CN108842807A - A kind of construction technology of the embedding rock single pile of offshore wind power foundation embedded type - Google Patents

A kind of construction technology of the embedding rock single pile of offshore wind power foundation embedded type Download PDF

Info

Publication number
CN108842807A
CN108842807A CN201810698964.6A CN201810698964A CN108842807A CN 108842807 A CN108842807 A CN 108842807A CN 201810698964 A CN201810698964 A CN 201810698964A CN 108842807 A CN108842807 A CN 108842807A
Authority
CN
China
Prior art keywords
pile
steel
grouting
hole
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810698964.6A
Other languages
Chinese (zh)
Other versions
CN108842807B (en
Inventor
熊汉东
庞双喜
黄桥兴
戴其其
林志航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Third Aviation Bureau Sixth Engineering Xiamen Co ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Sanhang (xiamen) Engineering Co Ltd, China Construction Third Engineering Bureau Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical In Sanhang (xiamen) Engineering Co Ltd
Priority to CN201810698964.6A priority Critical patent/CN108842807B/en
Publication of CN108842807A publication Critical patent/CN108842807A/en
Application granted granted Critical
Publication of CN108842807B publication Critical patent/CN108842807B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of construction technologies of the embedding rock single pile of offshore wind power foundation embedded type, including following below scheme:Steel-pipe pile and steel pile casting production, the inserting of steady stake putting up platform, steel pile casting, steel pile casting vibration set, drill, the implantation of borehole cleaning, steel-pipe pile, back cover concrete placings, the rockfill grouting of stake outer wall and recycles steel pile casting;Drilling process includes drilling machine in place, installation drilling rod, slurrying and drilling and forming hole step;Before the drilling and forming hole step for completing drilling process, in order to prevent collapse hole, advanced horizontal high voltage jet grouting pile construction;Construction of High Pressure Jet Grouting Pile includes drilling, lower injection pipe, injection, pile process.Construction technology of the invention, using steady stake platform auxiliary positioning, embedding rock construction is carried out using steel pile casting, it hangs ship using main and auxiliary hang ship cooperation and steel-pipe pile is lifted by crane and be inserted into steel pile casting, it can be improved construction efficiency, the horizontal resistivity and anti-group of ability for effectively improving embedded rock pile, meet the requirement of Structural Design and construction.

Description

Construction process of offshore wind power foundation implanted rock-socketed single pile
Technical Field
The invention relates to a construction process of an implanted rock-socketed single pile of an offshore wind power foundation.
Background
In the field of offshore wind power plant foundation design, comprehensive division is carried out according to different stratum structures and characteristics, and according to the cause types and engineering characteristics of various rock-soil layers, and the commonly adopted single-pile foundation comprises a non-rock-socketed single pile, a rock-socketed single pile and an implanted rock-socketed single pile. The construction of the pile foundation is a first-aid project of an offshore wind power project, offshore wind power construction is carried out on an open sea non-shield area which is far away from land and has the water depth of 16-19 m, the pile foundation is restrained by natural conditions such as weather, tide, waves and the like and is also in a tropical storm frequent area, and fan equipment has high requirements on bearing, uplift resistance and deformation of the foundation, so that the required pile foundation has a large diameter and a deep soil penetration depth, the fan foundation can bear huge fan overturning moment and bear wave and water load, and the construction period control of the construction progress is particularly critical.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a construction process of an implanted rock-socketed single pile of an offshore wind power foundation, which can improve the construction efficiency, effectively improve the horizontal resistance and the poking resistance of the rock-socketed pile and meet the requirements of engineering structure design and construction.
The purpose of the invention is realized as follows: a steel pipe pile with the diameter of 6.7m and the wall thickness of 60-80 mm is adopted for a single pile related to the construction process of an implanted rock-socketed single pile of an offshore wind power foundation, the steel pipe pile is driven into fractured strongly weathered granite, the total depth of penetration is 22.9-27.6 m, the pile top elevation is 15m, and the pile bottom elevation is about minus 43-minus 46 m;
the construction process comprises the following steps: manufacturing a steel pipe pile and a steel pile casing, building a stable pile platform, inserting the steel pile casing, vibrating the steel pile casing, drilling, cleaning holes, implanting the steel pipe pile, pouring bottom sealing concrete, backfilling and grouting the outer wall of the pile and recovering the steel pile casing; wherein,
the manufacturing process of the steel pipe pile and the steel casing comprises the steps of blanking of a pipe joint, processing of a pipe joint groove, rolling and forming of the pipe joint, assembling of a flange at the top of a pile body, splicing of the pile body and coating of an anticorrosive coating;
the pile stabilizing platform erection process comprises the following steps:
the lower platform and the four auxiliary process piles are positioned through the relative positions of the positioning platform ship and steel pipe piles at the closure of the lower platform, then the four auxiliary process piles are inserted and driven, and then the auxiliary process piles and the upper and lower parts of auxiliary process pile sleeves on the lower platform are firmly welded through steel plate strips;
moving away the positioning platform ship, inserting and driving two positioning process piles, and firmly welding the positioning process piles with the upper and lower parts of a positioning process pile sleeve on the lower platform through steel plate strips;
thirdly, installing an upper platform after the ③ steel casing insertion process is finished;
the steel casing inserting process comprises the following steps:
firstly, processing a lower platform of a pile stabilizing platform into a guide frame platform, wherein the center of the guide frame platform is the center of the steel pipe pile;
lifting the steel casing to a guide frame platform by the auxiliary lifting boat and slowly falling into the guide frame platform, stopping sinking when the steel casing passes through a lower platform of the guide frame platform, measuring the verticality of the steel casing by two leveling rulers, and tightly holding the steel casing at the bottom layer of the guide frame platform by a hydraulic jack after the verticality meets the requirement, and slowly sinking;
measuring and rechecking the verticality of the steel casing when the steel casing is sunk to the mud surface junction, continuing to sink to be stable after meeting the requirement, sleeving the steel casing with a hydraulic four-linkage vibrating hammer at the top of the steel casing, lifting the hydraulic four-linkage vibrating hammer with an auxiliary crane ship, vibrating and sinking the steel casing, and rechecking the verticality of the steel casing when the penetration of the steel casing reaches the hammer stopping standard, and then reinforcing the connection between the steel casing and the guide frame platform after the hammer is stopped and the verticality of the steel casing is rechecked;
the drilling process comprises the steps of positioning a drilling machine, installing a drill rod, preparing slurry and drilling to form a hole;
when the drilling machine is in place, firstly hanging away a hydraulic four-linkage vibration hammer, then erecting the drilling machine, adopting a gas-lift reverse circulation hydraulic power drilling machine provided with a hob bit, and locking the drilling machine and the steel casing through a pile gripper;
when the step of installing the drill rod is carried out, the drill bit and the drill rod are assembled on a deck of the main crane ship and then installed on the drilling machine;
when the step of preparing the slurry is carried out, the retaining wall slurry adopts the PHP high-performance slurry which is not dispersed, has low solid phase and high viscosity, firstly the bentonite slurry is stirred by a slurry stirrer in a slurry pool, then the bentonite slurry is pumped into the steel retaining cylinder by a slurry pump, and when the performance index of the slurry in the steel retaining cylinder meets the construction requirement, a hole is drilled;
when the drilling hole forming step is carried out, when a drilling machine starts drilling, the diameter of the drilled hole is increased from small to large, a small hole is drilled when the upper part is looser soil layer, the diameter of the drilled hole is more than 200mm smaller than the inner diameter of the steel pipe pile, the diameter of the drilled hole is expanded when the lower part is hard rock layer, and the diameter of the drilled hole is 100-200 mm larger than the inner diameter of the steel pipe pile;
during the hole cleaning process, lifting the drilling tool to be 30-50 cm away from the bottom of the hole, slowly rotating the drilling tool, supplementing high-quality slurry, performing reverse circulation hole cleaning, and simultaneously keeping a water head in the hole to prevent hole collapse;
when the steel pipe pile implanting process is carried out, firstly, a drilling machine is moved away, the steel pipe pile is hoisted and erected from a transport pile in a lifting and hanging mode of matching a main crane ship and an auxiliary crane ship, the steel pipe pile is placed into a steel casing through the main crane ship, then the steel pipe pile is positioned to the pile center position of the steel casing through a positioning system, then a jack on a lower platform is adopted to hold the steel pipe pile tightly, the center deviation of the steel pipe pile is confirmed to be within an error, the steel pipe pile is slowly lowered by the main crane ship after the verticality of the steel pipe pile meets the requirement, until the steel pipe pile stops sinking, then a hydraulic pile driving hammer is sleeved at the top of the steel pipe pile, after the steel pipe pile sinks to be stable, the hydraulic pile driving hammer slowly hammers a pile top tool flange with small energy, and the striking energy of the hydraulic pile driving hammer is increased from small energy to high energy until the steel;
when the bottom sealing concrete pouring process is carried out, the height of the bottom sealing is 1.5m, C40 underwater undispersed concrete is adopted, and a vertical guide pipe method is adopted for carrying out three-point pouring, wherein the three-point pouring comprises the steps of guide pipe installation, secondary hole cleaning, underwater concrete pouring and secondary pouring;
when the pile outer wall backfill grouting process is carried out, grouting is carried out between the outer wall of the bottom of the steel pipe pile and rock soil;
and when the steel protection cylinder recycling process is carried out, the steel protection cylinder is pulled out through a hydraulic four-linkage vibration hammer.
According to the construction process of the offshore wind power foundation implanted rock-socketed single pile, before the drilling and hole forming step of the drilling process is completed, high-pressure jet grouting pile construction is performed to prevent hole collapse; the high-pressure rotary jet grouting pile construction comprises the working procedures of drilling, lower jet pipe, jetting and pile forming; the inner diameter phi of the drilled hole is 600mm, the drilled hole is annularly arranged along the inner wall 300mm of the steel casing with the inner diameter phi of 750mm, and adjacent holes are lapped by 100 mm; when in rotary spraying, the spraying pressure is 0.6-0.8 MPa, and the spraying flow is 0.8-1.2 m 3/min; the lifting speed of the jet pipe is 10-15 cm/min, and the rotating speed of the jet pipe is 10-15 r/min.
According to the construction process of the offshore wind power foundation implantation type rock-socketed single pile, when the steel pipe pile implantation process is carried out, a pile top tool flange is installed at the top of the steel pipe pile, is of an L-shaped cross section structure, and is tightly attached and connected with the pile top flange through a connecting bolt.
In the construction process of the offshore wind power foundation implanted rock-socketed single pile, when the guide pipe installation step of the bottom sealing concrete pouring process is carried out, an operation platform is firstly erected at the top of the steel pipe pile, and three guide pipes with the inner diameter of 300mm and three grouting material hoppers connected with the tops of the three guide pipes are installed on the operation platform; the three guide pipes are arranged in the pile hole in an equilateral triangle manner by connecting the centers of the three guide pipes, the side length of each equilateral triangle is equal to the flowing radius of the concrete by 2.5-4.0 m, and the distance from the bottom end of each guide pipe to the bottom of the pile hole is 30-50 cm; when the secondary hole cleaning step is carried out, firstly, the air pipe is put into the guide pipe, the upper part of the air pipe is connected with an air pipe of the air compressor through a special joint, and the special joint is connected with the guide pipe; lifting the guide pipe to a certain height, wherein the height is determined according to the deposition thickness of the bottom of the pile hole, then starting an air compressor to supply air, slowly lowering the guide pipe while circulating after the air lift reverse circulation is normal until the guide pipe is lowered to the bottom of the pile hole, and removing sediment at the bottom of the pile hole when the sand content in the discharged slurry meets the requirement; when the underwater concrete pouring step is carried out, the concrete is mixed on site and then is pumped into the guide pipe, and pouring is carried out from the bottom of the hole upwards; and when the secondary driving step is carried out, a hydraulic pile driving hammer is adopted to drive the steel pipe pile to the designed elevation before the initial setting of the concrete.
In the construction process of the offshore wind power foundation implanted rock-socketed single pile, when the backfill grouting process of the outer wall of the pile is carried out, four sets of grouting systems are arranged, and each set of grouting system comprises four grouting pipes and four grout return pipes; during grouting, firstly, grouting is carried out on a pile end grouting system, a grout return pipe is plugged when the grout return pipe discharges grout, grouting is carried out on the grouting pipe continuously until the rated grouting pressure is reached, and grouting is stopped and a grouting opening is plugged after the grouting flow is less than 2L/min and maintained for 0.5h under the rated grouting pressure or when the grouting flow is suddenly increased and the grouting pressure is suddenly reduced in the grouting process.
The construction process of the offshore wind power foundation implanted rock-socketed single pile adopts the pile stabilizing platform for auxiliary positioning, adopts the steel casing for rock-socketed construction, adopts the main crane ship and the auxiliary crane ship to be matched to lift and insert the steel pipe pile into the steel casing, can efficiently finish pile sinking construction, is also provided with the appropriate hammering equipment and drilling equipment, monitors and adjusts the posture of the steel pipe pile in the whole course to ensure that the single pile is smoothly and vertically driven into a seabed rock layer, simultaneously adopts targeted measures to keep the hole wall stable, prevents abnormal conditions such as drill jamming, drill burying and the like, ensures the bearing capacity and the stability of a pile body of the rock-socketed single pile, effectively improves the construction efficiency, effectively improves the horizontal resistance and the anti-pulling capacity of the rock-socketed pile, and meets the requirements of engineering structure design and construction.
Drawings
FIG. 1 is a flow chart of the construction process of the offshore wind power foundation implanted rock-socketed mono-pile of the present invention;
FIG. 2a is a front view of a pile stabilizing platform adopted in the construction process of the offshore wind power foundation implanted rock-socketed single pile;
figure 2b is a schematic plan view of the upper deck of the lower deck of the pile stabilized platform of the present invention;
figure 2c is a schematic plan view of the lower one of the lower platforms of the pile stabilized platform of the present invention;
FIG. 3 is a state diagram of the construction process of the offshore wind power foundation implanted rock-socketed single pile during the steel pipe pile implantation process;
FIG. 4 is a schematic structural diagram of a grouting system adopted in the bottom-sealing concrete pouring process of the offshore wind power foundation implanted rock-socketed mono-pile construction process of the invention;
FIG. 5 is a layout diagram of a guide pipe during a bottom sealing concrete pouring process of the offshore wind power foundation implanted rock-socketed mono-pile construction process;
FIG. 6 is a schematic diagram of a grouting position during a pile outer wall backfill grouting process of the offshore wind power foundation implanted rock-socketed single pile construction process.
Detailed Description
The invention will be further explained with reference to the drawings.
Referring to fig. 1 to 6, according to the construction process of the offshore wind power foundation implanted rock-socketed mono-pile, a steel pipe pile with the diameter of 6.7m and the wall thickness of 60-80 mm is adopted, and is driven into the disintegrated strong weathering granite, the total soil penetration depth is 22.9-27.6 m, the pile top elevation is 15m, and the pile bottom elevation is about minus 43-minus 46 m.
The construction process of the offshore wind power foundation implanted rock-socketed single pile comprises the following steps: manufacturing a steel pipe pile and a steel pile casing, building a stable pile platform, inserting the steel pile casing, vibrating the steel pile casing, drilling, cleaning holes, implanting the steel pipe pile, pouring bottom sealing concrete, backfilling and grouting the outer wall of the pile and recovering the steel pile casing.
The manufacturing process of the steel pipe pile and the steel casing comprises the steps of pipe joint blanking, pipe joint groove processing, pipe joint rolling forming, pile body top flange assembling, pile body splicing and anticorrosive coating.
The pile stabilizing platform 10 comprises an upper platform 12, a lower platform 11, four auxiliary process piles 13, two positioning process piles 14, an outer keel beam 15 and a set of positioning system consisting of twelve 100T jacks 20; the lower platform 11 is composed of an upper platform 111 and a lower platform 112, seven jacks 20 are arranged on the upper platform 111 around the closure, and five jacks 20 are arranged on the lower platform 112 around the closure and staggered with the seven jacks 20 on the upper platform 111; the outer keel beam 15 is installed at the keel of the upper deck 111 after the steel pipe pile 100 is inserted into the keel (see fig. 2a to 2 c).
The pile stabilizing platform building process comprises the following steps:
the lower platform and the four auxiliary process piles are positioned through the relative positions of the positioning platform ship and steel pipe piles at the closure of the lower platform, then the four auxiliary process piles are inserted and driven, and then the auxiliary process piles and the upper and lower parts of auxiliary process pile sleeves on the lower platform are firmly welded through steel plates;
moving away the positioning platform ship, inserting and driving two positioning process piles, and firmly welding the positioning process piles with the upper and lower parts of a positioning process pile sleeve on the lower platform through steel plate strips;
and thirdly, installing an upper platform after the ③ steel casing insertion process is finished so as to carry out rock-socketed construction.
The steel casing inserting process comprises the following steps:
firstly, processing a lower platform of a pile stabilizing platform into a guide frame platform, wherein the center of the guide frame platform is the center of the steel pipe pile;
lifting the steel casing to a guide frame platform by the auxiliary lifting boat and slowly falling into the guide frame platform, stopping sinking when the steel casing passes through a lower platform of the guide frame platform, measuring the verticality of the steel casing by two leveling rulers, and tightly holding the steel casing at the bottom layer of the guide frame platform by a hydraulic jack after the verticality meets the requirement, and slowly sinking;
and thirdly, when the steel pile casing sinks to the mud surface junction, measuring and rechecking the verticality of the steel pile casing, continuing to sink to be stable according to the requirement, sleeving the hydraulic four-linkage vibration hammer at the top of the steel pile casing, lifting the hydraulic four-linkage vibration hammer by an auxiliary crane ship, vibrating and sinking the steel pile casing, waiting for the penetration of the steel pile casing to reach the standard of stopping the hammer, rechecking the verticality of the steel pile casing by stopping the hammer, and meeting the design requirement and then reinforcing the connection between the steel pile casing and the guide frame platform.
The drilling process comprises the steps of positioning a drilling machine, installing a drill rod, preparing slurry and drilling to form a hole;
when the drilling machine is in place, firstly hanging away a hydraulic four-linkage vibration hammer, then erecting the drilling machine, adopting a gas-lift reverse circulation hydraulic power drilling machine provided with a hob bit, locking the drilling machine and a steel casing through a pile gripper, and ensuring that the center of the drilling machine bit and the center of the steel casing are on the same plumb line, wherein the deviation is not more than 10 cm;
during the step of installing the drill rod, during initial drilling, the drill bit consists of a heavy balancer and a heavy drill rod; the drill bit and the drill rod are assembled on a deck of the main crane ship and then are installed on the drilling machine, and in the drilling process, the second section of drill rod and the subsequent drill rods are directly installed on a platform of the main crane ship;
when the step of preparing the slurry is carried out, the retaining wall slurry adopts the PHP high-performance slurry which is not dispersed, has low solid phase and high viscosity, firstly the bentonite slurry is stirred by a slurry stirrer in a slurry pool, then the bentonite slurry is pumped into the steel retaining cylinder by a slurry pump, and when the performance index of the slurry in the steel retaining cylinder meets the construction requirement, a hole is drilled;
when the drilling pore-forming step is carried out, a slurry retaining wall is adopted, water is timely supplemented into the steel retaining cylinder, and the water head difference between the inside and the outside of the steel retaining cylinder is kept; when a drilling machine starts to drill holes, the diameter of the drilled holes is increased from small to large, small holes are drilled when the upper part of the drilled holes is looser than a loose soil layer, the diameter of the drilled holes is required to be more than 200mm smaller than the inner diameter of the steel pipe pile so as to ensure the vertical bearing capacity of the steel casing, the diameter of the drilled holes is required to be enlarged when the drilled holes meet a hard rock layer at the lower part, and the diameter of the drilled holes is 100-200 mm larger;
before the drilling and hole forming step, in order to prevent hole collapse, high-pressure jet grouting pile construction is firstly carried out, wherein the high-pressure jet grouting pile construction comprises the working procedures of drilling, lower jet pipe injection and pile forming; the inner diameter phi of the drilled hole is 600mm, the drilled hole is annularly arranged along the inner wall 300mm of the steel casing with the inner diameter phi of 750mm, and adjacent holes are lapped by 100 mm; when in rotary spraying, the spraying pressure is 0.6-0.8 MPa, and the spraying flow is 0.8-1.2 m 3/min; the lifting speed of the jet pipe is 10-15 cm/min, and the rotating speed of the jet pipe is 10-15 r/min.
When the hole cleaning process is carried out, lifting the drilling tool to be 30-50 cm away from the bottom of the hole, slowly rotating the drilling tool, supplementing high-quality slurry, carrying out reverse circulation hole cleaning, and simultaneously keeping a water head in the hole to prevent hole collapse;
when the steel pipe pile implantation process is carried out, drilling and cleaning holes in a steel pile casing to a designed elevation, stopping in time to remove a drill rod after the final hole acceptance is finished, moving a drilling machine away, placing a main hanging ship and an auxiliary hanging ship in place, hoisting and erecting the steel pipe pile from a pile transportation barge in a mode that the main hanging ship and the auxiliary hanging ship are matched for hoisting, connecting the main hanging ship with a main lifting lug at the upper part of the steel pipe pile, connecting the auxiliary hanging ship with a turnover lifting lug at the lower part of the steel pipe pile, placing the steel pipe pile into the steel pile casing through the main hanging ship, positioning the steel pipe pile 100 to the pile center position of the steel pile casing 300, tightly holding the steel pipe pile by a jack on a lower platform, confirming that the center deviation of the steel pipe pile is within an error, slowly lowering the steel pipe pile by using the main hanging ship after the verticality of the steel pipe pile meets the requirement, stopping sinking of the steel pipe pile, sleeving a hydraulic pile hammer on the top of the steel pipe pile, and, the hydraulic pile hammer slowly hammers the pile top tool flange with small energy, the pile top tool flange is of an L-shaped cross section structure, and is tightly attached and connected with the pile top flange through a connecting bolt, so that the hydraulic pile hammer hammers the pile top tool flange to protect the pile top flange from being damaged during hammering; the striking energy of the hydraulic pile hammer is increased from small to large until the steel pipe pile reaches the designed bottom elevation; closely paying attention to the perpendicularity of the pile body in the pile sinking process, and ensuring that the perpendicularity of the steel pipe pile is within 3 per mill (see figure 3);
when the bottom sealing concrete pouring process is carried out, the height of the bottom sealing is 1.5m, C40 underwater undispersed concrete is adopted, and a vertical guide pipe method is adopted for carrying out three-point pouring, wherein the three-point pouring comprises the steps of guide pipe installation, secondary hole cleaning, underwater concrete pouring and secondary pouring;
in the guide pipe installation step, an operation platform is firstly erected at the top of the steel pipe pile, and three guide pipes 30 with the inner diameter of 300mm, and a grouting inner hopper 31 and an outer hopper 32 (see fig. 4 and 5) which are sequentially connected with the tops of the three guide pipes 30 are installed on the operation platform; the three guide pipes 30 are arranged in the pile hole in an equilateral triangle manner by connecting the centers of the three guide pipes, the side length of each equilateral triangle is equal to the flowing radius of the concrete by 2.5-4.0 m, and the distance from the bottom end of each guide pipe 30 to the bottom of the pile hole is 30-50 cm;
when the secondary hole cleaning step is carried out, firstly, the air pipe is put into the guide pipe, the upper part of the air pipe is connected with an air pipe of the air compressor through a special joint, and the special joint is connected with the guide pipe; lifting the guide pipe to a certain height, wherein the height is determined according to the deposition thickness of the bottom of the pile hole, then starting an air compressor to supply air, slowly lowering the guide pipe while circulating after the air lift reverse circulation is normal until the guide pipe is lowered to the bottom of the pile hole, and removing sediment at the bottom of the pile hole when the sand content in the discharged slurry meets the requirement;
when the underwater concrete pouring step is carried out, the concrete is mixed on site and then is pumped into the guide pipe, and pouring is carried out from the bottom of the hole upwards;
and in the secondary driving step, the steel pipe pile is driven to the designed elevation by adopting a vibration hammer before the initial setting of the concrete.
When the pile outer wall backfill grouting process is carried out, grouting is carried out between the outer wall of the bottom of the steel pipe pile 100 and rock soil (see figure 6); four sets of grouting systems are arranged, and each set of grouting system comprises four grouting pipes and four slurry return pipes; when grouting, firstly grouting a grouting system at the end part of the pile, plugging the grout return pipe when the grout return pipe is discharged, continuing grouting the grouting pipe until the rated grouting pressure is reached, and stopping grouting and plugging a grouting port when the grouting flow is less than 2L/min and is maintained for 0.5h under the rated grouting pressure or when the grouting flow is increased and the grouting pressure is suddenly reduced in the grouting process.
The construction process of the implanted rock-socketed pile of the offshore wind power foundation adopts the pile stabilizing platform for auxiliary positioning, adopts the steel casing for rock-socketed construction, adopts the main crane ship and the auxiliary crane ship to be matched to lift and insert the steel pipe pile into the steel casing, can efficiently finish pile sinking construction, is also provided with the appropriate hammering equipment and drilling equipment, monitors and adjusts the posture of the steel pipe pile in the whole course to ensure that the single pile is smoothly and vertically driven into a seabed rock layer, simultaneously adopts targeted measures to keep the hole wall stable, prevents abnormal conditions such as drill jamming, drill burying and the like, ensures the bearing capacity and the stability of a pile body of the non-rock-socketed single pile, effectively improves the construction efficiency, effectively improves the horizontal resistance and the anti-pulling capacity of the rock-socketed pile, and meets the requirements of engineering structure design and construction.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and therefore all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (5)

1. A construction process of an implanted rock-socketed single pile of an offshore wind power foundation is characterized in that a steel pipe pile with the diameter of 6.7m and the wall thickness of 60-80 mm is adopted for driving the single pile into fractured strongly weathered granite, the total soil penetration depth is 22.9-27.6 m, the pile top elevation is 15m, and the pile bottom elevation is about minus 43-minus 46 m; the construction process comprises the following steps: manufacturing a steel pipe pile and a steel pile casing, building a stable pile platform, inserting the steel pile casing, vibrating the steel pile casing, drilling, cleaning holes, implanting the steel pipe pile, pouring bottom sealing concrete, backfilling and grouting the outer wall of the pile and recovering the steel pile casing; it is characterized in that the preparation method is characterized in that,
the manufacturing process of the steel pipe pile and the steel casing comprises the steps of blanking of a pipe joint, processing of a pipe joint groove, rolling and forming of the pipe joint, assembling of a flange at the top of a pile body, splicing of the pile body and coating of an anticorrosive coating;
the pile stabilizing platform erection process comprises the following steps:
the lower platform and the four auxiliary process piles are positioned through the relative positions of the positioning platform ship and steel pipe piles at the closure of the lower platform, then the four auxiliary process piles are inserted and driven, and then the auxiliary process piles and the upper and lower parts of auxiliary process pile sleeves on the lower platform are firmly welded through steel plate strips;
moving away the positioning platform ship, inserting and driving two positioning process piles, and firmly welding the positioning process piles with the upper and lower parts of a positioning process pile sleeve on the lower platform through steel plate strips;
thirdly, installing an upper platform after the ③ steel casing insertion process is finished;
the steel casing inserting process comprises the following steps:
firstly, processing a lower platform of a pile stabilizing platform into a guide frame platform, wherein the center of the guide frame platform is the center of the steel pipe pile;
lifting the steel casing to a guide frame platform by the auxiliary lifting boat and slowly falling into the guide frame platform, stopping sinking when the steel casing passes through a lower platform of the guide frame platform, measuring the verticality of the steel casing by two leveling rulers, and tightly holding the steel casing at the bottom layer of the guide frame platform by a hydraulic jack after the verticality meets the requirement, and slowly sinking;
measuring and rechecking the verticality of the steel casing when the steel casing is sunk to the mud surface junction, continuing to sink to be stable after meeting the requirement, sleeving the steel casing with a hydraulic four-linkage vibrating hammer at the top of the steel casing, lifting the hydraulic four-linkage vibrating hammer with an auxiliary crane ship, vibrating and sinking the steel casing, and rechecking the verticality of the steel casing when the penetration of the steel casing reaches the hammer stopping standard, and then reinforcing the connection between the steel casing and the guide frame platform after the hammer is stopped and the verticality of the steel casing is rechecked;
the drilling process comprises the steps of positioning a drilling machine, installing a drill rod, preparing slurry and drilling to form a hole;
when the drilling machine is in place, firstly hanging away a hydraulic four-linkage vibration hammer, then erecting the drilling machine, adopting a gas-lift reverse circulation hydraulic power drilling machine provided with a hob bit, and locking the drilling machine and the steel casing through a pile gripper;
when the step of installing the drill rod is carried out, the drill bit and the drill rod are assembled on a deck of the main crane ship and then installed on the drilling machine;
when the step of preparing the slurry is carried out, the retaining wall slurry adopts the PHP high-performance slurry which is not dispersed, has low solid phase and high viscosity, firstly the bentonite slurry is stirred by a slurry stirrer in a slurry pool, then the bentonite slurry is pumped into the steel retaining cylinder by a slurry pump, and when the performance index of the slurry in the steel retaining cylinder meets the construction requirement, a hole is drilled;
when the drilling hole forming step is carried out, when a drilling machine starts drilling, the diameter of the drilled hole is increased from small to large, a small hole is drilled when the upper part is looser soil layer, the diameter of the drilled hole is more than 200mm smaller than the inner diameter of the steel pipe pile, the diameter of the drilled hole is expanded when the lower part is hard rock layer, and the diameter of the drilled hole is 100-200 mm larger than the inner diameter of the steel pipe pile;
during the hole cleaning process, lifting the drilling tool to be 30-50 cm away from the bottom of the hole, slowly rotating the drilling tool, supplementing high-quality slurry, performing reverse circulation hole cleaning, and simultaneously keeping a water head in the hole to prevent hole collapse;
when the steel pipe pile implanting process is carried out, firstly, a drilling machine is moved away, the steel pipe pile is hoisted and erected from a transport pile in a lifting and hanging mode of matching a main crane ship and an auxiliary crane ship, the steel pipe pile is placed into a steel casing through the main crane ship, then the steel pipe pile is positioned to the pile center position of the steel casing through a positioning system, then a jack on a lower platform is adopted to hold the steel pipe pile tightly, the center deviation of the steel pipe pile is confirmed to be within an error, the steel pipe pile is slowly lowered by the main crane ship after the verticality of the steel pipe pile meets the requirement, until the steel pipe pile stops sinking, then a hydraulic pile driving hammer is sleeved at the top of the steel pipe pile, after the steel pipe pile sinks to be stable, the hydraulic pile driving hammer slowly hammers a pile top tool flange with small energy, and the striking energy of the hydraulic pile driving hammer is increased from small energy to high energy until the steel;
when the bottom sealing concrete pouring process is carried out, the height of the bottom sealing is 1.5m, C40 underwater undispersed concrete is adopted, and a vertical guide pipe method is adopted for carrying out three-point pouring, wherein the three-point pouring comprises the steps of guide pipe installation, secondary hole cleaning, underwater concrete pouring and secondary pouring;
when the pile outer wall backfill grouting process is carried out, grouting is carried out between the outer wall of the bottom of the steel pipe pile and rock soil;
and when the steel protection cylinder recycling process is carried out, the steel protection cylinder is pulled out through a hydraulic four-linkage vibration hammer.
2. The offshore wind power foundation implanted rock-socketed mono-pile construction process according to claim 1, wherein before the drilling and hole forming step of the drilling process is completed, high-pressure jet grouting pile construction is performed to prevent hole collapse; the high-pressure rotary jet grouting pile construction comprises the working procedures of drilling, lower jet pipe, jetting and pile forming; the inner diameter phi of the drilled hole is 600mm, the drilled hole is annularly arranged along the inner wall 300mm of the steel casing with the inner diameter phi of 750mm, and adjacent holes are lapped by 100 mm; when in rotary spraying, the spraying pressure is 0.6-0.8 MPa, and the spraying flow is 0.8-1.2 m 3/min; the lifting speed of the jet pipe is 10-15 cm/min, and the rotating speed of the jet pipe is 10-15 r/min.
3. The offshore wind power foundation implantation type rock-socketed mono-pile construction process according to claim 1, wherein a pile top tooling flange is installed at the top of the steel pipe pile during the steel pipe pile implantation process, the pile top tooling flange is of an L-shaped cross-section structure, and is tightly attached and connected with the pile top flange through a connecting bolt.
4. The offshore wind power foundation implanted rock-socketed single pile construction process according to claim 1, wherein in the conduit installation step of the back cover concrete pouring process, an operation platform is firstly erected at the top of the steel pipe pile, and three conduits with the inner diameter of 300mm and grouting material hoppers connected with the tops of the three conduits are installed on the operation platform; the three guide pipes are arranged in the pile hole in an equilateral triangle manner by connecting the centers of the three guide pipes, the side length of each equilateral triangle is equal to the flowing radius of the concrete by 2.5-4.0 m, and the distance from the bottom end of each guide pipe to the bottom of the pile hole is 30-50 cm; when the secondary hole cleaning step is carried out, firstly, the air pipe is put into the guide pipe, the upper part of the air pipe is connected with an air pipe of the air compressor through a special joint, and the special joint is connected with the guide pipe; lifting the guide pipe to a certain height, wherein the height is determined according to the deposition thickness of the bottom of the pile hole, then starting an air compressor to supply air, slowly lowering the guide pipe while circulating after the air lift reverse circulation is normal until the guide pipe is lowered to the bottom of the pile hole, and removing sediment at the bottom of the pile hole when the sand content in the discharged slurry meets the requirement; when the underwater concrete pouring step is carried out, the concrete is mixed on site and then is pumped into the guide pipe, and pouring is carried out from the bottom of the hole upwards; and when the secondary driving step is carried out, a hydraulic pile driving hammer is adopted to drive the steel pipe pile to the designed elevation before the initial setting of the concrete.
5. The offshore wind power foundation implanted rock-socketed mono-pile construction process according to claim 1, wherein when the pile outer wall backfill grouting process is performed, four sets of grouting systems are provided, each set of grouting system comprises four grouting pipes and four back grouting pipes; during grouting, firstly, grouting is carried out on a pile end grouting system, a grout return pipe is plugged when the grout return pipe discharges grout, grouting is carried out on the grouting pipe continuously until the rated grouting pressure is reached, and grouting is stopped and a grouting opening is plugged after the grouting flow is less than 2L/min and maintained for 0.5h under the rated grouting pressure or when the grouting flow is suddenly increased and the grouting pressure is suddenly reduced in the grouting process.
CN201810698964.6A 2018-06-29 2018-06-29 Construction process of offshore wind power foundation implanted rock-socketed single pile Active CN108842807B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810698964.6A CN108842807B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation implanted rock-socketed single pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810698964.6A CN108842807B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation implanted rock-socketed single pile

Publications (2)

Publication Number Publication Date
CN108842807A true CN108842807A (en) 2018-11-20
CN108842807B CN108842807B (en) 2020-07-31

Family

ID=64199873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810698964.6A Active CN108842807B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation implanted rock-socketed single pile

Country Status (1)

Country Link
CN (1) CN108842807B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930605A (en) * 2019-02-25 2019-06-25 上海智平基础工程有限公司 A kind of method that pile foundation construction removes sediment
CN110130343A (en) * 2019-05-09 2019-08-16 中铁四局集团第二工程有限公司 Steel casing planting construction method suitable for deep water bare rock condition
CN110777780A (en) * 2019-10-25 2020-02-11 天津大学 Concrete pipe pile offshore pile sinking construction method
CN111058439A (en) * 2019-12-23 2020-04-24 青岛森建基础工程有限公司 Construction method of immersed tube rock-socketed cast-in-place pile
CN111236215A (en) * 2020-02-13 2020-06-05 中交第三航务工程局有限公司 Rock-socketed construction process of large-diameter steel pipe inclined pile of offshore wind power high-rise pile cap foundation
CN111749259A (en) * 2020-06-19 2020-10-09 中交第一航务工程局有限公司 Equipment and construction method suitable for rock-socketed construction of offshore wind power high-rise pile cap foundation
CN112900479A (en) * 2021-01-27 2021-06-04 中交第三航务工程局有限公司宁波分公司 Construction method of implanted single-pile foundation of ocean tidal current energy generator set
CN113957900A (en) * 2021-09-26 2022-01-21 广东华蕴海上风电科技有限公司 Grouting and bottoming implementation method for large-diameter rock-socketed single pile
CN114370041A (en) * 2021-12-30 2022-04-19 中国能源建设集团广东省电力设计研究院有限公司 Basic platform of offshore converter station
CN114482110A (en) * 2021-12-29 2022-05-13 湖南省正邦建设工程有限公司 Steel casing group pile concrete expanded foundation construction device and construction method
CN114837178A (en) * 2022-06-09 2022-08-02 上海博强重工集团有限公司 Installation method of wind power foundation pile
CN114892646A (en) * 2022-06-16 2022-08-12 深圳市市政工程总公司 Construction method for rotary excavation bored pile in cofferdam
CN114960635A (en) * 2022-06-09 2022-08-30 中交第二航务工程勘察设计院有限公司 Implanted steel pipe pile self-anchoring structure and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100232878A1 (en) * 2009-03-10 2010-09-16 Vitaly Boris Feygin Universal Framed Cofferdam
CN103924585A (en) * 2014-05-06 2014-07-16 江苏蓝潮海洋风电工程建设有限公司 Novel method for constructing wind power rock-embedded pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100232878A1 (en) * 2009-03-10 2010-09-16 Vitaly Boris Feygin Universal Framed Cofferdam
CN103924585A (en) * 2014-05-06 2014-07-16 江苏蓝潮海洋风电工程建设有限公司 Novel method for constructing wind power rock-embedded pile

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
张跃辉: "超大直径钢管桩近海施工关键技术", 《中国港湾建设》 *
朱立群: "高压旋喷桩在钻孔桩塌孔与串孔漏浆处理中的应用", 《价值工程》 *
李志义等: "《秦沈客运专线施工技术》", 31 October 2005, 中国铁道出版社 *
闫富有等: "《地下工程施工》", 31 December 2011, 黄河水利出版社 *
顾孙平等: "《建筑基桩通论》", 31 January 2016, 同济大学出版社 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109930605A (en) * 2019-02-25 2019-06-25 上海智平基础工程有限公司 A kind of method that pile foundation construction removes sediment
CN110130343A (en) * 2019-05-09 2019-08-16 中铁四局集团第二工程有限公司 Steel casing planting construction method suitable for deep water bare rock condition
CN110777780A (en) * 2019-10-25 2020-02-11 天津大学 Concrete pipe pile offshore pile sinking construction method
CN111058439B (en) * 2019-12-23 2022-03-08 青岛森建基础工程有限公司 Construction method of immersed tube rock-socketed cast-in-place pile
CN111058439A (en) * 2019-12-23 2020-04-24 青岛森建基础工程有限公司 Construction method of immersed tube rock-socketed cast-in-place pile
CN111236215A (en) * 2020-02-13 2020-06-05 中交第三航务工程局有限公司 Rock-socketed construction process of large-diameter steel pipe inclined pile of offshore wind power high-rise pile cap foundation
CN111749259A (en) * 2020-06-19 2020-10-09 中交第一航务工程局有限公司 Equipment and construction method suitable for rock-socketed construction of offshore wind power high-rise pile cap foundation
CN112900479A (en) * 2021-01-27 2021-06-04 中交第三航务工程局有限公司宁波分公司 Construction method of implanted single-pile foundation of ocean tidal current energy generator set
CN113957900A (en) * 2021-09-26 2022-01-21 广东华蕴海上风电科技有限公司 Grouting and bottoming implementation method for large-diameter rock-socketed single pile
CN114482110A (en) * 2021-12-29 2022-05-13 湖南省正邦建设工程有限公司 Steel casing group pile concrete expanded foundation construction device and construction method
CN114482110B (en) * 2021-12-29 2024-06-11 湖南省正邦建设工程有限公司 Steel pile casing pile group concrete enlarged foundation construction device and construction method
CN114370041A (en) * 2021-12-30 2022-04-19 中国能源建设集团广东省电力设计研究院有限公司 Basic platform of offshore converter station
CN114837178A (en) * 2022-06-09 2022-08-02 上海博强重工集团有限公司 Installation method of wind power foundation pile
CN114960635A (en) * 2022-06-09 2022-08-30 中交第二航务工程勘察设计院有限公司 Implanted steel pipe pile self-anchoring structure and construction method thereof
CN114892646A (en) * 2022-06-16 2022-08-12 深圳市市政工程总公司 Construction method for rotary excavation bored pile in cofferdam

Also Published As

Publication number Publication date
CN108842807B (en) 2020-07-31

Similar Documents

Publication Publication Date Title
CN108842807B (en) Construction process of offshore wind power foundation implanted rock-socketed single pile
CN108842806B (en) Construction process of offshore wind power foundation non-rock-socketed single pile
CN206721958U (en) A kind of full-automatic open caisson digging system of major diameter
WO2017020697A1 (en) Construction device and method for offshore wind turbine foundation with piling performed later
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN107059906A (en) A kind of method that utilization underground shaft robot applies major diameter open caisson
CN112012237A (en) Multi-cylinder reinforced composite single-pile foundation of offshore wind turbine and construction method
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN113006075B (en) Steel pipe pile implanting method for implanting rock-socketed pile foundation construction
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN113818460A (en) Cofferdam construction method based on high-standard environmental protection requirement
CN111997062A (en) Method for treating support deviation of steel sheet pile in coastal soft soil deep foundation pit
CN104563126B (en) Construction method for bored pile by rotary drilling rig
EP2261425A1 (en) Hybrid offshore large pile - gravity foundation for constructions, and installation method therefor
WO2011023745A1 (en) Method of installation of large diameter piles
CN212200387U (en) Diaphragm wall foundation steel guide wall structure in deep water soft silt area
CN202969333U (en) Steel truss rock-socketed wharf structure
AU2012313196A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN114960715B (en) Underground engineering surge treatment device and control method
JP2020128672A (en) Installation method of mono-pile foundation for offshore wind power generation and mono-pile foundation for offshore wind power generation
CN109930624A (en) A kind of embedding petrographic province blower foundation of offshore wind farm and construction method
CN214738266U (en) Vertical jacking implementation structure in underwater tunnel suitable for hard stratum
CN209816867U (en) A supporting construction for peripheral foundation ditch of existing building
CN112523225A (en) Construction method for supporting foundation pit by combining static pressure steel sheet pile with reinforced concrete inner support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee after: CCCC Third Aviation Bureau Sixth Engineering (Xiamen) Co.,Ltd.

Patentee after: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee before: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee before: CCCC Sanya (Xiamen) Engineering Co.,Ltd.

Patentee before: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.