CN108867372A - Prefabricated bridge floor of mating formation, construction method and method for maintaining - Google Patents

Prefabricated bridge floor of mating formation, construction method and method for maintaining Download PDF

Info

Publication number
CN108867372A
CN108867372A CN201810841253.XA CN201810841253A CN108867372A CN 108867372 A CN108867372 A CN 108867372A CN 201810841253 A CN201810841253 A CN 201810841253A CN 108867372 A CN108867372 A CN 108867372A
Authority
CN
China
Prior art keywords
prefabricated bridge
stringer
prefabricated
crossbeam
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810841253.XA
Other languages
Chinese (zh)
Inventor
张建东
冉晓勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Weihai Yitong New Material Co Ltd
Original Assignee
Weihai Yitong New Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Weihai Yitong New Material Co Ltd filed Critical Weihai Yitong New Material Co Ltd
Priority to CN201810841253.XA priority Critical patent/CN108867372A/en
Publication of CN108867372A publication Critical patent/CN108867372A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides the prefabricated bridge floor of mating formation of one kind, construction method and method for maintaining, which solve prefabricated bridges to generate displacement in the case where being acted on by vehicle dynamic load, and collision is caused to cause service life short because of rigid connection, the technical problem that maintenance cost is high, the time is long.It is equipped with muti-piece prefabricated bridge and stringer, prefabricated bridge described in muti-piece is disposed in parallel relation to one another, rides upon the upper surface of the stringer, the prefabricated bridge is equipped with rib of slab, the stringer is equipped with card slot, card and construction are formed by rib of slab card and in card slot, are mutually fixed by card with construction between the prefabricated bridge and the stringer.It the composite can be widely applied in bridge structure.

Description

Prefabricated bridge floor of mating formation, construction method and method for maintaining
Technical field
The present invention relates to a kind of deck structure, construction method and method for maintaining, more particularly to a kind of prefabricated bridge floor of mating formation, apply Work method and method for maintaining.
Background technique
Short/Medium Span Bridge generallys use beam bridge or arcuately bridge, and when deck paving, that is, runway is mated formation, it is that wheel is straight Connect the position of effect.Runway is mated formation there are diversified forms, there is cement concrete, bituminous concrete, bituminous surface treatment and mud Tie rubble etc..The low cost of concrete pavement, wear-resisting property is good, is suitble to Heavy Traffic, but preserving period is long, repair in the future compared with Trouble;Asphalt concrete pavement lighter weight, maintenance is convenient, and the speed that is open to traffic is fast, but easy to aging and deformation;At asphalt surface It controls and mats formation with mud knot rubble, durability is poor.Cement concrete is either used, or bridge floor paving is done using bituminous concrete Dress, after its breakage, requiring to restrict driving is open to traffic, and damaged place is carried out cutting and is cut, maintenance is then poured, need consuming compared with The long time seriously affects public transport life, and bridge floor is also required to consume biggish human and material resources cost when mating formation.
Summary of the invention
It is a primary object of the present invention to, overcome defect existing for existing bridge structure, and provide and a kind of prefabricated mat formation Bridge floor, construction method and method for maintaining reduce maintenance cost, shorten maintenance cycle, the influence to public transport are reduced, thus more Add and be suitable for being widely popularized, and with the utility value in industry.
For this purpose, the technical scheme is that, a kind of prefabricated bridge floor of mating formation includes muti-piece prefabricated bridge and stringer, Prefabricated bridge described in muti-piece is disposed in parallel relation to one another, rides upon the upper surface of the stringer, and the prefabricated bridge is equipped with plate Rib, the stringer are equipped with card slot, and card and construction, the prefabricated bridge and the stringer are formed by rib of slab card and in card slot Between by card and construction mutually fix;
Preferably, in prefabricated bridge lower surface end position, the card slot is arranged described for the rib of slab setting On stringer and at rib of slab opposite position.
Preferably, the prefabricated bridge floor of mating formation further includes crossbeam, and the crossbeam is inverted T-shape structure, the stringer Vertical is arranged at the upper surface of the crossbeam, and the stringer both ends are ridden upon respectively on the crossbeam.
Preferably, assembled seam is provided between the prefabricated bridge being disposed adjacent, the assembled seam, which is internally provided with, to be filled out Fill material.
Preferably, the upper surface of the prefabricated bridge is provided with hole for hoist.
Preferably, the hole for hoist at least two, the hole for hoist are rectangular configuration.
Preferably, the construction method of the prefabricated bridge floor of mating formation, including following operating procedure:
(1) crossbeam, and elevation control are installed, it is cementing integral in the node location casting concrete of the crossbeam;
(2) with the perpendicular installation stringer of the crossbeam, stringer lower surface band is fluted, and the stringer is more, adjusts The position of whole stringer is in groove in same horizontal line;
(3) it is high to bridge floor top mark to pour crossbeam, so that stringer and crossbeam is linked to be an entirety, increases the globality of bridge;
(4) while crossbeam and stringer are constructed, the prefabricated prefabricated bridge with rib of slab;
(5) mat formation prefabricated bridge, there are holes for hoist on prefabricated bridge, prefabricated bridge is lifted by crane by hole for hoist, And adjust adjacent prefabricated bridge spacing;
(6) gap in card and construction is filled with high-strength mortar, fills the assembly between prefabricated bridge with flexible material Seam.
Preferably, the method for maintaining of prefabricated bridge floor of mating formation, including following operating procedure:
(1) bridge floor is checked, discovery there are damaged relatively serious floorings;
(2) prefabricated bridge of equivalent specifications is prepared;
(3) standard curing is hoisted to scene to design strength;
(4) it by damaged floorings, is sling by hole for hoist, carries out the separation and dismounting with former bridge floor;
(5) new prefabricated bridge is mounted on corresponding position;
(6) gap in card and construction is filled with high-strength mortar, fills the assembly between prefabricated bridge with flexible material Seam.
The invention has the advantages that prefabricated bridge floor of mating formation uses the composite structure of pin-connected panel, be prefabricated in the factory floorings, It is fixed on stringer by card and construction, is being pacified between prefabricated bridge and stringer between prefabricated bridge and prefabricated bridge There are the splicing seams of 1cm when dress, fill prefabricated bridge and prefabricated bridge using flexible material, prefabricated bridge and stringer it Between gap, complete the construction of bridge floor;The present invention uses the prefabricated bridge with rib of slab to be connected with the stringer with card slot, It overcomes prefabricated bridge and generates displacement in the case where being acted on by vehicle dynamic load;While facilitating construction, due to rigidly connected Position is isolated by flexible material, is played the role of buffering, is extended the service life of bridge floor, and it is permanent originally to reduce maintenance;? Prefabricated bridge upper surface setting hole for hoist be for convenience replacement operation, will not large area destruction bridge deck structure, reduce To the obstruction time of traffic.
Detailed description of the invention
Fig. 1 is prefabricated bridge floor top view of mating formation;
Fig. 2 is prefabricated bridge floor front section view of mating formation;
Fig. 3 is prefabricated bridge floor side sectional view of mating formation;
Fig. 4 is floorings main view;
Fig. 5 is floorings left view;
Fig. 6 is floorings bottom view.
Symbol description in figure:
1. prefabricated bridge, 2. crossbeams, 3. stringers, 4. holes for hoist, 5. cards and construction, 6. assembled seams.
Specific embodiment
The present invention is described further below with reference to embodiment.
The structural schematic diagram of prefabricated mat formation bridge floor and all parts of the invention as shown in figs. 1 to 6, including prefabricated bridge 1, Crossbeam 2, stringer 3, hole for hoist 4, card and construction 5 and assembled seam 6.
Crossbeam 2 is inverted T-shape structure, and stringer 3 is vertical to be arranged at the upper surface of crossbeam 2,3 both ends of stringer difference It rides upon in the inverted T-shape structure of crossbeam 2.Muti-piece prefabricated bridge 1 is disposed in parallel relation to one another, rides upon the upper surface of stringer 3, It is mutually fixed by card with construction 5 between prefabricated bridge 1 and stringer 3;Card and construction 5 are formed by rib of slab card and in card slot, plate Rib setting is in 1 lower surface end position of prefabricated bridge, and card slot setting is on stringer 3 and at rib of slab opposite position.Adjacent One centimeter or so of assembled seam 6 is provided between the prefabricated bridge 1 of setting, flexible packing material is filled in 6 inside of assembly seam.
In order to facilitate maintenance in floorings breakage, four rectangles are symmetrically arranged in the upper surface of prefabricated bridge 1 The hole for hoist 4 of structure, convenient for construction.
The construction method of prefabricated bridge floor of mating formation, including following operating procedure:
(1) in precasting yard prefabricated crossbeam 2, stringer 3 (both ends have dowel), prefabricated bridge 1 (the equal smooth flat in surface);
(2) prefabricated crossbeam 2 is installed on pile cover, lap of splice 30cm, and with high strength cement mortar it is levelling and adjustment Crossbeam 2 installs bottom absolute altitude, makes its top surface absolute altitude to designed elevation h1;
(3) it after crossbeam 2 being installed, there are wet seam (node) between two panels prefabricated crossbeam 2, is poured by the scene of concrete It builds, so that each independent prefabricated crossbeam is joined together Integral cross beam 2 (lower half portion of crossbeam), and be just connected into one with substructure It is whole;
(4) prefabricated stringer 3 is being installed with the perpendicular direction of prefabricated crossbeam 2, lap of splice 30cm, prefabricated stringer 3 Upper surface band is fluted, and prefabricated stringer 3 is more, is disposed side by side on crossbeam 2 (lower half portion of crossbeam), equally, use is high-strength Cement mortar is spent, the top surface absolute altitude of prefabricated stringer 3 is adjusted, makes the designed elevation h0 of the top surface absolute altitude bridge floor of prefabricated stringer, Groove needs in the same plane;
(5) it is high to bridge floor top mark to pour crossbeam (lower half portion of crossbeam is prefabricated crossbeam, and top half is cast-in-place crossbeam) H0 makes stringer and crossbeam be linked to be an entirety, increases the globality of bridge (structural sections);
(6) mat formation floorings, be up to the floorings (there are holes for hoist 4 for prefabricated bridge) of installation strength, pass through lifting Prefabricated bridge is lifted by crane in hole, is transported with wooden handcart to construction site, and adjust the spacing of floorings, controls in 1cm;
(7) with the gap in high-strength mortar filling connecting structure 5, with flexible material (such as extrusion molding styrofoam, pitch Flax silk, rubber strip etc.) filling prefabricated bridge between gap 6;
(8) bridge deck works construction is completed.
The method for maintaining of prefabricated bridge floor of mating formation, including following operating procedure:
(1) bridge floor is checked, discovery there are the floorings of badly broken, and bridge floor plate surface forms full-length cracks (fracture width ω >=0.3mm) or concrete fall off;
(2) position, the specification, quantity of damaged floorings are recorded;
(3) floorings for replacing needs, in the prefabricated bridge floor of prefabricated manufacturer's Prefabrication dimension and quantity Plate, and specification is marked on floorings;
(4) in precast plant's standard curing prefabricated bridge to design strength, by transport vehicle by the preset bridge of dimension Panel is transported to scene;
(5) high-strength mortar by connecting structure filling is rejected, and by the prefabricated bridge that hole for hoist lifting is damaged, is realized With the separation and dismounting of former bridge floor;
(6) eliminating impurities in connecting structure are clean, and the flexible material being attached on prefabricated bridge is rejected and is done Only;
(7) new prefabricated bridge is mounted on corresponding position, and adjusts the spacing of new floorings and former floorings, control System is in 1cm;
(8) with the gap in high-strength mortar filling connecting structure, the gap between prefabricated bridge is filled with flexible material;
(9) it repeats the above steps, there is damaged prefabricated bridge successively to replace for other, until all replacement is completed.
Only as described above, only specific embodiments of the present invention, when the model that cannot be limited the present invention with this and implement It encloses, therefore the displacement of its equivalent assemblies, or according to equivalent changes and modifications made by the invention patent protection scope, should still belong to this hair The scope that bright claims are covered.

Claims (8)

1. a kind of prefabricated bridge floor of mating formation, characterized in that it include muti-piece prefabricated bridge (1) and stringer (3), it is prefabricated described in muti-piece Floorings (1) are disposed in parallel relation to one another, ride upon the upper surface of the stringer (3), and the prefabricated bridge (1) is equipped with rib of slab, The stringer (3) is equipped with card slot, and card and construction (5), the prefabricated bridge (1) and institute are formed by rib of slab card and in card slot It states and is mutually fixed by card with construction (5) between stringer (3).
2. prefabricated bridge floor of mating formation according to claim 1, which is characterized in that the rib of slab is arranged in the prefabricated bridge (1) lower surface end position, the card slot setting is on the stringer (3) and at rib of slab opposite position.
3. prefabricated bridge floor of mating formation according to claim 1, which is characterized in that further include crossbeam (2), the crossbeam (2) is Inverted T-shape structure, the vertical setting of the stringer (3) is at the upper surface of the crossbeam (2), stringer (3) both ends It is ridden upon on the crossbeam (2) respectively.
4. prefabricated bridge floor of mating formation according to claim 1, which is characterized in that the prefabricated bridge (1) being disposed adjacent it Between be provided with assembled seam (6), the assembled seam (6) is internally provided with packing material.
5. prefabricated bridge floor of mating formation according to any one of claims 1 to 4, which is characterized in that the prefabricated bridge (1) Upper surface is provided with hole for hoist (4).
6. prefabricated bridge floor of mating formation according to claim 5, which is characterized in that the hole for hoist (4) at least two, it is described Hole for hoist (4) is rectangular configuration.
7. the construction method of prefabricated bridge floor of mating formation according to claim 1, which is characterized in that including following operating procedure:
(1) crossbeam (2) are installed, and elevation control, it is cementing integral in the node location casting concrete of the crossbeam (2);
(2) with the crossbeam (2) perpendicular installation stringer (3), stringer (3) lower surface band is fluted, and the stringer (3) is More, the position of stringer (3) is adjusted, is in groove in same horizontal line;
(3) it is high to bridge floor top mark to pour crossbeam (2), so that stringer (3) and crossbeam (2) is linked to be an entirety, increases the entirety of bridge Property;
(4) while crossbeam (2) and stringer (3) are constructed, the prefabricated prefabricated bridge (1) with rib of slab;
(5) mat formation prefabricated bridge (1), there are hole for hoist (4) on prefabricated bridge (1), lifted by crane by hole for hoist (4) prefabricated Floorings (1), and adjust adjacent prefabricated bridge (1) spacing;
(6) gap in card and construction (5) is filled with high-strength mortar, fills the spelling between prefabricated bridge (1) with flexible material Dress seam (6).
8. the method for maintaining of prefabricated bridge floor of mating formation according to claim 1, which is characterized in that including following operating procedure,
(1) bridge floor is checked, discovery there are damaged relatively serious floorings;
(2) prefabricated bridge (1) of equivalent specifications is prepared;
(3) standard curing is hoisted to scene to design strength;
(4) it by damaged floorings, is sling by hole for hoist (4), carries out the separation and dismounting with former bridge floor;
(5) new prefabricated bridge (1) is mounted on corresponding position;
(6) gap in card and construction (5) is filled with high-strength mortar, fills the spelling between prefabricated bridge (1) with flexible material Dress seam (6).
CN201810841253.XA 2018-07-27 2018-07-27 Prefabricated bridge floor of mating formation, construction method and method for maintaining Withdrawn CN108867372A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810841253.XA CN108867372A (en) 2018-07-27 2018-07-27 Prefabricated bridge floor of mating formation, construction method and method for maintaining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810841253.XA CN108867372A (en) 2018-07-27 2018-07-27 Prefabricated bridge floor of mating formation, construction method and method for maintaining

Publications (1)

Publication Number Publication Date
CN108867372A true CN108867372A (en) 2018-11-23

Family

ID=64305685

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810841253.XA Withdrawn CN108867372A (en) 2018-07-27 2018-07-27 Prefabricated bridge floor of mating formation, construction method and method for maintaining

Country Status (1)

Country Link
CN (1) CN108867372A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003342915A (en) * 2002-05-28 2003-12-03 Hayashi Kensetsu Kogyo Kk Vertical placing joint mechanism in concrete floor slab placing
JP2010070992A (en) * 2008-09-19 2010-04-02 Nippon Light Metal Co Ltd Tool for closing hollow part of extruded section and method of installing floor slab for bridge
CN105113420A (en) * 2015-09-16 2015-12-02 宁波路宝科技实业集团有限公司 Prefabricated reinforced concrete simply-supported girder bridge deck pavement and maintenance structure and construction method
CN105274944A (en) * 2014-06-11 2016-01-27 上海申继交通科技有限公司 Hollow slab beam bridge hinge joint and quick maintenance method for bridge deck pavement
CN107542039A (en) * 2017-10-10 2018-01-05 储君 A kind of bridge floor laying method
CN108625284A (en) * 2018-06-08 2018-10-09 苏交科集团股份有限公司 Assembled concrete beam plate and installation and method for maintaining

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003342915A (en) * 2002-05-28 2003-12-03 Hayashi Kensetsu Kogyo Kk Vertical placing joint mechanism in concrete floor slab placing
JP2010070992A (en) * 2008-09-19 2010-04-02 Nippon Light Metal Co Ltd Tool for closing hollow part of extruded section and method of installing floor slab for bridge
CN105274944A (en) * 2014-06-11 2016-01-27 上海申继交通科技有限公司 Hollow slab beam bridge hinge joint and quick maintenance method for bridge deck pavement
CN105113420A (en) * 2015-09-16 2015-12-02 宁波路宝科技实业集团有限公司 Prefabricated reinforced concrete simply-supported girder bridge deck pavement and maintenance structure and construction method
CN107542039A (en) * 2017-10-10 2018-01-05 储君 A kind of bridge floor laying method
CN108625284A (en) * 2018-06-08 2018-10-09 苏交科集团股份有限公司 Assembled concrete beam plate and installation and method for maintaining

Similar Documents

Publication Publication Date Title
CN107974891B (en) Municipal road assembling unit and construction method thereof
CN106436549B (en) A kind of long-life high intensity bridge floor steel box-girder and its assemble method
CN101230563B (en) Method for replacing bridge bearing without traffic interruption and special device thereof
CN206428551U (en) A kind of repeatable assembled engagement temporary pavement plate utilized of monoblock type
CN105200868A (en) Novel slab ballastless track structure
CN205242181U (en) Novel board -like ballastless track structure
CN103938546A (en) Simple-supported continuous construction method and structure thereof
CN102839601A (en) Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure
CN106939553B (en) A kind of Steel Bridge Deck and steel box arch rib installation method
CN113152306B (en) Small-radius large-gradient prefabricated T beam frame construction method
CN108060636A (en) The construction method of overall assembled composite beam bridge
CN102322025A (en) Pre-stressing reinforced and widened bridge structure
CN205529742U (en) Prefabricated assembly concrete structure inter -layer
CN110747903A (en) Porous frame bridge and assembling construction method thereof
CN108547209B (en) Single-hole prefabricated hollow slab bridge without expansion joint and construction method thereof
CN108625284A (en) Assembled concrete beam plate and installation and method for maintaining
KR20050108867A (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
CN112281663B (en) Construction method for widening connection of upper structures of new and old bridges
CN202194081U (en) Hinge joint disease treatment structure of hollow slab bridge
CN106320192A (en) Beam section replacement reinforcement method for large-span concrete continuous beam bridge
CN208563105U (en) A kind of precast assembly concrete slab
KR100415768B1 (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
CN105507109A (en) Damaged concrete pavement panel reinforcing structure and method
CN206070351U (en) A kind of high intensity bridge floor steel box-girder
US20140369750A1 (en) Grout containment sheet and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20181123