CN108951963A - The construction method of assembled wall - Google Patents

The construction method of assembled wall Download PDF

Info

Publication number
CN108951963A
CN108951963A CN201810959220.5A CN201810959220A CN108951963A CN 108951963 A CN108951963 A CN 108951963A CN 201810959220 A CN201810959220 A CN 201810959220A CN 108951963 A CN108951963 A CN 108951963A
Authority
CN
China
Prior art keywords
wall
floor slab
precast floor
construction method
lifters
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810959220.5A
Other languages
Chinese (zh)
Other versions
CN108951963B (en
Inventor
朱凤起
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengde Green Building Energy Saving Technology Co Ltd
Original Assignee
Chengde Green Building Energy Saving Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengde Green Building Energy Saving Technology Co Ltd filed Critical Chengde Green Building Energy Saving Technology Co Ltd
Publication of CN108951963A publication Critical patent/CN108951963A/en
Application granted granted Critical
Publication of CN108951963B publication Critical patent/CN108951963B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction method of assembled wall, the wall internal structure has the cavity being intervally arranged, and is equipped with concrete rib between adjacent cavity, described method includes following steps: S1: cleaning, unwrapping wire, absolute altitude survey are set;S2: installation positioning leveling part;S3: wall lifting;S4: wall positioning is adjusted;S5: reinforcing bar binding;S6: cast-in-place region template is installed;S7: correction wall body vertical degree;S8: installation precast floor slab supporting element;S9: hoisting prefabricated floor;S10: precast floor slab supporting element is adjusted;S11: reinforcing bar is laid on precast floor slab;S12: the cavity, cast-in-place area and precast floor slab are poured.The construction method is used for the assembly of the precast wall body with the cavity that is intervally arranged, and guarantees the accuracy and stability of assembly.

Description

The construction method of assembled wall
Technical field
The present invention relates to construction engineering technical field, especially a kind of construction method of assembled wall.
Background technique
Excessively a kind of precast wall body structure of the present inventor's once invention, precast wall body structure is interior to be equipped with multiple be intervally arranged Cavity, be placed with concrete rib between adjacent cavity.As inventor is invented, it is disclosed in the prefabricated of CN107097331A Wall body structure is that linear type wall and CN107511914A with the cavity that is intervally arranged are disclosed with the cavity that is intervally arranged L-type and T-type precast wall body structure etc..
But above-mentioned patent only describes the manufacturing method of precast wall body structure, but fail to disclose how using this Wall carries out assembled in situ.Since this wall body structure itself is different from traditional precast wall body, such as still using existing normal Assembly method is advised, can make the stability of assembly and accuracy that can not ensure.
Summary of the invention
The object of the present invention is to provide a kind of construction methods of assembled wall, suitable for having the pre- of cavity that be intervally arranged The assembly of wall processed guarantees the accuracy and stability of assembly.
To achieve the goals above, the construction method of a kind of assembled wall provided by the invention, wall inside structure The cavity being intervally arranged is made, is equipped with concrete rib between adjacent cavity, described method includes following steps:
The construction method of assembled wall, the wall internal structure have a cavity being intervally arranged, between adjacent cavity Equipped with concrete rib, which is characterized in that described method includes following steps:
S1: cleaning, unwrapping wire, absolute altitude survey are set: construction personnel is clean, smooth by land clearing first, then according to construction drawing Paper, which is put, sets axis, wall sideline and control line;Copy the absolute altitude for surveying ground under wall;
S2: installation positioning leveling part: it includes pedestal and lifters two parts that the positioning, which levels part, and the is offered on pedestal One mounting hole, the second mounting hole is offered in lifters, and the lifters can be along lifting on the inside of the pedestal;The bottom surface of pedestal Equipped with vertical adjustment screw rod and vertical adjustment nut, vertical adjustment screw rod top passes through the bottom surface of lifters;The two sides side of pedestal Face is equipped with lateral adjustments screw rod and lateral adjustments nut;
The mounting means of the positioning leveling part includes: to stamp location hole on the ground, makes the first mounting hole and location hole To just, the first mounting hole and location hole are passed through with bolt, the position of adjustment positioning leveling part, then fastening bolt, fixes and determine The pedestal of position leveling part;
S3: wall lifting: lifting wall, by the pre-buried internal thread of the second mounting hole of the lifters of positioning leveling part and wall To just, the second mounting hole of lifters and the pre-buried internal thread of wall are then successively penetrated with bolt, tightens bolt, then by wall It slowly falls, and then the lifters on wall is slowly fallen within into positioning and are leveled on the pedestal of part;
S4: wall positioning is adjusted:
S41: verticality is adjusted
Inclined support bar is installed in the side of wall, inclined support bar one end and wall are hinged, and the other end supports on the ground, tiltedly Support rod is to adjustably adjust bar, and the length by adjusting inclined support bar adjusts the verticality of wall, to meet the requirements;
S42: height adjustment
Make wall on the control line, adjust the vertical adjustment nut on positioning leveling part pedestal, vertical adjustment nut is upward When rotation, lifters are raised, and then wall height is driven to increase, and when vertical adjustment nut is rotated down, lifters are reduced, in turn So that wall height reduces;
S43: horizontal direction is adjusted, and horizontal direction adjusts the adjusting including front and back and left and right both direction;
The lateral adjustments nut on positioning leveling part pedestal is adjusted, the left-right position tune of the lateral adjustments nut of two sides is passed through Section, determines the position on the left and right directions of wall;It is equipped with telescopically adjustable straight-bar below inclined support bar, is adjusted by straight-bar Position on wall front-rear direction;
S5: reinforcing bar binding
When two neighboring wall lateral connection, stirrup is first placed, vertical reinforcement, upper layer and lower layer wall are then placed in stirrup Vertical reinforcement between body is connected by screw shell, is finally bound;
S6: installing cast-in-place region template, postpones the gap to be formed to enclose wall in fixed bit, forms cast-in-place area;Installation The pad side of wall bottom, so that pad side blocks the gap between wall and ground;
S7: correction wall body vertical degree
It is corrected again by verticality of the inclined support bar to wall;
S8: installation precast floor slab supporting element
Precast floor slab supporting element includes fixed part, support portion and adjustment portion three parts;Fixed part is bolted on wall Internal side, support portion include the pipe fitting for penetrating through fixed part, and the top of pipe fitting is fixedly connected with supporter, and lower part is fixed with connecting plate; Pad side is equipped with above supporter;Adjustment portion includes the adjusting screw rod for penetrating through connecting plate and fixed part, adjusting screw rod one end and fixation Portion is fixedly connected, and the other end is equipped with adjusting nut;
The mounting means of precast floor slab supporting element are as follows: the fixed part of supporting element is bolted on wall;
S9: hoisting prefabricated floor;
Precast floor slab is lifted by crane, precast floor slab is placed in the pad side of the support portion;
S10: precast floor slab supporting element is adjusted
The adjusting nut below adjusting screw rod is screwed, upward turn is lifted support portion upwards relative to fixed part, lift The height of high precast floor slab, downward turn decline support portion relative to fixed part, reduce the height of precast floor slab;
S11: reinforcing bar is laid on precast floor slab;
S12: the cavity, cast-in-place area and precast floor slab are poured.
Alternatively and preferably, if the wall is that exterior wall further includes the steps that exterior wall slurry seal before step S3, The step of exterior wall slurry seal includes:
Slurry seal component is set on the ground, and after wall lifting is slowly fallen, seat is on slurry seal component, by the siphonal lobe of exterior wall Gap sealing between plate and ground avoids flowing out outside wall when casting concrete;
Before step S5, further include the steps that exterior-wall heat insulation and waterproof, heat preservation is added in the gap between two exterior walls Lath keeps the temperature and exterior wall waterproof adhesive tape is arranged between lath.
Alternatively and preferably, in step s 2, the height that wall both ends need to be referred to when positioning leveling part places levelling, is protected Demonstrate,prove the vertical distance of the grouting thickness and precast floor slab and wall of wall bottom.
It alternatively and preferably, in step s3, need to be according to following standard operation:
During wall lifting, suspension centre jail is hung, and wall must not tilt, and light rise is put down gently;After wall is hung to above floor, away from ground The high position in about one layer of face carries out position adjustment, is allowed to installation direction to just.
It alternatively and preferably, in step s 4, need to be according to following standard operation:
Wall first fixes inclined support bar when aligning, adjust wall body vertical degree, then adjusts wall short transverse position, most Horizontal direction position is adjusted afterwards.
It alternatively and preferably, in step s 4, need to be according to following standard operation:
It can decoupling device after being fixed to inclined support bar and positioning leveling part;Wirerope must not scrape the steel of wall when decoupling device Muscle.
It alternatively and preferably, in step s 4, need to be according to following standard operation if the wall is exterior wall:
Other than needing when exterior wall is aligned subject to impeller outside, upper and lower level is straight.
Alternatively and preferably, it is laid with before reinforcing bar on precast floor slab, the method also includes set aside pre-embedded pipelines.
Alternatively and preferably, the bottom of the wall is configured with reinforcing bar link slot, and the reinforcing bar link slot is by wall bottom The longitudinal reinforcement in portion exposes;
The construction method further include:
After pouring to precast floor slab, upper one layer of ground is formed, the longitudinal reinforcement of lower layer's wall faces upward from ground It stretches out, will complete to dock in the reinforcing bar link slot of one layer of wall bottom on the partial insertion of stretching, and the step of repeating S1-S12.
Alternatively and preferably, it when pouring the cavity, is irrigated with funnel, without vibrating, controls blanking velocity Lower than predetermined value.
The construction method of wall provided by the invention is first leveled with positioning leveling part, is guaranteed before lifting wall Position is accurate, is configured with cavity in wall in advance, and filling cavity can be formed by complete wall, and wall quilt when cast in situs Only there are smaller distance, the region that existing formwork supporting plate encloses only accounts for the part of very little, reduces and apply on after positioning leveling and ground It the workload of work and avoids leading to wall outer dimension error because of the existing excessive operating error in formwork supporting plate part.In installation precast floor slab When, without using traditional support frame, but with precast floor slab supporting element, structure is simple, and it is easy for installation, so that construction efficiency obtains It is substantially improved.
Detailed description of the invention
Fig. 1 is the facade structures signal of linear type assembled wall in wall construction method provided in an embodiment of the present invention Figure;
Fig. 2 is the side structure signal of linear type assembled wall in wall construction method provided in an embodiment of the present invention Figure;
Fig. 3 is the plan structure signal of linear type assembled wall in wall construction method provided in an embodiment of the present invention Figure;
Fig. 4 is the overlooking structure diagram of L-type assembled wall in wall construction method provided in an embodiment of the present invention;
Fig. 5 is the overlooking structure diagram of T-type assembled wall in wall construction method provided in an embodiment of the present invention;
Fig. 6 is the schematic view of the front view of positioning leveling part pedestal;
Fig. 7 is the overlooking structure diagram of positioning leveling part pedestal;
Fig. 8 be Fig. 6 in A-A to cross-sectional view (signal of pedestal installation condition);
Side structure schematic view when Fig. 9 is the installation of positioning leveling part, wall lifting and adjustment;
Schematic perspective view when Figure 10 is the installation of positioning leveling part, wall lifting and adjustment;
Figure 11 is exterior wall slurry seal position view;
Figure 12 is schematic diagram when inclined support bar adjustment wall body vertical is spent;
Figure 13 is the schematic diagram of cast-in-place area's steel-bar arrangement and binding;
Figure 14 is the schematic diagram of exterior-wall heat insulation and waterproof;
Figure 15 is the overlooking structure diagram (linear type interior wall) that cast-in-place area's node template installs;
Figure 16 is the overlooking structure diagram (T-type interior wall) of cast-in-place area's node;
Figure 17 is the overlooking structure diagram (L-type interior wall) of cast-in-place area's node;
Figure 18 is the overlooking structure diagram (linear type exterior wall) of cast-in-place area's node;
Figure 19 is the overlooking structure diagram (T-type exterior wall) of cast-in-place area's node;
Figure 20 is the overlooking structure diagram (L-type exterior wall) of cast-in-place area's node;
Figure 21 is the schematic diagram of live formwork on the outside of wall and ground gap;
The schematic diagram of the first pad side of setting on the inside of Figure 22 wall and ground gap;
Figure 23 is the schematic view of the front view of precast floor slab supporting element;
Figure 24 is the scheme of installation (side view) of precast floor slab supporting element;
Figure 25 is precast floor slab lifting schematic diagram;
Figure 26 is the integral installation of form bracing part and adjustment position view;
Figure 27 is form bracing part installation and adjustment position partial enlargement diagram;
Figure 28 is the structural schematic diagram of straight-bar;
Figure 29 is the schematic diagram of interior wall in one embodiment;
Figure 30 is the schematic diagram of exterior wall in one embodiment;
Figure 31 is the schematic diagram of interior wall in another embodiment;
Figure 32 is the schematic diagram of exterior wall in another embodiment;
Figure 33 is the schematic diagram of interior wall in another embodiment;
Figure 34 is the schematic diagram of exterior wall in another embodiment;
Figure 35 is interior wall wall connecting schematic diagram up and down;
Figure 36 is exterior wall wall connecting schematic diagram up and down.
In figure:
100- wall;The first wall of 101-;The second wall of 102-;103- cavity;104 concrete ribs;105- longitudinal reinforcement; 106- transverse steel;The pre-buried internal thread of 107-;The outer impeller of 108-;Page board in 109-;110- insulation board;The cast-in-place area's template of 111-; 112- screw shell;The cast-in-place region 113-;114- keeps the temperature lath;115- tubular coagulations soil pours channel;116- lower concrete Connect cavity;117- reinforcing bar link slot;118- lateral direction penetrating hole;
200- positioning leveling part;201- pedestal;202- lifters;203- protrusion;First side of pad 204-;205- fixes spiral shell Bar;2011- base plate;2012- pedestal wing plate;2013- base vertical plate;2014- lateral adjustments screw rod;2015- lateral adjustments Nut;2016- vertical adjustment screw rod;2017- vertical adjustment nut;The first mounting hole of 2018-;The first fixing bolt of 2019-; 2021- fixing piece;The second mounting hole of 2022-;The second fixing bolt of 2023-;2024- lifters bottom hole;
300- precast floor slab supporting element;301- support portion;302- fixed part;303- floor height adjusting screw rod;The building 304- Plate height adjustment nut;305- third fixing bolt;Second side of pad 306-;3011- pipe fitting;The 4th fixing bolt of 3012-; The first support plate of 3013-;3014- starting stave;The second support plate of 3015-;The second riser of 3016-;3021- fixed part vertical plate; 3022- third mounting hole;3023- stiffening plate;3024- fixed part bottom plate;3025- casing;
The ground 400-;500- precast floor slab;600- system of enfeoffment component;700- inclined support bar;701- straight-bar;7011- straight-bar is solid Determine portion;The positive and negative silk adjusting screw rod of 7012-.
Specific embodiment
Several illustrative embodiments shown in below with reference to the accompanying drawings describe the principle and spirit of the invention.It should Understand, describe these embodiments just for the sake of make those skilled in the art can better understand that in turn realize the present invention, It is not intended to limit the scope of the invention in any way.
The embodiment of the present invention provides a kind of construction method of assembled wall.In an embodiment of the present invention, the wall 100 internal structure of body has the cavity 103 being intervally arranged, and 103 side of cavity is the first wall 101, and the other side is the second wall 102, it is equipped with concrete rib 104 between adjacent cavity 103, the first wall 101 and the second wall 102 are connected.Cavity 103 parts are used for cast in situs, pour rear concrete full of cavity 103, form complete wall.From the overall structure of wall For, it can be linear type, L-type or T-type, wherein L-type or T-type are suitable for the assembly of corner wall as shown in Figs. 1-5.First It is equipped with the staggered reinforcing bar of transverse and longitudinal in wall 101 and the second wall 102, transverse steel 106 is stretched out from the side of wall, longitudinal reinforcement 105 stretch out from the top of wall.It is inner wall structure shown in Fig. 1-5, if it is exterior wall, in the first wall 101 and sky A piece of insulation board is added again between chamber 103 or the second wall 102 and cavity 103, remaining structure is identical with inner wall.
The construction method of assembled wall provided in an embodiment of the present invention includes the following steps:
S1: cleaning, unwrapping wire, absolute altitude survey are set: construction personnel is clean, smooth by land clearing first, then according to construction drawing Paper, which is put, sets axis, wall sideline and control line;Copy the absolute altitude for surveying ground under wall.
S2: installation positioning leveling part: the positioning leveling part includes pedestal and lifters two parts.Positioning leveling part pedestal On offer the first mounting hole, offer the second mounting hole in lifters, the lifters can be along lifting on the inside of the pedestal; The bottom surface of pedestal is equipped with vertical adjustment screw rod and vertical adjustment nut, and vertical adjustment screw rod top passes through the bottom surface of lifters;Bottom The two sides side of seat is equipped with lateral adjustments screw rod and lateral adjustments nut.
As shown in figs 6-8, the mounting means of positioning leveling part includes: to stamp location hole on the ground, makes the first mounting hole With location hole to just, the first mounting hole and location hole are passed through with bolt, adjustment positioning levels the position of part, then fastening bolt, Fix the pedestal of positioning leveling part.
Positioning leveling part need to refer to the height at wall both ends when placing levelling, guarantee the grouting thickness of wall bottom and prefabricated The vertical distance of floor and wall.
The specific structure of positioning leveling part is introduced in detail further below.As previously mentioned, positioning leveling part 200 mainly includes 202 two parts of pedestal 201 and lifters.Pedestal 201 includes base plate 2011, and the two sides of base plate 2011 are to be vertically arranged Pedestal wing plate 2012.It is vertically disposed base vertical plate 2013 between pedestal wing plate 2012.The substantially channel steel of lifters 202 Shape is provided with horizontal mouth-sealed portion in the bottom of channel steel, forms lifters bottom plate, lifters bottom plate two sides are vertically arranged Lifters wing plate, the lifters vertical plate being vertically arranged between lifters wing plate.Width (the i.e. two lifters wing plate outer walls of channel steel The distance between) it is less than pedestal inboard width, so that the lifters based on channel steel can move up and down in pedestal.Pedestal One first mounting hole 2018 is offered on bottom plate 2011, and (the present embodiment is strip-shaped hole, before pedestal 201 may be implemented along strip-shaped hole The adjustment of rear direction is conveniently adjusted position base, certainly can also be other shapes), for the location hole with ground to just, so as to After the merging of first fixing bolt 2019 pedestal 201 and ground will be fixed.It is also vertically provided with and is used on base plate 2011 The vertical adjustment screw rod 2016 of wall height is adjusted, 2016 one end of vertical adjustment screw rod is fixed on base plate 2011, and even It is connected to vertical adjustment nut 2017, the lifters bottom hole 2024 that the other end is opened up from lifters mouth-sealed portion is pierced by upwards. The bore of lifters bottom hole 2024 is greater than the diameter of vertical adjustment screw rod 2016, in the horizontal direction in order to lifters main body Front, rear, left and right can realize micro-adjustment so that Adjustment precision is more acurrate.In lifters 202 close to the one side of wall, that is, rise Interval opens up two the second mounting holes 2022 on drop part vertical plate, for the pre-buried internal thread 107 with wall to just, and then second is consolidated Determine bolt 2023 and is placed in wall 100 to realize fixation.Two protrusions 203 (one are also provided in the outside of pedestal wing plate 2012 And with reference to Figure 22 and following description), for installing the first pad side 204 for blocking wall bottom inside gap, to the position of pad side It sets and plays limit and fixed function.
The two sides of pedestal wing plate 2012 offer through-hole respectively, and lateral adjustments screw rod 2014 is provided in through-hole, is laterally adjusted Lateral adjustments nut 2015 is socketed on section screw rod 2014.It is equipped with fixing piece 2021 at the back side of lifters 202, can such as be used The nut that can be rotated along the second fixing bolt 2023 on the second mounting hole 2022.
By the control of the width differential of lifters 202 and pedestal 201 in grade, the achievable grade of precast wall body 100 Displacement, therefore precast wall body 100 be displaced distance can more accurately control.It is fixed to remove after the completion of 100 structure construction of wall Position adjustment tool part, convenient disassembly is quick, and positioning adjustment tool part can recycle, and can also need to be embedded to according to construction In 100 structure of wall.The adjusting of wall height, left and right can be realized by leveling part 200 by one group of positioning.
S3: wall lifting: lifting wall, as shown in figure 9, by 2022 He of the second mounting hole of the lifters of positioning leveling part The pre-buried internal thread 107 of wall 100 as shown in Figure 10, then successively penetrates lifters 202 with the second fixing bolt 2023 to just The pre-buried internal thread 107 of second mounting hole 2022 and wall tightens the second fixing bolt 2023, then slowly falls wall 100, And then the lifters 202 on wall are slowly fallen on the pedestal 201 of positioning leveling part.
During wall lifting, suspension centre jail is hung, and wall must not tilt, and light rise is put down gently;After wall is hung to above floor, away from ground The high position in about one layer of face carries out position adjustment, is allowed to installation direction to just.
In addition, if the wall 100 is exterior wall (including interior impeller 109, outer impeller 108 and insulation board 110) in step Before S3, further include the steps that exterior wall slurry seal, the step of exterior wall slurry seal includes:
As shown in figure 11, slurry seal component 600, such as PE stick soft body object are set on ground 400, lifted by crane slowly in wall After falling, the bottom of wall 100 can directly seat on slurry seal component 600, by the seam between the outer impeller of exterior wall and ground Gap sealing avoids flowing out outside wall when casting concrete.
S4: wall positioning is adjusted:
S41: verticality is adjusted
As shown in figure 12, inclined support bar 700 is installed in the side of wall 100,700 one end of inclined support bar and wall 100 are cut with scissors It connects, the other end is supported on ground 400, and inclined support bar 700 is to adjustably adjust bar, and the length by adjusting inclined support bar is adjusted The verticality of wall, to meet the requirements.
S42: height adjustment
Make wall on the control line, with continued reference to Fig. 9 and Figure 10, adjusts the vertical adjustment on positioning leveling part pedestal 201 Nut 2017, when vertical adjustment nut 2017 rotates upwards, lifters are raised, and then wall height is driven to increase, vertical adjustment When nut 2017 is rotated down, lifters are reduced, so that wall height reduces;
S43: horizontal direction is adjusted, the vertical adjustment of lateral adjustments and front and back including left and right.
As shown in Figure 9 and Figure 10, the lateral adjustments nut 2015 on positioning leveling part pedestal 201 is adjusted, two sides are passed through The left-right position of lateral adjustments nut is adjusted, and determines the position on the left and right directions (transverse direction) of wall 100.As shown in figure 12, exist It is equipped with telescopically adjustable straight-bar 701 (such as the straight-bar to stretch using positive and negative screw thread structure) below inclined support bar 700, passes through straight-bar Position on 701 adjustment wall front-rear directions.Figure 28 shows a kind of specific straight-bar structure.Straight-bar 701 is fixed including straight-bar Portion 7011 and positive and negative screw thread adjusting screw rod 7012 can reserve a standing screw in the strip-shaped hole of positioning leveling 200 pedestal of part 205.Straight-bar fixed part 7011 includes the horizonal base plate that inclined plate and inclined plate portion integral are connected, and offers screw hole on horizonal base plate, It is connected on standing screw 205.The threaded sleeve on positive and negative screw thread adjusting screw rod 7012 is rotated, screw portion is stretched out or is shunk, And then adjust the position in the front-back direction of wall.
In addition, in step s 4, it need to be according to following standard operation:
Wall first fixes inclined support bar when aligning, adjust wall body vertical degree, then adjusts wall short transverse position, most Horizontal direction position is adjusted afterwards.
It can decoupling device after being fixed to inclined support bar and positioning leveling part;Wirerope must not scrape the steel of wall when decoupling device Muscle.
If the wall is exterior wall, other than also being needed in exterior wall levelling outside impeller subject to, upper and lower level is straight.
After having adjusted the height of wall, there are certain gap between the bottom and ground of wall, i.e., wall relative to Ground is lifted a bit of height h1.
S5: reinforcing bar binding
When two neighboring wall lateral connection, since the side of precast wall body only has transverse steel 106, so needing to pacify again Fill longitudinal reinforcement 105.During installation, stirrup is placed first, then places vertical reinforcement in stirrup, between upper layer and lower layer wall Longitudinal reinforcement 105 by screw shell 112 connect (as shown in figure 13).For example, the longitudinal reinforcement of lower layer's wall can be made It stretches out to be formed upwards and reserves vertical muscle, the vertical muscle bottom of upper wall screw shell 112 is connected into longitudinal reinforcement, it is most laggard Row binding.
In addition, if being installation exterior wall, before step S5, further include the steps that exterior-wall heat insulation and waterproof, i.e., such as Figure 14 Shown, the gap addition between the wall 100 of two exterior walls keeps the temperature lath 114, and setting exterior wall is used anti-between heat preservation lath 114 Glue item.
S6: installing cast-in-place region template, postpones the gap to be formed to enclose wall in fixed bit, forms cast-in-place area;Installation The pad side of wall bottom, so that pad side blocks the gap between wall and ground.
In conjunction with Figure 13 and Figure 15, two neighboring wall 100 horizontally generates gap in lateral connection, and the two of gap After side is installed with cast-in-place area's template 111, gap is just closed by the template of two sides, forms the cast-in-place region of lateral node 113.Figure 16-Figure 20 shows the plan structure of the walls of other several shapes in laterally docking, wherein exterior wall due to Side has insulating layer, it is only necessary to install the cast-in-place region template of side.
In addition, as previously mentioned, wall lifts certain altitude h1 relative to ground after being adjusted by positioning leveling part.This Height is but also form a gap between the bottom and ground of wall.It is closed (such as by the first pad side 204 inside in gap Shown in Figure 22), the outside in gap show formwork supporting plate 115 by bottom and closes (as shown in figure 21), can be with if wall is exterior wall It is blocked by the slurry seal component in above mentioned step S3.
S7: correction wall body vertical degree
After having installed template, it is corrected again by verticality of the inclined support bar to wall;
S8: installation precast floor slab supporting element
Precast floor slab supporting element includes fixed part, support portion and adjustment portion three parts;Fixed part is bolted on wall Internal side, support portion include the pipe fitting for penetrating through fixed part, and the top of pipe fitting is fixedly connected with supporter, and lower part is fixed with connecting plate; Pad side is equipped with above supporter;Adjustment portion includes the adjusting screw rod for penetrating through connecting plate and fixed part, adjusting screw rod one end and fixation Portion is fixedly connected, and the other end is equipped with adjusting nut;
As shown in figure 24, the mounting means of precast floor slab supporting element are as follows: be bolted the fixed part of supporting element On wall.
In the following, the specific structure of precast floor slab supporting element is described in further detail.As previously mentioned, as shown in figure 23, it is prefabricated Form bracing part includes fixed part 302, support portion 301 and adjustment portion three parts.The substantially angle bar of fixed part 302, including it is solid Determine portion's bottom plate 3024 and fixed part vertical plate 3021.The two sides of fixed part bottom plate 3024 are equipped with the (the present embodiment three of stiffening plate 3023 It is angular, can also be other shapes), for reinforcing the stability of fixed part.The side that fixed part 302 is close to wall offers third Mounting hole 3022 is fixed on the inside of wall by third fixing bolt 305.Fixed part bottom plate 3024 offers connecting hole, and one Vertically arranged floor height adjusting screw rod 303 is welded on connecting hole.Support portion includes 3013 He of the first support plate of bottom Second support plate 3015 at top is set in the first support plate 3013 there are two pipe fitting 3011 side by side, and pipe fitting 3011, which passes through, to be fixed 3015 bottom surface of the second support plate is connected to after portion's bottom plate 3024.Pipe fitting 3011 is relatively thick, more steady to the support of precast floor slab It is fixed.The middle part of first support plate 3013 also offers through-hole, and the bottom of floor height adjusting screw rod 303 is pierced by downwards from through-hole, And floor height adjusting nut 304 is installed.Also it is connected with a vertical starting stave 3014 in first support plate 3013, also may be used Form the shape of angle bar.Second support plate 3015 is equipped with the second riser 3016, generally also forms angle shape, but angle side To with fixed part on the contrary, also to form angle with the first support plate of bottom 3013 and starting stave 3014 opposite.In the second support plate 3015 are equipped with the second pad side 306, are used to support the precast floor slab 500 on top, and the side of the second riser 3016 offers through-hole, Hole is built into the 4th fixing bolt 3012, withstands the second pad side 306, and the second pad side 306 is prevented to be subjected to displacement in adjustment process, It improves and generates error in precast floor slab height adjustment, and convenient disassembly.As described below, it is adjusted by floor height About 304 turn of nut, it can adjust the height of precast floor slab.The outside of pipe fitting 3011 can also be arranged casing 3025, make It obtains more stable in 3011 moving process of pipe fitting.Convenient for disassembly and assembly, the flexible adjustment using this precast floor slab supporting element, avoid using Individually large size support frame bring is cumbersome, improves construction efficiency.
S9: hoisting prefabricated floor
After fixing precast floor slab supporting element on wall, as shown in figure 25, precast floor slab is lifted by crane, by precast floor slab 500 It is placed in the second pad side 306 of the support portion.
S10: precast floor slab supporting element is adjusted
As illustrated in figs. 25-27, the floor height adjusting nut 304 for screwing 303 lower section of floor height adjusting screw rod, revolves upwards It is dynamic to raise the height of precast floor slab so that support portion is lifted upwards relative to fixed part, downward turn make support portion relative to Fixed part decline, reduces the height of precast floor slab.
S11: reinforcing bar is laid on precast floor slab;In addition, in some embodiments, be laid on precast floor slab reinforcing bar it Before, the step of the method also includes set aside pre-embedded pipelines.
S12: the cavity, cast-in-place area and precast floor slab are poured.
It when pouring the cavity, is irrigated with funnel, without vibrating, control blanking velocity is lower than predetermined value.
After concrete enters cast-in-place region, the lateral node of two neighboring wall is formed.Concrete Filled precast wall body Cavity in after, form complete precast wall body, and the gap filling between wall and ground is expired.Pouring precast floor slab Afterwards, the ground of a upper floor is formed.
After one layer of wall of having constructed, if you need to carry out the construction of upper wall, it can connect in the bottom distributing bar of wall Access slot, the reinforcing bar link slot expose the longitudinal reinforcement of wall bottom;The longitudinal reinforcement of lower layer's wall is stretched upwardly from ground Out, it then will complete to dock in the reinforcing bar link slot of one layer of wall bottom on the partial insertion of stretching, and repeat the step of S1-S12 Suddenly, so that it may complete the assembly of upper wall.It loops back and forth like this, after assembly, completes entire work progress.It is described below several Bottom has the wall body structure of reinforcing bar link slot.
As shown in figure 29, there is tubular coagulations soil to pour channel 115, bottom is that lower concrete connects cavity inside wall 116, in bottom, wall inner conformation has reinforcing bar link slot 117, exposes longitudinal reinforcement 105.Have laterally in the side of wall Through hole 118.Figure 30 is the exterior wall form of the wall.
As shown in figure 31, it is all there is tubular coagulations soil to pour channel 115, bottom is with the something in common of Figure 29 Lower concrete connects cavity 116, but the shape of lower concrete connection cavity 116 is that (the other half is half arc to half cell type Shape), certainly, this is a kind of example of shape, can also connect cavity using the lower concrete of other shapes.Similarly, Also there is reinforcing bar link slot 117.Figure 32 is the exterior wall form of the wall.
As shown in figure 33, also there is tubular coagulations soil to pour channel 115, the lower concrete of bottom connects cavity 116 Shape be it is box-like, reinforcing bar link slot 117 also is located at wall bottom.The edge of box cavity can be linear type and be also possible to Arc or other shapes.Figure 34 is the exterior wall form of the wall.
Mode of the above several walls in connection is essentially identical, is all to extend into the longitudinal reinforcement at the top of lower wall Connection in the reinforcing bar link slot of wall bottom.Figure 35 shows the assembly connection mode of interior wall, and Figure 36 shows the assembly of exterior wall Connection type.This connection type quick and precisely, improves the accuracy of construction efficiency and operation.
Specific case used herein elaborates inventive concept, the explanation of above example is only intended to Help understands core of the invention thought.It should be pointed out that for those skilled in the art, not departing from this Under the premise of inventive concept, any obvious modification, equivalent replacement or the other improvements made should be included in the present invention Protection scope within.

Claims (10)

1. the construction method of assembled wall, the wall internal structure has the cavity being intervally arranged, and sets between adjacent cavity There is concrete rib, which is characterized in that described method includes following steps:
S1: cleaning, unwrapping wire, absolute altitude survey are set: construction personnel is clean, smooth by land clearing first, is then put according to construction drawing If axis, wall sideline and control line;Copy the absolute altitude for surveying ground under wall;
S2: installation positioning leveling part: the positioning leveling part includes pedestal and lifters two parts, and the first peace is offered on pedestal Hole is filled, the second mounting hole is offered in lifters, the lifters can be along lifting on the inside of the pedestal;The bottom surface of pedestal is equipped with Vertical adjustment screw rod and vertical adjustment nut, vertical adjustment screw rod top pass through the bottom surface of lifters;The two sides side of pedestal is set There are lateral adjustments screw rod and lateral adjustments nut;
The mounting means of the positioning leveling part includes: to stamp location hole on the ground, makes the first mounting hole and location hole to just, The first mounting hole and location hole are passed through with bolt, the position of adjustment positioning leveling part, then fastening bolt, fixes positioning leveling The pedestal of part;
S3: wall lifting: lifting wall, by the pre-buried internal thread pair of the second mounting hole of the lifters of positioning leveling part and wall Just, the second mounting hole of lifters and the pre-buried internal thread of wall are then successively penetrated with bolt, are tightened bolt, are then delayed wall It is slow to fall, and then the lifters on wall are slowly fallen within into positioning and are leveled on the pedestal of part;
S4: wall positioning is adjusted:
S41: verticality is adjusted
Inclined support bar is installed in the side of wall, inclined support bar one end and wall are hinged, and the other end supports on the ground, bearing diagonal Bar is to adjustably adjust bar, and the length by adjusting inclined support bar adjusts the verticality of wall, to meet the requirements;
S42: height adjustment
Make wall on the control line, adjust the vertical adjustment nut on positioning leveling part pedestal, vertical adjustment nut rotates upwards When, lifters are raised, and then wall height is driven to increase, and when vertical adjustment nut is rotated down, lifters are reduced, so that Wall height reduces;
S43: horizontal direction is adjusted, and horizontal direction adjusts the adjusting including front and back and left and right both direction;
The lateral adjustments nut on positioning leveling part pedestal is adjusted, is adjusted by the left-right position of the lateral adjustments nut of two sides, Determine the position on the left and right directions of wall;It is equipped with telescopically adjustable straight-bar below inclined support bar, wall is adjusted by straight-bar Position on body front-rear direction;
S5: reinforcing bar binding
When two neighboring wall lateral connection, first place stirrup, then place vertical reinforcement in stirrup, upper layer and lower layer wall it Between vertical reinforcement by screw shell connect, finally bound;
S6: installing cast-in-place region template, postpones the gap to be formed to enclose wall in fixed bit, forms cast-in-place area;Wall is installed The pad side of bottom, so that pad side blocks the gap between wall and ground;
S7: correction wall body vertical degree
It is corrected again by verticality of the inclined support bar to wall;
S8: installation precast floor slab supporting element
Precast floor slab supporting element includes fixed part, support portion and adjustment portion three parts;Fixed part is bolted in wall Side, support portion include the pipe fitting for penetrating through fixed part, and the top of pipe fitting is fixedly connected with supporter, and lower part is fixed with connecting plate;Support Pad side is equipped with above body;Adjustment portion includes the adjusting screw rod for penetrating through connecting plate and fixed part, and adjusting screw rod one end and fixed part are solid Fixed connection, the other end are equipped with adjusting nut;
The mounting means of precast floor slab supporting element are as follows: the fixed part of supporting element is bolted on wall;
S9: hoisting prefabricated floor;
Precast floor slab is lifted by crane, precast floor slab is placed in the pad side of the support portion;
S10: precast floor slab supporting element is adjusted
The adjusting nut below adjusting screw rod is screwed, upward turn is lifted support portion upwards relative to fixed part, raises pre- The height of floor processed, downward turn decline support portion relative to fixed part, reduce the height of precast floor slab;
S11: reinforcing bar is laid on precast floor slab;
S12: the cavity, cast-in-place area and precast floor slab are poured.
2. construction method according to claim 1, which is characterized in that if the wall is exterior wall, before step S3, Further include the steps that exterior wall slurry seal, the step of exterior wall slurry seal includes:
On the ground be arranged slurry seal component, wall lifting slowly fall after, seat on slurry seal component, by the outer impeller of exterior wall with Gap sealing between ground avoids flowing out outside wall when casting concrete;
Before step S5, further include the steps that exterior-wall heat insulation and waterproof, the gap addition heat preservation lath between two exterior walls, It keeps the temperature and exterior wall waterproof adhesive tape is set between lath.
3. construction method according to claim 1, which is characterized in that in step s 2, when positioning leveling part places levelling The height that wall both ends need to be referred to guarantees the vertical distance of the grouting thickness and precast floor slab and wall of wall bottom.
4. construction method according to claim 1, which is characterized in that in step s3, need to be according to following standard operation:
During wall lifting, suspension centre jail is hung, and wall must not tilt, and light rise is put down gently;After wall is hung to above floor, about away from ground One layer high of position carries out position adjustment, is allowed to installation direction to just.
5. construction method according to claim 1, which is characterized in that in step s 4, need to be according to following standard operation:
Wall first fixes inclined support bar when aligning, adjust wall body vertical degree, then adjusts wall short transverse position, finally adjusts Horizontal direction position.
6. construction method according to claim 1, which is characterized in that in step s 4, need to be according to following standard operation:
It can decoupling device after being fixed to inclined support bar and positioning leveling part;Wirerope must not scrape the reinforcing bar of wall when decoupling device.
7. construction method according to claim 1, which is characterized in that in step s 4, if the wall is exterior wall, need to press According to following standard operation:
Other than needing when exterior wall is aligned subject to impeller outside, upper and lower level is straight.
8. construction method according to claim 1, which is characterized in that be laid with before reinforcing bar on precast floor slab, the side Method further includes set aside pre-embedded pipeline.
9. construction method according to claim 1, which is characterized in that the bottom of the wall is configured with reinforcing bar link slot, The reinforcing bar link slot exposes the longitudinal reinforcement of wall bottom;
The construction method further include:
After pouring to precast floor slab, upper one layer of ground is formed, the longitudinal reinforcement of lower layer's wall stretches out upwardly from ground, Docking, and the step of repeating S1-S12 will be completed on the partial insertion of stretching in the reinforcing bar link slot of one layer of wall bottom.
10. construction method according to claim 1, which is characterized in that when pouring the cavity, filled with funnel Note, without vibrating, control blanking velocity is lower than predetermined value.
CN201810959220.5A 2018-03-23 2018-08-22 Construction method of assembled wall Active CN108951963B (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201810246324 2018-03-23
CN2018102463241 2018-03-23
CN2018102571636 2018-03-27
CN201810257163.6A CN108331348A (en) 2018-03-23 2018-03-27 The construction method of assembled wall

Publications (2)

Publication Number Publication Date
CN108951963A true CN108951963A (en) 2018-12-07
CN108951963B CN108951963B (en) 2020-06-02

Family

ID=62932436

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810257163.6A Pending CN108331348A (en) 2018-03-23 2018-03-27 The construction method of assembled wall
CN201810959220.5A Active CN108951963B (en) 2018-03-23 2018-08-22 Construction method of assembled wall

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201810257163.6A Pending CN108331348A (en) 2018-03-23 2018-03-27 The construction method of assembled wall

Country Status (1)

Country Link
CN (2) CN108331348A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441500A (en) * 2020-04-29 2020-07-24 林进卓 Combined assembly type building convenient to install and production device thereof
CN111472471A (en) * 2020-04-29 2020-07-31 南宁学院 Multifunctional composite wall
CN112343222A (en) * 2020-11-09 2021-02-09 北京市建筑装饰设计工程有限公司 Assembly type superposed shear wall structure, construction system and construction method thereof
CN114197911A (en) * 2021-12-17 2022-03-18 江苏省子午建筑设计有限公司 Outer-sleeve type extension and reconstruction design method for civil old house
CN116290456A (en) * 2023-01-18 2023-06-23 北京房修一建筑工程有限公司 Assembled building construction technology

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853785A (en) * 2019-01-22 2019-06-07 河南聚誉帆工程技术咨询有限公司 Assembled integral fills partition wall and fabrication and installation method
CN109914823B (en) * 2019-04-15 2021-03-02 锦汇建设集团有限公司 Method for installing prefabricated wall board of prefabricated building
CN110042942A (en) * 2019-04-23 2019-07-23 深圳市湛艺建设集团有限公司 A kind of compound passive type wall construction method of antidetonation and decoration combined wall
CN110318482B (en) * 2019-06-24 2024-05-03 天元建设集团有限公司 Multifunctional assembled movable composite wall and construction method thereof
CN110644781B (en) * 2019-09-29 2024-05-17 上海建工五建集团有限公司 Prefabricated laminated slab installation and adjustment device and method
CN111663794A (en) * 2020-07-02 2020-09-15 北京住总集团有限责任公司 Wall body leveling mechanism for longitudinal rib superposed shear wall and construction method
CN112112261B (en) * 2020-09-21 2022-03-04 福建创润建设有限公司 Fabricated building and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3779500A (en) * 1971-06-14 1973-12-18 Jim Cox Co Form support bracket
JP2000054640A (en) * 1998-08-12 2000-02-22 Maeda Corp Sleeper-supporting jack device
JP2001241190A (en) * 2000-02-29 2001-09-04 Taisei Corp Leveling implement for floor installation frame
WO2015011641A1 (en) * 2013-07-24 2015-01-29 Doyle Phillip Paul Semi rigid precast wall system
CN105569242A (en) * 2015-12-28 2016-05-11 中民筑友有限公司 Assembling method for composite floor slabs
CN105781125A (en) * 2016-03-04 2016-07-20 李藏柱 Installation method for assembly type building
CN206360361U (en) * 2016-06-23 2017-07-28 深圳市金世纪工程实业有限公司 Shear wall exterior wall cantilevered plate regularization aluminum alloy pattern plate support system
CN107663950A (en) * 2017-11-10 2018-02-06 承德绿建建筑节能科技有限公司 A kind of component leveling and precast wall body structure applied to precast wall body structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3779500A (en) * 1971-06-14 1973-12-18 Jim Cox Co Form support bracket
JP2000054640A (en) * 1998-08-12 2000-02-22 Maeda Corp Sleeper-supporting jack device
JP2001241190A (en) * 2000-02-29 2001-09-04 Taisei Corp Leveling implement for floor installation frame
WO2015011641A1 (en) * 2013-07-24 2015-01-29 Doyle Phillip Paul Semi rigid precast wall system
CN105569242A (en) * 2015-12-28 2016-05-11 中民筑友有限公司 Assembling method for composite floor slabs
CN105781125A (en) * 2016-03-04 2016-07-20 李藏柱 Installation method for assembly type building
CN206360361U (en) * 2016-06-23 2017-07-28 深圳市金世纪工程实业有限公司 Shear wall exterior wall cantilevered plate regularization aluminum alloy pattern plate support system
CN107663950A (en) * 2017-11-10 2018-02-06 承德绿建建筑节能科技有限公司 A kind of component leveling and precast wall body structure applied to precast wall body structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441500A (en) * 2020-04-29 2020-07-24 林进卓 Combined assembly type building convenient to install and production device thereof
CN111472471A (en) * 2020-04-29 2020-07-31 南宁学院 Multifunctional composite wall
CN111472471B (en) * 2020-04-29 2022-12-02 南宁学院 Multifunctional composite wall
CN112343222A (en) * 2020-11-09 2021-02-09 北京市建筑装饰设计工程有限公司 Assembly type superposed shear wall structure, construction system and construction method thereof
CN114197911A (en) * 2021-12-17 2022-03-18 江苏省子午建筑设计有限公司 Outer-sleeve type extension and reconstruction design method for civil old house
CN116290456A (en) * 2023-01-18 2023-06-23 北京房修一建筑工程有限公司 Assembled building construction technology

Also Published As

Publication number Publication date
CN108951963B (en) 2020-06-02
CN108331348A (en) 2018-07-27

Similar Documents

Publication Publication Date Title
CN108951963A (en) The construction method of assembled wall
US8028476B1 (en) Pool leveling system
CN106245678B (en) Outer wall of basement single side formwork construction method based on steel pipe truss
CN104264902B (en) Structure for connecting concrete filled steel tubular column with pile foundation
CN209144855U (en) Adjustable positioning bracket profile steel concrete column embedded column base structure
CN110016938B (en) Positioning and verticality adjusting device for rectangular lattice column of reverse construction method foundation pit
CN107030875A (en) The bridge prefabrication assembly removable adjustable type alignment system of cushion cap embedded ribs and localization method
CN106702892A (en) Quick-installation comb plate extending device and construction method thereof
CN109518980A (en) Prefabricated concrete structure column lifts absolute altitude and perpendicularity regulating device and its construction method
US8707636B1 (en) Memorial foundation system and installation method
KR20110002343A (en) Pylon of cable-stayed bridge having composite combination structure and construction method thereof
RU2436899C1 (en) Correction method of inclination and non-uniform settlement of large high-rise structure and its foundation
KR20200092593A (en) Concrete slab of bridge with precast cantilever slab and concrete slab of bridge construction method therefor
JP2005090116A (en) Method for erecting steel frame column and positioning frame body used for it
KR20130025188A (en) Bar support for mass reinforced concrete member and method of upper bar arrangement using the same
CN208363650U (en) The mounting bracket of prefabricated components, the precast wall body containing the bracket
CN114382170B (en) Construction method of upper prefabricated vertical component
CN107324186A (en) Outdoor installs the levelling device and leveling construction method of elevator additional
JP3544436B2 (en) Fixing structure of panel in building structure with concrete wall panel and fixing method
JP6792239B2 (en) Scuttling prevention device for steel pipe piles and scuttling prevention method
JPH10317391A (en) Foundation structure for steel tower and method for constructing the same
CN211446555U (en) Bailey beam limiting device for bridge abutment of steel trestle
KR102038505B1 (en) support for structure and construction methods thereof
JPH08158341A (en) Joining structure of pile and beam
KR101962173B1 (en) Construction method of underground structure wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant