CN108867627A - A kind of construction method convenient for transmission of electricity stake disassembly - Google Patents

A kind of construction method convenient for transmission of electricity stake disassembly Download PDF

Info

Publication number
CN108867627A
CN108867627A CN201810859939.1A CN201810859939A CN108867627A CN 108867627 A CN108867627 A CN 108867627A CN 201810859939 A CN201810859939 A CN 201810859939A CN 108867627 A CN108867627 A CN 108867627A
Authority
CN
China
Prior art keywords
stake
pile
construction
mud
transmission
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810859939.1A
Other languages
Chinese (zh)
Inventor
秦海军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mianyang Ding Fei Electronic Technology Co Ltd
Original Assignee
Mianyang Ding Fei Electronic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mianyang Ding Fei Electronic Technology Co Ltd filed Critical Mianyang Ding Fei Electronic Technology Co Ltd
Priority to CN201810859939.1A priority Critical patent/CN108867627A/en
Publication of CN108867627A publication Critical patent/CN108867627A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/60Piles with protecting cases

Abstract

The invention discloses a kind of construction methods convenient for transmission of electricity stake disassembly, and described method includes following steps:S1:Levelling of the land is carried out first, will first be evened whole barrier on removing subsurface, ground within the scope of foundation construction out by Center stake formation level, is repaired the sidewalk led into stake position;S2:Water supply pipe and power supply line are installed, carries out a point hole by design drawing requirement and measures, in the place setting pile foundation axis not influenced by pile foundation construction and high process control stake, and perform record;S3:Shaft tower number in pool is drained using sand pocket cofferdam, and by the water in cofferdam, and filling pile construction should be segmented according to the length of reinforcing cage of design, and steel reinforcement cage machining shed and cement is arranged and stores canopy, backup power source should also be arranged, sandstone stacks field and cinder field out;S4:Using mud off percussive drill pore-creating filling pile, the clay storage field of 2 times of single pile side's amounts should be set, using mud off rotary rig pore-creating filling pile.

Description

A kind of construction method convenient for transmission of electricity stake disassembly
Technical field
The present invention relates to a kind of construction methods, and in particular to a kind of construction method convenient for transmission of electricity stake disassembly.
Background technique
With the fast development of urban economy and the quickening of urbanization process, power engineering construction project is increasing.No It needs not take up an area space of planes in road surface erection shaft tower and conducting wire, is easy to keep the power cable engineering of appearance of the city neat appearance also to get over Come more.
The construction of normal cable engineering is all that fluting is laid with power pipe, causes to enable the disgustful road " zipper of citizen Phenomenon ".Simultaneously during building power channel, for example all kinds of municipal administrations of node that can not be passed through by traditional excavation technology are encountered unavoidably Cross pipe-line point, highway, railway, bridge, river and above ground structure etc..Therefore, conventional heavy excavation construction technology is increasingly It is not suitable with the needs of urban development.
An emerging technology --- trenchless technology has obtained more and more extensive answer in power pipe engineering in recent years With.Although trenchless technology is started late, but popularizing with application, and no matter theoretically trenchless technology, or is constructing Process aspect has the development advanced by leaps and bounds.Although trenchless technology is come out first with high-tech advantage, no-dig technique There is also many risks directly or indirectly in construction for technology.Since construction has scene property, complexity, mutability under earth's surface And comprehensive feature, easily cause in construction surface buildings depression, roadbed subsidence cracking, underground structure and underground to have pipeline Damage etc. the problems such as.
Since the method that Horizontal Directional Drilling is excavated relative to tradition has many advantages, so that it is being laid with city electricity Hydraulic piping using more and more extensive.
Power pipe construction is combined back there are multitube and is dragged with construction characteristics such as compaction groutings, resistance when not only back to drag Increase, and the grouting pressure that acts on pipeline outer wall while pipeline critical external compressive resistance ability can be reduced, with time dragging for single pipe Construction has significant difference.
To guarantee the safety of pipeline itself and the quality of engineering, the pull-back force in construction should be carried out before going back to hauling pipe road It calculates, and force analysis is carried out to electricity channel, to guarantee the safety in pipeline returning and mortar depositing construction.
Summary of the invention
The technical problem to be solved by the present invention is to the disassembly installation steps of current power transmission stake are cumbersome, the construction in entire stake face Process is slowly, and it is an object of the present invention to provide a kind of construction method convenient for transmission of electricity stake disassembly, solves the problem above-mentioned.
The present invention is achieved through the following technical solutions:
A kind of construction method convenient for transmission of electricity stake disassembly, described method includes following steps:S1:It is flat that place is carried out first It is whole, will first be evened out by Center stake formation level whole within the scope of foundation construction, remove subsurface, the barrier on ground, repair lead into The sidewalk of stake position;S2:Water supply pipe and power supply line are installed, carries out a point hole by design drawing requirement and measures, not by pile foundation The place setting pile foundation axis of construction infection and high process control stake, and perform record;S3:Shaft tower number in pool uses Sand pocket cofferdam, and the water in cofferdam is drained, filling pile construction should be segmented according to the length of reinforcing cage of design, and reinforcing bar is arranged Cage machining shed and cement store canopy, backup power source should also be arranged, sandstone stacks field and cinder field out;S4:It is impacted using mud off The clay storage field of 2 times of single pile sides amount should be arranged in drilling machine pore-creating filling pile, using mud off rotary rig pore-creating filling pile, The mud pit of one 3 times of single pile sides amount and the mud-settling pit of 2 times of single pile side amount should be set.
Casing is made of 4~8mm steel plate, should be greater than bit diameter 100mm with its diameter when rotary rig;Use impact drill When machine, preferably greater than bit diameter 200mm.
Casing position should be buried correctly, tamp between casing and crater wall using clay, casing center and stake position centre deviation It is not greater than 50mm.
Shield-tube embedment depth is not preferably less than 1m in clay, and 1.5m, and mud face in retaining hole are not preferably less than in sand It is higher by level of ground water 1m or more.
Compared with prior art, the present invention having the following advantages and benefits:By trenchless technology and power cable Laying combine, for guarantee pipeline itself safety and engineering quality, return hauling pipe road before reply construction in return drag Power is calculated, and carries out force analysis to electricity channel, to guarantee the safety in pipeline returning and mortar depositing construction.To current Power transmission and transformation comb trenchless engineering construction method has carried out effective supplement, has also standardized supervisor in non-excavation laying electric power Supervisory basis and supervision behavior in pipeline construction.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, below with reference to embodiment, the present invention is made Further to be described in detail, exemplary embodiment of the invention and its explanation for explaining only the invention, are not intended as to this The restriction of invention.
Embodiment
A kind of construction method convenient for transmission of electricity stake disassembly, described method includes following steps:S1:It is flat that place is carried out first It is whole, will first be evened out by Center stake formation level whole within the scope of foundation construction, remove subsurface, the barrier on ground, repair lead into The sidewalk of stake position;S2:Water supply pipe and power supply line are installed, carries out a point hole by design drawing requirement and measures, not by pile foundation The place setting pile foundation axis of construction infection and high process control stake, and perform record;S3:Shaft tower number in pool uses Sand pocket cofferdam, and the water in cofferdam is drained, filling pile construction should be segmented according to the length of reinforcing cage of design, and reinforcing bar is arranged Cage machining shed and cement store canopy, backup power source should also be arranged, sandstone stacks field and cinder field out;S4:It is impacted using mud off The clay storage field of 2 times of single pile sides amount should be arranged in drilling machine pore-creating filling pile, using mud off rotary rig pore-creating filling pile, The mud pit of one 3 times of single pile sides amount and the mud-settling pit of 2 times of single pile side amount should be set.
Casing is made of 4~8mm steel plate, should be greater than bit diameter 100mm with its diameter when rotary rig;Use impact drill When machine, preferably greater than bit diameter 200mm.
Casing position should be buried correctly, tamp between casing and crater wall using clay, casing center and stake position centre deviation It is not greater than 50mm.
Shield-tube embedment depth is not preferably less than 1m in clay, and 1.5m, and mud face in retaining hole are not preferably less than in sand It is higher by level of ground water 1m or more.
The performance and technical indicator of slurrying are generally by four indices such as the specific gravity of mud, viscosity, sand factor, colloiditys Lai really It is fixed.When modulating drilling slurry, different mud properties is selected according to the condition of the method for drilling, geological condition and bored concrete pile itself Index is generally selected referring to table one.
Geological condition Specific gravity Viscosity (second) Percent sand (%) Colloidity (%)
General geology 1.1~1.3 16~22 ≤ 4~8 〉95
Loose geology of easily collapsing 1.4~1.6 19~28 ≤ 4~8 〉95
Table one
Compared with prior art, the present invention having the following advantages and benefits:By trenchless technology and power cable Laying combine, for guarantee pipeline itself safety and engineering quality, return hauling pipe road before reply construction in return drag Power is calculated, and carries out force analysis to electricity channel, to guarantee the safety in pipeline returning and mortar depositing construction.To current Power transmission and transformation comb trenchless engineering construction method has carried out effective supplement, has also standardized supervisor in non-excavation laying electric power Supervisory basis and supervision behavior in pipeline construction.
Above-described specific embodiment has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that being not intended to limit the present invention the foregoing is merely a specific embodiment of the invention Protection scope, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (4)

1. a kind of construction method convenient for transmission of electricity stake disassembly, which is characterized in that described method includes following steps:
S1:First carry out levelling of the land, will first be evened out within the scope of foundation construction by Center stake formation level it is whole, remove subsurface, Barrier on ground repairs the sidewalk led into stake position;
S2:Water supply pipe and power supply line are installed, carries out a point hole by design drawing requirement and measures, do not influenced by pile foundation construction Place setting pile foundation axis and high process control stake, and perform record;
S3:Shaft tower number in pool is drained using sand pocket cofferdam, and by the water in cofferdam, and filling pile construction should be according to setting The length of reinforcing cage of meter is segmented, and steel reinforcement cage machining shed is arranged and cement stores canopy, backup power source should also be arranged, sandstone is stacked Field and out cinder field;
S4:Using mud off percussive drill pore-creating filling pile, the clay of 2 times of single pile sides amount should be arranged in the shield-tube embedment of bored concrete pile Field is stored, using mud off rotary rig pore-creating filling pile, the mud pit and one 2 times that 3 times of single pile side is measured should be set The mud-settling pit of single pile side's amount.
2. a kind of construction method convenient for transmission of electricity stake disassembly according to claim 1, which is characterized in that casing using 4~ The production of 8mm steel plate, should be greater than bit diameter 100mm with its diameter when rotary rig;When with percussive drill, preferably greater than bit diameter 200mm。
3. a kind of construction method convenient for transmission of electricity stake disassembly according to claim 1, which is characterized in that casing position should bury If correct, tamped between casing and crater wall using clay, casing center and stake position centre deviation are not greater than 50mm.
4. a kind of construction method convenient for transmission of electricity stake disassembly according to claim 1, which is characterized in that shield-tube embedment depth It is not preferably less than 1m in clay, 1.5m is not preferably less than in sand, and mud face is higher by level of ground water 1m or more in retaining hole.
CN201810859939.1A 2018-08-01 2018-08-01 A kind of construction method convenient for transmission of electricity stake disassembly Withdrawn CN108867627A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810859939.1A CN108867627A (en) 2018-08-01 2018-08-01 A kind of construction method convenient for transmission of electricity stake disassembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810859939.1A CN108867627A (en) 2018-08-01 2018-08-01 A kind of construction method convenient for transmission of electricity stake disassembly

Publications (1)

Publication Number Publication Date
CN108867627A true CN108867627A (en) 2018-11-23

Family

ID=64306704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810859939.1A Withdrawn CN108867627A (en) 2018-08-01 2018-08-01 A kind of construction method convenient for transmission of electricity stake disassembly

Country Status (1)

Country Link
CN (1) CN108867627A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN202500147U (en) * 2012-03-19 2012-10-24 中国电力科学研究院 Power transmission line enlarged top filling pile base
CN204590062U (en) * 2015-04-17 2015-08-26 国家电网公司 A kind of pole tower pile used for transmission line
CN107165160A (en) * 2017-07-19 2017-09-15 上海宝冶集团有限公司 Electric drill bores construction filling pile construction engineering method with rotary digging relay
CN107938700A (en) * 2017-11-17 2018-04-20 九州职业技术学院 A kind of installation method of assembled underground pipe gallery

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN202500147U (en) * 2012-03-19 2012-10-24 中国电力科学研究院 Power transmission line enlarged top filling pile base
CN204590062U (en) * 2015-04-17 2015-08-26 国家电网公司 A kind of pole tower pile used for transmission line
CN107165160A (en) * 2017-07-19 2017-09-15 上海宝冶集团有限公司 Electric drill bores construction filling pile construction engineering method with rotary digging relay
CN107938700A (en) * 2017-11-17 2018-04-20 九州职业技术学院 A kind of installation method of assembled underground pipe gallery

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴远波: "浅析钻孔(泥浆护壁)灌注桩的施工技术", 《城市建筑》 *

Similar Documents

Publication Publication Date Title
Chen et al. Long rectangular box jacking project: a case study
CN109371974A (en) A kind of PHC tubular pole implantation construction method suitable for hard geology
CN102392458B (en) Piling beam cofferdam construction method used for bare rock foundation construction in water
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN111851597B (en) Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method
CN202194148U (en) Waterproof curtain
CN103015429A (en) Long auger rotary-jet mixing steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN103016842B (en) Mud soft soil foundation earth source heat pump direct-burried heat exchanger reverse construction engineering method
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN105926626B (en) Overlength pneumatic down hole hammer vibrates jet grouting pile construction technique
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN101597903B (en) Construction method of cylindrical slurry core pile for retaining and protecting foundation pit
CN216787094U (en) Real-time active servo steel underground diaphragm wall construction method pile
CN108867627A (en) A kind of construction method convenient for transmission of electricity stake disassembly
Hwang et al. Design and construction of deep excavations in Taiwan
CN108798717A (en) A kind of borehole design method that tunnel vault wall rock grouting under urban road is reinforced
CN110778788B (en) Protection method for laying heat supply pipeline after shallow earth covering under road surface
CN220318548U (en) Soil retaining structure for water-facing pit support in narrow region
CN102561390B (en) The application of contrary sequence method technique in the structure construction of underground substation
Sinna Application of trenchless construction technology in construction of water supply and drainage in urban road construction
Huang Construction Technology of Deep Foundation Pit Support in Municipal Civil Engineering Foundation Construction
Zhou et al. Design of Municipal Sewer Pipe Jacking under Complex Geological Conditions in Plateau Regions

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination