕宇
周川江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201810965260.0A priority Critical patent/CN108978650A/en
Publication of CN108978650A publication Critical patent/CN108978650A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of retarded adhesive prestressed single-pile foundations, including ontology, it is equipped with several delayed bonding prestressed tendons along longitudinal direction in the ontology, wherein the delayed bonding prestressed tendon is greater than the arrangement quantity in the compression-side of the ontology in the arrangement quantity of the tension side of the ontology.The present invention increases delayed bonding prestressed tendon in single-pile foundation, by calculating single-pile foundation pile body institute bending moment, according to single-pile foundation not having in tension side and compression-side load, bigger tensile strength is needed in tension side, therefore, it is greater than compression-side in the quantity of the delayed bonding prestressed tendon of tension side setting, along pile body, delayed bonding prestressed tendon is rationally set, it can not only be under the premise of meeting bearing requirements, reduce stake diameter and reduces the quantity of regular reinforcement, and the advantages of having bonding and Non-cohesive Prestressing Force Technology, is combined, it maximizes favourable factors and minimizes unfavourable ones, without reserving hole channel, without grouting, easy construction, structure is safe and reliable.

Description

A kind of retarded adhesive prestressed single-pile foundation
Technical field
The present invention relates to track engineering field, in particular to a kind of retarded adhesive prestressed single-pile foundation.
Background technique
For suspension type monorail because pier shaft is higher, line spacing is larger, and basis top institute bending moment is larger, excavates and subtracts to reduce Few construction period, basis is often arranged to single-pile foundation, when single-pile foundation pile body institute bending moment is larger, by increasing stake diameter And the quantity of regular reinforcement come resist bending be it is uneconomical and less reasonable, therefore, how to meet load requirement Under the premise of, realize that reducing stake diameter and driving depth is of great significance to single-pile foundation.
Summary of the invention
It is an object of the invention to overcome the above-mentioned deficiency in the presence of the prior art, provide a kind of retarded adhesive prestressed Single-pile foundation.
In order to achieve the above-mentioned object of the invention, the present invention provides following technical schemes:
A kind of retarded adhesive prestressed single-pile foundation, including ontology are equipped with several slow cohesions in the ontology and answer in advance Power muscle, wherein the delayed bonding prestressed tendon is greater than the compression in the ontology in the arrangement quantity of the tension side of the ontology The arrangement quantity of side.
Delayed bonding prestressed tendon refers in construction stage prestress wire dilatation freedom, not with around, slow setting is bonded Agent generates bonding, and presstressed reinforcing steel passes through cured slow setting adhesive and surrounding concrete in predetermined period after the completion of construction Generate cementation.
The present invention increases delayed bonding prestressed tendon in single-pile foundation, and curved suffered by single-pile foundation pile body by calculating Square is needed according to single-pile foundation in the difference of tension side (lineback trackside) and compression-side (upper thread trackside) load in tension side Therefore tensile strength that will be bigger is greater than compression-side in the quantity of the delayed bonding prestressed tendon of tension side setting, reasonable along pile body Delayed bonding prestressed tendon is set, can not only reduce stake diameter under the premise of meeting bearing requirements and reduce the quantity of regular reinforcement, And the advantages of having bonding and Non-cohesive Prestressing Force Technology is combined, it maximizes favourable factors and minimizes unfavourable ones, is not necessarily to reserving hole channel, without grouting, apply Work is easy, and structure is safe and reliable.
In particular, the retarded adhesive prestressed single-pile foundation can be directly used for assembled installation, due to using slow cohesion Presstressed reinforcing steel, can be to be transported when being assembled to scene in factory process, with regard to pre-buried delayed bonding prestressed tendon, then tensioning The presstressed reinforcing steel can not only save prefabrication and field erected time, process, reduce labor cost and construction cost, Moreover, avoiding loss of prestress caused by too early tensioning.
Preferably, the delayed bonding prestressed tendon is symmetrical arranged along the horizontal path centerline axis of the ontology, convenient Processing and installation.
Preferably, in ontology arrangement, there are many delayed bonding prestressed tendons of different length, and closer to described The quantity of the top area of ontology, the corresponding delayed bonding prestressed tendon of the ontology unit area is more.According to single pile base The requirement of plinth structure stress, the delayed bonding prestressed tendon of settable a variety of different sizes, in the case where meeting load requirement, section The about setting of delayed bonding prestressed tendon, has saved material and construction cost.
Specifically, the ontology top area and be located at tension side adjacent two delayed bonding prestressed tendons it Between angle be 10 ° -30 °, the ontology bottom section and be located at adjacent two of tension side it is described retarded adhesive prestressed Angle between muscle is 40 ° -80 °.
Preferably, when delayed bonding prestressed tendon described in tensioning, the longer delayed bonding prestressed tendon of pretensioning length, then The shorter delayed bonding prestressed tendon of tensioning length.In general, tensioned prestressing bar should be divided into two stages progress, work as stake The solidifying native intensity of body and elasticity modulus reach the 95% of design value, and carry out phase tensioning, a phase tensioning steel when 10 day age of satisfaction Beam is the longer steel beam of length, after phase tensioning, after the completion of bridge pier and beam body are set up, and tensioning residue steel beam.
Preferably, the delayed bonding prestressed tendon is pierced by the top of the ontology, and is fixed on the ontology by anchorage On.
Preferably, the anchorage uses low retraction anchorage, and retraction value is less than or equal to 10mm, and anchorage is grasped in anchoring operation Make simple and effective, and stability is high.
Preferably, the anchorage is surrounded by sealing off and covering anchorage concrete.
Preferably, the delayed bonding prestressed tendon is positioned by Steel bar rack.
Preferably, the delayed bonding prestressed tendon is high-strength underrelaxation slow-adhesion prestress steel strand.
Compared with prior art, beneficial effects of the present invention:
The present invention increases delayed bonding prestressed tendon in single-pile foundation, and curved suffered by single-pile foundation pile body by calculating Square is needed according to single-pile foundation in the difference of tension side (lineback trackside) and compression-side (upper thread trackside) load in tension side Therefore tensile strength that will be bigger is greater than compression-side in the quantity of the delayed bonding prestressed tendon of tension side setting, reasonable along pile body Delayed bonding prestressed tendon is set, can not only reduce stake diameter under the premise of meeting bearing requirements and reduce the quantity of regular reinforcement, And the advantages of having bonding and Non-cohesive Prestressing Force Technology is combined, it maximizes favourable factors and minimizes unfavourable ones, is not necessarily to reserving hole channel, without grouting, apply Work is easy, and structure is safe and reliable.
In particular, the retarded adhesive prestressed single-pile foundation can be directly used for assembled installation, due to using slow cohesion Presstressed reinforcing steel, can be to be transported when being assembled to scene in factory process, with regard to pre-buried delayed bonding prestressed tendon, then tensioning The presstressed reinforcing steel can not only save prefabrication and field erected time, process, reduce labor cost and construction cost, Moreover, avoiding loss of prestress caused by too early tensioning.
Detailed description of the invention:
Fig. 1 is the structural schematic diagram of the retarded adhesive prestressed single-pile foundation of one kind of the present invention.
Fig. 2 is the A-A cross-sectional view in Fig. 1.
Fig. 3 is the B-B cross-sectional view in Fig. 1.
Fig. 4 is the C-C cross-sectional view in Fig. 1.
Fig. 5 is the anchoring schematic diagram of delayed bonding prestressed tendon of the present invention.
Marked in the figure: 1- ontology, 11- tension side, 12- compression-side, 2- delayed bonding prestressed tendon, 3- anchorage, 4- reinforcing bar, 5- Sealing off and covering anchorage concrete, 6- parallel circuit center line, 7- horizontal path center line.
Specific embodiment
Below with reference to test example and specific embodiment, the present invention is described in further detail.But this should not be understood It is all that this is belonged to based on the technology that the content of present invention is realized for the scope of the above subject matter of the present invention is limited to the following embodiments The range of invention.
As shown in Figure 1, a kind of retarded adhesive prestressed single-pile foundation, including ontology 1, the ontology 1 are armored concrete Structure is equipped with several reinforcing bars 4 in the ontology 1 along longitudinal direction.The ontology 1 can position according to installation and loading characteristic, It is divided into tension side 11 and compression-side 12, specifically, tension side 11 is normally at lineback trackside, compression-side 12 is then located at upper thread road Side.There are two symmetry axis in the generally circular in cross section section of the ontology 1, according to the positional relationship with driving route, respectively in parallel Central lines of track 6 and horizontal path center line 7.
As shown in figs 2-4, several delayed bonding prestressed tendons 2 are additionally provided in the ontology 1, the slow cohesion is answered in advance Power muscle 2 is positioned by Steel bar rack, and the delayed bonding prestressed tendon 2 is twisted using the retarded adhesive prestressed steel of high-strength underrelaxation Line.And the delayed bonding prestressed tendon 2 is significantly greater than in the arrangement quantity of the tension side 11 of the ontology 1 in the ontology 1 The arrangement quantity of compression-side 12, the delayed bonding prestressed tendon 2 are set along 7 axial symmetry of horizontal path center line of the ontology 1 It sets.
The delayed bonding prestressed tendon 2 includes mainly two different length, as shown in Fig. 2, at the top of the ontology 1 When, the delayed bonding prestressed tendon 2 of different length is pierced by the top of the ontology 1, and is fixed on the ontology 1 by anchorage 3 On, sealing off and covering anchorage (as shown in Figure 5) is finally carried out by sealing off and covering anchorage concrete 5 again, compared with bonded prestress, delayed bonding prestressed tendon 2 do not need to wear bellows, do not need to be in the milk, and reduce twice complicated procedures of forming, and reducing live manual operation influences, construction quality It is easy to get guarantee.
As shown in figure 3, the quantity of the delayed bonding prestressed tendon 2 is more, including two kinds at the top of the ontology 1 The delayed bonding prestressed tendon 2 of different length, the angle a between adjacent two delayed bonding prestressed tendons 2 of tension side are 10 ° -30 °, two delayed bonding prestressed tendons 2 are then only set in compression-side.
As shown in figure 4, the quantity of the delayed bonding prestressed tendon 2 significantly reduces, shorter at the lower part of the ontology 1 Delayed bonding prestressed tendon 2 all terminate at the middle part of ontology 1, the lower part of ontology 1 only includes that the longer slow cohesion of length is answered in advance Power muscle 2, at this point, the angle b between adjacent two delayed bonding prestressed tendons 2 of tension side is 40 ° -80 °.
When delayed bonding prestressed tendon 2 described in tensioning, two stages progress should be divided into.When the solidifying native intensity and elasticity of ontology 1 Modulus reaches the 95% of design value, and phase tensioning is carried out when 10 day age of satisfaction, and phase tensioning steel beam is the longer steel of length Beam, after phase tensioning, after the completion of bridge pier and beam body are set up, tensioning residue steel beam.Steel Shu Zhangla uses stretching force and elongation Dual control, and based on the control of steel beam stretching force.
Above embodiments are only to illustrate the present invention and not limit the technical scheme described by the invention, although this explanation The present invention has been described in detail referring to above-mentioned each embodiment for book, but the present invention is not limited to above-mentioned specific implementation Mode, therefore any couple of present invention modifies or equivalent replacement;And the technical side of all spirit and scope for not departing from invention Case and its improvement, are intended to be within the scope of the claims of the invention.

Claims (10)

1. a kind of retarded adhesive prestressed single-pile foundation, which is characterized in that including ontology (1), in the ontology (1) along longitudinal direction Equipped with several delayed bonding prestressed tendons (2), wherein tension side of the delayed bonding prestressed tendon (2) in the ontology (1) (11) arrangement quantity is greater than the arrangement quantity in the compression-side (12) of the ontology (1).
2. the retarded adhesive prestressed single-pile foundation of one kind according to claim 1, which is characterized in that the slow cohesion is answered in advance Power muscle (2) is arranged along horizontal path center line (7) axial symmetry of the ontology (1).
3. the retarded adhesive prestressed single-pile foundation of one kind according to claim 1, which is characterized in that in the ontology (1) Arrange the delayed bonding prestressed tendon (2) there are many different length, and the top area closer to the ontology (1), it is described The quantity of the corresponding delayed bonding prestressed tendon (2) of ontology (1) unit area is more.
4. the retarded adhesive prestressed single-pile foundation of one kind according to claim 3, which is characterized in that in the ontology (1) Top area and be located at tension side adjacent two delayed bonding prestressed tendons (2) between angle be 10 ° -30 °, in institute It states the bottom section of ontology (1) and the angle being located between adjacent two delayed bonding prestressed tendons (2) of tension side is 40°-80°。
5. the retarded adhesive prestressed single-pile foundation of one kind according to claim 3, which is characterized in that slow cohesion described in tensioning When presstressed reinforcing steel (2), the longer delayed bonding prestressed tendon (2) of pretensioning length, then shorter described slow viscous of tensioning length It ties presstressed reinforcing steel (2).
6. the retarded adhesive prestressed single-pile foundation of one kind according to claim 1, which is characterized in that the slow cohesion is answered in advance Power muscle (2) is pierced by the top of the ontology (1), and is fixed on the ontology (1) by anchorage (3).
7. the retarded adhesive prestressed single-pile foundation of one kind according to claim 6, which is characterized in that the anchorage (3) is adopted With low retraction anchorage, retraction value is less than or equal to 10mm.
8. the retarded adhesive prestressed single-pile foundation of one kind according to claim 6, which is characterized in that the anchorage (3) It is surrounded by sealing off and covering anchorage concrete (5).
9. the retarded adhesive prestressed single-pile foundation of -8 any described one kind according to claim 1, which is characterized in that described slow viscous Knot presstressed reinforcing steel (2) is positioned by Steel bar rack.
10. the retarded adhesive prestressed single-pile foundation of -8 any described one kind according to claim 1, which is characterized in that described slow Binding prestress reinforcement (2) is high-strength underrelaxation slow-adhesion prestress steel strand.
CN201810965260.0A 2018-08-22 2018-08-22 A kind of retarded adhesive prestressed single-pile foundation Pending CN108978650A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810965260.0A CN108978650A (en) 2018-08-22 2018-08-22 A kind of retarded adhesive prestressed single-pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810965260.0A CN108978650A (en) 2018-08-22 2018-08-22 A kind of retarded adhesive prestressed single-pile foundation

Publications (1)

Publication Number Publication Date
CN108978650A true CN108978650A (en) 2018-12-11

Family

ID=64547390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810965260.0A Pending CN108978650A (en) 2018-08-22 2018-08-22 A kind of retarded adhesive prestressed single-pile foundation

Country Status (1)

Country Link
CN (1) CN108978650A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020089029A (en) * 2001-05-22 2002-11-29 이윤주 Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
JP2002371529A (en) * 2001-06-13 2002-12-26 Nippon Steel Corp Water area structure with retarding chamber
CN101629418A (en) * 2009-08-03 2010-01-20 天津市建筑科学研究院 Post-tensioned prestressing cast pile and construction method thereof
CN103835311A (en) * 2014-02-25 2014-06-04 中交第一航务工程勘察设计院有限公司 Post-tensioned prestressing underground diaphragm wall and construction method
CN105350531A (en) * 2015-10-21 2016-02-24 葛建 Pipe pile-anchor rod composite foundation capable of bearing pulling and pressing bidirectional loads and construction technology
CN206512711U (en) * 2017-02-24 2017-09-22 中铁二十五局集团第五工程有限公司 A kind of slow-adhesion prestress steel strand fixed structure
CN208668406U (en) * 2018-08-22 2019-03-29 中铁二院工程集团有限责任公司 A kind of retarded adhesive prestressed single-pile foundation

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020089029A (en) * 2001-05-22 2002-11-29 이윤주 Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
JP2002371529A (en) * 2001-06-13 2002-12-26 Nippon Steel Corp Water area structure with retarding chamber
CN101629418A (en) * 2009-08-03 2010-01-20 天津市建筑科学研究院 Post-tensioned prestressing cast pile and construction method thereof
CN103835311A (en) * 2014-02-25 2014-06-04 中交第一航务工程勘察设计院有限公司 Post-tensioned prestressing underground diaphragm wall and construction method
CN105350531A (en) * 2015-10-21 2016-02-24 葛建 Pipe pile-anchor rod composite foundation capable of bearing pulling and pressing bidirectional loads and construction technology
CN206512711U (en) * 2017-02-24 2017-09-22 中铁二十五局集团第五工程有限公司 A kind of slow-adhesion prestress steel strand fixed structure
CN208668406U (en) * 2018-08-22 2019-03-29 中铁二院工程集团有限责任公司 A kind of retarded adhesive prestressed single-pile foundation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
全国高校建筑施工研究会: "高效预应力结构设计施工实例应用手册", 中国建筑工业出版社, pages: 1056 - 1057 *

Similar Documents

Publication Publication Date Title
CN105863145B (en) Beam-string structure, beam string and building
CN203007856U (en) External prestressing reinforcement system for hollow slab girder bridge
CN108708498A (en) A kind of external prestressing strengthening concrete frame beam structure and its construction method
CN106639355A (en) Reinforced concrete beam structure
CN107794837A (en) Suitable for the prefabricated assembled bridge pier and its construction method of middle meizoseismal area
CN100529264C (en) Method of applying prestress and connecting means used therein and prestressed concrete beam therefrom
CN104947603A (en) Reinforced concrete girder bridge girder reinforcing structure and method
CN109750791A (en) A kind of assembled large overhanging steel structure
CN107338864A (en) A kind of prefabricated reinforced concrete frame structure node
CN109653531A (en) A kind of external prestressing steel strand connector and mating tensioning equipment
CN108678225A (en) The built-in steel plate combined shear wall of built-in presstressed reinforcing steel steel pipe concrete frame and the practice
CN208668406U (en) A kind of retarded adhesive prestressed single-pile foundation
CN108330806A (en) The steel-that compoiste adhering anchors shear connections knot mixes combined beam structure and production method
CN105735099B (en) Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing
CN202787099U (en) Reinforced concrete cap beam external prestressing structure
CN106958319A (en) Precast concrete post component and connected node
CN205630974U (en) Pre -tensioning system precast beam pedestal
CN103088962A (en) Prestressed reinforced concrete precast beam based on pre-tensioning method
CN106930436A (en) A kind of reinforced concrete shear wall of built-in prestress steel diagonal brace
CN104562944B (en) Long span steel-concrete composite beam cable-stayed bridge limit steel case anchoring temporarily system
CN108978650A (en) A kind of retarded adhesive prestressed single-pile foundation
CN208685434U (en) The retarded adhesive prestressed precast pier of suspension type monorail of the Y type with flanged joint
CN205557349U (en) Device is changed to jib
CN108824175A (en) The retarded adhesive prestressed precast pier of suspension type monorail of the Y type with flanged joint
CN110524675A (en) A kind of pre-tensioning system precast H-beam and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination