CN108842806A - A kind of construction technology of the non-embedding rock single pile of offshore wind power foundation - Google Patents

A kind of construction technology of the non-embedding rock single pile of offshore wind power foundation Download PDF

Info

Publication number
CN108842806A
CN108842806A CN201810697687.7A CN201810697687A CN108842806A CN 108842806 A CN108842806 A CN 108842806A CN 201810697687 A CN201810697687 A CN 201810697687A CN 108842806 A CN108842806 A CN 108842806A
Authority
CN
China
Prior art keywords
steel
pipe pile
pile
platform
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810697687.7A
Other languages
Chinese (zh)
Other versions
CN108842806B (en
Inventor
熊汉东
傅晓亮
庞双喜
黄桥兴
丁友文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Third Aviation Bureau Sixth Engineering Xiamen Co ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Sanhang (xiamen) Engineering Co Ltd, China Construction Third Engineering Bureau Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical In Sanhang (xiamen) Engineering Co Ltd
Priority to CN201810697687.7A priority Critical patent/CN108842806B/en
Publication of CN108842806A publication Critical patent/CN108842806A/en
Application granted granted Critical
Publication of CN108842806B publication Critical patent/CN108842806B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of construction technologies of the non-embedding rock single pile of offshore wind power foundation, including following below scheme:Steel-pipe pile production, steady stake putting up platform, pitching pile, first strike pile sinking, drilling, borehole cleaning and strike-on pile sinking.Pitching pile process includes steel-pipe pile lifting, steel-pipe pile enters Longkou, steel-pipe pile positioning is held tightly and steel-pipe pile sinks and sets step.Drilling process includes drilling machine in place, installation drilling rod, slurrying and drilling and forming hole step.Construction technology of the invention is respectively into the Longkou stage, heavy set the stage, opens the hammer last stage, normal pile sinking stage, continuous pile sinking stage, pile head elevation control stage also in the verticality of six stage control steel-pipe piles.Construction technology of the invention, can be improved construction efficiency, effectively improves the horizontal resistivity and anti-group of ability of non rock rooted pile, meets the requirement of Structural Design and construction.

Description

A kind of construction technology of the non-embedding rock single pile of offshore wind power foundation
Technical field
The present invention relates to a kind of construction technologies of the non-embedding rock single pile of offshore wind power foundation.
Background technique
Wind power plant basic engineering field at sea, according to different earth formation and characteristic, and according to each rock-soil layer origin cause of formation Type and engineering characteristic carry out comprehensive division, and the single-pile foundation generallyd use includes non-embedding rock single pile, embedding rock single pile and embedded type Embedding rock single pile.The construction of pile foundation is the leading engineering of offshore wind farm project, and for separate land and the depth of water is up to 16m~19m's Off-lying sea carries out the construction of offshore wind farm without shielding region, due to the constraint by natural conditions such as meteorology, trend, waves, and is in Take place frequently region and Fan Equipment of tropical storm has very high requirement to the carrying on basis, withdrawal resistance, deformation, it is therefore desirable to Pile foundation diameter is big, embedded depth is deep, so that blower foundation can bear huge blower tilting moment and bear wave, water flow lotus Load effect, there are also be exactly construction speed duration control it is particularly critical.
Summary of the invention
A kind of non-embedding rock single pile of offshore wind power foundation is provided it is an object of the invention to overcome the deficiencies of existing technologies Construction technology, it can be improved construction efficiency, effectively improves the horizontal resistivity and anti-group of ability of non rock rooted pile, meets engineering The requirement of structure design and construction.
The object of the present invention is achieved like this:A kind of construction technology of the non-embedding rock single pile of offshore wind power foundation, it is involved Single pile using 7.0~7.3m of diameter, 60~80mm of wall thickness steel-pipe pile, squeeze into cataclastic shape strong weathered granite, always bury Depth is 39.2~45.9m, height of pile top 15m, stake bottom about -54~-63m of absolute altitude;
Construction technology of the invention includes following below scheme:Steel-pipe pile production, is bored steady stake putting up platform, pitching pile, first strike pile sinking Hole, borehole cleaning, strike-on pile sinking;
The steel-pipe pile production process includes tube coupling blanking, tube coupling retaining wall on slope, tube coupling roll-forming, pile body top flange Assembly, pile body splicing and corrosion-inhibiting coating coating step;The diameter of manufactured steel-pipe pile is 7.0~7.3m, wall thickness is 60~80mm;
The steady stake putting up platform process includes the following steps:
1. steady stake platform includes upper and lower platform, four auxiliary process stakes, two positioning process stakes and a set of positioning system; Lower platform and four auxiliary process stakes first pass through steel-pipe pile relative position at the Longkou of locating platform ship and lower platform and are positioned, The inserting piling of four auxiliary process stakes is carried out again, then by the auxiliary process pipe casing upper and lower part in auxiliary process stake and lower platform Pass through steel plate strip firm welding;
2. locating platform ship is first removed, then two positioning process stakes of inserting piling, it then will be in positioning process stake and lower platform Positioning process pipe casing upper and lower part passes through steel plate strip firm welding;
3. installing upper mounting plate after pitching pile process;
The pitching pile process includes steel-pipe pile lifting, steel-pipe pile enters Longkou, steel-pipe pile positioning is held tightly and steel-pipe pile sinks and sets step Suddenly;
When progress steel-pipe pile lifting step, ship is hung using master and steel-pipe pile is lifted by crane and erected by the way of ship cooperation lifts by auxiliary hang Stake;First by the main main lifting lug in two sides for hanging ship elder generation hanging buckle steel-pipe pile, every main lifting lug in side hangs two wirerope, then hangs the auxiliary ship that hangs Turn over the wirerope of lifting lug;Starting again, which makes master hang ship, hangs ship synchronous hoisting with auxiliary, when steel-pipe pile leaves the deck that pile transport is refuted completely When 0.5m, pause lifting checks the stress condition of every wirerope, continues to lift by crane after without exception;When steel-pipe pile is refuted apart from pile transport 6~7m of deck when, pile transport, which is refuted, exits construction area;Then master hangs ship and hangs ship mutual cooperation completion soldier piles with auxiliary;Complete soldier piles Afterwards, it is auxiliary hang ship and continue to transfer suspension hook so that wirerope is not stressed, while the main ship that hangs continues to rise suspension hook, when the turn lifting lug of steel-pipe pile When being in 2~3m of the water surface or more, the turn shackle on steel-pipe pile is extracted out by tender;
When carrying out the steel-pipe pile and entering Longkou step, ship lifting steel-pipe pile is hung by main, and slowly enter the dragon of steady stake platform Mouthful, start slowly to transfer steel-pipe pile when the pile center position that steel-pipe pile is in Longkou;When the turn lifting lug on steel-pipe pile away from When from steady stake platform top surface 1m, stops decentralization steel-pipe pile, then cut off lifting lug is turned over, be completed at the same time the lower platform of steady stake platform The installation of outer Longkou beam;
When carrying out the steel-pipe pile positioning holding step, the posture of steel-pipe pile is first measured, then by being arranged on steady stake platform Positioning system adjustment steel-pipe pile verticality, then adjust positioning system hold tightly steel-pipe pile;
When carrying out that the steel-pipe pile is heavy to set step, main to hang ship decentralization wirerope, steel-pipe pile is sunk down under the action of self-weight Stop sinking after certain depth under mud face, after confirmation steel-pipe pile is stablized, the main ship that hangs continues to transfer wirerope, is in wirerope not Stress and the state that do not break off relations;Sight look into 15 minutes confirmation steel-pipe piles it is unchanged after, release the wirerope at main lifting lug;
When carrying out the first strike pile sinking process, hydraulic hammer and fuller are lifted by crane by the main ship that hangs, when stake top tooling flange and liquid After hammer contact, suspension hook is gradually transferred, piling weight is stepped up, the posture for observing 15 minutes confirmation steel-pipe piles is unchanged Afterwards, hydraulic hammer is started, hydraulic hammer first sinks steel-pipe pile with small energy crawl, when steel-pipe pile buries 30m, is changed to continuously sink steel The hit energy of tubular pole, hydraulic hammer is ascending;
The drilling process includes drilling machine in place, installation drilling rod, slurrying and drilling and forming hole step;
When carrying out drilling machine step in place, hydraulic hammer is first hung, the upper mounting plate of steady stake platform is then installed, then sets up drilling machine, Using the gas lift reverse circulation hydraulic power drilling machine for being configured with drag bit and roller cutter bit, by pile gripper by drilling machine and steel-pipe pile Locking;
When carrying out installation drilling rod step, drill bit, drilling rod are installed to drilling machine after assembly well on the main deck for hanging ship again On;
Carry out slurrying step when, slurry coat method using do not disperse, low solid phase, highly viscous PHP high performance slurry, first Bentonite slurry is stirred using slurry mixer in mud pit, is then pumped in steel-pipe pile using slush pump, works as steel-pipe pile Aperture is crept into after interior mud property index meets construction requirement;The mud of reacting cycle discharge, after being purified using mud separator It is recycled;
It include following process when progress drilling and forming hole step:
1. first being crept into using drag bit clear water, welding-on array wirerope brush, wirerope brush on the outer diameter guard ring of drill bit Outer diameter be greater than 5~10cm of steel-pipe pile internal diameter, with guarantee in drilling process by steel-pipe pile inner wall stratum attachment scrub Completely;
2. after drill bit drills out steel-pipe pile, atm number, medium bit pressure, slow-speed drilling and forming hole, bore diameter is than in steel-pipe pile The small 200mm of diameter, in drilling process every piece drilling rod of drilling will cleaning bottom of hole, to guarantee that bore diameter and verticality are all satisfied requirement;
3. creep into basement rock, brill replacement roller cutter bit is mentioned, using atm number, medium bit pressure, slow-speed of revolution drilling and forming hole;? In boring procedure, preliminary surveying hole depth is carried out using run of steel;
4. protruding into progress precise measurement hole depth in hole using professional measuring staff behind whole hole;
When carrying out borehole cleaning process, by drilling tool lifting extremely from 30~50cm of bottom hole, slow rotary tools, and high-quality mud is supplemented Slurry carries out reacting cycle borehole cleaning, while head in retaining hole, prevents collapse hole;
When carrying out strike-on pile sinking process, drilling machine is removed, master hangs ship and repositions, and hydraulic hammer is seated to the top of steel-pipe pile Portion strikes to designed elevation steel-pipe pile by hydraulic hammer.
The construction technology of the non-embedding rock single pile of above-mentioned offshore wind power foundation, wherein risen in the steel-pipe pile of the pitching pile process When hanging step, first carry out it is auxiliary hang secure operation, another mistake water (flow) direction carry out it is main hangs secure, the main lifting direction for hanging ship is opposite The Longkou of steady stake platform, then berthing is refuted in pile transport, the main crane for hanging ship is rotated to the main lifting lug of steel-pipe pile, while the auxiliary ship that hangs Crane is rotated to the turn lifting lug of steel-pipe pile.
The construction technology of the non-embedding rock single pile of above-mentioned offshore wind power foundation, wherein in the drilling for carrying out the drilling process When pore formation step, to prevent collapse hole, drill 4~5m, stops drilling, change hydraulic hammer carry out pile sinking operation, so circulation until Steel-pipe pile extremely design bottom absolute altitude.
The construction technology of the non-embedding rock single pile of above-mentioned offshore wind power foundation, wherein the construction technology is also entering Longkou rank Section heavy set the stage, opens hammer last stage, normal pile sinking stage, continuous pile sinking stage and pile head elevation control stage and take measures to control The verticality of steel-pipe pile processed;
Entering the Longkou stage, using the positioning system top in place after, lean against steel-pipe pile using 120 laser digital display horizontal rules Wall surface on, adjust the verticality of steel-pipe pile, verticality starts lower stake after meeting the requirements, until positioning system when steel-pipe pile enters mud 1m Fixing belt is tight;
Set the stage heavy, after steel-pipe pile enters mud, steady stake platform edge and on the extended line on steel-pipe pile side with mutual Vertical mode sets up two total stations, keeps the observation sight of two total stations orthogonal and tangent with steel-pipe pile side, passes through two Two height differences are the floor projection difference and height difference of 20m or more height on platform total station observation steel-pipe pile side, calculate the steel of the direction The gradient of tubular pole, it is primary in steel-pipe pile every sinking 1m observation, more than requiring to adjust steel-pipe pile by the main ship that hangs in time;
The hammer last stage is being opened, hydraulic hammer needs all-the-way tracking to observe, stops fuller immediately simultaneously when noting abnormalities in the fuller stage Adjust the verticality of steel-pipe pile;
In the normal pile sinking stage, in the case where guaranteeing steel pipe pile verticality, hydraulic hammer is started, it is first heavy with the hammering of small energy Stake, crawl 2~3 are hammered into shape, and a period of time is suspended, and are continued crawl 2~3 after without exception and are hammered into shape, are again paused for for a period of time, such 3~4 It is secondary, and observation steel-pipe pile data are measured, adjust steel-pipe pile posture;15 minutes are observed after adjustment, continues pile sinking after unchanged, every 1~2m is observed, adjustment is primary, when steel-pipe pile continues to bury 10m, is changed to observe every 3~4m, be adjusted once, work as steel-pipe pile Continue to bury 10m when, be changed to normal hammer piling;
At the continuous pile sinking stage, only observed when cutting off main lifting lug primary;
In the pile head elevation control stage, go out the cross at steel-pipe pile center using GPS setting-out on the lower platform of steady stake platform Axis is simultaneously marked, and makes the cross axis markers on cross axis markers and steady stake platform with steel-pipe pile by positioning system It is overlapped, surveys the elevation of top surface and label of steady stake platform;Mobile absolute altitude instruction device is installed on steady stake platform before piling, The absolute altitude instruction device has regulating height and horizontal functional with horizontal pointer or dress laser alignment device;Absolute altitude is referred to The horizontal pointer of showing device is directed toward the scale side finished with steel-pipe pile, according to the top mark of the steady stake platform of setting height and steel-pipe pile Top mark it is high, adjust horizontal pointer to suitable absolute altitude, when hydraulic hammer sinks steel-pipe pile, pass through the scale and water with steel-pipe pile The relativeness of flat pointer carries out record of sunk plies and pile head elevation control, and carries out with steel-pipe pile and stop hammering mark line into shape, wait stop Hammer reading stops hammering into shape when consistent with platform height.
The construction technology of the non-embedding rock single pile of above-mentioned offshore wind power foundation, wherein the stake top tooling flange is L tee section Structure is fitted closely with stake top flange by attachment bolt and is connect.
The construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention hangs ship using master and the auxiliary ship that hangs is combined steel pipe Stake lifting and inserting, and steady stake platform auxiliary positioning is used, piling construction can be efficiently completed, adaptable hammering equipment is also equipped with And drilling device, the posture of monitored over time and adjustment steel-pipe pile, to guarantee that single pile smoothly and is vertically driven into marine rock layer In, while specific aim measure is taken, keep hole wall to stablize, the appearance of the unusual conditions such as pre- preventing sticking, burying not only ensure that non- The bearing capacity of embedding rock single pile and the stability of pile body, also effectively increase construction efficiency, and effectively improve non rock rooted pile Horizontal resistivity and anti-group of ability, meet the requirement of Structural Design and construction.
Detailed description of the invention
Fig. 1 is the flow chart of the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention;
Fig. 2 a is the main view for the steady stake platform that the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention uses;
Fig. 2 b is the floor map of the upper platform in the lower platform of steady stake platform of the invention;
Fig. 2 c is the floor map of lower layer's platform in the lower platform of steady stake platform of the invention;
State diagram when Fig. 3 is the construction technology progress pitching pile process of the non-embedding rock single pile of offshore wind power foundation of the invention;
Fig. 4 a is bowing for the stake top tooling flange that the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention uses View;
Fig. 4 b is the A-A direction view in Fig. 4 a;
Fig. 5 is that putting down for pile body inclining degree control is carried out in the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention Face schematic diagram;
Fig. 6 is the plane signal that plane control is carried out in the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention Figure;
Fig. 7 is the schematic diagram that absolute altitude control is carried out in the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings.
Fig. 1 to Fig. 7 is please referred to, single pile involved in the construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention is adopted With the steel-pipe pile of 7.0~7.3m of diameter, 60~80mm of wall thickness, squeeze into cataclastic shape strong weathered granite, total embedded depth is 39.2~45.9m, height of pile top 15m, stake bottom about -54~-63m of absolute altitude.
The construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention includes following below scheme:Steel-pipe pile production, steady stake Putting up platform, pitching pile, first strike pile sinking, drilling, borehole cleaning, strike-on pile sinking.
Steel-pipe pile production process includes tube coupling blanking, tube coupling retaining wall on slope, tube coupling roll-forming, pile body top flange dress Match, pile body splices and corrosion-inhibiting coating coating step.
Steady stake platform 10 includes upper mounting plate 12, the auxiliary process stake 13, two of lower platform 11, four positioning process stake 14, outer Longkou beam 15 and a set of positioning system being made of 12 100T jack 20;Lower platform 11 is by upper platform 111 and lower layer Platform 112 is constituted, and arranges seven jack 20 around Longkou on upper platform 111, lower layer's platform 112 is around Longkou and and upper layer Seven jack 20 on platform 111 arrange five jack 20 with being staggered;Outer Longkou beam 15 is pacified after steel-pipe pile 100 enters Longkou Mounted in the Longkou of upper platform 111 (see Fig. 2 a to Fig. 2 c).
Steady stake putting up platform process includes the following steps:
1. lower platform 11 and four auxiliary process stakes 13 first pass through steel-pipe pile at the Longkou of locating platform ship and lower platform 11 Relative position is positioned, then carries out the inserting piling of four auxiliary process stakes 13, then will be in auxiliary process stake 13 and lower platform 11 Auxiliary process pipe casing upper and lower part pass through steel plate strip firm welding;
2. locating platform ship is first removed, then two positioning process stakes 14 of inserting piling, then by positioning process stake 14 and lower platform On positioning process pipe casing upper and lower part pass through steel plate strip firm welding;
3. installing upper mounting plate 12 after pitching pile process.
Pitching pile process includes steel-pipe pile lifting, steel-pipe pile enters Longkou, steel-pipe pile positioning is held tightly and steel-pipe pile sinks and sets step;
When progress steel-pipe pile lifting step, ship is hung using master and steel-pipe pile is lifted by crane and erected by the way of ship cooperation lifts by auxiliary hang Stake;First carry out it is auxiliary hang secure operation, another mistake water (flow) direction carry out it is main hangs secure, the main lifting direction for hanging ship is flat against steady stake The Longkou of platform, then berthing is refuted in pile transport, and the main crane for hanging ship is rotated to the main lifting lug of steel-pipe pile, while the auxiliary crane rotation for hanging ship It goes at the turn lifting lug of steel-pipe pile;First by the main main lifting lug in two sides for hanging ship elder generation hanging buckle steel-pipe pile, every main lifting lug in side hangs two Wirerope, and be φ 16mm × 100m cable wind rope in the top of the main lifting lug in every side, the auxiliary ship that hangs then is hung into turn lifting lug Wirerope;Starting again, which makes master hang ship, hangs ship synchronous hoisting with auxiliary, when steel-pipe pile leaves the deck 0.5m that pile transport is refuted completely, temporarily Stop lifting by crane, checks the stress condition of every wirerope, continue to lift by crane after without exception;When steel-pipe pile apart from the deck that pile transport is refuted 6~ When 7m, pile transport, which is refuted, exits construction area;Then master hangs ship and hangs ship mutual cooperation completion soldier piles with auxiliary;It is auxiliary to hang ship after completing soldier piles Continuing decentralization suspension hook makes wirerope not stress, while the main ship that hangs continues to rise suspension hook, when the turn lifting lug of steel-pipe pile is in the water surface When above 2~3m, the turn shackle on steel-pipe pile is extracted out by tender;
It carries out when steel-pipe pile enters Longkou step (see Fig. 3), steel-pipe pile 100 is lifted by crane by the main ship 200 that hangs, and slowly enter steady stake The Longkou of platform 10 starts slowly to transfer steel-pipe pile when the pile center position that steel-pipe pile 100 is in Longkou;When on steel-pipe pile Turn lifting lug apart from steady 10 top surface 1m of stake platform when, stop decentralization steel-pipe pile, then by turn over lifting lug cut off, be completed at the same time steady stake The installation of the outer Longkou beam 15 of the lower platform 11 of platform;
When carrying out steel-pipe pile positioning holding step, the posture of steel-pipe pile is first measured, then pass through the positioning system on steady stake platform Then the verticality of system adjustment steel-pipe pile adjusts positioning system and holds steel-pipe pile tightly;
When carrying out that steel-pipe pile is heavy to set step, main to hang ship decentralization wirerope, steel-pipe pile sinks down into mud face under the action of self-weight Stop sinking after lower certain depth, after confirmation steel-pipe pile is stablized, the main ship that hangs continues to transfer wirerope, is in wirerope and does not stress And the state that do not break off relations;Sight look into 15 minutes confirmation steel-pipe piles it is unchanged after, release the wirerope at main lifting lug.
When carrying out first strike pile sinking process, hydraulic hammer and fuller are lifted by crane by the main ship that hangs, must assure that during fuller hydraulic The central axes of hammer and steel-pipe pile match, and are damaged for protection stake top flange 101 when beating, pacify on stake top flange 101 Stake top tooling flange 102 is filled, stake top tooling flange 102 is L tee section structure, close by attachment bolt and stake top flange 101 It is fitted and connected (see Fig. 4 a and Fig. 4 b);After stake top tooling flange and hydraulic hammer contact, gradually transfer suspension hook, make piling weight by Step increases, observe 15 minutes confirmation steel-pipe piles posture it is unchanged after, start hydraulic hammer, hydraulic hammer is first sunk with small energy crawl Steel-pipe pile is changed to continuously sink steel-pipe pile, the hit energy of hydraulic hammer is ascending when steel-pipe pile buries 30m.
Drilling process includes drilling machine in place, installation drilling rod, slurrying and drilling and forming hole step;
When carrying out drilling machine step in place, hydraulic hammer is first hung, the upper mounting plate of steady stake platform is then installed, then sets up drilling machine, Using the gas lift reverse circulation hydraulic power drilling machine for being configured with drag bit and roller cutter bit, by pile gripper by drilling machine and steel-pipe pile Locking, and guarantee drilling machine bit central and steel-pipe pile center on same plumb line, deviation is not greater than 10cm;
When carrying out installation drilling rod step, drill bit is made of heavy balancer and stem;Drill bit, drilling rod hang ship in master Deck on it is assembled good after be installed on drilling machine again, in drilling process, the second section drilling rod and subsequent drilling rod directly hang ship in master Platform on install;
Carry out slurrying step when, slurry coat method using do not disperse, low solid phase, highly viscous PHP high performance slurry, first Bentonite slurry is stirred using slurry mixer in mud pit, is then pumped in steel-pipe pile using slush pump, works as steel-pipe pile Aperture is crept into after interior mud property index meets construction requirement;The mud of reacting cycle discharge, after being purified using mud separator It is recycled;
It include following process when progress drilling and forming hole step:
1. first being crept into using drag bit clear water, welding-on array wirerope brush, wirerope brush on the outer diameter guard ring of drill bit Outer diameter be greater than 5~10cm of steel-pipe pile internal diameter, with guarantee in drilling process by steel-pipe pile inner wall stratum attachment scrub Completely;
2. after drill bit drills out steel-pipe pile, atm number, medium bit pressure, slow-speed drilling and forming hole, bore diameter is than in steel-pipe pile The small 200mm of diameter, in drilling process every piece drilling rod of drilling will cleaning bottom of hole, to guarantee that bore diameter and verticality are all satisfied requirement;
3. creep into basement rock, brill replacement roller cutter bit is mentioned, using atm number, medium bit pressure, slow-speed of revolution drilling and forming hole;? In boring procedure, preliminary surveying hole depth is carried out using run of steel;
4. protruding into progress precise measurement hole depth in hole using professional measuring staff behind whole hole.
To prevent collapse hole, drill 4~5m, stops drilling, changes hydraulic hammer and carries out pile sinking operation, so circulation is until steel pipe Stake extremely design bottom absolute altitude.
When carrying out borehole cleaning process, by drilling tool lifting extremely from 30~50cm of bottom hole, slow rotary tools, and high-quality mud is supplemented Slurry carries out reacting cycle borehole cleaning, while head in retaining hole, prevents collapse hole;
When carrying out strike-on pile sinking process, steel-pipe pile internal drilling and borehole cleaning to designed elevation, and after the completion of whole hole is checked and accepted and When shut down and remove drilling rod, remove drilling machine, it is main to hang ship and reposition, and hydraulic hammer is seated to the top of steel-pipe pile, by hydraulic Hammer strikes to designed elevation steel-pipe pile.
Construction technology of the invention also takes measures to control the verticality of steel-pipe pile six stages, is respectively into Longkou rank Section heavy set the stage, opens the hammer last stage, normal pile sinking stage, continuous pile sinking stage, pile head elevation control stage;
Entering the Longkou stage, using positioning system by steel pipe stake top in place after, lean against steel using 120 laser digital display horizontal rules In the outside wall surface of tubular pole, the verticality of steel-pipe pile is adjusted, verticality starts lower stake after meeting the requirements, until steel-pipe pile is determined when entering mud 1m Position system fixing belt is tight;
Set the stage heavy, after steel-pipe pile enters mud, steady stake platform 10 edge and on the extended line on steel-pipe pile side with phase Mutually vertical mode sets up two total stations, the outside wall surface phase for keeping the observation sight of two total stations orthogonal and with steel-pipe pile It cuts, which is erected on bracket, and bracket is fixed on the lower platform of steady stake platform 10, top level when fixed Ruler is levelling;It is the floor projection difference and height difference of 20m or more height, meter by two height differences on two total station observation steel-pipe pile sides The gradient (see Fig. 5) for calculating the steel-pipe pile of the direction, it is primary in steel-pipe pile every sinking 1m observation, more than requiring to hang by master in time Ship adjustment;
The hammer last stage is being opened, the hydraulic hammer fuller stage needs all-the-way tracking to observe, stops fuller when noting abnormalities immediately and adjust The verticality of whole steel-pipe pile;
In the normal pile sinking stage, in the case where guaranteeing steel pipe pile verticality, hydraulic hammer is started, first with small energy hydraulic hammer Stake is sunk, crawl 2~3 is hammered into shape, and a period of time is suspended, and is continued crawl 2~3 after without exception and is hammered into shape, is again paused for for a period of time, such 3 ~4 times, and observation steel-pipe pile data are measured, adjust steel-pipe pile posture;15 minutes are observed after completing pile body adjustment, it is unchanged subsequent Continuous pile sinking, it is primary every 1~2m observation, adjustment, when steel-pipe pile continues to bury 10m, it is changed to every 3~4m observation, adjustment one Secondary, when steel-pipe pile continues to bury 10m, steel-pipe pile embedded depth about 30m, regulating measures can not play corrective action at this time, It is changed to normal hammer piling;
At the continuous pile sinking stage, only observed when cutting off main lifting lug primary;
In the pile head elevation control stage, go out 100 center of steel-pipe pile using GPS setting-out on the lower platform of steady stake platform 10 Cross axis is simultaneously marked, and makes the cross on cross axis markers and steady stake platform with steel-pipe pile 100 by positioning system Axis markers are overlapped, and survey the elevation of top surface of steady stake platform and label (see Fig. 6);Energy is installed on steady stake platform 100 before piling Mobile absolute altitude instruction device, the absolute altitude instruction device 30 have adjustable height with horizontal pointer or dress laser alignment device Low and horizontal functional;The horizontal pointer of absolute altitude instruction device 30 is directed toward to the scale side finished with steel-pipe pile 100, according to setting Steady stake platform top mark height and steel-pipe pile top mark it is high, adjust horizontal pointer to suitable absolute altitude (see Fig. 7), hydraulic hammer is sunk When steel-pipe pile, record of sunk plies and pile head elevation control are carried out by the relativeness of scale and horizontal pointer with steel-pipe pile, And carried out with steel-pipe pile and stop hammering mark line (cutting off main lifting lug repetition measurement platform height) into shape, wait stop hammer reading and platform height one Stop to hammer into shape when cause.
The construction technology of the non-embedding rock single pile of offshore wind power foundation of the invention hangs ship using master and the auxiliary ship that hangs is combined steel pipe Stake lifting and inserting, and steady stake platform auxiliary positioning is used, piling construction can be efficiently completed, adaptable hammering equipment is also equipped with And drilling device, the posture of monitored over time and adjustment steel-pipe pile, to guarantee that single pile smoothly and is vertically driven into marine rock layer In, while specific aim measure is taken, keep hole wall to stablize, the appearance of the unusual conditions such as pre- preventing sticking, burying not only ensure that non- The bearing capacity of embedding rock single pile and the stability of pile body, also effectively increase construction efficiency, and effectively improve non rock rooted pile Horizontal resistivity and anti-group of ability, meet the requirement of Structural Design and construction.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or modification, therefore all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (5)

1. a kind of construction technology of the non-embedding rock single pile of offshore wind power foundation, single pile uses 7.0~7.3m of diameter, 60~80mm of wall thickness Steel-pipe pile, squeeze into cataclastic shape strong weathered granite, total embedded depth is 39.2~45.9m, height of pile top 15m, stake bottom About -54~-63m of absolute altitude;The construction technology includes following below scheme:Steel-pipe pile production, steady stake putting up platform, pitching pile, first strike are heavy Stake, drilling, borehole cleaning, strike-on pile sinking;It is characterized in that,
The steel-pipe pile production process includes tube coupling blanking, tube coupling retaining wall on slope, tube coupling roll-forming, pile body top flange dress Match, pile body splices and corrosion-inhibiting coating coating step;
The steady stake putting up platform process includes the following steps:
1. steady stake platform includes upper and lower platform, four auxiliary process stakes, two positioning process stakes and a set of positioning system;It is lower flat Platform and four auxiliary process stakes first pass through steel-pipe pile relative position at the Longkou of locating platform ship and lower platform and are positioned, then into Then the inserting piling of four auxiliary process stakes of row passes through auxiliary process stake and the auxiliary process pipe casing upper and lower part on lower platform Steel plate strip firm welding;
2. locating platform ship is first removed, then two positioning process stakes of inserting piling, then by the positioning in positioning process stake and lower platform Technique pipe casing upper and lower part passes through steel plate strip firm welding;
3. installing upper mounting plate after pitching pile process;
The pitching pile process includes steel-pipe pile lifting, steel-pipe pile enters Longkou, steel-pipe pile positioning is held tightly and steel-pipe pile sinks and sets step;
When carrying out steel-pipe pile lifting step, ship is hung and auxiliary hang lifts by crane steel-pipe pile and soldier piles by the way of ship cooperation lifts using main; First by the main main lifting lug in two sides for hanging ship elder generation hanging buckle steel-pipe pile, every main lifting lug in side hangs two wirerope, then turns over the auxiliary ship extension that hangs The wirerope of body lifting lug;Starting again, which makes master hang ship, hangs ship synchronous hoisting with auxiliary, when steel-pipe pile leaves the deck that pile transport is refuted completely When 0.5m, pause lifting checks the stress condition of every wirerope, continues to lift by crane after without exception;When steel-pipe pile is refuted apart from pile transport 6~7m of deck when, pile transport, which is refuted, exits construction area;Then master hangs ship and hangs ship mutual cooperation completion soldier piles with auxiliary;Complete soldier piles Afterwards, it is auxiliary hang ship and continue to transfer suspension hook so that wirerope is not stressed, while the main ship that hangs continues to rise suspension hook, when the turn lifting lug of steel-pipe pile When being in 2~3m of the water surface or more, the turn shackle on steel-pipe pile is extracted out by tender;
When carrying out the steel-pipe pile and entering Longkou step, ship lifting steel-pipe pile is hung by main, and slowly enter the Longkou of steady stake platform, when Start slowly to transfer steel-pipe pile when the pile center position that steel-pipe pile is in Longkou;When the turn lifting lug on steel-pipe pile is apart from steady stake When the 1m of platform top surface, stops decentralization steel-pipe pile, then cut off lifting lug is turned over, be completed at the same time the outer Longkou of the lower platform of steady stake platform The installation of beam;
When carrying out the steel-pipe pile positioning holding step, the posture of steel-pipe pile is first measured, then determine by what is be arranged on steady stake platform Then the verticality of position system call interception steel-pipe pile adjusts positioning system and holds steel-pipe pile tightly;
When carrying out that the steel-pipe pile is heavy to set step, main to hang ship decentralization wirerope, steel-pipe pile sinks down into mud face under the action of self-weight Stop sinking after lower certain depth, after confirmation steel-pipe pile is stablized, the main ship that hangs continues to transfer wirerope, is in wirerope and does not stress And the state that do not break off relations;Sight look into 15 minutes confirmation steel-pipe piles it is unchanged after, release the wirerope at main lifting lug;
When carrying out the first strike pile sinking process, hydraulic hammer and fuller are lifted by crane by the main ship that hangs, when stake top tooling flange and hydraulic hammer After contact, gradually transfer suspension hook, be stepped up piling weight, observe 15 minutes confirmation steel-pipe pile posture it is unchanged after, open Hydrodynamic hammer, hydraulic hammer first sink steel-pipe pile with small energy crawl, when steel-pipe pile buries 30m, are changed to continuously sink steel-pipe pile, The hit energy of hydraulic hammer is ascending;
The drilling process includes drilling machine in place, installation drilling rod, slurrying and drilling and forming hole step;
When carrying out drilling machine step in place, hydraulic hammer is first hung, the upper mounting plate of steady stake platform is then installed, then sets up drilling machine, used It is configured with the gas lift reverse circulation hydraulic power drilling machine of drag bit and roller cutter bit, is locked drilling machine and steel-pipe pile by pile gripper Gu;
When carrying out installation drilling rod step, drill bit, drilling rod are installed on drilling machine after assembly well on the main deck for hanging ship again;
Carry out slurrying step when, slurry coat method using do not disperse, low solid phase, highly viscous PHP high performance slurry, first in mud Bentonite slurry is stirred using slurry mixer in stock tank, is then pumped in steel-pipe pile using slush pump, when in steel-pipe pile Aperture is crept into after mud property index meets construction requirement;The mud of reacting cycle discharge, is recycled after being purified using mud separator It uses;
It include following process when progress drilling and forming hole step:
1. first being crept into using drag bit clear water, the welding-on array wirerope brush on the outer diameter guard ring of drill bit, outside wirerope brush Diameter is greater than 5~10cm of steel-pipe pile internal diameter, to guarantee to scrub clean the stratum attachment on steel-pipe pile inner wall in drilling process;
2. after drill bit drills out steel-pipe pile, atm number, medium bit pressure, slow-speed drilling and forming hole, bore diameter is smaller than the internal diameter of steel-pipe pile 200mm, in drilling process every piece drilling rod of drilling will cleaning bottom of hole, to guarantee that bore diameter and verticality are all satisfied requirement;
3. creep into basement rock, brill replacement roller cutter bit is mentioned, using atm number, medium bit pressure, slow-speed of revolution drilling and forming hole;It is drilling In the process, preliminary surveying hole depth is carried out using run of steel;
4. protruding into progress precise measurement hole depth in hole using professional measuring staff behind whole hole;
When carrying out borehole cleaning process, by drilling tool lifting extremely from 30~50cm of bottom hole, slow rotary tools, and premium mud is supplemented, into Row reacting cycle borehole cleaning, while head in retaining hole, prevent collapse hole;
When carrying out strike-on pile sinking process, drilling machine is removed, master hangs ship and repositions, and hydraulic hammer is seated to the top of steel-pipe pile, Steel-pipe pile is struck to designed elevation by hydraulic hammer.
2. the construction technology of the non-embedding rock single pile of offshore wind power foundation according to claim 1, which is characterized in that inserted described When the steel-pipe pile of stake process lifts by crane step, first carry out it is auxiliary hang secure operation, another mistake water (flow) direction carry out it is main hangs secure, master hangs The lifting direction of ship is against the Longkou of steady stake platform, and then berthing is refuted in pile transport, and the main crane for hanging ship, which is rotated to the master of steel-pipe pile, to be hung At ear, while the auxiliary crane for hanging ship is rotated to the turn lifting lug of steel-pipe pile.
3. the construction technology of the non-embedding rock single pile of offshore wind power foundation according to claim 1, which is characterized in that carrying out institute When stating the drilling and forming hole step of drilling process, to prevent collapse hole, drill 4~5m, stops drilling, changes hydraulic hammer and carries out pile sinking work Industry, so circulation are until steel-pipe pile extremely design bottom absolute altitude.
4. the construction technology of the non-embedding rock single pile of offshore wind power foundation according to claim 1, which is characterized in that the construction Technique is also entering the Longkou stage, heavy setting the stage, opens hammer last stage, normal pile sinking stage, continuous pile sinking stage and stake top absolute altitude control Stage processed takes measures to control the verticality of steel-pipe pile;
Entering the Longkou stage, using the positioning system top in place after, the wall of steel-pipe pile is leaned against using 120 laser digital display horizontal rules On face, the verticality of steel-pipe pile is adjusted, verticality starts lower stake after meeting the requirements, until positioning system is fixed when steel-pipe pile enters mud 1m Band is tight;
Set the stage heavy, after steel-pipe pile enters mud, steady stake platform edge and on the extended line on steel-pipe pile side to be mutually perpendicular to Mode set up two total stations, keep the observation sight of two total stations orthogonal and tangent with steel-pipe pile side, it is complete by two Instrument of standing observes the floor projection difference and height difference that two height differences on steel-pipe pile side are 20m or more height, calculates the steel-pipe pile of the direction Gradient, it is primary in steel-pipe pile every sinking 1m observation, more than requiring to adjust steel-pipe pile by the main ship that hangs in time;
The hammer last stage is being opened, hydraulic hammer needs all-the-way tracking to observe, stops fuller when noting abnormalities immediately and adjust in the fuller stage The verticality of steel-pipe pile;
In the normal pile sinking stage, in the case where guaranteeing steel pipe pile verticality, hydraulic hammer is started, first with small energy hammer piling, Crawl 2~3 is hammered into shape, and a period of time is suspended, and is continued crawl 2~3 after without exception and is hammered into shape, is again paused for for a period of time, such 3~4 times, and Measurement observation steel-pipe pile data, adjust steel-pipe pile posture;15 minutes are observed after adjustment, continues pile sinking after unchanged, every 1~2m Observation, adjustment are primary, when steel-pipe pile continues to bury 10m, be changed to observe every 3~4m, adjustment it is primary, when steel-pipe pile continue into When native 10m, it is changed to normal hammer piling;
At the continuous pile sinking stage, only observed when cutting off main lifting lug primary;
In the pile head elevation control stage, go out the cross axis at steel-pipe pile center using GPS setting-out on the lower platform of steady stake platform And mark, the cross axis markers weight on cross axis markers and steady stake platform with steel-pipe pile is made by positioning system It closes, surveys the elevation of top surface and label of steady stake platform;Mobile absolute altitude instruction device is installed on steady stake platform before piling, it should Absolute altitude instruction device has regulating height and horizontal functional with horizontal pointer or dress laser alignment device;Absolute altitude is indicated The horizontal pointer of device is directed toward the scale side finished with steel-pipe pile, according to the top mark height of the steady stake platform of setting and steel-pipe pile Top mark is high, adjusts horizontal pointer to suitable absolute altitude, when hydraulic hammer sinks steel-pipe pile, passes through the scale and level with steel-pipe pile The relativeness of pointer carries out record of sunk plies and pile head elevation control, and carries out with steel-pipe pile and stop hammering mark line into shape, hammers into shape wait stop Stop hammering into shape when reading consistent with platform height.
5. the construction technology of the non-embedding rock single pile of offshore wind power foundation according to claim 1, which is characterized in that the stake top Tooling flange is L tee section structure, is fitted closely and is connect with stake top flange by attachment bolt.
CN201810697687.7A 2018-06-29 2018-06-29 Construction process of offshore wind power foundation non-rock-socketed single pile Active CN108842806B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810697687.7A CN108842806B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation non-rock-socketed single pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810697687.7A CN108842806B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation non-rock-socketed single pile

Publications (2)

Publication Number Publication Date
CN108842806A true CN108842806A (en) 2018-11-20
CN108842806B CN108842806B (en) 2020-04-07

Family

ID=64199957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810697687.7A Active CN108842806B (en) 2018-06-29 2018-06-29 Construction process of offshore wind power foundation non-rock-socketed single pile

Country Status (1)

Country Link
CN (1) CN108842806B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577323A (en) * 2018-12-18 2019-04-05 中交第三航务工程局有限公司宁波分公司 Tubular pole reinforcing device and method
CN110158634A (en) * 2019-05-14 2019-08-23 中交第一航务工程局有限公司 Construction system and construction method for offshore wind farm steel-pipe pile band hammer staking out pile sinking
CN110217698A (en) * 2019-07-01 2019-09-10 风潮海洋工程(深圳)有限公司 A kind of offshore wind farm large-diameter pile overturning tooling and method for turning
CN111364456A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Offshore generator pile and construction platform thereof
CN111364470A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Construction method for inner protective cylinder redrawing pile sinking
CN111945767A (en) * 2020-07-24 2020-11-17 中交第三航务工程局有限公司 Construction process of pile-first outer jacket type jacket of offshore wind power booster station
CN112726686A (en) * 2020-12-30 2021-04-30 保利长大工程有限公司 Offshore large-diameter single-pile sinking measurement method
CN113638386A (en) * 2021-08-19 2021-11-12 中交第三航务工程局有限公司 Offshore wind power single pile socketed foundation construction is with assembled platform
CN114837178A (en) * 2022-06-09 2022-08-02 上海博强重工集团有限公司 Installation method of wind power foundation pile
CN116876498A (en) * 2023-09-06 2023-10-13 南通泰胜蓝岛海洋工程有限公司 Calibration method for pile sinking positioning frame hanging installation
CN117449760A (en) * 2023-12-21 2024-01-26 水发能源集团有限公司 Soil layer drilling device for foundation construction of wind power equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924585A (en) * 2014-05-06 2014-07-16 江苏蓝潮海洋风电工程建设有限公司 Novel method for constructing wind power rock-embedded pile
CN104032765A (en) * 2014-07-01 2014-09-10 江苏龙源振华海洋工程有限公司 Shallow sea wind power plant rock-socketed monopile foundation construction method
CN106088140A (en) * 2016-06-28 2016-11-09 江苏海上龙源风力发电有限公司 A kind of batholith sea bed offshore wind turbine embedding rock single-pile foundation construction technique
CN106120839A (en) * 2016-07-12 2016-11-16 中交第三航务工程局有限公司 A kind of construction technology of off-lying sea blower foundation embedded rock pile
CN106759449A (en) * 2017-03-30 2017-05-31 福建省水利水电勘测设计院(水利部福建水利水电勘测设计研究院) A kind of embedding rock single-pile foundation of batholith sea bed offshore wind turbine and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103924585A (en) * 2014-05-06 2014-07-16 江苏蓝潮海洋风电工程建设有限公司 Novel method for constructing wind power rock-embedded pile
CN104032765A (en) * 2014-07-01 2014-09-10 江苏龙源振华海洋工程有限公司 Shallow sea wind power plant rock-socketed monopile foundation construction method
CN106088140A (en) * 2016-06-28 2016-11-09 江苏海上龙源风力发电有限公司 A kind of batholith sea bed offshore wind turbine embedding rock single-pile foundation construction technique
CN106120839A (en) * 2016-07-12 2016-11-16 中交第三航务工程局有限公司 A kind of construction technology of off-lying sea blower foundation embedded rock pile
CN106759449A (en) * 2017-03-30 2017-05-31 福建省水利水电勘测设计院(水利部福建水利水电勘测设计研究院) A kind of embedding rock single-pile foundation of batholith sea bed offshore wind turbine and its construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
周曙等: "大水位差钢管嵌岩桩施工工艺研究", 《中国水运》 *
张跃辉: "超大直径钢管桩近海施工关键技术", 《中国港湾建设》 *
黄炳南: "海上风电基础大直径嵌岩桩施工技术", 《中国港湾建设》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577323B (en) * 2018-12-18 2020-12-18 中交第三航务工程局有限公司宁波分公司 Tubular pile reinforcing method
CN109577323A (en) * 2018-12-18 2019-04-05 中交第三航务工程局有限公司宁波分公司 Tubular pole reinforcing device and method
CN110158634A (en) * 2019-05-14 2019-08-23 中交第一航务工程局有限公司 Construction system and construction method for offshore wind farm steel-pipe pile band hammer staking out pile sinking
CN110158634B (en) * 2019-05-14 2024-02-06 中交第一航务工程局有限公司 Construction system and construction method for pile sinking of offshore wind power steel pipe pile with hammer
CN110217698A (en) * 2019-07-01 2019-09-10 风潮海洋工程(深圳)有限公司 A kind of offshore wind farm large-diameter pile overturning tooling and method for turning
CN110217698B (en) * 2019-07-01 2024-04-30 风潮海洋工程(深圳)有限公司 Offshore wind power large-diameter single pile overturning tool and overturning method
CN111364456B (en) * 2020-03-28 2021-10-15 江苏龙源振华海洋工程有限公司 Construction platform of offshore generator pile
CN111364470A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Construction method for inner protective cylinder redrawing pile sinking
CN111364456A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Offshore generator pile and construction platform thereof
CN111945767A (en) * 2020-07-24 2020-11-17 中交第三航务工程局有限公司 Construction process of pile-first outer jacket type jacket of offshore wind power booster station
CN112726686A (en) * 2020-12-30 2021-04-30 保利长大工程有限公司 Offshore large-diameter single-pile sinking measurement method
CN113638386A (en) * 2021-08-19 2021-11-12 中交第三航务工程局有限公司 Offshore wind power single pile socketed foundation construction is with assembled platform
CN113638386B (en) * 2021-08-19 2022-09-09 中交第三航务工程局有限公司 Offshore wind power single pile socketed foundation construction is with assembled platform
CN114837178A (en) * 2022-06-09 2022-08-02 上海博强重工集团有限公司 Installation method of wind power foundation pile
CN116876498A (en) * 2023-09-06 2023-10-13 南通泰胜蓝岛海洋工程有限公司 Calibration method for pile sinking positioning frame hanging installation
CN116876498B (en) * 2023-09-06 2023-12-01 南通泰胜蓝岛海洋工程有限公司 Calibration method for pile sinking positioning frame hanging installation
CN117449760A (en) * 2023-12-21 2024-01-26 水发能源集团有限公司 Soil layer drilling device for foundation construction of wind power equipment
CN117449760B (en) * 2023-12-21 2024-03-15 水发能源集团有限公司 Soil layer drilling device for foundation construction of wind power equipment

Also Published As

Publication number Publication date
CN108842806B (en) 2020-04-07

Similar Documents

Publication Publication Date Title
CN108842806A (en) A kind of construction technology of the non-embedding rock single pile of offshore wind power foundation
CN108842807A (en) A kind of construction technology of the embedding rock single pile of offshore wind power foundation embedded type
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN101824919B (en) Deep hole underwater installation and locating method of steel pipe column in weak watery stratum
CN107152027A (en) Offshore wind farm multi-column pier foundation pile sinking construction method and special leading truck
CN110397076A (en) A kind of deep water large-section in-situ concrete pile construction method
CN109853567B (en) Pile sinking method for offshore wind power rock-socketed steel pipe pile
EP3039192A1 (en) Method of installing a foundation for an offshore wind turbine and a template for use herein
CN102268871B (en) Construction method of turnover platform for underwater pile foundation of bridge
CN110984004B (en) Method for dismantling lower supporting structure of bridge
CN110468833A (en) Drilled grouting piles under water constructing device and its application method for cruiseway
CN105275381A (en) Drilling construction method for water-rich cobble stratum by utilizing impact drill
CN208235570U (en) A kind of embedding rock single pile construction system of offshore wind turbine base expanding and base expanding formula
CN103924585A (en) Novel method for constructing wind power rock-embedded pile
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN104153391A (en) Open caisson geometrical shape monitoring method based on differential GPS
CN104196026A (en) A method for pulling out underwater steel pipe piles for temporary projects of bridges
CN104047542A (en) Pipe hammer system of percussion drill for rock-socketed inclined pile and impact construction method of rock-socketed inclined pile
CN110158579A (en) A kind of bored pile construction method
CN109853531A (en) A kind of pile foundation construction process of cast-in-situ bored pile
KR20200081143A (en) Pre-piling template using spudcan and installation method of offshore structure using thereof
CN113006075A (en) Steel pipe pile implanting method for implanting rock-socketed pile foundation construction
CN113897959A (en) Underwater positioning guide frame for offshore wind power foundation pile sinking and pile sinking construction method
CN110241731A (en) A method of forming rock-socketed pile foundation in seabed
CN210827529U (en) Single-pile reinforced foundation of offshore wind power anti-icing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee after: CCCC Third Aviation Bureau Sixth Engineering (Xiamen) Co.,Ltd.

Patentee after: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee before: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee before: CCCC Sanya (Xiamen) Engineering Co.,Ltd.

Patentee before: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder