- CN108824754A CN108824754A CN201810836119.0A CN201810836119A CN108824754A CN 108824754 A CN108824754 A CN 108824754A CN 201810836119 A CN201810836119 A CN 201810836119A CN 108824754 A CN108824754 A CN 108824754A
- Authority
- CN
- China
- Prior art keywords
- fastener
- macroplate
- stone
- wallboard
- back box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/02—Flooring or floor layers composed of a number of similar elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
The invention discloses a kind of integral bathroom ground installation structure and installation methods, including ground, waterproof back box on the ground is set, wallboard on the inside of waterproof back box is set and the floor in waterproof back box and between wallboard is set, the floor includes the floor ceramic tile that macroplate stone is moulded substrate and is fixed on macroplate stone modeling substrate, macroplate stone modeling substrate one end is adjacent to wallboard, the first fastener is fixedly installed in the other end, junction of first fastener between macroplate stone modeling substrate is symmetrical arranged, and first plane is concordant on fastener and macroplate stone modeling substrate is arranged;The second fastener is fixedly installed in corresponding position in the waterproof back box;The beneficial effects of the invention are as follows:Macroplate stone moulds substrate and forms overall plate by the way that Nian Jie glue-line is fixed with floor ceramic tile, and macroplate stone modeling substrate side is mounted with the first fastener, and is fixed by the cooperation of second the first fastener of fastener, and the structure install convenient, speed of application are fast.
Description
Technical field
The present invention relates to building decoration technical fields, and in particular to a kind of integral bathroom ground installation structure and installation side
Method.
Background technique
A kind of integral bathroom ground mounting means be suitable for integral bathroom ground facing, can be widely applied to public building and
Residential architecture.Prefabrication, in-site installation can reach the effect that construction efficiency is high, speed of application is fast.Ground needs between conventional sanitation
Waterproof is done, with cement mortar paving, construction efficiency is low, complicated construction technique.
Summary of the invention
In order to solve the problems in the existing technology, the present invention provides a kind of integral bathroom ground of high construction efficiency peaces
Assembling structure and installation method.
Technical scheme is as follows:
A kind of integral bathroom ground installation structure, which is characterized in that including ground, setting waterproof back box on the ground, setting
Wallboard on the inside of waterproof back box and the floor in waterproof back box and between wallboard is set, the floor includes macroplate
Stone modeling substrate and the floor ceramic tile being fixed on macroplate stone modeling substrate, described macroplate stone modeling substrate one end and wallboard paste
Tightly, the first fastener is fixedly installed in the other end, and junction of first fastener between macroplate stone modeling substrate is symmetrically set
It sets, and plane is concordant on the first fastener and macroplate stone modeling substrate is arranged;Corresponding position fixation is set in the waterproof back box
The second fastener is set, second fastener is engaged by clamping with the first fastener respectively, and two macroplate stones modeling substrate is fixed
Connection.
A kind of integral bathroom ground installation structure, which is characterized in that close to wall on the macroplate stone modeling substrate
Waterproof adhesive tape is equipped at the position of plate.
A kind of integral bathroom ground installation structure, which is characterized in that the macroplate stone modeling substrate is equipped with viscous
Glue-line is connect, and is fixedly connected by bonding glue-line with floor ceramic tile.
A kind of integral bathroom ground installation structure, which is characterized in that the floor ceramic tile is being located at macroplate stone
The junction moulded between substrate is equipped with filler rod.
A kind of integral bathroom ground installation structure, which is characterized in that the wallboard includes wallboard base and setting
Wallboard surface layer in wallboard base.
A kind of integral bathroom ground installation structure, which is characterized in that the floor ceramic tile is arranged in macroplate stone
Mould substrate on and with the first fastener end position flush.
A kind of integral bathroom ground installation method, which is characterized in that include the following steps:
1) waterproof back box is placed into ground, the position of waterproof back box edge is determined according to finished surface unwrapping wire, it is ensured that waterproof back box
Position and drawing position consistency;
2)MS glue is played at waterproof back box external corner, waterproof back box position is fixed, it is ensured that back box position will not occur when subsequent installation
Offset;
3)Integral bathroom metope is installed:Wallboard base and wallboard surface layer are installed;
4)The installation of ground plate:It is installed from most Edge BOB(beginning of block), waterproof adhesive tape is pasted onto macroplate stone-plastic plate and ground porcelain
The side of brick;Plate is put it on the ground, it is flat-pushing, so that macroplate stone-plastic plate is inserted into wallboard surface layer bottom, waterproof adhesive tape is by wallboard
The gap of surface layer and floor ceramic tile stoppers;By the second fastener back full coat MS glue, there is the first fastener for aforementioned panels are packaged
One end is lifted, and the second fastener is caught in the first fastener, and macroplate stone-plastic plate is laid flat, and guarantees the back of the second fastener
It is come into full contact with the surface of waterproof back box;Waterproof adhesive tape is pasted macroplate stone-plastic plate and floor ceramic tile by the installation of another plate
Side equipped with waterproof adhesive tape is put into waterproof back box surface, the side equipped with the first fastener is raised, made equipped with anti-by side
The side macroplate stone-plastic plate of glue item is inserted into wallboard surface layer bottom, and waterproof adhesive tape is by the seam of wallboard surface layer and macroplate stone-plastic plate
Gap stoppers;Side equipped with the first fastener is slowly put down, is caught in the first fastener in the second fastener;Firmly by filler rod
It is inserted among two plates, guarantees the gap for keeping 1-3mm among two first fasteners, guarantee that the first fastener is not fallen out.
The beneficial effects of the invention are as follows:
1)Macroplate stone moulds substrate and forms overall plate by the way that Nian Jie glue-line is fixed with floor ceramic tile, and macroplate stone moulds substrate side
It is mounted with the first fastener, and is fixed by the cooperation of second the first fastener of fastener, the structure install convenient, construction
Speed is fast, and scene is not necessarily to cement mortar.
2)Second fastener can be bonding in factory with macroplate stone modeling substrate, is positioned in advance, guarantees that positioning is quasi-
Really, in-site installation is convenient.
3)Macroplate stone moulds substrate side, and bonding waterproof adhesive tape is, it can be achieved that water-proof function in advance, and scene is without further
Installation.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is schematic enlarged-scale view at A of the present invention;
Fig. 3 is schematic enlarged-scale view at B of the present invention;
In figure:The ground 1-, 2- waterproof back box, 3- wallboard base, 4- wallboard surface layer, 5- macroplate stone modeling substrate, 6- floor ceramic tile,
7- is bonded glue-line, 8- filler rod, the second fastener of 9-, 10- waterproof adhesive tape, the first fastener of 11-.
Specific embodiment
Below in conjunction with Figure of description, the invention will be further described.
As shown in Figure 1-3, a kind of integral bathroom ground installation structure, including ground 1, waterproof back box 2, wallboard base 3, wall
Board finish 4, macroplate stone modeling substrate 5, floor ceramic tile 6, bonding glue-line 7, filler rod 8, the second fastener 9, waterproof adhesive tape 10 and the
One fastener 11.
Waterproof back box 2 is arranged on ground 1, wallboard setting is arranged in waterproof back box 2 on 2 inside of waterproof back box, floor
And between wallboard, wallboard includes wallboard base 3 and the wallboard surface layer 4 being arranged in wallboard base 3, and macroplate stone moulds substrate
Waterproof adhesive tape 10 is equipped on 5 at the position of wallboard surface layer 4;Floor includes macroplate stone modeling substrate 5 and is fixed at big
Slabstone moulds the floor ceramic tile 6 on substrate 5, and macroplate stone moulds substrate 5 and is equipped with bonding glue-line 7, and passes through bonding glue-line 7 and ground
Furring tile 6 is fixedly connected;Macroplate stone modeling 5 one end of substrate is adjacent to wallboard, the other end the first fastener 11 of fixed setting, and first
Junction of the fastener 11 between macroplate stone modeling substrate 5 is symmetrical arranged, and the first fastener 11 moulds substrate 5 with macroplate stone
Upper plane is concordantly arranged, and the setting of floor ceramic tile 6 is on macroplate stone modeling substrate 5 and equal with 11 end position of the first fastener
Together;The second fastener 9 is fixedly installed in corresponding position in waterproof back box 2, and the second fastener 9 is clamped with the first fastener 11 respectively
Cooperation, and two macroplate stones modeling substrate 5 is fixedly connected;Floor ceramic tile 6 is in the junction being located between macroplate stone modeling substrate 5
Equipped with filler rod 8.Waterproof back box 2 is first placed into original ground 1, then carries out the installation of integral bathroom metope, including wallboard base 3
And the installation of wallboard surface layer 4;Metope carries out the installation of ground facing after being installed.First fastener 11 is caught in the second fastener
In 12, wherein in factory, bonding, accurate positioning, in-site installation are convenient with waterproof back box 2 for the second fastener 12;It will carry out ground
Face composite plates(Macroplate stone is moulded substrate 5 and is fixedly connected with floor ceramic tile 6 by Nian Jie glue-line 7)Installation, finally be caught in it is embedding
Item 8, is fixed, and prevents plate mobile or falls off.
A kind of integral bathroom ground installation method, includes the following steps:
1) waterproof back box 2 is placed into ground 1, the position of 2 edge of waterproof back box is determined according to finished surface unwrapping wire, it is ensured that the anti-bottom
2 position of box and drawing position consistency;
2)MS glue is played at 2 external corner of waterproof back box, 2 position of waterproof back box is fixed, it is ensured that back box position will not be sent out when subsequent installation
Raw offset;
3)Integral bathroom metope is installed:Wallboard base 3 and wallboard surface layer 4 are installed;
4)The installation of ground plate:It is installed from most Edge BOB(beginning of block), waterproof adhesive tape 10 is pasted onto macroplate stone-plastic plate 5 and ground
The side of ceramic tile 6;Plate is placed on ground 1, it is flat-pushing, so that macroplate stone-plastic plate 5 is inserted into 4 bottom of wallboard surface layer, waterproof adhesive tape
10 stopper wallboard surface layer 4 and the gap of floor ceramic tile 6;By 9 back full coat MS glue of the second fastener, have for aforementioned panels are packaged
One end of one fastener 11 is lifted, and the second fastener 9 is caught in the first fastener 11, macroplate stone-plastic plate 5 is laid flat, and is guaranteed
The back of second fastener 9 and the surface of waterproof back box 2 come into full contact with;Another plate installation, pastes big plate for waterproof adhesive tape 10
Side equipped with waterproof adhesive tape 10 is put into 2 surface of waterproof back box by the side of block stone-plastic plate 5 and floor ceramic tile 6, will be equipped with first
The side of fastener 11 is raised, and the side macroplate stone-plastic plate 5 equipped with waterproof adhesive tape 10 is made to be inserted into 4 bottom of wallboard surface layer, waterproof
Adhesive tape 10 stoppers wallboard surface layer 4 and the gap of macroplate stone-plastic plate 5;Side equipped with the first fastener is slowly put down, is made
First fastener 11 is caught in the second fastener 9;Firmly filler rod 8 is inserted among two plates, guarantees two first fasteners 11
Centre keeps the gap of 2mm, guarantees that the first fastener 11 is not fallen out.
Claims (7)
1. a kind of integral bathroom ground installation structure, which is characterized in that including ground(1), be arranged on ground(1)On the anti-bottom
Box(2), be arranged in waterproof back box(2)The wallboard of inside and setting are in waterproof back box(2)Floor interior and between wallboard, institute
Stating floor includes macroplate stone modeling substrate(5)And it is fixed at macroplate stone modeling substrate(5)On floor ceramic tile(6), described
Macroplate stone moulds substrate(5)One end is adjacent to wallboard, and the first fastener is fixedly installed in the other end(11), first fastener
(11)Substrate is moulded in macroplate stone(5)Between junction be symmetrical arranged, and the first fastener(11)Substrate is moulded with macroplate stone
(5)Upper plane is concordantly arranged;The waterproof back box(2)The second fastener is fixedly installed in upper corresponding position(9), second card
Fastener(9)Respectively with the first fastener(11)It is engaged by clamping, and two macroplate stones is moulded into substrate(5)It is fixedly connected.
2. a kind of integral bathroom ground installation structure according to claim 1, which is characterized in that the macroplate stone moulds base
Plate(5)It is upper that waterproof adhesive tape is equipped at the position of wallboard(10).
3. a kind of integral bathroom ground installation structure according to claim 1, which is characterized in that the macroplate stone moulds base
Plate(5)It is equipped with bonding glue-line(7), and pass through bonding glue-line(7)With floor ceramic tile(6)It is fixedly connected.
4. a kind of integral bathroom ground installation structure according to claim 1, which is characterized in that the floor ceramic tile(6)
Substrate is moulded being located at macroplate stone(5)Between junction be equipped with filler rod(8).
5. a kind of integral bathroom ground installation structure according to claim 1, which is characterized in that the wallboard includes wallboard
Base(3)And it is arranged in wallboard base(3)On wallboard surface layer(4).
6. a kind of integral bathroom ground installation structure according to claim 1, which is characterized in that the floor ceramic tile(6)
Setting moulds substrate in macroplate stone(5)It is upper and with the first fastener(11)End position flush.
7. -6 any a kind of integral bathroom ground installation method according to claim 1, which is characterized in that including walking as follows
Suddenly:
1) by waterproof back box(2)It is placed into ground(1), waterproof back box is determined according to finished surface unwrapping wire(2)The position of edge, it is ensured that
Waterproof back box(2)Position and drawing position consistency;
2)Waterproof back box(2)MS glue is played at external corner, by waterproof back box(2)Position is fixed, it is ensured that back box position is not when subsequent installation
It can shift;
3)Integral bathroom metope is installed:Wallboard base is installed(3)And wallboard surface layer(4);
4)The installation of ground plate:It is installed from most Edge BOB(beginning of block), by waterproof adhesive tape(10)It is pasted onto macroplate stone-plastic plate(5)With
Floor ceramic tile(6)Side;Plate is placed on ground(1)On, it is flat-pushing, make macroplate stone-plastic plate(5)It is inserted into wallboard surface layer(4)Bottom
Portion, waterproof adhesive tape(10)By wallboard surface layer(4)With floor ceramic tile(6)Gap stopper;By the second fastener(9)Back full coat MS
Glue has the first fastener for aforementioned panels are packaged(11)One end lift, by the second fastener(9)It is caught in the first fastener(11)
In, by macroplate stone-plastic plate(5)It is laid flat, guarantees the second fastener(9)Back and waterproof back box(2)Surface come into full contact with;
Another plate installation, by waterproof adhesive tape(10)Paste macroplate stone-plastic plate(5)With floor ceramic tile(6)Side, waterproof will be housed
Adhesive tape(10)Side be put into waterproof back box(2)Surface will be equipped with the first fastener(11)Side raise, make equipped with marine glue
Item(10)Side macroplate stone-plastic plate(5)It is inserted into wallboard surface layer(4)Bottom, waterproof adhesive tape(10)By wallboard surface layer(4)With it is big
Plate stone-plastic plate(5)Gap stopper;Side equipped with the first fastener is slowly put down, the first fastener is made(11)It is caught in
Two fasteners(9)In;Firmly by filler rod(8)It is inserted among two plates, guarantees two first fasteners(11)Centre keeps 1-3mm
Gap, guarantee the first fastener(11)It does not fall out.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810836119.0A CN108824754A (en) | 2018-07-26 | 2018-07-26 | A kind of integral bathroom ground installation structure and installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810836119.0A CN108824754A (en) | 2018-07-26 | 2018-07-26 | A kind of integral bathroom ground installation structure and installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108824754A true CN108824754A (en) | 2018-11-16 |
Family
ID=64141204
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810836119.0A Pending CN108824754A (en) | 2018-07-26 | 2018-07-26 | A kind of integral bathroom ground installation structure and installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108824754A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577589A (en) * | 2018-11-26 | 2019-04-05 | 浙江亚厦装饰股份有限公司 | A kind of external corner wallboard splicing construction and its joining method |
CN110065276A (en) * | 2019-04-30 | 2019-07-30 | 上海今润装饰材料有限公司 | Novel SPC latches ceramic tile composite floor board |
CN112982885A (en) * | 2021-03-10 | 2021-06-18 | 德才装饰股份有限公司 | Floor structure and paving method thereof |
CN114575550A (en) * | 2022-03-23 | 2022-06-03 | 安徽三建工程有限公司 | Wet pasting process for floor tiles in kitchens and bathrooms |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203924585U (en) * | 2014-04-30 | 2014-11-05 | 蔡逸民 | Weather strip and wood floor bolck concatenation unit |
CN205063051U (en) * | 2015-10-09 | 2016-03-02 | 浙江亚厦装饰股份有限公司 | End box on ground between whole bathroom |
CN108265938A (en) * | 2017-12-30 | 2018-07-10 | 浙江亚厦装饰股份有限公司 | Ground paving system and method |
-
2018
- 2018-07-26 CN CN201810836119.0A patent/CN108824754A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203924585U (en) * | 2014-04-30 | 2014-11-05 | 蔡逸民 | Weather strip and wood floor bolck concatenation unit |
CN205063051U (en) * | 2015-10-09 | 2016-03-02 | 浙江亚厦装饰股份有限公司 | End box on ground between whole bathroom |
CN108265938A (en) * | 2017-12-30 | 2018-07-10 | 浙江亚厦装饰股份有限公司 | Ground paving system and method |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577589A (en) * | 2018-11-26 | 2019-04-05 | 浙江亚厦装饰股份有限公司 | A kind of external corner wallboard splicing construction and its joining method |
CN110065276A (en) * | 2019-04-30 | 2019-07-30 | 上海今润装饰材料有限公司 | Novel SPC latches ceramic tile composite floor board |
CN112982885A (en) * | 2021-03-10 | 2021-06-18 | 德才装饰股份有限公司 | Floor structure and paving method thereof |
CN114575550A (en) * | 2022-03-23 | 2022-06-03 | 安徽三建工程有限公司 | Wet pasting process for floor tiles in kitchens and bathrooms |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108824754A (en) | A kind of integral bathroom ground installation structure and installation method | |
CN207332369U (en) | A kind of assembled integral vacuum toilet | |
CN103774817A (en) | Special-shaped decorative stone wall surface sticking method | |
CN204343622U (en) | A kind of syndeton of combined floor | |
CN102535807A (en) | Modular wall tile pre-bonding structure and construction method thereof | |
CN210482881U (en) | General fabricated floor tile with all specifications of floor tiles in market | |
CN100462515C (en) | External wall ceramic tile wall surface with heat insulation function and constructing method thereof | |
CN201531072U (en) | Cast-in-situ non-bearing internal partition free from plastering | |
CN113718994A (en) | Connecting structure and method for keel wall and masonry wall | |
CN102644376B (en) | Construction method of recycled concrete wall | |
CN211369445U (en) | Compound ceramic tile spreads fast and pastes structure | |
JPH11315601A (en) | Building exterior heat insulating wall and execution method thereof | |
CN211229273U (en) | Assembled 90 degrees wallboard reentrant corner connection structure of non- | |
CN216920808U (en) | Keel wall and masonry wall connecting structure | |
CN211646851U (en) | Assembled bathroom imitative texture partition wall bottom waterproof construction | |
CN201588366U (en) | Mesh connection type facing brick | |
CN206554331U (en) | A kind of sound insulation cracking resistance decorates prefabricated indoor partition panel | |
CN209990034U (en) | Light-duty equipment base node structure | |
CN115405060B (en) | Method for combining ceramic tile and putty at bealock | |
CN214498158U (en) | Wall body reentrant corner ceramic tile mounting structure | |
CN210767619U (en) | Household ceramic tile structure | |
CN215054760U (en) | Embedded structure of wall brick mirror surface | |
CN211396406U (en) | Cement-based ceramic tile | |
CN2742070Y (en) | Reinforced cement binding force porcelain tile | |
JPH0211534Y2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |