CN108868835A - Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel - Google Patents

Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel Download PDF

Info

Publication number
CN108868835A
CN108868835A CN201810617701.8A CN201810617701A CN108868835A CN 108868835 A CN108868835 A CN 108868835A CN 201810617701 A CN201810617701 A CN 201810617701A CN 108868835 A CN108868835 A CN 108868835A
Authority
CN
China
Prior art keywords
steel side
buried steel
side waterstop
tunnel
waterstop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810617701.8A
Other languages
Chinese (zh)
Inventor
周玉亮
赵西民
张华�
刘志强
江良雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201810617701.8A priority Critical patent/CN108868835A/en
Publication of CN108868835A publication Critical patent/CN108868835A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention belongs to tunnel construction technical fields, reinforcement means is installed more particularly to buried steel side waterstop in a kind of short abutment wall in tunnel, it solves buried steel side waterstop in existing tunnel to be not fixed firmly, the problem of being easily distorted, positioning and damage, its poor sealing performance caused not can guarantee traffic safety in construction quality and tunnel.Buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel of the present invention, it is easy to operate, rapid, firm, operation is convenient and safe, sizing, assembles fastly, material is simple, the problem of can effectively solve buried steel side waterstop in existing to be not fixed firmly, being easily distorted, positioning and damage, cause its sealing performance that cannot give full play to, it is applied widely, there is certain promotional value and application value.

Description

Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel
Technical field
The invention belongs to tunnel construction technical fields, and in particular to buried steel side waterstop in a kind of short abutment wall in tunnel Reinforcement means is installed.
Background technique
Currently, generally being used in the design of Railway Tunnel guarded drainage longitudinal direction construction joint:In bury rubber watertight strip+ The composite water-proof plate structure of back patch waterstop, the quality of engineering construction quality directly influence the operation security in tunnel later period.
In terms of the traffic-operating period in the tunnel to have come into operation from the current country, the phenomenon that percolating water, is still had, and is especially concentrated Longitudinal construction joint position of short abutment wall and two linings in tunnel.Through analyzing, in short abutment wall, the embedded depth of buried steel side waterstop is not One, the distortion of steel side is to influence the matter of utmost importance of installation quality, there is the normal use of equipment in the traffic safety and hole to tunnel It seriously affects.The mature technology that buried steel side waterstop is installed still without at present.Existing installation, which is reinforced, usually utilizes stopper mould Plate is fixed, since stopper template is fixed difficult, is not connected firmly, cause in buried steel side waterstop turned round during casting concrete Song, deformation, positioning, even damage, it is damaged the problems such as, cause its sealing performance that cannot give full play to, seriously affect water-stagnating effect.
Summary of the invention
The present invention is not fixed firmly to solve buried steel side waterstop in existing tunnel, is easily distorted, positioning and damage, The problem of causing its poor sealing performance not can guarantee traffic safety in construction quality and tunnel, and then provide a kind of short side in tunnel Buried steel side waterstop installs reinforcement means in wall.
The present invention is achieved through the following technical solutions:Waterstop installation in buried steel side is reinforced in a kind of short abutment wall in tunnel Method includes the following steps:
S1. anchor bar is arranged in the position on the first branch face at tunnel both ends and apart from 1~2 meter of inverted arch end;
S2. lower layer's reinforcing bar of inverted arch is bound after installation back patch waterstop on the tunnel face Chu Zhi;
S3. the buried steel side waterstop along the short abutment wall length direction placement in tunnel, buried steel side waterstop is close to anchoring steel by The vertical clamp in one end of muscle, vertical fixture are connect by wirerope with anchor bar, and wirerope in vertical fixture and It is provided with cord holder between anchor bar, adjusts cord holder, wirerope is tightened, buried steel side waterstop is in pulling force effect in Lower guarantee is along the straight of tunnel direction;
S4. after the top bars for binding inverted arch, the installation site absolute altitude of buried steel side waterstop, utilizes mutual cooperation in Horizontal fixture, horizontal fixture fixing card and fixing card hangs muscle by length direction of the buried steel side waterstop along tunnel fix, The lower steel plate of buried steel side waterstop is fixed in the altitude range of short abutment wall in so that;
S5. the flatness and absolute altitude of buried steel side waterstop repeat step S3 and S4 if any not being inconsistent in repetition measurement, buried in The fixation of steel side waterstop meets specification and design requirement;
S6. inverted arch concrete is poured, after inverted arch concrete strength is met the requirements, removes horizontal fixture, longitudinal fixture and stringing Device simultaneously gives over to the spare of next ring inverted arch;
S7. carry out the reinforcing bar binding of the short abutment wall in tunnel, formwork and pour, so far in the lower half of buried steel side waterstop be cast in In short abutment wall.
Horizontal fixture top is arranged at intervals with multiple horizontal fixture fixing cards, is connected with down eight at the top of horizontal fixture fixing card The fixing card hangs muscle of word, fixing card hangs muscle are fixed on the exposed steel bar of short abutment wall and inverted arch.
Horizontal fixture is that the symmetrically arranged angle steel in buried steel side waterstop two sides, horizontal fixture are fixed in the horizontal direction in In on the upper layer steel plate of buried steel side waterstop.
Horizontal fixture fixing card is the steel plate at buried steel side waterstop both ends in being symmetricly set on, the phase on two pieces of steel plate top It is provided with bolt hole with position, is connected with bolt in bolt hole, enables to two blocks of steel plate clamping steel plates to stop by tightening bolt Water band.
The absolute altitude of the anchor bar middle line absolute altitude of buried steel side waterstop horizontally in is identical.
Vertical fixture is two blocks of steel plates at buried steel side waterstop both ends in being symmetricly set on, and the length of vertical fixture is greater than In buried steel side waterstop width, and vertical fixture both ends exceed in the position of buried steel side sealing bandwidth have spiral shell Keyhole, bolt hole realize the clamping of the buried steel side waterstop of centering by the cooperation with bolt.
The specified features and beneficial effect that the present invention has compared with prior art are:
Buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel of the present invention, easy to operate, rapid, firm, Operation is convenient and safe, sizing, assembles fastly, and material is simple, can effectively solve buried steel side waterstop in existing and is not fixed firmly, Yi Fa The problem of giving birth to distortion, positioning and damage, causing its sealing performance that cannot give full play to, it is applied widely, there is certain popularization Value and application value.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention.
In figure:The exposed steel bar of 1- short abutment wall and inverted arch, 2- horizontal fixture, 3- horizontal fixture fixing card, 4- fixing card are hung Muscle, the longitudinal direction 5- construction joint, the vertical fixture of 6-, 7- wirerope, 8- cord holder, 9- anchor bar, buried steel side waterstop in 10-, 11- inverted arch.
Specific embodiment
The present invention is further elaborated referring to Fig.1, waterstop installation in buried steel side is reinforced in a kind of short abutment wall in tunnel Method includes the following steps:
S1. anchor bar 9 is arranged in the position on the first branch face at tunnel both ends and apart from 1~2 meter of 11 end of inverted arch;
S2. lower layer's reinforcing bar of inverted arch 11 is bound after installation back patch waterstop on the tunnel face Chu Zhi;
S3. the buried steel side waterstop 10 along the short abutment wall length direction placement in tunnel, buried steel side waterstop 10 is close to anchor by Gu one end of reinforcing bar 9 is clamped with vertical fixture 6, vertical fixture 6 is connect by wirerope 7 with anchor bar 9, and wirerope 7 exists It is provided with cord holder 8 between vertical fixture 6 and anchor bar 9, cord holder 8 is adjusted, wirerope 7 is tightened, the buried steel side in Waterstop 10 guarantees under a stretching force along the straight of tunnel direction;
S4. after the top bars for binding inverted arch 11, the installation site absolute altitude of buried steel side waterstop 10 in, using mutual Horizontal fixture 2, horizontal fixture fixing card 3 and the fixing card hangs muscle 4 of the cooperation length of buried steel side waterstop 10 along tunnel by Direction is fixed so that in the lower steel plate of buried steel side waterstop 10 be fixed in the altitude range of short abutment wall;
S5. the flatness and absolute altitude of buried steel side waterstop 10 repeat step S3 and S4 if any not being inconsistent in repetition measurement, bury in The fixation of formula steel side waterstop 10 meets specification and design requirement;
S6. inverted arch concrete is poured, after inverted arch concrete strength is met the requirements, removes horizontal fixture 2, longitudinal fixture 6 and tight Line device 8 simultaneously gives over to the spare of next ring inverted arch 11;
S7. carry out the reinforcing bar binding of the short abutment wall in tunnel, formwork and pour, so far in the lower half of buried steel side waterstop 10 pour In short abutment wall.
2 top of horizontal fixture is arranged at intervals with multiple horizontal fixture fixing cards 3, is connected at the top of horizontal fixture fixing card 3 The fixing card hangs muscle 4 of eight words, fixing card hangs muscle 4 are fixed on the exposed steel bar 1 of short abutment wall and inverted arch.Horizontal fixture 2 be In the 10 symmetrically arranged angle steel in two sides of buried steel side waterstop, horizontal fixture 2 be fixed in the horizontal direction in buried steel side sealing On upper layer steel plate with 10.Horizontal fixture fixing card 3 is the steel plate at waterstop 10 both ends in buried steel side in being symmetricly set on, two pieces The same position on steel plate top is provided with bolt hole, is connected with bolt in bolt hole, enables to two blocks of steel by tightening bolt Buried steel side waterstop 10 during board is tight.The absolute altitude of the anchor bar 9 middle line mark of buried steel side waterstop 10 horizontally in It is high identical.Vertical fixture 6 is two blocks of steel plates at waterstop 10 both ends in buried steel side in being symmetricly set on, the length of vertical fixture 6 The width of buried steel side waterstop 10 in being greater than, and vertical 6 both ends of fixture exceed in 10 width of buried steel side waterstop position Bolt hole is had, bolt hole realizes the clamping of the buried steel side waterstop 10 of centering by the cooperation with bolt.
5 position of longitudinal construction joint of the short abutment wall in tunnel and two linings is arranged in the present invention buried steel side waterstop 10 by, i.e., In the lower half portion of buried steel side waterstop 10 be located in short abutment wall, in the top half of buried steel side waterstop 10 be located at tunnel Two lining concrete in.Buried steel side waterstop 10 is easy to appear positioning phenomenon when fixed due in, so that the mark of waterstop Height, which is unable to get, to be effectively ensured, while the flatness of waterstop along its length is influenced by more serious.It is buried due in Also there are certain methods and device for its accurate positioning in the extensive use of steel side waterstop 10, but all with steel side waterstop Pouring together makes it be unable to get effective popularization in concrete, lacking the advantage recycled.It is related in the present invention Horizontal fixture 2, longitudinal fixture 6, horizontal fixture fixing card 3, fixing card hangs muscle 4 and cord holder 8 are recyclable spare part.

Claims (6)

1. buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel, which is characterized in that include the following steps:
S1. on the first branch face at tunnel both ends and apart from inverted arch(11)Anchor bar is arranged in the position that 1~2 meter of end(9);
S2. inverted arch is bound after installation back patch waterstop on the tunnel face Chu Zhi(11)Lower layer's reinforcing bar;
S3. the buried steel side waterstop along the short abutment wall length direction placement in tunnel(10), the buried steel side waterstop by(10)It leans on Nearly anchor bar(9)The vertical fixture in one end(6)It clamps, vertical fixture(6)Pass through wirerope(7)With anchor bar(9)Even It connects, and wirerope(7)In vertical fixture(6)With anchor bar(9)Between be provided with cord holder(8), adjust cord holder(8), by steel Cord(7)It tightens, the buried steel side waterstop in(10)Guarantee under a stretching force along the straight of tunnel direction;
S4. inverted arch is bound(11)Top bars after, the buried steel side waterstop in(10)Installation site absolute altitude, utilize Mutually matched horizontal fixture(2), horizontal fixture fixing card(3)And fixing card hangs muscle(4)The buried steel side waterstop by(10) Length direction along tunnel is fixed so that in buried steel side waterstop(10)Lower steel plate be fixed on the altitude range of short abutment wall It is interior;
S5. buried steel side waterstop in repetition measurement(10)Flatness and absolute altitude repeat step S3 and S4 if any not being inconsistent, until in Buried steel side waterstop(10)Fixation meet specification and design requirement;
S6. inverted arch concrete is poured, after inverted arch concrete strength is met the requirements, removes horizontal fixture(2), longitudinal fixture(6) And cord holder(8)And give over to next ring inverted arch(11)It is spare;
S7. carry out the reinforcing bar binding of the short abutment wall in tunnel, formwork and pour, so far in buried steel side waterstop(10)Lower half pour It builds in short abutment wall.
2. buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel according to claim 1, feature exists In horizontal fixture(2)Top is arranged at intervals with multiple horizontal fixture fixing cards(3), horizontal fixture fixing card(3)Top is connected with The fixing card hangs muscle of eight words(4), fixing card hangs muscle(4)It is fixed on the exposed steel bar of short abutment wall and inverted arch(1)On.
3. buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel according to claim 2, feature exists In horizontal fixture(2)It is the buried steel side waterstop in(10)The symmetrically arranged angle steel in two sides, horizontal fixture(2)Along level side The buried steel side waterstop in being fixed on(10)Upper layer steel plate on.
4. buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel according to claim 2, feature exists In horizontal fixture fixing card(3)For buried steel side waterstop in being symmetricly set on(10)The steel plate at both ends, two pieces of steel plate top Same position is provided with bolt hole, is connected with bolt in bolt hole, enables to bury in two pieces of steel plate clampings by tightening bolt Formula steel side waterstop(10).
5. buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel according to claim 1, feature exists In anchor bar(9)Absolute altitude in buried steel side waterstop(10)Middle line absolute altitude horizontally is identical.
6. buried steel side waterstop installs reinforcement means in the short abutment wall in a kind of tunnel according to claim 1, feature exists In vertical fixture(6)For buried steel side waterstop in being symmetricly set on(10)Two blocks of steel plates at both ends, vertical fixture(6)Length Spend buried steel side waterstop in being greater than(10)Width, and vertical fixture(6)Both ends exceed in buried steel side waterstop(10)It is wide The position of degree has bolt hole, and bolt hole realizes the buried steel side waterstop of centering by the cooperation with bolt(10)Folder Tightly.
CN201810617701.8A 2018-06-15 2018-06-15 Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel Pending CN108868835A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810617701.8A CN108868835A (en) 2018-06-15 2018-06-15 Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810617701.8A CN108868835A (en) 2018-06-15 2018-06-15 Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel

Publications (1)

Publication Number Publication Date
CN108868835A true CN108868835A (en) 2018-11-23

Family

ID=64338935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810617701.8A Pending CN108868835A (en) 2018-06-15 2018-06-15 Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel

Country Status (1)

Country Link
CN (1) CN108868835A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984240A (en) * 2019-11-19 2020-04-10 中冶天工集团有限公司 Fixing device and fixing method for buried steel-edged rubber water stop in underground structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202578718U (en) * 2012-05-18 2012-12-05 中铁十二局集团第七工程有限公司 Locating system for embedded part at construction joint between tunnel invert and secondary lining
JP2013044111A (en) * 2011-08-22 2013-03-04 Taisei Corp Water cutoff structure and construction method thereof
CN107143360A (en) * 2017-07-20 2017-09-08 中铁二局集团有限公司 A kind of short abutment wall waterstop fixing means in tunnel
CN206636587U (en) * 2017-03-15 2017-11-14 中铁十七局集团第一工程有限公司 Water stop installing device is buried in inverted arch
CN206753626U (en) * 2017-05-27 2017-12-15 中铁十七局集团第四工程有限公司 Steel side waterstop alignment system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013044111A (en) * 2011-08-22 2013-03-04 Taisei Corp Water cutoff structure and construction method thereof
CN202578718U (en) * 2012-05-18 2012-12-05 中铁十二局集团第七工程有限公司 Locating system for embedded part at construction joint between tunnel invert and secondary lining
CN206636587U (en) * 2017-03-15 2017-11-14 中铁十七局集团第一工程有限公司 Water stop installing device is buried in inverted arch
CN206753626U (en) * 2017-05-27 2017-12-15 中铁十七局集团第四工程有限公司 Steel side waterstop alignment system
CN107143360A (en) * 2017-07-20 2017-09-08 中铁二局集团有限公司 A kind of short abutment wall waterstop fixing means in tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984240A (en) * 2019-11-19 2020-04-10 中冶天工集团有限公司 Fixing device and fixing method for buried steel-edged rubber water stop in underground structure

Similar Documents

Publication Publication Date Title
CN109162296A (en) Single side formwork system and the construction method poured using system progress exterior wall
CN108086355A (en) Pre-buried channel flow installing and fixing method under cast-in-place piping lane traditional handicraft
CN109695473A (en) A kind of railway tunnel built-in groove channel fixing device and fixing means
CN102817324A (en) Construction method for quickly installing pot rubber bearing by using epoxy resin mortar
CN111692430B (en) Underwater repairing method for large-diameter HDPE pipeline
CN108868835A (en) Buried steel side waterstop installs reinforcement means in a kind of short abutment wall in tunnel
CN211547824U (en) Device for fixing flexible water stop
CN212563272U (en) Induced seam department steel limit rubber waterstop mounting structure of tunnel
CN209604088U (en) A kind of railway tunnel built-in groove channel fixing device
CN107401414B (en) Tunnel annular telescopic water stop fixing die and application method
CN210975898U (en) Prefabricated template system of basement outer wall post-cast strip
CN208949920U (en) Single side formwork system
CN208748862U (en) A kind of assembled heat insulation wall body structure
CN111119354A (en) Novel universal construction joint waterproof manufacturing method
CN216277925U (en) Tunnel stagnant water fixing device
CN206529907U (en) A kind of waterstop fixing device suitable for different wall thicknesses
CN206694045U (en) A kind of lining concrete in tunnel two-stage hinge upset self-locking combination steel end mould
CN208088145U (en) A kind of T beam flange plates cantilever bracket fixing device
CN206607610U (en) A kind of waterstop auxiliary positioning support
CN209011852U (en) A kind of lining plug of hinge-type two for fixing tunnel steel plate water stopper
CN215170084U (en) Be arranged in short side wall of tunnel to bury formula waterstop fixing device
CN205990627U (en) Bury waterstop in connected entrance and fixing and protection integrated device is installed
CN111271096A (en) Tunnel induced seam steel edge rubber water stop mounting structure and method
CN106808564B (en) Three-word buckle type box girder end sealing template and box girder end sealing method
CN216640570U (en) Sleeve of pre-stressed anchor cable of crown beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181123

RJ01 Rejection of invention patent application after publication