CN108941524A CN201710377493.4A CN201710377493A CN108941524A CN 108941524 A CN108941524 A CN 108941524A CN 201710377493 A CN201710377493 A CN 201710377493A CN 108941524 A CN108941524 A CN 108941524A
Authority
CN
China
Prior art keywords
flange
ladle
maing ladle
valve
molten metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710377493.4A
Other languages
Chinese (zh)
Inventor
周茂敬
巨邦昌
李国伟
铁全福
兰青
王海东
海永升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGHAI BEICHEN TECHNOLOGY Co Ltd
Original Assignee
QINGHAI BEICHEN TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGHAI BEICHEN TECHNOLOGY Co Ltd filed Critical QINGHAI BEICHEN TECHNOLOGY Co Ltd
Priority to CN201710377493.4A priority Critical patent/CN108941524A/en
Publication of CN108941524A publication Critical patent/CN108941524A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/005Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like with heating or cooling means
    • B22D41/01Heating means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/14Closures
    • B22D41/16Closures stopper-rod type, i.e. a stopper-rod being positioned downwardly through the vessel and the metal therein, for selective registry with the pouring opening
    • B22D41/18Stopper-rods therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/14Closures
    • B22D41/16Closures stopper-rod type, i.e. a stopper-rod being positioned downwardly through the vessel and the metal therein, for selective registry with the pouring opening
    • B22D41/20Stopper-rod operating equipment
    • CCHEMISTRY; METALLURGY
    • C25ELECTROLYTIC OR ELECTROPHORETIC PROCESSES; APPARATUS THEREFOR
    • C25CPROCESSES FOR THE ELECTROLYTIC PRODUCTION, RECOVERY OR REFINING OF METALS; APPARATUS THEREFOR
    • C25C3/00Electrolytic production, recovery or refining of metals by electrolysis of melts
    • C25C3/04Electrolytic production, recovery or refining of metals by electrolysis of melts of magnesium

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Casting Support Devices, Ladles, And Melt Control Thereby (AREA)

Abstract

The present invention relates to generating metal magnesium by electrolyzing magnesium chloride fields, specifically disclose the High aititude transfer vehicle-mounted device of two-maing ladle of molten metal magnesium, including bottom bracket, shell of two-maing ladle, liner, vacuum tube, plug valve control mechanism, plug valve valve rod, plug valve spool, melt transfer pipe, liquidometer.The magnesium operation of two-maing ladle out in low atmospheric pressure high altitude localities may be implemented in the High aititude transfer vehicle-mounted device of two-maing ladle of molten metal magnesium of the invention, it can be to avoid vacuum pipe due to line clogging caused by the suction of sublimate inside liner, the necessary time of two-man ladle out magnesium and transfer melt operation can be significantly reduced by the heating function that setting is two-mand ladle simultaneously, can satisfy the needs of high production capacity electrolysis of magnesium chloride production so that two-maing ladle.

Description

High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium
Technical field
This application involves generating metal magnesium by electrolyzing magnesium chloride fields more particularly to High aititude to shift the vehicle-mounted lift of molten metal magnesium Bag apparatus.
Background technique
With the magnesium chloride development of resources of the amount of containing high in the exploitation of high altitude localities salt lake resources, especially salt lake, make The electrolysis of magnesium chloride production magnesium metal and chlorine Processes and apparatus highlands be able to apply and development.The electrolysis of magnesium chloride Cheng Zhonghui generates magnesium metal, is initially to exist in the form of molten metal magnesium, and also to carry out repeatedly in the process of production Transfer is further finished in different process equipments with realizing, final to obtain the metal magnesium ingot for meeting the requirements quality Or magnesium alloy.Molten metal magnesium from electrolytic cell goes out magnesium and transfer in each process equipment then and becomes to realize whole in the process Body magnesium ingot and the necessary process of magnesium alloy production.
The transfer process of earliest initial stage conventional melt magnesium metal mainly manually realizes, however artificial realizes melting gold The transfer of category magnesium be there is a problem that many.It is primarily due to the high temperature that molten metal magnesium there are about 700 DEG C, manually goes out magnesium so that depending merely on And there are great security risks for the process shifted;Secondly manually go out magnesium in the electrolysis of magnesium chloride production of high yield to be obviously difficult to Realize matched magnesium and transport capacity out.Why such method is traditional magnesium eletrolysis the reason of can be applied at that time Yield is universal relatively low and without corresponding special equipment.Magnesium out artificial simultaneously, which lacks molten metal magnesium in the process of transfer, to be protected Warm measure makes the time needed for obtaining magnesium and transfer process have very high limitation, primarily to preventing molten metal magnesium from existing Solidification in transfer process.
Later period as the production capacity of the electrolysis of magnesium chloride constantly expand and it is artificial go out magnesium existing for problems answering of to two-man ladle With being developed.Although tradition is two-mand ladle for going out the transfer ability of magnesium and molten metal magnesium to have compared with manual method and significantly be mentioned Height, while solving artificial magnesium out and the safety problem of transfer, but there is many deficiencies.
Liner must be preheated before operation by two-maing ladle first, and tradition two-man ladle before magnesium out liner preheating mainly according to It leans against using melt transfer pipe that the heat in closing down magnesium electrolysis bath above molten metal magnesium is empty while vacuumize operation in liner Aspiration enters liner and is preheated, and the process makes to show that magnesium operation, the time that place occupies and overhead traveling crane occupies are longer, accounts for entire molten The ratio for melting the magnesium metal transfer tasks time is great, seriously limits operating efficiency, it is difficult to adapt to the needs of high production capacity.Although compared with people The efficiency of work improves, but needs further to be solved.
Secondly tradition, which is two-mand ladle, mainly relies on the negative pressure of vacuum formed in liner of two-maing ladle and melt transfer pipe by closing down magnesium electrolysis bath Middle molten metal magnesium is pumped into liner and carries out out magnesium operation.And the height of negative pressure of vacuum not only decides in liner in the process The size of the height difference of magnesium also decides the size of suction speed of the molten metal magnesium in pipe out, can make if suction speed is excessively slow The blocking that solidification causes tube body occurs at the molten metal magnesium in melt transfer pipe.Tradition, which is two-mand ladle, herein to rely in reduction Gallbladder volume and matched vacuum system ability is improved to carry out the promotion of negative pressure of vacuum to it, and vacuum system ability mentions The limitation for suffering from investment, local atmospheric pressure and technique itself is risen, this allows for traditional volume two-mand ladle by very big Limitation.But with electrolytic chlorination magnesium production capacity it is continuous expansion and tradition two-man ladle liner volume limitation problem so that tradition is two-mand ladle It is difficult to meet industry production capacity demand now.This problem is more prominent in the small high altitude localities of atmospheric pressure.
In addition, tradition two-mans ladle and two-mans ladle inside liner that there are a large amount of sublimates when carrying out out magnesium operation, and these distil Object can be brought into vacuum pipe while liner vacuumizes and be attached on inner wall of the pipe, and vacuum pipe latus rectum is caused to reduce Pipe end negative pressure reduces, and even will cause the blocking of pipeline when serious.These are attached to the sublimate of inner wall of the pipe not simultaneously Just it inspects periodically and is difficult to effectively be cleared up.
Summary of the invention
Brief summary of the present invention is given below, in order to provide the basic reason about certain aspects of the invention Solution.It should be appreciated that this summary is not an exhaustive overview of the invention.It is not intended to determine key of the invention Or pith, nor is it intended to limit the scope of the present invention.Its purpose only provides certain concepts in simplified form, with This is as the preamble in greater detail discussed later.
The present invention is intended to provide one kind, which is provided with plug valve, cut-offs function, filtering function and heating function, melting can be improved It is vehicle-mounted that magnesium metal transfer tasks efficiency and the High aititude for adapting to various low atmospheric pressure High aititude operating environments shift molten metal magnesium It two-mans ladle device.
The present invention solves technical problem and adopts the following technical scheme that
High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: including bottom bracket, bottom plate of two-maing ladle, two-mans ladle outside Shell, liner, vacuum tube, plug valve control mechanism, lid of two-maing ladle, plug valve valve rod, plug valve spool, melt transfer pipe and liquidometer;It is lifting Bottom plate of two-maing ladle is arranged in incrustation bottom;In interior of shell setting liner of two-maing ladle;The liner includes manhole flange and blind flange, people Hole, top end socket, bottom bulkhead, plug valve valve seat, liner cylinder, conical seat, flange, liquidometer mounting hole;In described Bottom bulkhead is arranged in gallbladder cylinder body bottom, and plug valve valve seat is arranged in the bottom bulkhead lower part;It is sealed at the top of being arranged at the top of liner cylinder Head, the top end socket are set to shell upper of two-maing ladle, and manhole, liquidometer mounting hole and circular cone is arranged in top end socket top Shape seal receptacle;Flange is set at the top of the conical seat;Lid of two-maing ladle is arranged in top end socket top;The caping of two-maing ladle Plug valve control mechanism is arranged in portion and shell exterior of two-maing ladle;Valve stem seal flange is arranged in the conical seat and flange top, Airtight and watertight padding is set between the valve stem seal flange and conical seat;Vacuum is set on the manhole flange and blind flange Pipe, the end of the vacuum tube are arranged filter, are connected to inside the other end and liner of vacuum tube;Lid and the top of two-maing ladle Flame-proof thermal insulation material is set between portion's end socket;Described two-man ladle and two-mans ladle flame-proof thermal insulation material is arranged between bottom plate and liner at shell, Gap is equipped between the refractory material and liner;The plug valve valve rod passes through the conical seat, airtight and watertight padding and valve Bar sealing flange, there are gaps between the plug valve valve rod and conical seat and valve stem seal flange;The plug valve valve rod Plug valve spool is arranged in bottom.
The valve rod control mechanism includes rotating shaft supporting seat, cross bar, upright bar, speed reducer, speed reducer handwheel, and institute's support base is set It sets and covers two-maing ladle, the speed reducer setting is being two-mand ladle on shell, and the output end of speed reducer is arranged in the upright bar, tells deceleration The input terminal of speed reducer is arranged in machine handwheel, and the shaft perpendicular, plug valve with support base respectively is arranged in the middle part of the cross bar and both ends Valve rod and upright bar connection, may be implemented mutually to rotate each other.The speed reducer control handwheel can pass through output end of reducer reality The vertical movement of existing upright bar;The vertical fortune that cross bar drives plug valve valve rod and plug valve spool may be implemented in the vertical movement of the upright bar It is dynamic.
Electric heating wire is arranged in gap location between the flame-proof thermal insulation material and liner cylinder and bottom bulkhead, and the electricity adds Heated filament is fixed on flame-proof thermal insulation material, and gap is equipped between the electric heating wire and liner cylinder and bottom bulkhead.
Optionally, the bottom plate lower part setting bottom bracket of two-maing ladle, the bottom and bottom plate of two-maing ladle are using welding or bolt Connection.
Optionally, melt transfer pipe is arranged in plug valve valve seat lower part, adopts between the melt transfer pipe and plug valve valve seat With welded connecting, the melt transfer pipe inside plug valve valve seat and liner by being connected to.
Optionally, setting manhole and blind flange at the top of the manhole, the liquidometer mounting hole is interior to be arranged liquidometer.
The filter include air inlet pipe, top flange, outer housing, exhaust pipe, filter screen, flange in the bottom lid, filter plate, Filtration barrel body, pressure-measuring pipe, pressure gauge.Top flange is set at the top of the outer housing, and flange in the bottom lid is arranged in outer housing lower part, outside Exhaust pipe and pressure-measuring pipe is respectively set in shell side;Air inlet pipe is arranged in told top flange top, and top flange lower part was arranged Filter cylinder body;Filter plate is arranged in the filtration barrel body bottom;Air filter hole is uniformly arranged on the filter plate;The air inlet pipe and filtering The inside of cylinder is connected to;Filter screen is filled in the gap of the filtration barrel body and filter plate and flange in the bottom lid and outer housing;Institute Stating filter screen is stainless steel material;The air inlet pipe is connected to vacuum tube;It is connected to inside the exhaust pipe and outer housing;The top Portion's flange and outer housing are connected by screw bolts;The flange in the bottom lid and outer housing are connected by screw bolts.
The plug valve valve rod, plug valve spool, plug valve valve seat, conical seat and valve stem seal flange vertical center line It should keep on the same line.
Optionally, perforative valve-rod cavity up and down, valve stem seal flange bottom are set at the valve stem seal flange vertical centre Conical sealing face is arranged in portion, and bolt hole is arranged in valve stem seal flange top surface.
Optionally, using welded connecting between the liner cylinder and bottom bulkhead and top end socket.
Optionally, the lid of two-maing ladle, top end socket and shell of two-maing ladle are connected by screw bolts;It is described two-man ladle bottom plate with two-man ladle It is used clamping bolts or welded connection between shell.
Optionally, using welded connecting between the conical seat and top end socket;The plug valve valve seat with it is described Using welded connecting between bottom bulkhead.
Optionally, the outer surface of the plug valve spool and the inner surface of plug valve valve seat are cone or hemispherical.
Optionally, the conical seat is connected by screw bolts with valve stem seal flange.
Optionally, connecting flange, the connecting flange and melt transfer pipe are set in the middle part of the melt transfer pipe using resistance to The stainless steel material of high temperature.
Optionally, the liner, plug valve valve rod, plug valve spool and conical seat use stainless steel resistant to high temperature Matter.
Beneficial effects of the present invention are as follows:
(1) setting for passing through plug valve spool, plug valve valve rod, plug valve valve seat and plug valve control mechanism may be implemented to take out very to two-maing ladle Function is cut-off in sky and out magnesium operation.It cut-offs function first and can be realized and do not increasing vacuum system investment and reduction is two-mand ladle volume In the case where improve internal negative pressure value of two-maing ladle, to increase flow velocity of the magnesium liquid at magnesium initial stage of two-maing ladle out in melt transfer pipe, Avoid magnesium initial stage melt blocking melt transfer pipe of two-maing ladle out;Secondly this, which is two-mand ladle, is realizing two-maing ladle for low atmospheric pressure high altitude localities Also it can two-man ladle liner volume by increasing in low atmospheric pressure high altitude localities while magnesium operation out and increase the capacity two-mand ladle, after And the efficiency for single transfer melt of two-maing ladle can be improved, finally to two-man ladle and shifts the operation mode of molten metal magnesium and can adapt to The electrolysis of magnesium chloride operation of high production capacity.
(2) it by the setting of filter, can two-man ladle to avoid tradition a large amount of in the liner that two-man ladle when magnesium operation Sublimate is brought into vacuum pipe and is attached on inner wall of the pipe, then caused by vacuum pipe latus rectum reduce, pipe end Negative pressure reduces and possible line clogging problem.
(3) heating function two-mand ladle may be implemented in the setting of electric heating wire, so that two-maing ladle before carrying out out magnesium operation just To two-maing ladle, liner carries out pre- hot work, drastically reduces tradition and two-mans ladle and is preheated in magnesium operation out to magnesium operation, field out The necessary time that ground occupies and overhead traveling crane occupies makes energy of two-maing ladle to greatly improve the operating efficiency of two-man ladle out magnesium and transfer Meet the needs of the molten metal magnesium transfer tasks in high production capacity electrolysis of magnesium chloride production.
Detailed description of the invention
Below with reference to the accompanying drawings illustrate embodiments of the invention, the invention will be more easily understood it is above and its Its objects, features and advantages.Component in attached drawing is intended merely to show the principle of the present invention.In the accompanying drawings, identical or similar Technical characteristic or component will be indicated using same or similar appended drawing reference.
Fig. 1 is the main view cross-section structure signal that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention Figure;
Fig. 2 is the overlooking structure diagram that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention;
Fig. 3 is the top view cross section structural schematic diagram that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention;
Fig. 4 is the liner main view cross-section structure signal that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention Figure;
Fig. 5 is that the filter main view cross-section structure that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention shows It is intended to;
Fig. 6 is the filter plate front view structure signal that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention Figure;
Fig. 7 is the valve stem seal flange main view section that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention Structural schematic diagram;
Fig. 8 is the plug valve control mechanism front view structure that High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium in the embodiment of the present invention Schematic diagram;
The mark in the figure shows: 1- bottom bracket, 2- two-man ladle bottom plate, 3- two-man ladle shell, 4- flame-proof thermal insulation material, in 5- Gallbladder, 5a- manhole flange and blind flange, 5b- manhole, the top 5c- end socket, 5d- bottom bulkhead, 5e- plug valve valve seat, 5f- Liner cylinder, 5g- conical seat, 5h- flange, 5j- liquidometer mounting hole, 6- electric heating wire, 7- filter, 7a- air inlet pipe, 7b- top flange, 7c- outer housing, 7d- exhaust pipe, 7e- filter screen, 7f- flange in the bottom lid, 7g- Filter plate, 7h- filtration barrel body, 7j- pressure-measuring pipe, 7k- pressure gauge, 7m- filter hole, 8- vacuum tube, 9- valve stem seal method Orchid, 9a- valve-rod cavity, 9b- bolt hole, 9c- conical sealing face, 10- airtight and watertight padding, 11- plug valve control mechanism, 11a- Shaft, 11b- support base, 11c- cross bar, 11d- upright bar, 11e- speed reducer, 11f- speed reducer handwheel, 12- two-man ladle lid, 13- plug valve valve rod, 14- plug valve spool, 15- melt transfer pipe, 16- liquidometer, 17- connecting flange.
Specific embodiment
Embodiments of the present invention will be described below with reference to the accompanying drawings.It is retouched in an attached drawing of the invention or a kind of embodiment The elements and features stated can be combined with elements and features shown in one or more other attached drawings or embodiment.It answers When note that for purposes of clarity, being omitted known to unrelated to the invention, those of ordinary skill in the art in attached drawing and explanation Component and processing expression and description.
Embodiment
Referring to Fig. 1-4, the High aititude transfer vehicle-mounted device of two-maing ladle of molten metal magnesium includes bottom bracket 1, bottom plate 2 of two-maing ladle, lift Incrustation 3, liner 5, vacuum tube 8, plug valve control mechanism 11, lid 12 of two-maing ladle, plug valve valve rod 13, plug valve spool 14, melt transfer Pipe 15 and liquidometer 16;Two-maing ladle, bottom plate 2 of two-maing ladle is arranged in 3 bottom of shell;Liner 5 is set inside shell 3 of two-maing ladle;Liner 5 wraps Include manhole flange and blind flange 5a, manhole 5b, top end socket 5c, bottom bulkhead 5d, plug valve valve seat 5e, liner cylinder 5f, circular cone Shape seal receptacle 5g, flange 5h, liquidometer mounting hole 5j;Bottom bulkhead 5d, the bottom envelope is arranged in the bottom liner cylinder 5f Plug valve valve seat 5e is arranged in the head lower part 5d;End socket 5c, the top end socket 5c are set to lift at the top of being arranged at the top of liner cylinder 5f 3 top of incrustation, the vertical support of liner 5, which mainly passes through top end socket 5c and is supported on, two-mans ladle on shell 3;The top end socket The top 5c is arranged manhole 5b, liquidometer mounting hole 5j and conical seat 5g, and the setting of manhole can be to carrying out inside liner 5 Maintenance or cleaning;Flange 5h is set at the top of the conical seat 5g;Lid 12 of two-maing ladle is arranged in the top top end socket 5c;Institute It states and plug valve control mechanism 11 is set outside two-man ladle 12 top of lid and shell 3 of two-maing ladle;On the conical seat 5g and flange 5h Valve stem seal flange 9 is arranged in portion, and airtight and watertight padding 10 is arranged between the valve stem seal flange 9 and conical seat 5g, passes through The tightening for connection bolt of conical seat 5g and valve stem seal flange 9d squeezes airtight and watertight padding 10, thus realization pair It two-mans ladle herein the sealing of liner.Vacuum tube 8, the end setting of the vacuum tube 8 are set on the manhole flange and blind flange 5a Filter 7 can be filtered a large amount of sublimates generated in liner 5, sublimate is avoided largely to enter vacuum pipe system; It is connected to inside the other end of vacuum tube 8 and liner 5;Fire resistant heat preserving material is arranged in described two-man ladle between lid 12 and the top end socket 5c In shell 3 and the setting flame-proof thermal insulation material 4 between bottom plate 2 and liner 5 of two-maing ladle of two-maing ladle while expecting 4, primarily serve to liner Insulation effect slows down the cooling of molten metal magnesium and liner;Gap is equipped between the flame-proof thermal insulation material 4 and liner 5, around here Gap can be used for installing electric heating wire;The plug valve valve rod 13 passes through the conical seat 5g, airtight and watertight padding 10 and valve rod Sealing flange 9d, the plug valve valve rod 13 pass through the conical seat 5g, airtight and watertight padding 10 and valve stem seal flange 9d, institute State there are gap between plug valve valve rod 13 and conical seat 5g and valve stem seal flange 9d, plug valve valve rod 13 can be realized with Conical seat 5g, the relative motion of airtight and watertight padding 10 and valve stem seal flange 9d in vertical direction;The plug valve valve rod Plug valve spool 14 is arranged in 13 bottoms.
In above-described embodiment, the inner surface of 14 outer surface of plug valve spool and plug valve valve seat 5e are cone or hemisphere Shape, the two faying face are shape of the same race, and when closing can play preferable sealing function.
In above-described embodiment, referring to Fig. 8, the plug valve bar control mechanism 11 includes shaft 11a, support base 11b, cross bar 11c, upright bar 11d, speed reducer 11e, speed reducer handwheel 11f;The support base 11b setting is being two-mand ladle on lid 12, the speed reducer 11e setting is being two-mand ladle on shell 3, and the output end of speed reducer 11e, told speed reducer handwheel 11f setting is arranged in the upright bar 11d In the input terminal of speed reducer 11e, the middle part of the cross bar 11c and both ends setting shaft 11a respectively with support base 11b, plug valve valve Bar 13 and upright bar 11d connection, may be implemented mutually to rotate each other.The speed reducer control handwheel 11f can pass through speed reducer 11e Output end realize upright bar 11d vertical movement;The vertical movement of the upright bar 11d may be implemented cross bar 11c and drive plug valve valve Bar 13 and plug valve spool 14 are in vertical motion, and cross bar 11c plays the role of lever herein, while at plug valve spool 14 It is in close state when minimum point, fully open state is in when plug valve spool 14 is at the highest notch, opening degree can be with Carry out the rotation process that handwheel 11f is controlled speed reducer according to the actual needs of operation.
In above-described embodiment, the gap location between the flame-proof thermal insulation material 4 and liner cylinder 5f and bottom bulkhead 5d is set Electric heating wire 6 is set, electric heating wire 6 is fixed on flame-proof thermal insulation material 4, is sealed in electric heating wire 6 and liner cylinder 5f and bottom There are gaps between head 5d, and in order to avoid two-maing ladle when electric heating, electric leakage accident occurs for liner.
In above-described embodiment, 2 lower part of bottom plate setting bottom bracket 1, the bottom bracket 1 and the bottom plate 2 of two-maing ladle of two-maing ladle Using welding or being bolted, the setting of bottom bracket 1 can be to avoid the presence due to 2 lower part melt transfer pipe 15 of bottom plate of two-maing ladle And it can not be placed on two-man ladle transportation vehicle, while two-maing ladle in order to which itself the stabilization of guaranteeing to two-man ladle can be considered to be connected by screw bolts Transport vehicle and bottom bracket 1.
In above-described embodiment, melt transfer pipe 15, the melt transfer pipe 15 and plug is arranged in the lower part plug valve valve seat 5e Using being welded to connect between valve base 5e, the melt transfer pipe 15 inside plug valve valve seat 5e and liner 5 by being connected to., work as plug Valve core 14 in the open state, can carry out out magnesium operation to two-maing ladle, by molten metal magnesium by melt transfer pipe 15 from It is pumped into liner 5 in electrolytic cell.
In above-described embodiment, setting manhole flange and blind flange 5a, the liquidometer mounting hole 5j at the top of the manhole 5b Interior setting liquidometer 16, primarily to measuring the height of liquid level in liner.
In above-described embodiment, referring to Fig. 5, the filter 7 includes air inlet pipe 7a, top flange 7b, outer housing 7c, exhaust Pipe 7d, filter screen 7e, flange in the bottom lid 7f, filter plate 7g, filtration barrel body 7h, pressure-measuring pipe 7j, pressure gauge 7k.The outer housing 7c Top flange 7b is arranged in top, and flange in the bottom lid 7f is arranged in the lower part outer housing 7c, and exhaust pipe 7d is respectively set in the side outer housing 7c With pressure-measuring pipe 7j;Air inlet pipe 7a is arranged in the top told top flange 7b, and filtration barrel body 7h is arranged in the lower part top flange 7b;The mistake Filter plate 7g is arranged in the filter cylinder bottom body 7h;Referring to Fig. 6, filter hole 7m is uniformly arranged on the filter plate 7g;The air inlet pipe 7a It is connected to the inside of filtration barrel body 7h;The gap of the filtration barrel body 7h and filter plate 7g and flange in the bottom lid 7f and outer housing 7c Interior filling filter screen 7e;The filter screen 7e is stainless steel material;The air inlet pipe 7a is connected to vacuum tube 8;The exhaust pipe It is connected to inside 7d and outer housing 7c;The top flange 7b and outer housing 7c are connected by screw bolts;The flange in the bottom lid 7f and Shell 7c body is connected by screw bolts.
In above-described embodiment, the plug valve valve rod 13, plug valve spool 14, plug valve valve seat 5e, conical seat 5g and valve The vertical center line of bar sealing flange 9 should keep on the same line, can enable plug valve valve rod 13 in vertical direction Accurate motion, while 14 outer surface of plug valve spool can accurately be bonded with plug valve valve seat 5e inner surface and realize preferable leakproofness Energy.
In above-described embodiment, perforative valve-rod cavity up and down is set referring to Fig. 7, at 9 vertical centre of valve stem seal flange Conical sealing face 9c is arranged in 9a, 9 bottom of valve stem seal flange, and bolt hole 9b, valve-rod cavity 9a is arranged in 9 top surface of valve stem seal flange Setting can guarantee the relative motion of valve stem seal flange 9 Yu plug valve valve rod 13.
In above-described embodiment, the bottom bulkhead 5c and liner cylinder 5f and top end socket 5c and between liner cylinder 5f Using welded connecting;The lid 12 of two-maing ladle, top end socket 5c and shell 3 of two-maing ladle are connected by screw bolts, it is ensured that the day of liner 5 Often replacement and maintenance;Described two-man ladle uses clamping bolts or welded connection between bottom plate 2 and shell 3 of two-maing ladle;The cone is close It seals between seat 5g and top end socket 5c using welded connecting;Connected between the plug valve valve seat 5e and bottom bulkhead 5c using welding It connects.
In above-described embodiment, the conical seat 5g is connected by screw bolts with valve stem seal flange 9, can be by right Bolt tightens degree to control the compaction of airtight and watertight padding 10 between conical seat 5g and valve stem seal flange 9, from And to effectively being sealed at this, but to guarantee that plug valve valve rod 13 can be realized vertical movement and be unlikely in stuck state.
In above-described embodiment, connecting flange 17 is set, convenient for the day of melt transfer pipe 15 in the middle part of the melt transfer pipe 15 Often maintenance replacement, the melt transfer pipe 15 and connecting flange adopt 17 with stainless steel material resistant to high temperature, in high-temperature molten metal There is preferable corrosion resistance under the contact of magnesium, can to avoid as corrosion and caused by melt reveal accident.
In above-described embodiment, the liner 5, plug valve valve rod 13, plug valve spool 14 and conical seat 5g use resistance to height The stainless steel material of temperature has preferable corrosion resistance under the contact of high-temperature molten metal magnesium, can to avoid due to corrosion and Caused by melt reveal accident.
Working principle of the present invention is as follows: before magnesium operation out by electric heating wire be powered to the liner two-mand ladle into Row preheating after preheating reaches assigned temperature, is reliably fixed on lifting to the two-man ladle transportation vehicle that will two-man ladle and is transported at electrolytic cell Carry out out magnesium operation.It is existing when magnesium operation out to close plug valve spool, liner inside vacuumize by vacuum tube straight Reach specified negative pressure value to liner internal negative pressure, melt transfer pipe is inserted into the molten metal magnesium of electrolytic cell, while controlling plug Valve control device opens plug valve spool, and the negative pressure being previously formed in liner at this time can quickly extract magnesium liquid, in this process Middle vacuum tube should continue to provide negative pressure, to guarantee smoothly completing for whole process.When the liquidometer at top of two-maing ladle shows that liquid level reaches When to specified altitude assignment, plug valve is closed, while removing is external in the vacuum line for vacuum tube of two-maing ladle.To two-man ladle at this time, it is next to be transported to The operation that molten metal magnesium of two-maing ladle is discharged is carried out at the equipment of process, only need to open plug valve spool of two-maing ladle can be realized the operation, It at this time can also be by adjusting the discharge rate of interior melt of two-maing ladle to the control of plug valve spool.When two-maing ladle, interior melt is completely exhausted out Afterwards, can directly carry out next round goes out magnesium operation.
Transfer tasks are carried out using the molten metal magnesium that above-mentioned two-maing ladle carries out electrolysis of magnesium chloride generation, warm is Be lifted into two-man ladle transport vehicle or other equipment before preheated, do not need to occupy the available of two-man ladle transportation vehicle or other equipment Time, the time of this process saving account for about the 70%-80% of traditional magnesium operation of two-maing ladle out.The function that cut-offs of plug valve spool can be realized The quick extraction of molten metal magnesium greatly reduced melt so that the plugging rate of melt transfer pipe reduces 70-80% more in the past The maintenance cost of transfer pipe.This advantage then becomes apparent in the highlands of low atmospheric pressure.Table 1 is provided by the invention two-mans ladle Compared with the main indicator that tradition is two-mand ladle.
Table 1
Index Single operation average time (minute) Liner volume (cubic meter) Liner internal negative pressure value (MPa) when operation
Tradition is two-mand ladle 40 2-3 0.02-0.03
The present invention two-mans ladle 10 5-6 0.04-0.06
The High aititude transfer vehicle-mounted device of two-maing ladle of molten metal magnesium of the invention is not limited to the above specific embodiment and is carried out Description, also within protection scope of the present invention to the replacements of the conventional techniques of certain technical characteristics.

Claims (16)

1. High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: including bottom bracket, bottom plate of two-maing ladle, two-man ladle Shell, liner, vacuum tube, plug valve control mechanism, lid of two-maing ladle, plug valve valve rod, plug valve spool, melt transfer pipe and liquidometer;? Bottom plate of two-maing ladle is arranged in outer casing bottom of two-maing ladle;In interior of shell setting liner of two-maing ladle;The liner include manhole flange and blind flange, Manhole, top end socket, bottom bulkhead, plug valve valve seat, liner cylinder, conical seat, flange, liquidometer mounting hole;It is described Bottom bulkhead is arranged in liner cylinder body bottom, and plug valve valve seat is arranged in the bottom bulkhead lower part;At the top of being arranged at the top of liner cylinder End socket, the top end socket are set to shell upper of two-maing ladle, and manhole, liquidometer mounting hole and circle is arranged in top end socket top Conical sealing seat;Flange is set at the top of the conical seat;Lid of two-maing ladle is arranged in top end socket top;The lid of two-maing ladle Plug valve control mechanism is arranged in top and shell exterior of two-maing ladle;Valve stem seal method is arranged in the conical seat and flange top Airtight and watertight padding is arranged between the valve stem seal flange and conical seat in orchid;It is arranged on the manhole flange and blind flange Vacuum tube, the end of the vacuum tube are arranged filter, are connected to inside the other end and liner of the vacuum tube;The lid of two-maing ladle Flame-proof thermal insulation material is set between the top end socket;Two-man ladle shell and the setting fire resisting guarantor between bottom plate and liner that two-mans ladle Adiabator is equipped with gap between the refractory material and liner;The plug valve valve rod passes through the conical seat, sealing is filled out Material and valve stem seal flange, there are gaps between the plug valve valve rod and conical seat and valve stem seal flange;The plug Plug valve spool is arranged in valve stem bottom.
2. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the plug valve Control mechanism includes shaft, support base, cross bar, upright bar, speed reducer, speed reducer handwheel;Support base setting is covered two-maing ladle; The speed reducer setting is being two-mand ladle on shell;The output end of speed reducer is arranged in the upright bar;The speed reducer handwheel setting exists The input terminal of speed reducer;The middle part of the cross bar and both ends setting shaft connect respectively with support base, plug valve valve rod and upright bar and It may be implemented mutually to rotate each other.
3. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the fire resisting Electric heating wire is arranged in gap location between thermal insulation material and liner cylinder and bottom bulkhead, and the electric heating wire is fixed on fire resisting guarantor On adiabator, gap is equipped between the electric heating wire and liner cylinder and bottom bulkhead.
4. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: described to two-man ladle Bottom bracket is arranged in bottom plate lower part, and the bottom bracket using welding or is bolted with bottom plate of two-maing ladle.
5. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the plug valve Melt transfer pipe is arranged in valve seat lower part, using welded connecting, the melt transfer between the melt transfer pipe and plug valve valve seat Pipe inside plug valve valve seat and liner by being connected to.
6. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the manhole Manhole flange and blind flange is arranged in top;Liquidometer is set in the liquidometer mounting hole.
7. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the filtering Device include air inlet pipe, top flange, outer housing, exhaust pipe, filter screen, flange in the bottom lid, filter plate, filtration barrel body, pressure-measuring pipe, Pressure gauge;Top flange is set at the top of the outer housing, and flange in the bottom lid is arranged in outer housing lower part, and outer housing side is respectively set Exhaust pipe and pressure-measuring pipe;Air inlet pipe is arranged in told top flange top, and filtration barrel body is arranged in top flange lower part;The cartridge filter Filter plate is arranged in body bottom;Filter hole is uniformly arranged on the filter plate;The air inlet pipe is connected to the inside of filtration barrel body;Institute It states and fills filter screen in the gap of filtration barrel body and filter plate and flange in the bottom lid and outer housing;The filter screen is stainless steel Matter;The air inlet pipe is connected to vacuum tube;It is connected to inside the exhaust pipe and outer housing;The top flange and outer housing use It is bolted;The flange in the bottom lid and outer housing are connected by screw bolts.
8. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the plug valve Valve rod, plug valve spool, plug valve valve seat, conical seat and valve stem seal flange vertical center line should be maintained at same straight line On.
9. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the valve rod Perforative valve-rod cavity up and down is set at sealing flange vertical centre, and conical sealing face, valve rod is arranged in valve stem seal flange base Bolt hole is arranged in sealing flange top surface.
10. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: in described Using welded connecting between gallbladder cylinder and bottom bulkhead and top end socket.
11. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the lift Backpack cover, top end socket and shell of two-maing ladle are connected by screw bolts;It is described two-man ladle be connected by screw bolts between bottom plate and shell of two-maing ladle or It is welded to connect.
12. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the circle Using welded connecting between conical sealing seat and the top end socket;Using weldering between the plug valve valve seat and the bottom bulkhead It connects in succession.
13. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the plug The outer surface of valve core and the inner surface of plug valve valve seat are cone or hemispherical.
14. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: the circle Conical sealing seat is connected by screw bolts with valve stem seal flange.
15. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: described molten Connecting flange is set in the middle part of body transfer pipe, and the connecting flange and melt transfer pipe use stainless steel material resistant to high temperature.
16. High aititude according to claim 1 shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium, it is characterised in that: in described Gallbladder, plug valve valve rod, plug valve spool and conical seat use stainless steel material resistant to high temperature.
CN201710377493.4A 2017-05-25 2017-05-25 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium Pending CN108941524A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710377493.4A CN108941524A (en) 2017-05-25 2017-05-25 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710377493.4A CN108941524A (en) 2017-05-25 2017-05-25 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium

Publications (1)

Publication Number Publication Date
CN108941524A true CN108941524A (en) 2018-12-07

Family

ID=64494088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710377493.4A Pending CN108941524A (en) 2017-05-25 2017-05-25 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium

Country Status (1)

Country Link
CN (1) CN108941524A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111979564A (en) * 2020-09-01 2020-11-24 包头市金为达稀土材料有限公司 Constant-temperature table bag for vacuum suction injection of liquid rare earth metal
CN112176362A (en) * 2020-05-19 2021-01-05 金昆仑锂业有限公司 Multifunctional lithium discharging ladle for lithium electrolytic tank and lithium pumping and discharging method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001098004A1 (en) * 2000-06-22 2001-12-27 Hoei Shokai Co., Ltd Molten metal feeding method, molten metal feeding system, molten aluminum producing method, aluminum die-cast product producing method, car manufacturing method, transportation vehicle, container, and molten metal feeding device
CN101456072A (en) * 2007-12-11 2009-06-17 贵阳铝镁设计研究院 Method and device for controlling the switch of ladle suction-port
CN102485962A (en) * 2010-12-01 2012-06-06 沈阳铝镁设计研究院有限公司 Vacuum ladle used for pumping crude magnesium
CN202263909U (en) * 2011-09-07 2012-06-06 深圳市鼎正鑫科技有限公司 Novel transition tundish of magnesium alloy continuous casting system
CN203144533U (en) * 2013-03-30 2013-08-21 青海昊瑞金属科技有限公司 Dust collecting device with matched magnesium vacuum ladle
CN205323429U (en) * 2015-11-30 2016-06-22 金川集团股份有限公司 A vacuum filters device for liquid magnesium vacuum ladle
CN206732114U (en) * 2017-05-25 2017-12-12 青海北辰科技有限公司 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001098004A1 (en) * 2000-06-22 2001-12-27 Hoei Shokai Co., Ltd Molten metal feeding method, molten metal feeding system, molten aluminum producing method, aluminum die-cast product producing method, car manufacturing method, transportation vehicle, container, and molten metal feeding device
US20040089987A1 (en) * 2000-06-22 2004-05-13 Toru Kodama Molten metal feeding method, molten metal feeding system, molten aluminum producing method, aluminum die-cast producing method, car manufacturing method, transportation vehicle, container, and molten metal feeding device
CN101456072A (en) * 2007-12-11 2009-06-17 贵阳铝镁设计研究院 Method and device for controlling the switch of ladle suction-port
CN102485962A (en) * 2010-12-01 2012-06-06 沈阳铝镁设计研究院有限公司 Vacuum ladle used for pumping crude magnesium
CN202263909U (en) * 2011-09-07 2012-06-06 深圳市鼎正鑫科技有限公司 Novel transition tundish of magnesium alloy continuous casting system
CN203144533U (en) * 2013-03-30 2013-08-21 青海昊瑞金属科技有限公司 Dust collecting device with matched magnesium vacuum ladle
CN205323429U (en) * 2015-11-30 2016-06-22 金川集团股份有限公司 A vacuum filters device for liquid magnesium vacuum ladle
CN206732114U (en) * 2017-05-25 2017-12-12 青海北辰科技有限公司 High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176362A (en) * 2020-05-19 2021-01-05 金昆仑锂业有限公司 Multifunctional lithium discharging ladle for lithium electrolytic tank and lithium pumping and discharging method thereof
CN111979564A (en) * 2020-09-01 2020-11-24 包头市金为达稀土材料有限公司 Constant-temperature table bag for vacuum suction injection of liquid rare earth metal
CN111979564B (en) * 2020-09-01 2022-12-06 包头市金为达稀土材料有限公司 Constant-temperature table bag for vacuum suction injection of liquid rare earth metal

Similar Documents

Publication Publication Date Title
CN110238356B (en) Melt pouring device and method for aluminum-lithium alloy DC casting
CN105334138B (en) The fused salt infiltration experimental provision of MSR carbon materials
CN108941524A (en) High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium
CN206732114U (en) High aititude shifts the vehicle-mounted device of two-maing ladle of molten metal magnesium
CN104946904A (en) Industrial-grade metal lithium refining equipment and refining method
CN201046984Y (en) Alloy smelting furnace
CN203440069U (en) Fusion furnace for preparing fused salt
CN102485962B (en) Vacuum ladle used for pumping crude magnesium
CN108941514A (en) A kind of casting method for large-scale corrosion resistant aluminium magnesium alloy component
CN105772678A (en) Magnesium and magnesium alloy quantitative casting furnace
CN211564513U (en) Device for preparing rare earth magnesium alloy powder
CN207143346U (en) A kind of energy-saving aluminium liquid vacuum ladle
CN214300290U (en) Gas protection device in electroslag remelting refining process
CN214877236U (en) Metal lithium storage device
CN209736619U (en) Pneumatic casting ladle for molten aluminum transfer casting
CN202508518U (en) Explosion-proof storage tank
CN209588712U (en) Reduction furnace high position automatic charging device
CN105177318B (en) Reduction distillation method produces the high-temperature sealing structure of titanium sponge
CN218886456U (en) Novel steel slag hot-disintegrating tank drainage control device
CN207727161U (en) A kind of device preparing cast metals
CN201309897Y (en) Benzyl chloride continuous chlorination automatic control device
CN204461052U (en) One rises liquid melting furnace automatically
CN216741894U (en) Negative pressure filling type energy storage cavity
CN218402705U (en) Electrolytic aluminum production seals utmost point material hoisting device
CN211727439U (en) Coreless heating low-pressure casting furnace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181207