CN108842761A - 钻孔导引预制桩后压浆技术 - Google Patents

钻孔导引预制桩后压浆技术 Download PDF

Info

Publication number
CN108842761A
CN108842761A CN201810616322.7A CN201810616322A CN108842761A CN 108842761 A CN108842761 A CN 108842761A CN 201810616322 A CN201810616322 A CN 201810616322A CN 108842761 A CN108842761 A CN 108842761A
Authority
CN
China
Prior art keywords
pile
drilling
grouting
prefabricated pile
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810616322.7A
Other languages
English (en)
Inventor
高永光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810616322.7A priority Critical patent/CN108842761A/zh
Publication of CN108842761A publication Critical patent/CN108842761A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

发明“钻孔导引预制桩后压浆技术”适用于地基基础和地下空间技术领域,背景技术是预制桩在施工时受地层地质条件限制难以达到工程设计的理想深度,并且预制桩中没有预埋注浆管,而钻孔灌注桩钻孔成孔后,后序下钢筋笼及混凝土灌注时间较长,因此容易出现塌孔、灌注桩缩径、断桩以及孔底沉渣过厚等问题。发明“钻孔导引预制桩后压浆技术”可以显著改善以上不足,主要内容是通过钻孔导引将预先制造好的带有预埋注浆管的钢筋混凝土预制桩用工程机械静压或打入设计深度,然后再通过桩身预埋的注浆管对桩侧和桩底进行压力注浆,从而使桩基施工质量更容易控制,减少了桩基混凝土灌注环节,使施工周期更短,并使工程造价更低。

Description

钻孔导引预制桩后压浆技术
技术领域:
地基基础和地下空间工程技术
背景技术:
目前在地基基础工程领域,钢筋混凝土预制桩的入土深度受地层中坚硬夹层和孤石限制,有时无法达到工程设计的理想深度,预制桩中没有设计后压浆通道;钻孔灌注桩钻孔成孔后,后序下钢筋笼及混凝土灌注时间较长,因此容易出现塌孔、灌注桩缩径、断桩以及孔底沉渣过厚等现象。
发明内容:
本发明“钻孔导引预制桩后压浆技术”是一种关于桩基应用技术方法改进后新的技术方案和方法,可显著改善以上不足,主要内容是通过已完成钻孔将根据设计要求预制的带有注浆管的钢筋混凝土预制桩用工程机械静压或打入设计深度,然后再通过桩身预埋的注浆管进行桩侧和桩底压力注浆,这种新的桩基施工方案和方法,使桩基施工质量更容易控制,减少了桩基混凝土灌注环节,施工周期更短,单桩极限承载力及抗拔力显著提高,可显著降低工程造价。
具体实施方式:
1、这是一种新的简单的桩基施工技术方案和方法,即先根据工程设计要求,在预制工厂或工地现场将预埋有1根及以上注浆管的钢筋混凝土预制桩制作好备用,预埋在桩身的注浆管绑扎在钢筋笼上,钢筋混凝土预制桩的截面形状根据设计要求可以做成圆形、方形或多边形等。桩身的横截面积也可以是变化的,原则上上部桩身截面积应大于等于下部桩身截面积。桩端可以是平的或尖的(如圆锥形)等。
2、工地现场按照设计要求进行钻孔成孔,钻孔直径和截面积小于或等于钢筋混凝土预制桩直径和截面积,目的是让钢筋混凝土预制桩沉入钻孔时对桩周地层产生挤密效果并与钻孔周围地层(岩土体)紧密结合,从而提高桩周侧摩阻力。
3、现场钻孔按照设计达到设计孔深后,将预制好带有预埋注浆管的预制桩,用工程机械吊装并采取静压或打入的方式沉入钻孔至设计深度,然后开始通过预制桩中预留注浆管向桩侧和桩底进行压力注浆,浆液一般为水泥浆或水泥砂浆。整个工序结束后,桩侧摩阻力、桩端承载力显著提高,单桩极限承载力大幅度提高。

Claims (3)

1.发明“钻孔导引预制桩后压浆技术”是一种新的简单的桩基施工技术方案和方法,是指在桩基施工过程中,先按设计要求把预埋有注浆管的钢筋混凝土桩预制好备用,预制桩底部可以设置注浆容器,与预留注浆管连接,钻孔成孔后用工程机械将钢筋混凝土预制桩沿钻孔通过静压或打入达到设计深度,最后通过钢筋混凝土预埋注浆管进行桩侧桩底注浆的技术方案和方法。
2.发明“钻孔导引预制桩后压浆技术”,其中钻孔导引钢筋混凝土预制桩技术及混凝土预制桩中预埋1根或多根注浆管进行后压浆的方法是这种发明的两个特征。
3.根据权利要求2所述“钻孔导引钢筋混凝土预制桩技术”是指先用钻机按设计要求成孔,然后再将钢筋混凝土预制桩用工程机械沿钻孔静压或打入设计深度的方法。
CN201810616322.7A 2018-06-15 2018-06-15 钻孔导引预制桩后压浆技术 Pending CN108842761A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810616322.7A CN108842761A (zh) 2018-06-15 2018-06-15 钻孔导引预制桩后压浆技术

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810616322.7A CN108842761A (zh) 2018-06-15 2018-06-15 钻孔导引预制桩后压浆技术

Publications (1)

Publication Number Publication Date
CN108842761A true CN108842761A (zh) 2018-11-20

Family

ID=64202582

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810616322.7A Pending CN108842761A (zh) 2018-06-15 2018-06-15 钻孔导引预制桩后压浆技术

Country Status (1)

Country Link
CN (1) CN108842761A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110896644A (zh) * 2018-09-25 2020-03-20 高永光 全套管钻孔导引预制桩的注浆固结方法及其预制桩
CN113309089A (zh) * 2021-06-11 2021-08-27 河北省水利规划设计研究院有限公司 预制空心桩及其取土植桩施工方法
CN115030155A (zh) * 2022-05-31 2022-09-09 中国电建集团昆明勘测设计研究院有限公司 基于压浆工艺用于较硬地层的光伏支架预制桩施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1366114A (zh) * 2001-01-21 2002-08-28 陈如桂 一种建筑基础用的成孔预制注浆桩的施工方法
CN103603336A (zh) * 2013-10-31 2014-02-26 周兆弟 注浆预制桩及注浆方法
CN107761732A (zh) * 2017-10-26 2018-03-06 雨发建设集团有限公司 先高压旋喷引孔后注浆辅助静压桩沉桩施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1366114A (zh) * 2001-01-21 2002-08-28 陈如桂 一种建筑基础用的成孔预制注浆桩的施工方法
CN103603336A (zh) * 2013-10-31 2014-02-26 周兆弟 注浆预制桩及注浆方法
CN107761732A (zh) * 2017-10-26 2018-03-06 雨发建设集团有限公司 先高压旋喷引孔后注浆辅助静压桩沉桩施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110896644A (zh) * 2018-09-25 2020-03-20 高永光 全套管钻孔导引预制桩的注浆固结方法及其预制桩
CN110896644B (zh) * 2018-09-25 2021-04-09 高永光 全套管钻孔导引预制桩的注浆固结方法
CN113309089A (zh) * 2021-06-11 2021-08-27 河北省水利规划设计研究院有限公司 预制空心桩及其取土植桩施工方法
CN115030155A (zh) * 2022-05-31 2022-09-09 中国电建集团昆明勘测设计研究院有限公司 基于压浆工艺用于较硬地层的光伏支架预制桩施工方法
CN115030155B (zh) * 2022-05-31 2023-10-24 中国电建集团昆明勘测设计研究院有限公司 基于压浆工艺用于较硬地层的光伏支架预制桩施工方法

Similar Documents

Publication Publication Date Title
CN103835284B (zh) 一种岩溶地区钻孔灌注桩结构及施工方法
CN107503257B (zh) 一种傍山高填路堤稳定与变形控制结构及施工方法
CN102086645B (zh) 嵌岩桩及其施工方法
CN105672348A (zh) 一种深水区砂卵石地层截除桥梁桩基的施工方法
CN104179174B (zh) 一种多孔注浆管异形桩及其成桩方法
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN207109475U (zh) 傍山高填路堤稳定与变形控制结构
CN203741820U (zh) 一种岩溶地区钻孔灌注桩结构
CN103184734A (zh) 一种植入注浆组合桩及施工方法
CN100595391C (zh) 同步提土压灌矩形灌注桩成桩装置与方法
CN101812843A (zh) 中心灌注后压浆桩施工方法及其使用的灌注器和注浆器
CN103993598A (zh) 一种引孔植入布袋碎石注浆桩及施工方法
CN108842761A (zh) 钻孔导引预制桩后压浆技术
CN104631440A (zh) 一种既有大直径灌注桩劲芯增长基坑支护结构及施工方法
CN204023559U (zh) 一种多孔注浆管异形桩
CN107268608A (zh) 建筑垃圾地层钻孔桩成孔方法
CN110144881A (zh) 一种自沉型预制空心抗滑桩及其施工方法
CN108797578A (zh) 带分级扩大头的碎石注浆桩及其施工方法
CN107100160A (zh) 一种用于下水库拦沙坝振冲碎石桩的施工工艺
CN110080779A (zh) 隧道隧底溶洞处理施工方法
CN104196013B (zh) 一种复合y形桩及其施工方法
CN212248222U (zh) 一种注浆成型薄壁管桩的施工设备
CN104929101B (zh) 一种扩底‑多段侧扩的抗拔预应力锚固碎石桩及施工方法
CN208472713U (zh) 一种治理小型滑坡的组合结构微型桩
CN107447775A (zh) 滑坡灾害体造地排水加筋土挡墙结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 102600 Beijing Daxing District Kangzhuang Road No. 9 Central Railway Fifth Courtyard District B Building 703

Applicant after: Gao Yongguang

Address before: 100012 Huayu City, Tiejian, China 9-1-302, Shuiban South Street, Chaoyang District, Beijing

Applicant before: Gao Yongguang

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181120