CN108949202A - The coke dry quenching furnace and its working method of room are prestored with air-cooled hanger and annular - Google Patents

The coke dry quenching furnace and its working method of room are prestored with air-cooled hanger and annular Download PDF

Info

Publication number
CN108949202A
CN108949202A CN201811052954.1A CN201811052954A CN108949202A CN 108949202 A CN108949202 A CN 108949202A CN 201811052954 A CN201811052954 A CN 201811052954A CN 108949202 A CN108949202 A CN 108949202A
Authority
CN
China
Prior art keywords
annular
air
ring wall
room
dry quenching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811052954.1A
Other languages
Chinese (zh)
Other versions
CN108949202B (en
Inventor
白银石
魏振东
李旭东
王满
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Acre Coking and Refractory Engineering Consulting Corp MCC
Original Assignee
Acre Coking and Refractory Engineering Consulting Corp MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Acre Coking and Refractory Engineering Consulting Corp MCC filed Critical Acre Coking and Refractory Engineering Consulting Corp MCC
Priority to CN201811052954.1A priority Critical patent/CN108949202B/en
Publication of CN108949202A publication Critical patent/CN108949202A/en
Application granted granted Critical
Publication of CN108949202B publication Critical patent/CN108949202B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10BDESTRUCTIVE DISTILLATION OF CARBONACEOUS MATERIALS FOR PRODUCTION OF GAS, COKE, TAR, OR SIMILAR MATERIALS
    • C10B39/00Cooling or quenching coke
    • C10B39/02Dry cooling outside the oven

Abstract

The present invention relates to a kind of coke dry quenching furnaces and its working method that room is prestored with air-cooled hanger and annular, and the room that prestores of the coke dry quenching furnace prestores room by the annular that upper inner ring wall, upper outer ring wall and lower inner ring wall, lower outer ring wall form;The lower section that annular prestores room is cooling chamber;Cooling chamber exterior wall, top plate, lower outer ring wall and cooling indoor material surround annular passage, and annular passage side sets partition wall, and the other side sets recyclegas outlet;Lower inner ring wall and its top plate of top form lower central cylinder, and multiple levels prestore airflow channel across lower inner ring wall and lower outer ring wall, lower central cylinder is connected to annular passage;For air-cooled hanger by forming along multiple hollow beams that coke dry quenching furnace is circumferentially arranged, the outer end of hollow beam sets cooling gas inlet, and inner end sets cooling gas outlet and is connected to central upper portion cylinder.The present invention can overcome the shortcomings that conventional coke dry quenching furnace structure, reduce cloth segregation, reduce and prestore room top high-voltage caused by the big material of unit materialbeds comminution, reduce the drag losses of recyclegas.

Description

The coke dry quenching furnace and its working method of room are prestored with air-cooled hanger and annular
Technical field
The present invention relates to coke dry quenching furnace technical field more particularly to a kind of coke dry quenching furnaces that room is prestored with air-cooled hanger and annular And its working method.
Background technique
Coke dry quenching furnace is an important energy conservation and environmental protection facility of coking production, and the incandescent coke that released from coke oven can exist A large amount of thermal energy that coke carries are recycled while cooling, also avoid wet quenching water caused by environment, gas pollution, because This is widely applied in coking field.Coke oven production have it is periodically and intermittent, and coke furnace system need to carry out it is daily Regularly maintenance (maximum repair time coke over machinery day reaches 2h), therefore coke is packed into coke dry quenching furnace and carries out cooling time and the frequency It is influenced and restriction by coke oven production;On the other hand, the supply of cooling chamber coke needs continuous-stable in coke dry quenching furnace, with Just heat energy recycling system continuous and steady operation is ensured.In order to achieve the above objectives, usually on the top of coke dry quenching furnace, cooling chamber Top be arranged one prestore room, be used for a certain amount of coke of temporary storage, adapt to the daily periodic inspection of coke oven production requirement.
Conventional coke dry quenching furnace to prestore room generally cylindrical cross section (as shown in Figure 1), material is from prestoring the room top opening 1-1 period Ground is packed into, and freely falls into prestore room 1-2 under the effect of gravity, and natural packing forms top in the cylindrical space for prestoring room 1-2 Portion has the material bed 1-3 at annular peak, prestores the material accumulation cylindrical of the room lower part 1-2 and progresses into cooling chamber 1-4.? Prestore the room lower part 1-2, the annular passage 1-5 equipped with export for the recyclegas cooling with red-hot material, annular passage 1-5 by Interior ringwall 1-6 and outer ring wall 1-7 are surrounded.Interior ringwall 1-6 and the lower part outer ring wall 1-7 by the top cooling chamber 1-4 bracket 1-8 into Row support, is arranged chute 1-9 between the lower part interior ringwall 1-6 and bracket 1-8, for exporting the recyclegas for obtaining material thermal energy. The above-mentioned conventional cylindrical room of prestoring has the disadvantage in that
1) be relatively large in diameter due to prestoring room 1-2, material after bell 1-10 cloth in upper lower leaf and inside and outside not Controlled oblique throwing curvilinear motion state, when especially prestoring that level of filler material is lower in the 1-2 of room, material whereabouts height difference is larger, under The enormous impact fallen exacerbates the segregation of cloth, i.e. the biggish material of granularity tends to the two sides for being distributed in material peak, and granularity Lesser material is then distributed in the middle part of material peak.The segregation of cloth also leads to the segregation of cooling air-flow, causes the cooling degree of material not Uniformly, thermal energy can not be effectively recovered, to seriously reduce the cooling efficiency of coke dry quenching furnace.When material is nature difference When biggish mixture, above-mentioned operating condition is more unfavorable.
2) when coke dry quenching furnace prestore have material in the 1-2 of room when, internal is solid " caecum " structure, and air-flow can only pass through It is exported positioned at the chute mouth 1-9 for prestoring mouth bed of material periphery under the 1-2 of room, since the area of chute mouth 1-9 is limited, leads to air velocity Comparatively fast.Material biggish for unit materialbeds comminution, this increases not only the conveying energy consumptions of recyclegas, also change in the bed of material Pressure distribution, cause that prestore positive pressure at the top of the 1-2 of room larger, dust escapes when charging, seriously pollutes environment.
In addition, there is also following disadvantages for the corbels support structure of the conventional coke dry quenching furnace room of prestoring use:
1) bracket 1-8 is successively overhang by brick setting in chute section and is constituted, since its needs is in the operating condition of temperature frequent fluctuation The lower loading for bearing top masonry, the impact grinding of side material undermines cooling air-flow and the fierceness of material dust is washed away, therefore non- It is often easily damaged, the bracket structure strength reduction of damage influences the structural stability of interior ringwall 1-6.
2) structure successively overhang also causes the length of bracket 1-8 and height to be restricted, so as to cause annular passage 1-5 It is restricted with the circulation section of chute mouth 1-9 recyclegas.
3) while the presence of bracket 1-8 reduces chute mouth 1-9 circulation area, chute mouth 1-9 recyclegas is increased Flow velocity increases the recyclegas drag losses flowed through and prestores positive pressure at the top of the 1-2 of room, chute mouth 1-9 is also made to be easier to send out Biology material floats phenomenon, causes chute mouth 1-9 Severe blockage, further increases the operation energy consumption of the circulatory system.
Summary of the invention
The present invention provides a kind of coke dry quenching furnaces and its working method that room is prestored with air-cooled hanger and annular, can overcome The shortcomings that conventional coke dry quenching furnace structure, reduces cloth segregation, reduces and prestores ceiling portion height caused by the big material of unit materialbeds comminution Pressure, reduces the drag losses of recyclegas;It can avoid existing many adverse effects when conventional coke dry quenching furnace setting bracket simultaneously, subtract Few material floats the generation of phenomenon.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
The coke dry quenching furnace that room is prestored with air-cooled hanger and annular, prestores room and cooling chamber including what is be connected to up and down;It is described pre- Depositing room is that the annular collectively constituted by upper inner ring wall, upper outer ring wall and lower inner ring wall, lower outer ring wall prestores room;Cooling chamber exterior wall Top sets top plate, and air-cooled hanger is set above top plate, and upper inner ring wall and upper outer ring wall are built on air-cooled hanger;Air-cooled hanger Set interior ringwall and lower outer ring wall, the circular passage and upper inner ring wall of lower inner ring wall and lower outer ring wall composition and upper outer ring wall in lower section The circular passage of composition is aligned and is connected to;The lower section that annular prestores room is cooling chamber;Cooling chamber exterior wall, top plate, lower outer ring wall and Cooling indoor material surrounds annular passage, sets partition wall between the cooling chamber exterior wall of annular passage side and lower outer ring wall, annular The air duct side opposite with partition wall sets training wall and recyclegas outlet;Lower inner ring wall and its top plate of top form lower central Cylinder, along coke dry quenching furnace circumferential direction, multiple levels prestore airflow channel across lower inner ring wall and lower outer ring wall, by lower central cylinder and annular Air duct connection;For air-cooled hanger by forming along multiple hollow beams that coke dry quenching furnace is circumferentially arranged, the middle part of air-cooled hanger passes through suspention machine Structure is connect with the rack above coke dry quenching furnace, and the outer end of hollow beam extends respectively into except furnace shell and set cooling gas inlet, hollow Beam sets the central upper portion cylinder that cooling gas outlet is formed with upper inner ring wall close to the one end at coke dry quenching furnace center respectively and is connected to.
The bottom of the air-cooled hanger sets the cage skeleton of 2 annulars, and lower inner ring wall and lower outer ring wall are built respectively right Including around the cage skeleton answered and going along with sb. to guard him cage skeleton, cage skeleton is made of refractory metal material.
The cage skeleton is by along more circumferentially distributed vertical sunpenders of coke dry quenching furnace and being vertically arranged on vertical sunpender Multilayer brick plate composition, the height of brick plate is adjustable.
The level prestores airflow channel and is made of heat-resistant and wear-resistant material, and level, which prestores, sets recyclegas stream in airflow channel Quantity regulating device.
The air-cooled hanger is made of metal material, and the annular that it passes through upper inner ring wall, upper outer ring wall is formed prestores room Part outer lining is wear-resisting and heat-barrier material.
The working method of the coke dry quenching furnace that room is prestored with air-cooled hanger and annular, comprising:
1) red-hot material is packed by distributing device from the material loading port that annular prestores ceiling portion, and prestoring interior in annular is in Annular crest accumulation, and move down under the effect of gravity;Since annular prestores room limited width, caused by material natural packing Radial segregation degree it is small;Material, can be successively by the sky being evenly distributed during loading annular prestores room and moves down Cold hanger and the horizontal blocking for prestoring airflow channel, generated relative motion are equivalent to whipping process, can further destroy The cloth segregation status generated makes cloth tend to uniform;
2) after material prestores the outflow of room bottom from annular, the natural packing in cooling chamber forms the material heap with annular peak; Material bed entrance cooling chamber upper space is passed through after sufficiently exchanging heat from the recyclegas and material that cooling chamber bottom is fed, wherein one The inclination charge level that part recyclegas passes through on the inside of annular peak enters lower central cylinder, then prestores airflow channel by level and enter In annular passage, converge with another part recyclegas that inclination charge level enters annular passage on the outside of annular peak, uniformly distributed water It is flat to prestore airflow channel and mix the air-flow in lower central cylinder and annular passage uniformly, it is more advantageous to the steady of output gas flow temperature Fixed, last recyclegas exports discharge by being located at the recyclegas of annular passage side;
3) due to the conductive force of the furnace wall of coke dry quenching furnace and furnace shell, the air themperature in central upper portion cylinder is higher, to produce Suction force has been given birth to, has flowed into air constantly from the cooling air intake on air-cooled hanger, has been flowed out from cooling air outlet, by sky The cooling to air-cooled hanger is realized in the free convection of gas.
Compared with prior art, the beneficial effects of the present invention are:
1) room is prestored using annular, after circumferentially uniformly loading annular prestores room by material, material is in relatively narrow space Degree of segregation greatly reduces, and material is during being packed into annular and prestoring room and move down, and successively by circumferentially uniformly distributed air-cooled Hanger and the horizontal blocking for prestoring airflow channel, generated relative motion are similar to whipping process, can further destroy The cloth segregation status of generation makes cloth tend to uniform;
2) material forms annular material peak, medial and lateral charge level in cooling chamber upper space in the case where annular prestores the constraint of room The gross area increases, and inside recyclegas can prestore airflow channel by level and quickly export to external annular passage, more have Conducive to the uniform export of recyclegas, and reduce the resistance of recyclegas and the operation energy consumption of system;
3) it after prestoring room using annular, is equivalent to and prestores the material loading port in ceiling portion in cooling chamber upper space and annular Between be provided with enough height material seal, gas-circulating system and material loading port are effectively completely cut off, cooling chamber top is eliminated Influence of the space pressure to material charging apparatus;
4) the part recyclegas passed through out of the bed of material enters lower central cylinder and to prestore airflow channel laggard by level Enter in annular passage, uniformly distributed level prestores airflow channel and the air-flow of central tube and annular passage is uniformly mixed, more favorably In the stabilization of output gas flow temperature;
5) main body that annular prestores room is fixed by air-cooled hanger and suspension gear, is significantly reduced and is built to lower part cooling chamber The load of body, while conventional bracket structure is eliminated, keep the structure of coke dry quenching furnace more stable, Maintenance and Repair cost significantly drops Low, service life can significantly extend;
6) air-cooled hanger uses air natural cooling, does not need to increase extras and power consumption, increases coke dry quenching furnace Reliability of operation saves equipment investment and operating cost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of conventional coke dry quenching furnace.
Fig. 2 is the main view of the coke dry quenching furnace of the present invention that room is prestored with air-cooled hanger and annular.
Fig. 3 is the A-A view in Fig. 2.
Fig. 4 is the B-B view in Fig. 2.
In figure: 1-1., which prestores room top opening 1-2. and prestores, has the material bed 1-4. at annular peak cold at the top of the 1-3. of room But ringwall 1-7. outer ring wall 1-8. bracket 1-9. chute 1-10. bell in room 1-5. annular passage 1-6.
1. 3. annular of outer ring wall prestores 4. lower central cylinder of room, 5. level and prestores airflow channel 6. on upper inner ring wall 2. The lower outer ring wall 13. of the air-cooled 11. lower inner ring wall 12. of hanger of 7. partition wall of annular passage, 8. training wall, 9. cage skeleton 10. is cold But 14. material loading port of room exterior wall, 15. recyclegas exports 16. top plate, 17. suspension gear, 18. recyclegas flow tune 19. cooling air intake of regulating device, 20. cooling air outlet, 21. central upper portion cylinder
Specific embodiment
Specific embodiments of the present invention will be further explained with reference to the accompanying drawing:
As shown in figs 2-4, of the present invention that there is air-cooled hanger and annular to prestore the coke dry quenching furnace of room, including be connected to up and down Prestore room and cooling chamber;The room of prestoring is common by upper inner ring wall 1, upper outer ring wall 2 and lower inner ring wall 11, lower outer ring wall 12 The annular of composition prestores room 3;The top of cooling chamber exterior wall 13 sets top plate 16, and the top of top plate 16 sets air-cooled hanger 10, upper inner ring Wall 1 and upper outer ring wall 2 are built on air-cooled hanger 10;Interior ringwall 11 and lower outer ring wall 12 are set below air-cooled hanger 10, under Interior ringwall 11 is aligned simultaneously with the circular passage that lower outer ring wall 12 forms with upper inner ring wall 1 with the circular passage that upper outer ring wall 2 forms Connection;The lower section that annular prestores room 3 is cooling chamber;Cooling chamber exterior wall 13, top plate 16, lower outer ring wall 12 and cooling indoor material Surround annular passage 6, set partition wall 7 between the cooling chamber exterior wall 13 of 6 side of annular passage and lower outer ring wall 12, annular passage 6 with The opposite side of partition wall 7 sets training wall 8 and recyclegas outlet 15;Lower inner ring wall 11 and its top plate of top 16 form in lower part Heart cylinder 4, along coke dry quenching furnace circumferential direction, multiple levels prestore airflow channel 5 across lower inner ring wall 11 and lower outer ring wall 12, by lower central Cylinder 4 is connected to annular passage 6;Air-cooled hanger 10 by being formed along multiple hollow beams that coke dry quenching furnace is circumferentially arranged, air-cooled hanger 10 Middle part is connect by suspension gear 17 with the rack above coke dry quenching furnace, and the outer end of hollow beam extends respectively into except furnace shell and sets cold But gas access 19, hollow beam set cooling gas outlet 20 close to the one end at coke dry quenching furnace center respectively and connect with central upper portion cylinder 21 It is logical.
The bottom of the air-cooled hanger 10 sets the cage skeleton 9 of 2 annulars, and lower inner ring wall 11 and lower outer ring wall 12 are built respectively Including building around corresponding cage skeleton 9 and going along with sb. to guard him cage skeleton 9, cage skeleton 9 is made of refractory metal material.
The cage skeleton 9 is by along more circumferentially distributed vertical sunpenders of coke dry quenching furnace and being vertically arranged on vertical sunpender Multilayer brick plate composition, the height of brick plate is adjustable.
The level prestores airflow channel 5 and is made of heat-resistant and wear-resistant material, and level prestores in airflow channel 5 and sets recyclegas Flow regulator 18.
The air-cooled hanger 10 is made of metal material, and the annular that it passes through upper inner ring wall 1, upper outer ring wall 2 is formed is pre- Deposit room 3 part outer lining is wear-resisting and heat-barrier material.
The working method of the coke dry quenching furnace that room is prestored with air-cooled hanger and annular, comprising:
1) red-hot material is packed by distributing device from the material loading port 14 that annular prestores 3 top of room, prestores room 3 in annular Inside crest is accumulated in a ring, and is moved down under the effect of gravity;Since annular prestores room limited width, material natural packing institute Caused radial segregation degree is small;Material can be successively evenly distributed during loading annular prestores room 3 and moves down Air-cooled hanger 10 and the horizontal blocking for prestoring airflow channel 5, generated relative motion be equivalent to whipping process, can be into one Step destroys the cloth segregation status generated, and cloth is made to tend to uniform;
2) after material prestores the outflow of 3 bottom of room from annular, the natural packing in cooling chamber forms the material with annular peak Heap;Material bed entrance cooling chamber upper space is passed through after sufficiently exchanging heat from the recyclegas and material that cooling chamber bottom is fed, The inclination charge level that middle a part of recyclegas passes through on the inside of annular peak enters lower central cylinder 4, then prestores air-flow by level and lead to Road enters in annular passage 6, converges with another part recyclegas that inclination charge level enters annular passage 6 on the outside of annular peak, Uniformly distributed level, which prestores airflow channel 5, mixes the air-flow in lower central cylinder 4 and annular passage 6 uniformly, is more advantageous to output The stabilization of gas flow temperature, last recyclegas are discharged by being located at the recyclegas outlet 15 of 6 side of annular passage;
3) due to the conductive force of the furnace wall of coke dry quenching furnace and furnace shell, the air themperature in central upper portion cylinder 21 is higher, thus Suction force is produced, flows into air constantly from the cooling air intake on air-cooled hanger 10, is flowed out from cooling air outlet, according to The cooling to air-cooled hanger 10 is realized in free convection by air.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (6)

1. prestoring the coke dry quenching furnace of room with air-cooled hanger and annular, room and cooling chamber are prestored including what is be connected to up and down;Its feature exists In the room of prestoring is that the annular collectively constituted by upper inner ring wall, upper outer ring wall and lower inner ring wall, lower outer ring wall prestores room;It is cold Outdoor coping sets top plate, sets air-cooled hanger above top plate, upper inner ring wall and upper outer ring wall build air-cooled hanger it On;Interior ringwall and lower outer ring wall, the circular passage and upper inner ring of lower inner ring wall and lower outer ring wall composition are set below air-cooled hanger Wall is aligned and is connected to the circular passage that upper outer ring wall forms;The lower section that annular prestores room is cooling chamber;Cooling chamber exterior wall, top Plate, lower outer ring wall and cooling indoor material surround annular passage, the cooling chamber exterior wall of annular passage side and lower outer ring wall it Between set partition wall, the annular passage side opposite with partition wall sets training wall and recyclegas outlet;The top of lower inner ring wall and its top Board group is at lower central cylinder, and along coke dry quenching furnace circumferential direction, multiple levels prestore airflow channel across lower inner ring wall and lower outer ring wall, will under Portion's central tube is connected to annular passage;Air-cooled hanger by being formed along multiple hollow beams that coke dry quenching furnace is circumferentially arranged, air-cooled hanger Middle part is connect by suspension gear with the rack above coke dry quenching furnace, and the outer end of hollow beam extends respectively into except furnace shell and sets cooling Gas access, hollow beam set the central upper portion that cooling gas outlet is formed with upper inner ring wall close to the one end at coke dry quenching furnace center respectively Cylinder connection.
2. the coke dry quenching furnace according to claim 1 for prestoring room with air-cooled hanger and annular, which is characterized in that described air-cooled The bottom of hanger sets the cage skeleton of 2 annulars, and lower inner ring wall and lower outer ring wall are built respectively around corresponding cage skeleton And including going along with sb. to guard him cage skeleton, cage skeleton is made of refractory metal material.
3. the coke dry quenching furnace according to claim 2 for prestoring room with air-cooled hanger and annular, which is characterized in that the cage Skeleton is made of the multilayer brick plate along more circumferentially distributed vertical sunpenders of coke dry quenching furnace and being vertically arranged on vertical sunpender, The height of brick plate is adjustable.
4. the coke dry quenching furnace according to claim 1 for prestoring room with air-cooled hanger and annular, which is characterized in that the level It prestores airflow channel to be made of heat-resistant and wear-resistant material, level, which prestores, sets recyclegas flow regulator in airflow channel.
5. the coke dry quenching furnace according to claim 1 or 2 for prestoring room with air-cooled hanger and annular, which is characterized in that described Air-cooled hanger is made of metal material, and its part outer lining for prestoring room across the annular that upper inner ring wall, upper outer ring wall are formed is resistance to Mill and heat-barrier material.
6. the working method of the coke dry quenching furnace of room is prestored with air-cooled hanger and annular as described in claim 1, which is characterized in that Include:
1) red-hot material is packed by distributing device from the material loading port that annular prestores ceiling portion, prestores interior in a ring in annular Crest accumulation, and move down under the effect of gravity;Since annular prestores room limited width, diameter caused by material natural packing It is small to degree of segregation;Material can successively air-cooled be hung by what is be evenly distributed during being packed into annular and prestoring room and move down Frame and the horizontal blocking for prestoring airflow channel, generated relative motion are equivalent to whipping process, can further destroy The cloth segregation status of generation makes cloth tend to uniform;
2) after material prestores the outflow of room bottom from annular, the natural packing in cooling chamber forms the material heap with annular peak;From cold But the recyclegas and material that room bottom is fed pass through material bed into cooling chamber upper space, a portion after sufficiently exchanging heat The inclination charge level that recyclegas passes through on the inside of annular peak enters lower central cylinder, then prestores airflow channel by level and enter annular In air duct, converge with another part recyclegas that inclination charge level enters annular passage on the outside of annular peak, uniformly distributed level is pre- Depositing airflow channel mixes the air-flow in lower central cylinder and annular passage uniformly, is more advantageous to the stabilization of output gas flow temperature, Last recyclegas exports discharge by being located at the recyclegas of annular passage side;
3) due to the conductive force of the furnace wall of coke dry quenching furnace and furnace shell, the air themperature in central upper portion cylinder is higher, to produce Suction force flows into air constantly from the cooling air intake on air-cooled hanger, flows out from cooling air outlet, by air The cooling to air-cooled hanger is realized in free convection.
CN201811052954.1A 2018-09-10 2018-09-10 Dry quenching furnace with air cooling hanging frame and annular pre-chamber and working method thereof Active CN108949202B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811052954.1A CN108949202B (en) 2018-09-10 2018-09-10 Dry quenching furnace with air cooling hanging frame and annular pre-chamber and working method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811052954.1A CN108949202B (en) 2018-09-10 2018-09-10 Dry quenching furnace with air cooling hanging frame and annular pre-chamber and working method thereof

Publications (2)

Publication Number Publication Date
CN108949202A true CN108949202A (en) 2018-12-07
CN108949202B CN108949202B (en) 2024-01-30

Family

ID=64476483

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811052954.1A Active CN108949202B (en) 2018-09-10 2018-09-10 Dry quenching furnace with air cooling hanging frame and annular pre-chamber and working method thereof

Country Status (1)

Country Link
CN (1) CN108949202B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101709220A (en) * 2009-11-16 2010-05-19 中冶焦耐(大连)工程技术有限公司 Coke dry quenching furnace with annular air flue and inclined flue of new structure
CN203866244U (en) * 2014-06-06 2014-10-08 武汉钢铁(集团)公司 Dry coke quenching furnace
CN207556293U (en) * 2017-12-08 2018-06-29 四川川锅科泰达能源技术有限公司 A kind of packet wall water cooled wall type semi-coke heat recovery boiler
CN208980645U (en) * 2018-09-10 2019-06-14 中冶焦耐(大连)工程技术有限公司 The coke dry quenching furnace of room is prestored with air-cooled hanger and annular

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101709220A (en) * 2009-11-16 2010-05-19 中冶焦耐(大连)工程技术有限公司 Coke dry quenching furnace with annular air flue and inclined flue of new structure
CN203866244U (en) * 2014-06-06 2014-10-08 武汉钢铁(集团)公司 Dry coke quenching furnace
CN207556293U (en) * 2017-12-08 2018-06-29 四川川锅科泰达能源技术有限公司 A kind of packet wall water cooled wall type semi-coke heat recovery boiler
CN208980645U (en) * 2018-09-10 2019-06-14 中冶焦耐(大连)工程技术有限公司 The coke dry quenching furnace of room is prestored with air-cooled hanger and annular

Also Published As

Publication number Publication date
CN108949202B (en) 2024-01-30

Similar Documents

Publication Publication Date Title
CN108359756B (en) Dry centrifugal granulation and waste heat recycling system for liquid slag
CN207180340U (en) A kind of Active Lime Rotary Kiln secondary cooling energy saver
CN208980642U (en) Airflow channel is prestored with inclination and annular prestores the coke dry quenching furnace of room
CN106905988B (en) Dry quenching furnace with new exhaust structure
CN208980645U (en) The coke dry quenching furnace of room is prestored with air-cooled hanger and annular
CN209161944U (en) The coke dry quenching furnace of room is prestored with water cooling hanger and annular
CN108955276A (en) Vertical sinter cooler and sinter cooling means with revolving top
CN104629778A (en) Coke plugging prevention device of dry quenching furnace
CN208776655U (en) The coke dry quenching furnace of room is prestored with air-cooled support frame and annular
CN109608071A (en) A kind of multistage pre-heating system of cement predecomposition kiln
CN208980646U (en) The coke dry quenching furnace of room is prestored with water cooling support frame and annular
CN108949202A (en) The coke dry quenching furnace and its working method of room are prestored with air-cooled hanger and annular
CN108865191A (en) Airflow channel is prestored with inclination and annular prestores the coke dry quenching furnace and working method of room
CN108913169A (en) The coke dry quenching furnace and its working method of room are prestored with water cooling support frame and annular
CN108949201A (en) The coke dry quenching furnace and its working method of room are prestored with water cooling hanger and annular
CN206593485U (en) A kind of vertical sinter cooler
CN109135775A (en) The coke dry quenching furnace and its working method of room are prestored with air-cooled support frame and annular
CN108105763A (en) It is a kind of to prepare kaolin Circulation fluidized-bed furnace material returning device
CN207422866U (en) A kind of low energy consumption long-life type waste heat recovery shaft furnace
CN109652101B (en) Dry quenching furnace with furnace wall bearing airless chute structure in segmented mode
CN108105762B (en) It is a kind of to prepare kaolin Circulation fluidized-bed furnace material returning device application method
CN211199119U (en) Dry quenching furnace for dry quenching process
CN207113623U (en) Vertical sinter cooler with chute feeder
CN204550463U (en) One is dry puts out anti-coke blocking device in stove
JP5554607B2 (en) Coke dry fire extinguishing equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant