CN108867660A - Foundation pit support construction technology - Google Patents

Foundation pit support construction technology Download PDF

Info

Publication number
CN108867660A
CN108867660A CN201810938460.7A CN201810938460A CN108867660A CN 108867660 A CN108867660 A CN 108867660A CN 201810938460 A CN201810938460 A CN 201810938460A CN 108867660 A CN108867660 A CN 108867660A
Authority
CN
China
Prior art keywords
layer
layers
annular girder
steel
annular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810938460.7A
Other languages
Chinese (zh)
Other versions
CN108867660B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Gonggong Foundation Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810938460.7A priority Critical patent/CN108867660B/en
Publication of CN108867660A publication Critical patent/CN108867660A/en
Application granted granted Critical
Publication of CN108867660B publication Critical patent/CN108867660B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of foundation pit support construction technologies, it is characterized in that steel bearing column is arranged at foundation pit supporting construction center, pattern foundation pit supporting structure uses two-layer structure, one layer of supporting beam is set between one layer of annular girder and steel bearing column, steel lattice column is arranged in one layer of annular girder and one layer of supporting beam handover position, capping beam is set at the top of excavation slope, raker beam is set between capping beam and one layer of annular girder, two layers of supporting beam are set between two layers of annular girder and steel bearing column, waist rail is set in the middle part of excavation slope, and two layers are arranged two layers of supporting beam between annular girder and waist rail;Steel bearing column is higher by one layer of 1.5~1.8m of annular top surface of the beam, cable wire rope is arranged between steel bearing column and one layer of annular girder, steel bearing column protrudes into the following soil layer of basement bottom board.

Description

Foundation pit support construction technology
Technical field
The present invention relates to a kind of foundation pit support construction technologies, are suitable for building field.
Background technique
Since support beam span is very big when large span foundation pit support construction, supporting beam can bear very big pressure, if will Support beam section becomes larger can be very uneconomical, if supporting beam may go out under the effect of huge axle power using common support beam Now destroy.In order to reduce the axle power and moment of flexure of supporting beam, often in supporting beam following settings steel lattice column as supporting point, due to Weak soil is easy to appear Plastic Flow under external force, and steel lattice column is difficult in weak soil accurate positioning, and difficulty of construction is very big.And Steel lattice column will also anchor into soil layer, and steel lattice column length can be longer, and the cost is relatively high.Furthermore the presence of steel lattice column is to the earthwork Excavation can also be influenced.Not only safety had been can guarantee when how to solve foundation pit construction but also can easy to operate be the class that engineering staff faces Topic.
Summary of the invention
The present invention is to provide a kind of foundation pit support construction technology, and the traditional pattern foundation pit supporting structure security performance of solution is bad and operates not Convenient problem.
The present invention is using the more reasonable feature of annular beam stress, using annular girder as power transmission in foundation pit supporting construction Structure, and reduce in foundation pit supporting construction the dosage of steel lattice column as far as possible, on the one hand by space truss structure by part Vertical force is transferred to steel bearing column, and vertical force is passed to steel bearing column additionally by cable wire rope.
Steel bearing column is arranged at foundation pit supporting construction center in the present invention, and pattern foundation pit supporting structure uses two-layer structure, one layer of annular girder Diameter is 14~24m, and one layer of annular depth of beam is 600~650mm, width 300mm, between one layer of annular girder and steel bearing column One layer of supporting beam is set, and one layer of support depth of beam is 600~650mm, width 300mm, one layer of annular girder and one layer of supporting beam Join position and steel lattice column is set, capping beam is set at the top of excavation slope, and the depth of beam that bears down on one is 600~650mm, and width is 300mm is arranged one layer of supporting beam, raker beam is arranged between capping beam and one layer of annular girder between capping beam and one layer of annular girder, One layer of 1/4 circular arc of annular girder is arranged in along the 1/3 of circular arc direction or 2/3 in raker beam one end, and the setting of the raker beam other end is being pressed For top beam along its length at 1/4, diagonal brace depth of beam is 600~650mm, width 300mm;Two layers of annular girder diameter are 24~ 36m, two layers of annular depth of beam are 500~550mm, width 300mm, than one layer annular depth of beam of two layers of annular girder be high be because of Later layer annular girder bearing capacity, which is excavated, in two layers of soil layer is greater than one layer of annular girder.It is arranged between two layers of annular girder and steel bearing column Two layers of supporting beam, two layers of support depth of beam are 500~550mm, width 300mm, and two layers of annular girder and two layers of supporting beam join The not set steel lattice column in position, two layers of annular girder and two layers of supporting beam handover not set steel lattice column in position both can be convenient shoveling Waist rail can be arranged in construction again with saving construction cost, excavation slope middle part, and waist rail top mark height and waist rail top mark are high consistent, and waist rail height is 500~550mm, width 300mm, two layers are arranged two layers of supporting beam between annular girder and waist rail.Steel bearing column is higher by one layer of ring Cable wire rope, cable wire rope and one layer of annular girder drawknot node is arranged in 1.5~1.8m of ellbeam top surface between steel bearing column and one layer of annular girder It is uniformly distributed along one layer of annular girder circular arc.Steel bearing column protrudes into the following soil layer of basement bottom board to keep anchorage length, steel load Column bottom end is 1.5~1.7 times of the liftoff lower room bottom plate distance in steel load top end with a distance from basement bottom board.
The steel pipe that steel bearing column uses with a thickness of 15~18mm, steel pipe is interior to be reinforced every 0.5~0.7m setting steel plate, Join the rectangular preformed hole of position indwelling in steel bearing column and one layer of supporting beam or two layers of supporting beam, rectangular reserved hole depth is 100 ~120mm, width and length are identical as one layer of supporting beam or two layers of supporting beam, rectangular preformed hole bottom and top be respectively provided with steel every Temporary steel cladding plate is arranged in the rectangular preformed hole outside of plate, steel bearing column;One layer of supporting beam or two layers of branch during foundation pit construction The reinforcing bar of support beam is welded after protruding into rectangular preformed hole with steel diaphragm, and concrete is arranged in rectangular preformed hole.
Steel load column diameter carries out value according to foundation pit maximum span and excavation of foundation pit depth, and foundation pit maximum span is finger pressure Maximum distance of the top beam inner surface from opposite side capping beam inner surface.According to simulation analysis of computer as a result, steel load column diameter root According to 1 value of table, when foundation pit maximum span or excavation of foundation pit depth and 1 numerical value of table do not determine steel bearing column using interpolation method simultaneously Diameter.When longitudinal span and horizontal span are greater than 2, steel bearing column stress can mitigate, and can be held using reduction coefficient to steel Power column diameter is reduced, and when longitudinal span, which is greater than 1 with horizontal span, is less than or equal to 2, reduction coefficient uses 0.98, works as longitudinal direction When span and horizontal span are greater than 2 and are less than or equal to 2.3, reduction coefficient uses 0.96, when longitudinal span is greater than with horizontal span 2.3 and when being less than or equal to 2.6, reduction coefficient uses 0.94, when longitudinal span and horizontal span are greater than 2.6 and are less than or equal to 3, Reduction coefficient uses 0.92, and when longitudinal span is greater than 3 with horizontal span, reduction coefficient uses 0.9.Here horizontal span refers to The span in relatively large direction, longitudinal span refer to the span in relatively small direction.
1 steel bearing column diameter parameters of table
Construction procedure includes:
(1) construction steel bearing column;Steel bearing column is pressed into soil layer by hydraulic static piling;
(2) install one layer of annular girder, capping beam, one layer of supporting beam and raker beam reinforcing bar, install one layer of annular girder, bear down on one The template of beam, one layer of supporting beam and raker beam removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column, one layer of supporting beam Reinforcing bar protrude into after rectangular preformed hole and welded with the steel diaphragm of steel bearing column, the casting concrete in rectangular preformed hole, this Pour one layer of annular girder, capping beam, one layer of supporting beam and raker beam concrete again afterwards;
(3) tensioning cable wire rope;Using three-level tensioning, each grade be respectively 30% proof stress, 60% proof stress and 100% proof stress.
Tensioning platform is set up near steel bearing column, using each cable wire rope of intelligent tensioning equipment simultaneous tension, intelligence Drawing equipment includes jack, stretching oil pump, tensioning oil cylinder, computer control systems, sensor, and stretching oil pump controls tensioning Elongation, the installing of tensioning oil cylinder have the two-position two-way solenoid valve of hydraulic bridge, and hydraulic bridge controls the flow direction and flow of oil pressure, simultaneously There are one check valve in every group of tensioning oil cylinder, main function is can be fast in the short time when problem occurs for hydraulic tube etc. The function locking of tensioning oil cylinder, effective support of proof load are improved the safety of stretching process by speed.Electronic computer control System reflects the cable wire rope pressure intracavitary in tensioning cylinder force using cable wire rope stretching extension value variable signal as controlled parameter Strong variable signal acquires these signals by sensor, and passes the signal to computer control unit.Electronic computer Control centre is compared and calculates to signal immediately after receiving signal, when wherein certain controlled point has overproof possibility for discovery, Controller issues command signal at once, allows the two-position two-way solenoid valve generation of the point to act, hydraulic oil stream is closed, to promote this The tensioning oil cylinder of point rises or falls movement.
(4) reach design strength to one layer of annular girder, capping beam, one layer of supporting beam and raker beam concrete strength After 100%, the earthwork outside one layer of annular girder is excavated;The earthwork outside one layer of annular girder is excavated using tile and hierarchy, one layer of ring The earthwork outside ellbeam is divided into four pieces of excavations, excavates and uses symmetric mode, the additional stress generated when being excavated with reducing, and first piece The diagonal earthwork is excavated after having dug again;Stage excavation is with a thickness of 500~600mm;Earth excavation outside one layer of annular girder is to one The earthwork inside one layer of annular girder is excavated when half depth again, the earthwork inside one layer of annular girder is excavated using tile and hierarchy, and one layer The earthwork inside annular girder is divided into four pieces of excavations, and excavation excavates the diagonal earthwork after having dug using symmetric mode, first piece again;Point Layer excavates with a thickness of 500~600mm;One layer of annular girder is excavated again when earth excavation to half depth inside one layer of annular girder The remaining earthwork inside one layer of annular girder is finally excavated in the earthwork of external redundant again;
(5) install two layers of annular girder, waist rail, two layers of supporting beam reinforcing bar, install two layers of annular girder, waist rail, two layers of support The template of beam, removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column, and the reinforcing bar of two layers of supporting beam protrudes into rectangular reserved The steel diaphragm of Kong Houyu steel bearing column is welded, the casting concrete in rectangular preformed hole, hereafter pour again two layers of annular girder, Waist rail, two layers of supporting beam concrete;
(6) after two layers of annular girder, waist rail, two layers of supporting beam concrete strength reach the 100% of design strength, two are excavated The earthwork outside layer annular girder;The earthwork outside two layers of annular girder is excavated using tile and hierarchy, the earthwork outside two layers of annular girder It is divided into four pieces of excavations, excavation excavates the diagonal earthwork after having dug using symmetric mode, first piece again;Stage excavation is with a thickness of 500 ~600mm;The earthwork inside two layers of annular girder, two layers of ring are excavated when earth excavation to half depth outside two layers of annular girder again The earthwork inside ellbeam is excavated using tile and hierarchy, and the earthwork inside two layers of annular girder is divided into four pieces of excavations, is excavated using symmetrical Mode, first piece dug after excavate the diagonal earthwork again;Stage excavation is with a thickness of 500~600mm;Inside two layers of annular girder The earthwork of two layers of annular girder external redundant is excavated when earth excavation to half depth again;The basement of two layers of annular girder external range Bottom plate is divided into four pieces and is poured, and pours sequence and earth excavation sequence consensus, is i.e. is poured after first piece of earth excavation Build first piece of basement bottom board, other block basement bottom boards and so on;Steel plate water stopper is set between adjacent concrete block;
(7) it is excavated again after the basement bottom board to two layers of annular girder external range pours remaining inside two layers of annular girder The earthwork;The basement bottom board of two layers of annular girder internal range is divided into four pieces and is poured, and pours sequence and earth excavation sequence Unanimously, i.e., carry out pouring first piece of basement bottom board after first piece of earth excavation, other block basement bottom boards and so on; Steel plate water stopper is set between adjacent concrete block;
(8) reinforcing bar of sidewall of basement, template are installed and carries out casting concrete;
(9) supporting construction is removed, demolition of support structure uses double faced leather;First remove two layers of annular girder, waist rail, two Layer supporting beam;One layer of annular girder, capping beam, one layer of supporting beam and raker beam are removed again;Vertical hole can be used in supporting construction explosion Or angling hole.Blasting parameter is chosen by following experience:Hole depth is 0.7~0.8 depth of beam, and pitch-row is 0.56~0.8 depth of beam, is adopted When with quincunx cloth hole, pitch-row is 0.5~0.7 depth of beam;
(10) cable wire rope is removed;
(11) connection for cutting off one layer of supporting beam or two layers of support beam steel and steel bearing column, pulls out steel bearing column.Steel is held Power column can be with recycling and reusing, with save the cost.
The present invention has a safety feature, and constructing operation is convenient.
Detailed description of the invention
Fig. 1 is one layer of supporting construction schematic diagram, and Fig. 2 is two layers of supporting construction schematic diagram, and Fig. 3 is the signal of supporting construction facade Figure, Fig. 4 are that one layer of supporting construction excavates schematic diagram, and Fig. 5 is that two layers of supporting construction excavate schematic diagram.
1, steel bearing column, 2, cable wire rope, 3, one layers of annular girder, 4, steel lattice column, 5, one layers of supporting beam, 6, capping beam, 7, Raker beam, 8, two layers of annular girder, 9, two layers of supporting beam, 10, waist rail.
Specific embodiment
The present embodiment is described in detail below in conjunction with attached drawing.
Steel bearing column 1 is set at foundation pit supporting construction center, pattern foundation pit supporting structure uses two-layer structure, one layer of 3 diameter of annular girder For 14~24m, one layer of 3 height of annular girder is 600mm, and width 300mm is arranged one between one layer of annular girder 3 and steel bearing column 1 Layer supporting beam 5, one layer of 5 height of supporting beam are 600mm, width 300mm, and one layer of annular girder 3 and one layer of supporting beam 5 join position Steel lattice column 4 is set, capping beam 6 is set at the top of excavation slope, 6 height of capping beam is 600mm, width 300mm, capping beam 6 One layer of supporting beam 5 is set between one layer of annular girder 3, raker beam 7, raker beam 7 are set between capping beam 6 and one layer of annular girder 3 One layer of 31/4 circular arc of annular girder is arranged in along the 1/3 of circular arc direction or 2/3 in one end, and 7 other end of raker beam is arranged in capping beam 6 Along its length at 1/4,7 height of raker beam is 600mm, width 300mm;Two layers of 8 diameter of annular girder are 24m, two layers of annular 8 height of beam is 500mm, width 300mm.Two layers of supporting beam 9, two layers of support are set between two layers of annular girder 8 and steel bearing column 1 9 height of beam is 500mm, width 300mm, and two layers of annular girder 8 and two layers of supporting beam 9 join the not set steel lattice column 4 in position, base It cheats side slope middle and waist rail 10 is set, 10 height of waist rail is 500mm, and width 300mm is set between two layers of annular girder 8 and waist rail 10 Set two layers of supporting beam 9.Steel bearing column 1 is higher by one layer of annular girder, 3 top surface 1.6m, is arranged between steel bearing column 1 and one layer of annular girder 3 Cable wire rope 2, cable wire rope 2 are uniformly distributed with one layer of 3 drawknot node of annular girder along one layer of 3 circular arc of annular girder.Steel bearing column 1 protrudes into underground The following soil layer of room bottom plate, 1 bottom end of steel bearing column are 1 top of steel bearing column with a distance from basement bottom board with a distance from basement bottom board 1.6 again.
1 diameter of steel bearing column uses 0.95m, steel bearing column 1 using the steel pipe with a thickness of 16mm, in steel pipe every 0.5~ 0.7m setting steel plate is reinforced, rectangular pre- in steel bearing column 1 and one layer of supporting beam 5 or two layers of handover position indwelling of supporting beams 9 It boxes out, rectangular reserved hole depth is that 100mm, width and length are identical as one layer of supporting beam 5 or two layers of supporting beam 9, rectangular reserved Hole bottom and top are respectively provided with steel diaphragm, and temporary steel cladding plate is arranged outside the rectangular preformed hole of steel bearing column 1;In foundation pit construction mistake The reinforcing bar of one layer of supporting beam 5 or two layers of supporting beam 9 is welded after protruding into rectangular preformed hole with steel diaphragm in journey, rectangular preformed hole Interior setting concrete.
Construction procedure includes:
(1) construction steel bearing column 1;Steel bearing column 1 is pressed into soil layer by hydraulic static piling;
(2) reinforcing bar for installing one layer of annular girder 3, capping beam 6, one layers of supporting beam 5 and raker beam 7, installs one layer of annular girder 3, the template of 6, one layers of supporting beam 5 and raker beam 7 of capping beam removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column 1, The reinforcing bar of one layer of supporting beam 5 is protruded into after rectangular preformed hole and is welded with the steel diaphragm of steel bearing column 1, is poured in rectangular preformed hole Concrete is built, hereafter pours one layer of annular girder 3,6, one layers of supporting beam 5 of capping beam and 7 concrete of raker beam again;
(3) tensioning cable wire rope 2;Using three-level tensioning, each grade be respectively 30% proof stress, 60% proof stress and 100% proof stress.
Tensioning platform is set up near steel bearing column 1, using each cable wire rope 2 of intelligent tensioning equipment simultaneous tension, intelligence Tensioning equipment includes jack, stretching oil pump, tensioning oil cylinder, computer control systems, sensor, stretching oil pump control Elongation is drawn, the installing of tensioning oil cylinder has the two-position two-way solenoid valve of hydraulic bridge, and hydraulic bridge controls the flow direction and flow of oil pressure, together When in every group of tensioning oil cylinder there are one check valve, main function is can be in the short time when problem occurs for hydraulic tube etc. Rapidly by the function locking of tensioning oil cylinder, effective support of proof load improves the safety of stretching process.Electronic computer control System processed reflects that cable wire rope 2 is intracavitary in tensioning cylinder force using 2 stretching extension value variable signal of cable wire rope as controlled parameter Pressure change signal, these signals are acquired by sensor, and pass the signal to computer control unit.Electrometer Suan Ji control centre is compared and calculates to signal immediately after receiving signal, when wherein certain controlled point has overproof possibility for discovery When, controller issues command signal at once, allows the two-position two-way solenoid valve generation of the point to act, hydraulic oil stream is closed, to promote The tensioning oil cylinder of the point is set to rise or fall movement.
(4) reach design strength to one layer of annular girder 3,6, one layers of supporting beam 5 of capping beam and 7 concrete strength of raker beam After 100%, the earthwork outside one layer of annular girder 3 is excavated;The earthwork outside one layer of annular girder 3 is excavated using tile and hierarchy, and one layer The earthwork outside annular girder 3 is divided into four pieces of excavations, excavates and uses symmetric mode, the additional stress generated when being excavated with reducing, the One piece dug after excavate the diagonal earthwork again;Stage excavation is with a thickness of 500~600mm;Earth excavation outside one layer of annular girder 3 The earthwork inside one layer of annular girder 3 is excavated when to half depth again, the earthwork inside one layer of annular girder 3 is opened using tile and hierarchy It digs, the earthwork inside one layer of annular girder 3 is divided into four pieces of excavations, and excavation excavates diagonal again after having been dug using symmetric mode, first piece The earthwork;Stage excavation is with a thickness of 500~600mm;It is excavated again when earth excavation to half depth inside one layer of annular girder 3 One layer of annular girder, the 3 remaining earthwork in inside is finally excavated in the earthwork of one layer of 3 external redundant of annular girder again;
(5) reinforcing bar for installing 10, two layers of two layers of annular girder 8, waist rail supporting beam 9, installs two layers of annular girder 8, waist rail 10, two The template of layer supporting beam 9, removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column 1, and the reinforcing bar of two layers of supporting beam 9 protrudes into Steel diaphragm after rectangular preformed hole with steel bearing column 1 is welded, hereafter the casting concrete in rectangular preformed hole pours two again Layer 10, two layers of annular girder 8, waist rail 9 concrete of supporting beam;
(6) it after 10, two layers of two layers of annular girder 8, waist rail 9 concrete strength of supporting beam reach the 100% of design strength, opens Dig the earthwork outside two layers of annular girder 8;The earthwork outside two layers of annular girder 8 is excavated using tile and hierarchy, outside two layers of annular girder 8 The earthwork be divided into four pieces of excavations, excavate and use symmetric mode, first piece dug after excavate the diagonal earthwork again;Stage excavation thickness For 500~600mm;The soil inside two layers of annular girder 8 is excavated when earth excavation to half depth outside two layers of annular girder 8 again Square, the earthwork inside two layers of annular girder 8 is excavated using tile and hierarchy, and the earthwork inside two layers of annular girder 8 is divided into four pieces of excavations, is opened Dig use symmetric mode, first piece dug after excavate the diagonal earthwork again;Stage excavation is with a thickness of 500~600mm;To two layers of ring The earthwork of two layers of 8 external redundant of annular girder is excavated when earth excavation to half depth inside ellbeam 8 again;Outside two layers of annular girder 8 The basement bottom board of portion's range is divided into four pieces and is poured, and pours sequence and earth excavation sequence consensus, i.e. first piece of earthwork is opened Carry out pouring first piece of basement bottom board after digging, other block basement bottom boards and so on;It is set between adjacent concrete block Set steel plate water stopper;
(7) basement bottom board to two layers of 8 external range of annular girder is excavated again after pouring and is remained inside two layers of annular girder 8 The remaining earthwork;The basement bottom board of two layers of 8 internal range of annular girder is divided into four pieces and is poured, and it is suitable with earth excavation to pour sequence Sequence is consistent, i.e. carries out pouring first piece of basement bottom board after first piece of earth excavation, other block basement bottom boards successively class It pushes away;Steel plate water stopper is set between adjacent concrete block;
(8) reinforcing bar of sidewall of basement, template are installed and carries out casting concrete;
(9) supporting construction is removed, demolition of support structure uses double faced leather;First remove two layers of annular girder 8, waist rail 10, two layers of supporting beam 9;One layer of annular girder 3,6, one layers of supporting beam 5 of capping beam and raker beam 7 are removed again;Supporting construction explosion can Using vertical hole or angling hole.Blasting parameter is chosen by following experience:Hole depth is 0.75 depth of beam, and pitch-row is 0.6 depth of beam, is adopted When with quincunx cloth hole, pitch-row is 0.6 depth of beam;
(10) cable wire rope 2 is removed;
(11) connection for cutting off one layer of supporting beam 5 or two layers of supporting beam 9 reinforcing bar and steel bearing column 1, pulls out steel bearing column 1.

Claims (1)

1. a kind of foundation pit supporting construction, it is characterized in that steel bearing column is arranged at foundation pit supporting construction center, pattern foundation pit supporting structure uses two Layer structure, one layer of annular girder diameter are 14~24m, and one layer of annular depth of beam is 600~650mm, width 300mm, one layer of ring One layer of supporting beam be set between ellbeam and steel bearing column, one layer of support depth of beam is 600~650mm, width 300mm, one layer Steel lattice column is arranged in annular girder and one layer of supporting beam handover position, capping beam is arranged at the top of excavation slope, the depth of beam that bears down on one is 600 ~650mm, width 300mm, are arranged one layer of supporting beam between capping beam and one layer of annular girder, capping beam and one layer of annular girder it Between raker beam is set, one layer of 1/4 circular arc of annular girder is arranged in along the 1/3 of circular arc direction or 2/3 in raker beam one end, and raker beam is another One end is arranged at capping beam along its length 1/4, and diagonal brace depth of beam is 600~650mm, width 300mm;Two layers of annular girder Diameter is 24~36m, and two layers of annular depth of beam are 500~550mm, width 300mm;Between two layers of annular girder and steel bearing column Two layers of supporting beam are set, and two layers of support depth of beam are 500~550mm, width 300mm, two layers of annular girder and two layers of supporting beam Joining the not set steel lattice column in position, waist rail is set in the middle part of excavation slope, waist rail height is 500~550mm, width 300mm, Two layers are arranged two layers of supporting beam between annular girder and waist rail;Steel bearing column is higher by one layer of 1.5~1.8m of annular top surface of the beam, steel load Cable wire rope is set between column and one layer of annular girder, and cable wire rope uniformly divides with one layer of annular girder drawknot node along one layer of annular girder circular arc Cloth;Steel bearing column protrudes into the following soil layer of basement bottom board, and steel bearing column bottom end is steel load top end with a distance from basement bottom board 1.5~1.7 times with a distance from basement bottom board;
Steel load column diameter carries out value according to foundation pit maximum span and excavation of foundation pit depth;Steel load column diameter takes according to table 1 Value, when foundation pit maximum span or excavation of foundation pit depth and 1 numerical value of table do not determine steel load column diameter using interpolation method simultaneously;When When longitudinal span and horizontal span are greater than 2, steel load column diameter is reduced using reduction coefficient, when longitudinal span and transverse direction When span is greater than 1 less than or equal to 2, reduction coefficient uses 0.98, when longitudinal span and horizontal span greater than 2 and are less than or equal to 2.3 When, reduction coefficient uses 0.96, and when longitudinal span is greater than 2.3 and is less than or equal to 2.6 with horizontal span, reduction coefficient is used 0.94, when longitudinal span is greater than 2.6 and is less than or equal to 3 with horizontal span, reduction coefficient uses 0.92, when longitudinal span and cross When being greater than 3 to span, reduction coefficient uses 0.9;
1 steel bearing column diameter parameters of table
Construction procedure includes:
(1) construction steel bearing column;Steel bearing column is pressed into soil layer by hydraulic static piling;
(2) install one layer of annular girder, capping beam, one layer of supporting beam and raker beam reinforcing bar, install one layer of annular girder, capping beam, The template of one layer of supporting beam and raker beam removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column, one layer of supporting beam Reinforcing bar is protruded into after rectangular preformed hole and is welded with the steel diaphragm of steel bearing column, the casting concrete in rectangular preformed hole, hereafter One layer of annular girder, capping beam, one layer of supporting beam and raker beam concrete are poured again;
(3) tensioning cable wire rope;
(4) after one layer of annular girder, capping beam, one layer of supporting beam and raker beam concrete strength reach the 100% of design strength, Excavate the earthwork outside one layer of annular girder;The earthwork outside one layer of annular girder is excavated using tile and hierarchy, outside one layer of annular girder The earthwork be divided into four pieces of excavations, excavate and use symmetric mode, the additional stress generated when being excavated with reducing, first piece dug after again Excavate the diagonal earthwork;Stage excavation is with a thickness of 500~600mm;When earth excavation to half depth outside one layer of annular girder The earthwork inside one layer of annular girder is excavated again, and the earthwork inside one layer of annular girder is excavated using tile and hierarchy, in one layer of annular girder The earthwork in portion is divided into four pieces of excavations, and excavation excavates the diagonal earthwork after having dug using symmetric mode, first piece again;Stage excavation is thick Degree is 500~600mm;One layer of annular girder external redundant is excavated again when earth excavation to half depth inside one layer of annular girder The earthwork, finally excavate the remaining earthwork inside one layer of annular girder again;
(5) install two layers of annular girder, waist rail, two layers of supporting beam reinforcing bar, install two layers of annular girder, waist rail, two layers of supporting beam Template removes the temporary steel cladding plate outside the rectangular preformed hole of steel bearing column, after the reinforcing bar of two layers of supporting beam protrudes into rectangular preformed hole It is welded with the steel diaphragm of steel bearing column, the casting concrete in rectangular preformed hole, hereafter pours two layers of annular girder, waist again Beam, two layers of supporting beam concrete;
(6) after two layers of annular girder, waist rail, two layers of supporting beam concrete strength reach the 100% of design strength, two layers of ring are excavated The earthwork outside ellbeam;The earthwork outside two layers of annular girder is excavated using tile and hierarchy, and the earthwork outside two layers of annular girder is divided into Four pieces of excavations, excavation excavate the diagonal earthwork after having dug using symmetric mode, first piece again;Stage excavation with a thickness of 500~ 600mm;The earthwork inside two layers of annular girder, two layers of annular are excavated when earth excavation to half depth outside two layers of annular girder again The earthwork inside beam is excavated using tile and hierarchy, and the earthwork inside two layers of annular girder is divided into four pieces of excavations, is excavated using symmetrical side Formula, first piece dug after excavate the diagonal earthwork again;Stage excavation is with a thickness of 500~600mm;To the soil inside two layers of annular girder The earthwork of two layers of annular girder external redundant is excavated when being excavated to half depth again in side;The basement bottom of two layers of annular girder external range Plate is divided into four pieces and is poured, and pours sequence and earth excavation sequence consensus, is i.e. is poured after first piece of earth excavation First piece of basement bottom board, other block basement bottom boards and so on;Steel plate water stopper is set between adjacent concrete block;
(7) remaining soil inside two layers of annular girder is excavated after the basement bottom board to two layers of annular girder external range pours again Side;The basement bottom board of two layers of annular girder internal range is divided into four pieces and is poured, and pours sequence and earth excavation sequence consensus, That is carry out pouring first piece of basement bottom board after first piece of earth excavation, other block basement bottom boards and so on;It is adjacent Steel plate water stopper is set between concrete block;
(8) reinforcing bar of sidewall of basement, template are installed and carries out casting concrete;
(9) supporting construction is removed, demolition of support structure uses double faced leather;First remove two layers of annular girder, waist rail, two layers of branch Support beam;One layer of annular girder, capping beam, one layer of supporting beam and raker beam are removed again;
(10) cable wire rope is removed;
(11) connection for cutting off one layer of supporting beam or two layers of support beam steel and steel bearing column, pulls out steel bearing column.
CN201810938460.7A 2017-09-15 2017-09-15 Foundation pit supporting structure Active CN108867660B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810938460.7A CN108867660B (en) 2017-09-15 2017-09-15 Foundation pit supporting structure

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710829676.5A CN107338799B (en) 2017-09-15 2017-09-15 Large span foundation pit supporting construction
CN201810938460.7A CN108867660B (en) 2017-09-15 2017-09-15 Foundation pit supporting structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201710829676.5A Division CN107338799B (en) 2017-09-15 2017-09-15 Large span foundation pit supporting construction

Publications (2)

Publication Number Publication Date
CN108867660A true CN108867660A (en) 2018-11-23
CN108867660B CN108867660B (en) 2020-10-23

Family

ID=60215756

Family Applications (6)

Application Number Title Priority Date Filing Date
CN201810938479.1A Expired - Fee Related CN108867661B (en) 2017-09-15 2017-09-15 Foundation pit supporting construction method
CN201710829676.5A Active CN107338799B (en) 2017-09-15 2017-09-15 Large span foundation pit supporting construction
CN201810951757.7A Active CN109024613B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting construction method
CN201810951726.1A Active CN109024612B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting structure
CN201810951769.XA Expired - Fee Related CN108867662B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting construction method of strip steel anchor cable
CN201810938460.7A Active CN108867660B (en) 2017-09-15 2017-09-15 Foundation pit supporting structure

Family Applications Before (5)

Application Number Title Priority Date Filing Date
CN201810938479.1A Expired - Fee Related CN108867661B (en) 2017-09-15 2017-09-15 Foundation pit supporting construction method
CN201710829676.5A Active CN107338799B (en) 2017-09-15 2017-09-15 Large span foundation pit supporting construction
CN201810951757.7A Active CN109024613B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting construction method
CN201810951726.1A Active CN109024612B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting structure
CN201810951769.XA Expired - Fee Related CN108867662B (en) 2017-09-15 2017-09-15 Large-span foundation pit supporting construction method of strip steel anchor cable

Country Status (1)

Country Link
CN (6) CN108867661B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487261A (en) * 2018-04-10 2018-09-04 江西科技学院 A kind of arch steel structure support
CN113502828B (en) * 2021-07-23 2022-11-08 上海宝冶集团有限公司 Processing method for early warning of deep foundation pit
CN114319380A (en) * 2021-12-30 2022-04-12 珠海华发人居生活研究院有限公司 Construction method for deformation of inner support column of deep foundation pit

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0813494A (en) * 1994-06-29 1996-01-16 Maeda Corp Fixing method of earth retaining wall and timbering
KR20140069845A (en) * 2012-11-30 2014-06-10 쌍용건설 주식회사 Retaining wall using diagonal reinforcement member
CN105040728A (en) * 2015-06-05 2015-11-11 朱奎 Three-layer basement supporting structure
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN106049505A (en) * 2016-07-06 2016-10-26 江苏江中集团有限公司 Construction method for deep foundation pit supporting and protecting system
CN106836240A (en) * 2015-05-22 2017-06-13 朱奎 Basement annular brace construction method for supporting

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201125459Y (en) * 2007-11-16 2008-10-01 中国京冶工程技术有限公司 Slanting guy cable and suspended cable combined cable hinge structure
CN101615212B (en) * 2009-07-28 2011-10-26 武汉理工大学 Simplified design calculation method of piling-inner supporting system
KR20110024554A (en) * 2009-09-02 2011-03-09 (주)이랜드건설 Support structures for retaining wall and construction method thereof
CN101666095B (en) * 2009-09-11 2011-11-23 温州市金誉建设监理有限公司 Irregular foundation pit support and construction method
CN102660955B (en) * 2012-05-17 2015-05-13 上海强劲地基工程股份有限公司 Quick construction method for foundation pit slope support
KR101307821B1 (en) * 2013-05-08 2013-09-23 주식회사 시티기술단 Underground soil retaining wall structure for activity space securement
CN104099934B (en) * 2014-04-01 2016-01-20 浙江省建筑设计研究院 A kind of supporting and protection structure of Large Foundation Pit
CN203834487U (en) * 2014-04-10 2014-09-17 中国十五冶金建设集团有限公司 Section steel inner brace and Lassen pile support for excavation of dumbbell-shaped deep and large foundation pit
CN104695447B (en) * 2015-03-13 2017-01-25 朱奎 deep basement support
CN204676940U (en) * 2015-03-25 2015-09-30 马鞍山职业技术学院 Single column is outstanding draws Double Tops pin-connected panel reinforcing bar protection canopy
CN205475249U (en) * 2016-01-13 2016-08-17 中国建筑第八工程局有限公司 Landing stage structure that fetches earth under deep basal pit annular supports
CN106013446A (en) * 2016-06-12 2016-10-12 叶长青 Roof structure of large-span building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0813494A (en) * 1994-06-29 1996-01-16 Maeda Corp Fixing method of earth retaining wall and timbering
KR20140069845A (en) * 2012-11-30 2014-06-10 쌍용건설 주식회사 Retaining wall using diagonal reinforcement member
CN106836240A (en) * 2015-05-22 2017-06-13 朱奎 Basement annular brace construction method for supporting
CN105040728A (en) * 2015-06-05 2015-11-11 朱奎 Three-layer basement supporting structure
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN106049505A (en) * 2016-07-06 2016-10-26 江苏江中集团有限公司 Construction method for deep foundation pit supporting and protecting system

Also Published As

Publication number Publication date
CN108867662A (en) 2018-11-23
CN108867661A (en) 2018-11-23
CN108867662B (en) 2020-09-15
CN109024613B (en) 2020-09-15
CN108867660B (en) 2020-10-23
CN109024612B (en) 2020-10-09
CN107338799B (en) 2018-12-14
CN109024613A (en) 2018-12-18
CN108867661B (en) 2020-10-09
CN107338799A (en) 2017-11-10
CN109024612A (en) 2018-12-18

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN107542108A (en) A kind of reverse construction method of building basement structure
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN103981898A (en) Integral open-excavation node top-down underground engineering construction method
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN107338799B (en) Large span foundation pit supporting construction
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN108547641A (en) The bottom stab ilization system and its construction method in rich water soft stratum heavy haul railway tunnel
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN108385693B (en) Equal-generation anchor bolt supporting method and system for staged basement supporting
CN104975606A (en) Method for handling high-low strides at adjacent parts of reverse building foundation pit and adjacent foundation pit
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
KR100313720B1 (en) Composite Underground Structure Construction Method
CN106498957A (en) Steel sheet pile cofferdam construction platform and integral construction method
CN102410031A (en) Underground space structure constructed by pile wall construction method
CN209923935U (en) Co-location combined pile wall supporting structure in upper-soft and lower-hard stratum
CN101509258A (en) Method for precontrolling subsidence slant of sinking well
CN113027463A (en) Suspension type reverse wall working well supporting structure and construction method
CN101161947A (en) Integration method of lagging pile and dewatering well for foundation ditch support
CN204851265U (en) Bearing structure in work well under high water pressure condition
CN209066508U (en) Cross the existing electric power piping lane protection structure of tunnel foundation pit
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN111576445B (en) Isolation supporting structure of road tunnel foundation pit of underpass pipeline and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 325000, No. 48, Jingshan Hill Road, Ouhai District, Wenzhou, Zhejiang

Patentee after: Ye Changqing

Address before: 325000 No. 4, Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, China

Patentee before: Ye Changqing

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Patentee after: Ye Changqing

Address before: 325000 No. 48 Xinghai Road, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province

Patentee before: Ye Changqing

CP02 Change in the address of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20231024

Address after: No. 88 Asia Pacific Road, Shushan Street, Xiaoshan District, Hangzhou City, Zhejiang Province, 310000

Patentee after: Zhejiang Gonggong Foundation Engineering Co.,Ltd.

Address before: 325000 Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, 4

Patentee before: Ye Changqing

TR01 Transfer of patent right