CN108824432B - Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle - Google Patents

Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle Download PDF

Info

Publication number
CN108824432B
CN108824432B CN201810828075.7A CN201810828075A CN108824432B CN 108824432 B CN108824432 B CN 108824432B CN 201810828075 A CN201810828075 A CN 201810828075A CN 108824432 B CN108824432 B CN 108824432B
Authority
CN
China
Prior art keywords
bailey
frame
steel pipe
positioning
locating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810828075.7A
Other languages
Chinese (zh)
Other versions
CN108824432A (en
Inventor
杨泉勇
李哲
袁彬
段聂云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Guizhou Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Guizhou Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Guizhou Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201810828075.7A priority Critical patent/CN108824432B/en
Publication of CN108824432A publication Critical patent/CN108824432A/en
Application granted granted Critical
Publication of CN108824432B publication Critical patent/CN108824432B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a cantilever type adjustable positioning frame for steel pipe piles of a water bailey beam trestle, which comprises a bailey beam (1), wherein the end part of the bailey beam (1) is provided with a positioning frame through a connector (5), the upper surface and the lower surface of the positioning frame are respectively provided with two guide rails (3), and a row of horizontal positioning rods (6) are arranged between the two guide rails (3). The invention successfully solves the construction problems of cantilever type accurate positioning construction of the steel pipe pile of the steel trestle (or the water pile drilling platform), ensures the accuracy of the axis position of the steel pipe pile and the position of the beam part node, improves the stress state of the steel trestle (or the water pile drilling platform), has high economical efficiency, safety and reliability, short positioning time and improves the bearing capacity and stability compared with the traditional water ship positioning method.

Description

Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle
Technical Field
The invention relates to a positioning and adjusting device for an underwater upright post.
Background
In the construction of underwater piers of railway and highway bridges, bridge foundations are generally constructed by erecting steel pipe piles and drilling pile steel platforms of underwater bailey beam trestle bridges. The steel trestle beam part and the steel platform beam part are the most used bailey beams, and because of the characteristics of the bailey beam structure, the fulcras of the steel trestle and the steel platform upright posts (piers) are required to be placed at the junction of chord members at the joints of the bailey beams, so that the accuracy of the plane position of the steel pipe piles serving as the piers cannot exceed +20mm when the steel pipe piles are constructed, and the verticality of the steel pipe piles does not exceed 0.5%. The problem is usually solved by setting up a water positioning frame in water for accurate control, but the method needs water ship equipment, and has the advantages of complex operation, long construction period and high cost.
Disclosure of Invention
The invention aims to solve the technical problems that: aiming at the problem of difficult positioning when the steel pipe pile is inserted into water, the cantilever type positioning frame is provided.
The technical scheme of the invention is as follows:
the cantilever type adjustable positioning frame for the steel pipe piles of the underwater bailey trestle comprises a bailey beam, wherein the positioning frame is installed at the end part of the bailey beam through a connector, two guide rails are installed on the upper surface and the lower surface of the positioning frame, and a row of horizontal positioning rods are installed between the two guide rails.
The connector consists of a female head and a male head which are respectively arranged on the bailey beam or the locating frame, and the ears are provided with strip-shaped holes which are used for fixing the matching positions of the female head and the male head through bolts.
The connectors are mounted at the four corners of the end face of the beret beam.
The locating rack comprises a front set of bailey racks and a rear set of bailey racks, the bailey racks are connected with the end parts through cross beams, and guide rails are arranged on channel steel on the inner sides of the upper chord member and the lower chord member of the bailey racks.
The guide rail and the horizontal positioning rod are steel pipes and are connected through fasteners.
The end part of the beam is provided with a strip hole, and the mounting position of the outer bailey frame is adjusted through the strip hole.
The invention has the beneficial effects that:
the invention successfully solves the construction problems of cantilever type accurate positioning construction of the steel pipe pile of the steel trestle (or the water pile drilling platform), ensures the accuracy of the axis position of the steel pipe pile and the position of the beam part node, improves the stress state of the steel trestle (or the water pile drilling platform), has high economical efficiency, safety and reliability, short positioning time and improves the bearing capacity and stability compared with the traditional water ship positioning method.
The perpendicularity of the cantilever type positioning frame can be adjusted through strip holes on the male and female heads of the connector, and when the steel pipe column is placed into the positioning frame to be positioned, accurate positioning is performed by adjusting the position of the horizontal positioning rod on the guide rail.
Description of the drawings:
Fig. 1 is a schematic top view of the present invention.
Fig. 2 is a schematic side view.
Fig. 3 is a schematic diagram of a forward structure.
Fig. 4 is a schematic diagram of positioning and erecting.
Fig. 5 is a schematic view of steel pipe column positioning.
Fig. 6 is a schematic construction view after removing the spacer.
Fig. 7 is a schematic diagram of the adjusting structure of embodiment 2.
Detailed Description
Example 1: as shown in the figure, the locating rack is a frame structure formed by connecting two groups of parallel bailey frames 7 by using a cross beam 4, the two groups of bailey frames 7 are positioned on the front side and the rear side, triangular diagonal rods are added on the left side and the right side of the frame to improve the strength, a row of supporting steel plates 8 are welded on channel steel of the upper chord member and the lower chord member of the bailey frames 7, guide rails 3 are arranged on the supporting steel plates 8, a horizontal locating rod 6 is arranged between the two guide rails 3, and in the embodiment, the guide rails 3 and the horizontal locating rod 6 are all steel pipes and are connected with each other through fasteners 9. The upper chord member and the lower chord member of the locating frame bailey frame 7 are arranged at the end parts of the bailey beams 1 through connectors 5, the number of the bailey beams 1 is configured according to the length of the locating frame to ensure the strength, in the embodiment, two bailey beams 1 are respectively connected with the two ends of the locating frame, the connectors 5 are composed of female heads and male heads, 4 female heads or male heads are arranged at four corners of the end parts of each bailey beam 1, corresponding male heads or female heads are welded on the locating frame, strip holes are formed in the side surfaces of the female heads and the male heads, and bolts or pin pieces are arranged in the strip holes. The distance between the two bailey frames 7 on the locating frame is equal to the diameter of the steel pipe column, and the length of the bailey beam 1 after the locating frame is installed is equal to the span.
The concrete construction method comprises the following steps:
1. and erecting a first cross-beam steel trestle at cliffside.
2. And a locating frame of the second span is arranged (mainly for providing a construction operation platform for the front-row steel pipe piles and providing a support for installing a cantilever locating frame), and the two bailey beams 1 are connected with a bailey beam steel trestle of the first span.
3. The hoisting steel pipe pile enters the cantilever type locating rack and enters a locating space surrounded by a front bailey rack 7, a rear bailey rack 7, two upper horizontal locating rods 6 and two lower horizontal locating rods 6. After measurement, the deviation of the design position of the steel pipe pile is adjusted through the horizontal and vertical degrees of the cantilever-type locating frame, and the steel pipe pile is primarily fixed. After the position of the steel pipe pile is accurately adjusted through the horizontal positioning rod 6, the equipment drives the steel pipe pile to the designed position accurately. The perpendicularity of the locating rack is ensured by adjusting the matching distance between the female head and the male head of each connector 5. The horizontal position of the steel pipe column is adjusted by adjusting the position of the horizontal positioning rod 6 on the guide rail 3.
4. And (3) inserting and fixing the steel pipe column to a design position, taking down the bailey beam 1 and the locating frame, and erecting a second cross bailey beam steel trestle.
Example 2: the locating rack is the frame construction that forms by two sets of parallel bailey framves 7 with crossbeam 4 connection, and crossbeam 4 one end has a strip hole, can adjust the interval between the bailey frame 7 through the strip hole, and two sets of bailey frame 7 are located two sides around to increase triangle diagonal bar in the frame left and right sides and improve intensity (diagonal bar tip also has a strip hole), welding a row of holding steel plate 8 on the channel-section steel of bailey frame 7 upper and lower chord member, install guide rail 3 on holding steel plate 8, install horizontal locating lever 6 between two guide rails 3, in this embodiment, guide rail 3 and horizontal locating lever 6 are the steel pipe to realize interconnect through fastener 9. The upper chord member and the lower chord member of the locating frame bailey frame 7 are arranged at the end parts of the bailey beams 1 through connectors 5, the number of the bailey beams 1 is configured according to the length of the locating frame to ensure the strength, in the embodiment, two bailey beams 1 are respectively connected with the two ends of the locating frame, the connectors 5 are composed of female heads and male heads, 4 female heads or male heads are arranged at four corners of the end parts of each bailey beam 1, corresponding male heads or female heads are welded on the locating frame, strip holes are formed in the side surfaces of the female heads and the male heads, and bolts or pin pieces are arranged in the strip holes.
Three adjustments can be made in this embodiment: 1. the perpendicularity of the locating frame is adjusted by adjusting the locating positions of the upper strip holes of the upper and lower groups of connectors 5.2. The relative distance between the two groups of bailey frames 7 can be adjusted through the strip holes at the end parts of the cross beams 4, and the longitudinal position of the steel pipe column can be adjusted after the steel pipe column is put down. 3. The fastener 8 can be loosened, the transverse position of the horizontal positioning rod 6 can be adjusted, and the transverse position of the steel pipe column can be adjusted.

Claims (2)

1. The utility model provides an adjustable locating rack of aquatic bailey beam landing stage steel-pipe pile cantilever type, includes bailey beam (1), its characterized in that: the two bailey beams (1) are connected with a bailey beam steel trestle of a first span, the end parts of the two bailey beams (1) are provided with positioning frames through connectors (5), the upper surface and the lower surface of each positioning frame are provided with two guide rails (3), a row of horizontal positioning rods (6) are arranged between the two guide rails (3), each connector (5) consists of three lugs to form a female head and a male head, 4 female heads or male heads are arranged at four corners of the end part of each bailey beam (1), the corresponding male heads or female heads are welded on the positioning frames, strip-shaped holes are formed in the lugs, the matched positions of the female heads and the male heads are fixed through bolts, the connectors (5) are arranged on four corners of the end surfaces of the bailey beams (1), each positioning frame comprises a front group of bailey frame and a rear group of bailey frames (7), the end parts are connected through cross beams (4), the guide rails (3) are arranged on the inner sides of upper chord rods and the lower chord rods of the bailey frames (7), strip holes are formed in the end parts of the cross beams (4), and the bailey frames (7) on the outer sides are adjusted through strip holes;
The concrete construction method comprises the following steps:
1. setting up a first bridge steel trestle of the cross-beam at cliffside;
2. Installing a locating frame of the second span, and connecting the two bailey beams (1) with a bailey beam steel trestle of the first span;
3. Hoisting a steel pipe pile into a cantilever type locating frame, entering a locating space surrounded by a front bailey frame (7), a rear bailey frame (7), an upper two horizontal locating rods (6) and a lower two horizontal locating rods (6), adjusting the design position deviation of the steel pipe pile through the cantilever type locating frame horizontally and vertically after measurement, primarily fixing the steel pipe pile, accurately adjusting the position of the steel pipe pile through the horizontal locating rods (6), accurately driving the steel pipe pile into the design position by equipment, ensuring the verticality of the locating frame by adjusting the matching distance between a female head and a male head of each connector (5), and adjusting the position of the horizontal locating rods (6) on a guide rail (3);
4. and (3) inserting and fixing the steel pipe column to a design position, taking down the bailey beam (1) and the locating frame, and erecting a second cross bailey beam steel trestle.
2. The cantilever-type adjustable positioning frame for steel pipe piles of underwater bailey beam trestle according to claim 1, wherein the cantilever-type adjustable positioning frame is characterized in that: the guide rail (3) and the horizontal positioning rod (6) are steel pipes and are connected through a fastener (9).
CN201810828075.7A 2018-07-25 2018-07-25 Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle Active CN108824432B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810828075.7A CN108824432B (en) 2018-07-25 2018-07-25 Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810828075.7A CN108824432B (en) 2018-07-25 2018-07-25 Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle

Publications (2)

Publication Number Publication Date
CN108824432A CN108824432A (en) 2018-11-16
CN108824432B true CN108824432B (en) 2024-07-09

Family

ID=64139744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810828075.7A Active CN108824432B (en) 2018-07-25 2018-07-25 Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle

Country Status (1)

Country Link
CN (1) CN108824432B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980024A (en) * 2020-08-26 2020-11-24 中交二公局第五工程有限公司 Positioning and guiding equipment for foundation construction of steel trestle
CN113832862B (en) * 2021-10-14 2023-04-11 中铁十九局集团广州工程有限公司 Construction method of assembled steel trestle
CN115030160B (en) * 2022-05-17 2023-10-27 中铁四局集团有限公司 Steel pipe pile inserting and driving positioning method and positioning system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100733263B1 (en) * 2006-04-29 2007-06-28 삼보지질 주식회사 Guide frame apparatus for piling of casing and construction of inserting inconcrete pile on the sea or on the river
CN104929127A (en) * 2015-06-19 2015-09-23 中建海峡建设发展有限公司 Section steel positioning clip
CN209082499U (en) * 2018-07-25 2019-07-09 中铁五局集团贵州工程有限公司 Bailey beam trestle steel pipe pile cantilevered adjustable positioning frame in water

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202298623U (en) * 2011-10-27 2012-07-04 中交四航局第一工程有限公司 Light adjustable positioning device for steel protection barrel on sea
CN202718125U (en) * 2012-07-17 2013-02-06 宁波交通工程建设集团有限公司 Positioning and guiding frame for bailey steel trestle bridge pier foundation construction
CN104372743B (en) * 2014-10-31 2016-05-18 中铁四局集团第二工程有限公司 Trestle rapid constructing method
CN206706762U (en) * 2017-05-12 2017-12-05 中国港湾工程有限责任公司 Shellfish thunder steel trestle pile foundation construction positioning guiding rack
CN207362846U (en) * 2017-10-20 2018-05-15 中国水利水电第八工程局有限公司 Multipurpose leading truck for steel trestle steel-pipe pile
CN207512615U (en) * 2017-11-27 2018-06-19 山西省交通科学研究院 A kind of positioning device used for construction of bridge T steel welding of peg

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100733263B1 (en) * 2006-04-29 2007-06-28 삼보지질 주식회사 Guide frame apparatus for piling of casing and construction of inserting inconcrete pile on the sea or on the river
CN104929127A (en) * 2015-06-19 2015-09-23 中建海峡建设发展有限公司 Section steel positioning clip
CN209082499U (en) * 2018-07-25 2019-07-09 中铁五局集团贵州工程有限公司 Bailey beam trestle steel pipe pile cantilevered adjustable positioning frame in water

Also Published As

Publication number Publication date
CN108824432A (en) 2018-11-16

Similar Documents

Publication Publication Date Title
CN108824432B (en) Cantilever type adjustable positioning frame for steel pipe pile of underwater bailey beam trestle
CN109629569B (en) Steel pipe pile guide frame structure and construction method
CN110318548B (en) Assembled wall mounting bracket and construction method thereof
CN109279480A (en) A kind of steel structure lift shaft splicing apparatus and method
CN209275936U (en) A kind of steel structure lift shaft splicing apparatus
CN106351246B (en) The integral sleeve installation method of T-bolt diameter≤48mm
CN114016520A (en) Adjustable steel sheet pile supporting structure
CN112878933A (en) Large-span multi-section guide rail laying method
CN209082499U (en) Bailey beam trestle steel pipe pile cantilevered adjustable positioning frame in water
CN215052129U (en) Guardrail steel bar positioning device
CN209578560U (en) Lift is oriented to cohesion device
CN111206513B (en) Bridge translation construction structure and device and construction method for crossing existing line bridge
CN211647444U (en) Steel structure assembling supporting jig frame capable of adjusting elevation
CN210238492U (en) Crown beam type miniature pile construction formwork capable of being circulated
CN114411699A (en) Auxiliary device for steel pipe pile construction and construction method
CN220718278U (en) Platform roof beam welding frock
CN115492411B (en) High-precision rapid butt joint device and butt joint method for unitized high-altitude overhanging steel structure
CN220954491U (en) Disc buckle type supporting system
CN211889641U (en) Combined clamping fixture for boiler railing
CN220313288U (en) Mounting device for segment erector test platform
CN220747273U (en) Lattice column supports quick splicing device
CN218932909U (en) Quick positioner of pre-buried sleeve pipe of bridge beam supports bolt hole
CN114161051B (en) Combined platform and method for vertical boiler foundation construction of garbage incineration power plant
CN110777662A (en) Beam section mounting rack of cable-stayed bridge cable tower area and mounting method thereof
CN217782797U (en) High-altitude construction operation platform suitable for lattice column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant