CN108842785A - A kind of method of architectural engineering pit supporting - Google Patents
A kind of method of architectural engineering pit supporting Download PDFInfo
- Publication number
- CN108842785A CN108842785A CN201810731922.8A CN201810731922A CN108842785A CN 108842785 A CN108842785 A CN 108842785A CN 201810731922 A CN201810731922 A CN 201810731922A CN 108842785 A CN108842785 A CN 108842785A
- Authority
- CN
- China
- Prior art keywords
- construction
- foundation pit
- pit
- impervious wall
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention discloses a kind of methods of architectural engineering pit supporting, include the following steps the scheme of determining pattern foundation pit supporting structure;Levelling of the land, surveying setting-out are carried out on the design position of foundation pit;Filling pile construction:Using Auger drilling pore-forming, steel reinforcement cage and tremie method subaqueous concreting are placed in truck crane segmentation;Connection beam, angle brace and the construction of impervious wall:The foundation trench of impervious wall and connection beam is excavated, then impervious wall concreting, impervious wall exterior sheathing is removed, outside backfill, then connection beam of constructing, excavation pit;Soil bolt construction:Excavation of foundation pit is thick to anchor pole absolute altitude, and soil bolt of constructing is drilled, makes anchor head, wears anchor cable, slip casting, installed steel waist rail, steel pedestal, billet, wear outer anchorage, stretch-draw anchor;Earth excavation is excavated at steel strand wires absolute altitude;Supporting construction detection.Present invention construction is convenient, work efficiency is high, strong operability and construction quality are guaranteed, has the characteristics that reliability and security is high, is suitble to promote and apply.
Description
Technical field
The invention belongs to building foundation pit supporting technical field of construction, and in particular to a kind of side of architectural engineering pit supporting
Method.
Background technique
With the development of science and technology, people's lives production level significantly improves, under the promoting of this historical background,
Building trade is also in the development for carrying out high speed.In modern building field, whether construction technology or construction material
Quality level all has been significantly improved, this haves laid a good foundation for the architectural engineering construction in China.It is built in large-scale
It builds in object, foundation pit support construction technology would generally be applied to.
Pattern foundation pit supporting structure is the safety to guarantee Underground Construction and foundation pit surrounding environment, to foundation pit side-wall and surrounding enviroment
Supporting and retaining system, reinforcing and the safeguard measure of use.The purpose of pattern foundation pit supporting structure and effect 1. guarantee the stability of the soil body of foundation pit surrounding, together
When meet the requirement that basement construction has sufficient space, this is the necessary condition of earth excavation and basement construction.2. guaranteeing base
It is without damage during pattern foundation pit supporting structure and basement construction to cheat the facilities such as surrounding adjacent buildings and underground utilities, i.e. the crater wall soil body
Deformation, the vertically and horizontally displacement including ground and the underground soil body will control within the allowable range.3. by intercept water, precipitation,
The measures such as draining guarantee Foundation Pit Construction work surface more than level of ground water.At present during architectural engineering foundation construction,
Foundation pit support construction technology is more and more widely used, especially during modern urban construction so that foundation pit branch
Shield construction technology is widely used in underground structrue engineering, and in Base hole supporting technology specific implementation process, building is set
What meter staff paid close attention to it the most is exactly the size of its reliability and security.
Summary of the invention
The present invention provides a kind of method of architectural engineering pit supporting that reliability and security is high.
Its technical solution is:
A kind of method of architectural engineering pit supporting, includes the following steps:
Step 1 digs depth, foundation pit flat shape size, sitework geological conditions, ambient enviroment, close to buildings according to foundation pit
Status, determine the scheme of pattern foundation pit supporting structure;
Step 2 carries out levelling of the land, surveying setting-out on the design position of foundation pit;
Step 3, filling pile construction:Using Auger drilling pore-forming, steel reinforcement cage is placed in truck crane segmentation and tremie method underwater grouting is mixed
Solidifying soil;
Step 4, connection beam, angle brace and the construction of impervious wall:The foundation trench of impervious wall and connection beam is excavated, then impervious wall concrete pours
It builds, impervious wall exterior sheathing is removed, outside backfill, then connection beam of constructing, excavation pit;
Step 5, soil bolt construction:Excavation of foundation pit is thick to anchor pole absolute altitude, and soil bolt of constructing is drilled, makes anchor head, wears
Anchor cable, slip casting install steel waist rail, steel pedestal, billet, wear outer anchorage, stretch-draw anchor;
Step 6, earth excavation are excavated at steel strand wires absolute altitude;
Step 7, supporting construction detection.
Further, steel strand wires are docked by anchorage.
Further, in step 5, it is also necessary to the draining of construction foundation pit, precipitation facility.
Further, in step 7, the content of supporting detection includes:Support pile horizontal displacement observation, anchor pole pulling test, anchor
Bar acceptance test, Elastic Deformation of Foundation Pit observation, pile quality detection.
Beneficial effects of the present invention:
Using the method for architectural engineering pit supporting of the invention, constructing, convenient, work efficiency is high, strong operability and construction quality
It is guaranteed, have the characteristics that reliability and security is high, is suitble to promote and apply.
Detailed description of the invention
Fig. 1 is the method flow diagram of architectural engineering pit supporting.
Specific embodiment
Present invention will be explained in further detail with specific embodiment with reference to the accompanying drawing.
A kind of method of architectural engineering pit supporting, includes the following steps:
Step 1 digs depth, foundation pit flat shape size, sitework geological conditions, ambient enviroment, close to buildings according to foundation pit
Status, determine the scheme of pattern foundation pit supporting structure;
Step 2 carries out levelling of the land, surveying setting-out on the design position of foundation pit;
Step 3, filling pile construction:Using Auger drilling pore-forming, steel reinforcement cage is placed in truck crane segmentation and tremie method underwater grouting is mixed
Solidifying soil;
Step 4, connection beam, angle brace and the construction of impervious wall:The foundation trench of impervious wall and connection beam is excavated, then impervious wall concrete pours
It builds, impervious wall exterior sheathing is removed, outside backfill, then connection beam of constructing, excavation pit;
Step 5, soil bolt construction:Excavation of foundation pit is thick to anchor pole absolute altitude, and soil bolt of constructing is drilled, makes anchor head, wears
Anchor cable, slip casting install steel waist rail, steel pedestal, billet, wear outer anchorage, stretch-draw anchor;
Step 6, earth excavation are excavated at steel strand wires absolute altitude;
Step 7, supporting construction detection.
Steel strand wires are docked by anchorage.
In step 5, it is also necessary to the draining of construction foundation pit, precipitation facility.
In step 7, the content of supporting detection includes:Support pile horizontal displacement observation, anchor pole pulling test, anchor pole check and accept examination
It tests, Elastic Deformation of Foundation Pit observation, pile quality detection.
The foregoing is only a preferred embodiment of the present invention, the scope of protection of the present invention is not limited to this, it is any ripe
Know those skilled in the art within the technical scope of the present disclosure, the letter for the technical solution that can be become apparent to
Altered or equivalence replacement are fallen within the protection scope of the present invention.
Claims (4)
1. a kind of method of architectural engineering pit supporting, which is characterized in that include the following steps:
Step 1 digs depth, foundation pit flat shape size, sitework geological conditions, ambient enviroment, close to buildings according to foundation pit
Status, determine the scheme of pattern foundation pit supporting structure;
Step 2 carries out levelling of the land, surveying setting-out on the design position of foundation pit;
Step 3, filling pile construction:Using Auger drilling pore-forming, steel reinforcement cage is placed in truck crane segmentation and tremie method underwater grouting is mixed
Solidifying soil;
Step 4, connection beam, angle brace and the construction of impervious wall:The foundation trench of impervious wall and connection beam is excavated, then impervious wall concrete pours
It builds, impervious wall exterior sheathing is removed, outside backfill, then connection beam of constructing, excavation pit;
Step 5, soil bolt construction:Excavation of foundation pit is thick to anchor pole absolute altitude, and soil bolt of constructing is drilled, makes anchor head, wears
Anchor cable, slip casting install steel waist rail, steel pedestal, billet, wear outer anchorage, stretch-draw anchor;
Step 6, earth excavation are excavated at steel strand wires absolute altitude;
Step 7, supporting construction detection.
2. the method for architectural engineering pit supporting according to claim 1, which is characterized in that steel strand wires pass through anchorage pair
It connects.
3. the method for architectural engineering pit supporting according to claim 1, which is characterized in that in step 5, it is also necessary to construct
The draining of foundation pit, precipitation facility.
4. the method for architectural engineering pit supporting according to claim 1, which is characterized in that in step 7, supporting detection
Content includes:Support pile horizontal displacement observation, anchor pole pulling test, anchor pole acceptance test, Elastic Deformation of Foundation Pit observation, pile quality inspection
It surveys.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810731922.8A CN108842785A (en) | 2018-07-05 | 2018-07-05 | A kind of method of architectural engineering pit supporting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810731922.8A CN108842785A (en) | 2018-07-05 | 2018-07-05 | A kind of method of architectural engineering pit supporting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108842785A true CN108842785A (en) | 2018-11-20 |
Family
ID=64200272
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810731922.8A Pending CN108842785A (en) | 2018-07-05 | 2018-07-05 | A kind of method of architectural engineering pit supporting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108842785A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112813984A (en) * | 2020-12-31 | 2021-05-18 | 攀钢集团工程技术有限公司 | Deep foundation pit construction method under complex geological condition |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN107130610A (en) * | 2017-05-24 | 2017-09-05 | 广州市第建筑工程有限公司 | A kind of construction method of deep foundation pit support |
-
2018
- 2018-07-05 CN CN201810731922.8A patent/CN108842785A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102828520A (en) * | 2012-09-11 | 2012-12-19 | 中煤科工集团武汉设计研究院中汉岩土工程分公司 | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit |
CN107130610A (en) * | 2017-05-24 | 2017-09-05 | 广州市第建筑工程有限公司 | A kind of construction method of deep foundation pit support |
Non-Patent Citations (3)
Title |
---|
张雪,秦跃民: ""深基坑支护施工技术"", 《兰州工业高等专科学校学报》 * |
李凤宇: ""高层建筑深基坑支护探讨"", 《中国新技术新产品》 * |
楼卫杰: ""某大厦深基坑支护方案及施工分析"", 《科技与企业》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112813984A (en) * | 2020-12-31 | 2021-05-18 | 攀钢集团工程技术有限公司 | Deep foundation pit construction method under complex geological condition |
CN112813984B (en) * | 2020-12-31 | 2022-07-29 | 攀钢集团工程技术有限公司 | Deep foundation pit construction method under complex geological condition |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631470B (en) | The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method | |
CN104612162B (en) | A kind of Deep Foundation Pit of Metro Stations excavation construction method | |
CN102011397B (en) | Construction process of concrete form water-stopping occlusion pile | |
CN110631560B (en) | Underground excavation interval monitoring and measuring method for subway station in dense building area | |
CN105239563A (en) | Dry-method hole forming filling pile structure for post-grouting matched rotary drilling rig and construction method | |
CN103924585B (en) | The construction method of wind-powered electricity generation socketed pile | |
CN102425160A (en) | Construction engineering pile method combining rotary drilling rig with manual bottom expanding | |
CN102430277B (en) | Coarse grid sunk well for physically processing waste water and construction method thereof | |
CN106436788A (en) | Foundation reinforcement and inclination correction method for friction piles of high-rise building | |
CN106522235A (en) | Narrow site deep foundation pit excavation supporting construction method | |
CN104153371A (en) | Grouting-to-stop-water construction method of underwater rubble bed | |
CN105040715A (en) | Method for building bridge construction cofferdam through steel sheet piles | |
CN105714769A (en) | Construction method for anti-sliding cast-in-place pile | |
CN109706945A (en) | Come down fracture belt tunnel construction method | |
CN108316283A (en) | The devices and methods therefor of influence of foundation excavation is controlled using hole rising pouring slurry ground-connecting-wall | |
CN107165173A (en) | A kind of foundation pit supporting system and its construction method | |
CN113404042A (en) | Bridge pile position construction method | |
CN110714459A (en) | Construction method of cast-in-situ bored pile | |
CN108842785A (en) | A kind of method of architectural engineering pit supporting | |
CN105442694B (en) | Prestressed reinforced concrete sewage intercepting sewer pipe jacking construction method | |
CN115217112A (en) | Deep foundation pit construction method | |
CN107675700A (en) | The construction method of diaphram wall | |
CN107604907A (en) | A kind of Deep Foundation Pit Supporting Project anchor cable anti-seepage construction engineering method | |
CN103628485A (en) | Foundation-pit support structure construction process | |
CN207109806U (en) | The artificial friction pile of noiseless no airborne dust and short time limit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181120 |
|
RJ01 | Rejection of invention patent application after publication |