CN108951440A - The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert - Google Patents

The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert Download PDF

Info

Publication number
CN108951440A
CN108951440A CN201810889642.XA CN201810889642A CN108951440A CN 108951440 A CN108951440 A CN 108951440A CN 201810889642 A CN201810889642 A CN 201810889642A CN 108951440 A CN108951440 A CN 108951440A
Authority
CN
China
Prior art keywords
existing
culvert
steel sheet
sheet pile
roadbed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810889642.XA
Other languages
Chinese (zh)
Inventor
易群
刘飞
翁建龙
刘红桃
徐常胜
贺泳嘉
王家灿
刘正华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Zhuzhou Bridge Co Ltd
Original Assignee
China Railway Zhuzhou Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Zhuzhou Bridge Co Ltd filed Critical China Railway Zhuzhou Bridge Co Ltd
Priority to CN201810889642.XA priority Critical patent/CN108951440A/en
Publication of CN108951440A publication Critical patent/CN108951440A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Railway Tracks (AREA)

Abstract

The invention discloses the safeguard structures of existing roadbed in a kind of construction of extension culvert, including existing culvert ontology, the two sides of its entrance are existing roadbed side slope, Larsen steel sheet pile has continuously been squeezed at roadbed side slope, the plane and existing culvert central axis that the Larsen steel sheet pile is formed are in 45 ° of angles, and the starting point of continuous Larsen steel sheet pile is apart from existing line center line 3.5m, and end is located at the slope foot of roadbed side slope.Disclosed safeguard structure, not only adaptable, protection safety performance is good, and construction cost is low, short construction period.

Description

The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert
Technical field
A kind of the present invention relates to construction of railways field more particularly to railways in the construction of Business Line extension culvert existing road The safeguard structure and protection construction method of base.
Background technique
With the fast development of economic society, railway passenger and goods flow also increases substantially, and both wired speed of service was low, transports Disadvantage of poor quality, that route transportation capability is small is increasingly prominent, and the transport capacity of major part existing railway has been not suitable with transport and has increased Long needs.Therefore, the transport capacity to improve existing railway, it is necessary to which capacity expansion revamping is carried out to it.Both wired capacity expansion revamping Mainly having speed-raising both wired, double tracking expansion that can raise speed and create two-wire expansion the modes such as can raise speed, and principle is avoids greatly It tears open and changes greatly, selects the scheme that good in economic efficiency, shipping mass is high, small to both wired influence on system operation under the major premise of save the cost.
In existing railway capacity expansion revamping and yard, stock yard reconstruction construction, it is often necessary to carry out spreading to existing culvert and apply Work is removed newly-built to meet new needs.It is guarantee existing railway roadbed when the neighbouring existing extension culvert of Business Line is constructed at present Stabilization, prevent roadbed from cave-in accident occur, do not influence train normal operation, it is necessary to using temporary preventive measure to existing roadbed It is protected.
General safeguard procedures are using the methods of artificial digging pile, rotary digging drilling hole stake, rail pile and I-steel, wherein manually It is be easy to cause collapse hole accident when caisson, rotary digging drilling hole pile driving construction, construction period is longer, and project cost is higher and to railways train operation It influences big;Rail pile and the anti-dynamic load interference performance of steel H pile are poor, and strength of the mixing pile is lower to be difficult to ensure that existing roadbed is steady The disadvantages of determining, influencing Business Line operation security.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of short construction period, project cost is low and protection effect is good The safeguard structure of existing roadbed in extension culvert construction.
The technical scheme to solve the above technical problems is that in a kind of construction of extension culvert existing roadbed protection Structure, including existing culvert ontology, the two sides of entrance are existing roadbed side slope, have continuously squeezed into Larsen at roadbed side slope Steel sheet pile, the plane and existing culvert central axis which forms are in 45 ° of angles, and continuous Larsen steel sheet pile Starting point is apart from existing line center line 3.5m, and end is located at the slope foot of roadbed side slope.
Preferably, the half that the embedded depth of the Larsen steel sheet pile is long not less than stake.
Preferably, the Larsen steel sheet pile of two sides is arranged symmetrically with existing culvert central axes.
The protection construction method of existing roadbed, includes the following steps: in a kind of construction of extension culvert
A, according to existing roadbed banket type and compartment load determines the length and embedded depth of Larsen steel sheet pile, The gradient and height for measuring existing roadbed determine the integral planar position and single Larsen steel sheet pile of Larsen steel sheet pile Model;
B, using train travel gap, the railway protective fence at roadbed side slope is removed, smooth piling machine place, to piling position Carry out orientation measurement is set, while one Displacement & Settlement stake is set at interval of 5m at the roadbed road shoulder of existing culvert two sides, Using total station, coordinate and elevation before level observation is driven piles;
C, the underground utilities that construction is nearby influenced on culvert, which move, to be changed, protects, and is then drawn using high-frequency hydraulic hammer The piling of gloomy steel sheet pile operates, and the Larsen steel sheet pile of initial position is apart from existing line center line 3.5m, the Larsen steel plate of end Stake is located at roadbed side slope slope foot, and the Larsen steel sheet pile squeezed into and culvert center line are in 45 ° of angles;
D, during piling, horizontal displacement is carried out to each Displacement & Settlement stake every 1h and sedimentation value is observed, observed It is worth in allowed band and continues pile sinking, otherwise stops work and reinforce;
E, extension culvert construction is carried out after the completion of piling, and after constructing to extension culvert, Buried culvert under roadbed changeover portion is returned It fills out, then extracts Larsen steel sheet pile.
Preferably, the vibration force of the high-frequency hydraulic hammer is not less than 220KN.
The safeguard structure and construction method of existing roadbed, have such as in a kind of disclosed extension culvert construction It is lower the utility model has the advantages that
This structure is suitable for existing subgrade protection during running railway line construction extension culvert, especially in Subgrade of Heavy-haul Railway When side slope bears the interference of larger dynamic load, good protection work can be played by (entering) mouth two sides roadbed side slope out to existing culvert With;One-shot job place required for constructing is smaller, so do not limited by construction site size, strong applicability;
This structure uses Larsen steel sheet pile as existing roadbed reinforced protection stake, using it with high the moment of inertia, high intensity Can, to increase the rigidity of sheet pile wall, displacement deformation is effectively reduced, can guarantee the safety that existing roadbed side slope is reinforced Energy;Using the concept of steel sheet pile " plate-board combining structure ", so that steel sheet pile conjoined structure tight, can guarantee existing roadbed The protection effect of slope reinforcement improves the security performance and protection effect of protection;
It for steel sheet pile inserting piling, is operated using high-frequency hydraulic hammer, entire piling technology is mature, requires not construction site Height, construction is flexibly, conveniently;Steel sheet pile inserting piling about 7 ~ 9min of every 9m long, and the steel sheet pile construction time about 7 of every culvert Hour completes, and substantially reduces construction period;
Protect steel sheet pile used that can extract after engineering, recycled for multiple times, overall economic benefit is good, and work is greatly saved Journey investment.
Detailed description of the invention
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, in all the appended drawings, similar element Or part is generally identified by similar appended drawing reference.In attached drawing, each element or part might not be drawn according to actual ratio.
Fig. 1 is the floor plan of subgrade protection structure of the present invention;
Fig. 2 is the skiagraph of subgrade protection structure of the present invention.
Appended drawing reference:
The existing culvert ontology of 1-, 2- spreading culvert, 3- Larsen steel sheet pile, 4- top plate, 5- bottom plate, 6- wall, the existing roadbed side 7- Slope, the existing culvert central axes 8-, 9- existing line center line.
Specific embodiment
It is described in detail below in conjunction with embodiment of the attached drawing to technical solution of the present invention.Following embodiment is only used for Clearly illustrate technical solution of the present invention, therefore be only used as example, and cannot be used as a limitation and limit protection model of the invention It encloses.
If Fig. 1 shows, the safeguard structure of existing roadbed in a kind of disclosed extension culvert construction, including existing culvert Hole ontology 1, spreading culvert 2 and continuous Larsen steel sheet pile 3, wherein existing culvert ontology and spreading culvert all have top plate 4, Bottom plate 5 and two sides wall 6 select existing entrance side or outlet side with culvert to carry out spreading construction in spreading, will connect The top plate of long culvert is connect with the top plate of existing culvert, and the bottom plate of spreading culvert is connect with the bottom plate of existing culvert, spreading culvert Two sides wall connect with the two sides wall of existing culvert, whole spreading is formed, for the existing of existing culvert entrance two sides Roadbed side slope 7 applies man-hour requirement in spreading and carries out subgrade protection, Larsen steel sheet pile, and two sides are continuously squeezed into roadbed side slope It is arranged symmetrically with existing culvert central axes 8, the plane and existing culvert central axis that continuous Larsen steel sheet pile is formed are pressed from both sides in 45 ° Angle, and the starting point of continuous Larsen steel sheet pile is 3.5m apart from existing line center line 9, and end is located at the slope of roadbed side slope At foot.
The Larsen steel sheet pile is when squeezing into, the embedded depth half long not less than stake.
The protection construction method of existing roadbed, includes the following steps: in a kind of construction of extension culvert
A, according to existing roadbed banket type and compartment load determines the length and embedded depth of Larsen steel sheet pile, The gradient and height for measuring existing roadbed determine the integral planar position and single Larsen steel sheet pile of Larsen steel sheet pile Model, in which: the length of Larsen steel sheet pile is calculated using the method for cantilever beam, according to the height of foundation bottom to road shoulder Degree, the type of banketing of existing roadbed, every section railway carriage are fully loaded with gross weight, calculate the internal friction angle of unearthed conversion bulk density and soil, And then calculate coefficient of active earth pressure and coefficient of passive earth pressure;Geometrical relationship after being buried according to stake calculates steel sheet pile Anchorage length;Unearthed comprehensive pressure coefficient is calculated by the sum of various soil pressures, calculates stake further according to Bu Shi theoretical curve Embedded depth;Single steel plate pile length is the embedded depth that basic bottom adds stake to the height of road shoulder, and single Larsen steel plate The model selection of stake is to be obtained by checking maximal bending moment suffered by single stake with shearing;
B, using train travel gap, the railway protective fence at roadbed side slope is removed, smooth piling machine place, to piling position Carry out orientation measurement is set, while being spaced 5m at the roadbed road shoulder of existing culvert two sides and Displacement & Settlement stake is set, is utilized Total station, coordinate and elevation before level observation is driven piles;
C, the underground utilities that construction is nearby influenced on culvert, which move, to be changed, protects, and is then drawn using high-frequency hydraulic hammer The piling of gloomy steel sheet pile operates, and the vibration force of high-frequency hydraulic hammer is not less than 220KN, the Larsen steel sheet pile of initial position away from From existing line center line 3.5m, Larsen steel sheet pile that the Larsen steel sheet pile of end is located at roadbed side slope slope foot, and squeezes into Culvert center line is in 45 ° of angles;
D, during piling, horizontal displacement is carried out to each Displacement & Settlement stake every 1h and sedimentation value is observed, observed It is worth in allowed band and continues pile sinking, otherwise stops work and reinforce;
E, extension culvert construction is carried out after the completion of piling to be returned Buried culvert under roadbed changeover portion after band extension culvert construction It fills out, then extracts Larsen steel sheet pile.
Work progress is described in detail with one embodiment below
Certain engineering is 1.4 × 4.7m frame culvert spreading length 20.08m, and in 90 ° with railway center line, existing roadbed uses Drift-sand fills, roadbed height 3m, the specific steps are as follows:
1) dynamic load according to caused by the Roadbed Soil type and train operation, which determines, uses IV type Larsen steel sheet pile, average stake Long 9m;Larsen steel sheet pile embedded depth is not less than long 0.5 times of stake;Steel sheet pile position was both wired from existing culvert culvert body lateral extent Lu Zhizheng line 3.5m is extended at roadbed slope foot with culvert central axis angle at 45 °;
2) train travel gap is utilized, removing and change to move to railway protective fence at roadbed slope foot does not influence outside construction area, Smooth piling machine place;Unwrapping wire is measured to pile driving position;It is arranged at the existing roadbed road shoulder in culvert two sides every 5m and is displaced Settlement observation stake, using coordinate and elevation before total station, level observation piling position;
3) high-front shovel changes the outfit hydraulic high-frequency vibratory hammer, keeps piling machinery in place, wherein vibration hammer exciting force is not less than 220kN;
4) underground utilities before piling near exploration culvert, move to the pipeline for influencing construction and change, protect, move change finish it is laggard Row pile sinking operation carries out horizontal displacement, settlement observation to each observation stake every 1h in operation process, observes data in allowed band Interior continuation pile sinking, on the contrary it stops work immediately and other measures is taken to be reinforced;
5) it is finished to extension culvert construction, after the completion of road -culvert approach section backfill, extracts steel sheet pile, construction finishes.
Currently, existing extension culvert construction is affected to railway normal operation, do not carried out due to construction safety protection and Loss caused by causing train operation to be interrupted is inestimable, if during Business Line construction extension culvert both by this railway There is subgrade protection construction method to be applied to other similar engineering, not only greatly saves the investment of engineering itself, but also can be effective Reduction train operation because of caused by construction interrupt, and then reduce economic loss resulting from.Structure of the present invention is made For a security protection system, preventing train from overturning, the major accidents such as derailing, convenient transportation guarantees operation security etc. It is of great significance.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme should all cover within the scope of the claims and the description of the invention.

Claims (5)

1. the safeguard structure of existing roadbed in a kind of extension culvert construction, including existing culvert ontology, the two sides of entrance For existing roadbed side slope, it is characterised in that: continuously squeezed into Larsen steel sheet pile at roadbed side slope, which forms flat Face and existing culvert central axis are in 45 ° of angles, and the starting point of continuous Larsen steel sheet pile is apart from existing line center line 3.5m, and end is located at the slope foot of roadbed side slope.
2. the safeguard structure of existing roadbed in a kind of extension culvert construction according to claim 1, it is characterised in that: described The embedded depth of the Larsen steel sheet pile half long not less than stake.
3. the safeguard structure of existing roadbed in a kind of extension culvert construction according to claim 1, it is characterised in that: two sides Larsen steel sheet pile be arranged symmetrically with existing culvert central axes.
4. a kind of protection construction method based on structure described in claim 1, it is characterised in that include the following steps:
A, according to existing roadbed banket type and compartment load determines the length and embedded depth of Larsen steel sheet pile, The gradient and height for measuring existing roadbed determine the integral planar position and single Larsen steel sheet pile of Larsen steel sheet pile Model;
B, using train travel gap, the railway protective fence at roadbed side slope is removed, smooth piling machine place, to piling position Carry out orientation measurement is set, while being spaced 5m at the roadbed road shoulder of existing culvert two sides and Displacement & Settlement stake is set, is utilized Total station, coordinate and elevation before level observation is driven piles;
C, the underground utilities that construction is nearby influenced on culvert, which move, to be changed, protects, and is then drawn using high-frequency hydraulic hammer The piling of gloomy steel sheet pile operates, and the Larsen steel sheet pile of initial position is apart from existing line center line 3.5m, the Larsen steel plate of end Stake is located at roadbed side slope slope foot, and the Larsen steel sheet pile squeezed into and culvert center line are in 45 ° of angles;
D, during piling, horizontal displacement is carried out to each Displacement & Settlement stake every 1h and sedimentation value is observed, observed It is worth in allowed band and continues pile sinking, otherwise stops work and reinforce;
E, extension culvert construction is carried out after the completion of piling to be returned Buried culvert under roadbed changeover portion after band extension culvert construction It fills out, then extracts Larsen steel sheet pile.
5. the protection construction method of existing roadbed in a kind of extension culvert construction according to claim 4, it is characterised in that: The vibration force of the high-frequency hydraulic hammer is not less than 220KN.
CN201810889642.XA 2018-08-07 2018-08-07 The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert Pending CN108951440A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810889642.XA CN108951440A (en) 2018-08-07 2018-08-07 The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810889642.XA CN108951440A (en) 2018-08-07 2018-08-07 The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert

Publications (1)

Publication Number Publication Date
CN108951440A true CN108951440A (en) 2018-12-07

Family

ID=64468461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810889642.XA Pending CN108951440A (en) 2018-08-07 2018-08-07 The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert

Country Status (1)

Country Link
CN (1) CN108951440A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293665A (en) * 2021-06-02 2021-08-24 新疆铁道勘察设计院有限公司 Roadbed reinforcing method for long side of railway bridge and culvert connection

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139680A (en) * 2003-11-05 2005-06-02 Maeda Corp Sheet pile-type revetment structure and its construction method
KR20090016045A (en) * 2007-08-10 2009-02-13 최광욱 Waterway culvert using steel sheet piles and its construction method
CN106284366A (en) * 2015-05-25 2017-01-04 五冶集团上海有限公司 External pulling type Larsen steel sheet pile reinforcement means
CN208748543U (en) * 2018-08-07 2019-04-16 中铁株洲桥梁有限公司 The safeguard structure of existing roadbed in a kind of construction of extension culvert

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139680A (en) * 2003-11-05 2005-06-02 Maeda Corp Sheet pile-type revetment structure and its construction method
KR20090016045A (en) * 2007-08-10 2009-02-13 최광욱 Waterway culvert using steel sheet piles and its construction method
CN106284366A (en) * 2015-05-25 2017-01-04 五冶集团上海有限公司 External pulling type Larsen steel sheet pile reinforcement means
CN208748543U (en) * 2018-08-07 2019-04-16 中铁株洲桥梁有限公司 The safeguard structure of existing roadbed in a kind of construction of extension culvert

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李武斌: "桥涵接长施工中线路安全防护及其技术措施", 西部探矿工程, no. 08, 25 August 2005 (2005-08-25), pages 2 - 3 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293665A (en) * 2021-06-02 2021-08-24 新疆铁道勘察设计院有限公司 Roadbed reinforcing method for long side of railway bridge and culvert connection

Similar Documents

Publication Publication Date Title
CN101962928B (en) Construction method for processing aeolian sand roadbed base through impacting and grinding
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN102535263B (en) Roadbed with pile-net composite structure and construction method thereof
CN108385673B (en) Miniature upper filling ball sleeve pile and construction method thereof
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN101768924B (en) Overhead method for existing railway in area with soft foundation and high water level
CN106979021B (en) Large-section loess tunnel excavates and preliminary bracing quick closure cyclization method
CN104894937A (en) Construction method for mucky soft soil roadbase tubular pile
CN101215838A (en) Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN106088127A (en) Open caisson construction method
CN1288308C (en) Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre
CN103290846A (en) Construction method for preventing static-pressure precast tubular piles from floating
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN111365005A (en) Reinforcing structure and method for shield tunnel lower-penetrating elevated bridge foundation
CN102926388B (en) Earth moving method for deep foundation pit excavation
CN208748543U (en) The safeguard structure of existing roadbed in a kind of construction of extension culvert
CN106869038B (en) The auxiliary device and its construction method for preventing overpass from settling
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN108951440A (en) The safeguard structure and protection construction method of existing roadbed in a kind of construction of extension culvert
CN109723062A (en) Heave-load device hanging apparatus and hanging method based on proximity deep foundation pit construction environment
CN105239573B (en) The interplantation tube anchor rock construction method of shaped steel trestle
Alexiew et al. Foundation of a coal/coke stockyard on soft soil with geotextile encased columns and horizontal reinforcement
CN110205982A (en) Improve the channel design and its construction method of existing river levee flood control standard
CN201567523U (en) Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level
CN208073501U (en) Foundation base type is without inverted arch type tunnel lining structure and its drainage system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination