CN104929127A - Section steel positioning clip - Google Patents
Section steel positioning clip Download PDFInfo
- Publication number
- CN104929127A CN104929127A CN201510344778.9A CN201510344778A CN104929127A CN 104929127 A CN104929127 A CN 104929127A CN 201510344778 A CN201510344778 A CN 201510344778A CN 104929127 A CN104929127 A CN 104929127A
- Authority
- CN
- China
- Prior art keywords
- guide rail
- steel positioning
- shaped steel
- positioning clamp
- guide rails
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention relates to a section steel positioning clip which comprises a fixing frame, a pair of guide rails arranged on the fixing frame in parallel, and a pair of telescopic adjustment calipers arranged between the two guide rails. Each telescopic adjustment caliper comprises a length adjustment assembly which stretches and retracts in the direction perpendicular to the stretching direction of the guide rails, and sliding connectors which are arranged at the two ends of the length adjustment assembly and are in sliding fit with the guide rails. The section steel positioning clip is high in integrity, convenient to adjust and reusable. The section steel positioning clip has the advantages that the section steel positioning clip is adjustable, good in integrity and firm in quality, and can position all conventional HN section steel and guarantee that plane position deviation caused by mechanical vibration is avoided in the downward insertion process of the steel section; section steel positioning and checking are convenient through scale marks in the middle portions of the guide rails and the scale marks in small casings, the downward insertion accuracy of the steel section is improved, and the construction efficiency of a construction method pile is improved; the section steel positioning clip is convenient and quick to detach and install and reusable.
Description
Technical field
The present invention relates to the realm of building construction, particularly a kind of shaped steel positioning clamp.
Background technology
In SMW engineering method pile driving construction, when inserting under shaped steel, need position shaped steel with shaped steel positioning clamp, guarantee shaped steel under be inserted through the high-precision requirement of journey median-plane location, there is not plan-position deviation because of the mechanical shock be inserted through under shaped steel in journey.The common shaped steel positioning clamp in job site is four lumps of wood or square steel pipe composition, and this shaped steel positioning clamp is reinforced by the lumps of wood or square steel pipe is welded and fixed and forms card, but is of rude workmanship due to this shaped steel positioning clamp, cannot effectively position shaped steel.
Summary of the invention
The object of the present invention is to provide a kind of globality strong, be convenient to regulate and reusable shaped steel positioning clamp.
Object of the present invention is achieved through the following technical solutions: a kind of shaped steel positioning clamp, and it comprises fixed mount, is parallelly located at the pair of guide rails on fixed mount and is located at a pair telescopic adjustment slide calliper rule between two guide rails; Described telescopic adjustment slide calliper rule comprise along the length adjustment assembly stretched perpendicular to guide rail bearing of trend and are located at length adjustment assembly both ends and the slip joint coordinated with slide.
Compared to prior art, the invention has the advantages that:
Shaped steel positioning clamp has adjustable, can position by the HN shaped steel all to routine, and its good integrity, and quality is firm, guarantee shaped steel under be inserted through in journey and plan-position deviation can not occur because of mechanical shock; Scale in the middle part of guide rail and the scale on small casing are convenient to the check of shaped steel location, and the precision inserted under improve shaped steel, improves the efficiency of construction of engineering method stake; Shaped steel positioning clamp is convenient to disassembly, reusable.
Accompanying drawing explanation
Fig. 1 is the structural representation of a kind of shaped steel positioning clamp embodiment of the present invention.
Fig. 2 is the structural representation of telescopic adjustment slide calliper rule.
Label declaration: 1 fixed mount, 11 adjustment hole A, 2 guide rails, 21 adjustment hole B, 3 telescopic adjustment slide calliper rule, 31 length adjustment assemblies, 32 slip joint, 311 large sleeve pipes, 312 small casings, 313 rubber ferrule.
Detailed description of the invention
Below in conjunction with Figure of description and embodiment, content of the present invention is described in detail:
Be the embodiment schematic diagram of a kind of shaped steel positioning clamp provided by the invention as shown in Figure 1 to Figure 2.
A kind of shaped steel positioning clamp, it comprises fixed mount 1, is parallelly located at the pair of guide rails 2 on fixed mount 1 and is located at a pair telescopic adjustment slide calliper rule 3 between two guide rails 2; Described telescopic adjustment slide calliper rule 3 comprise along the length adjustment assembly 31 stretched perpendicular to guide rail 2 bearing of trend and are located at length adjustment assembly 31 both ends and the slip joint 32 be slidably matched with guide rail 2.Between the rectangular frame that HN shaped steel is formed at two guide rails 2 and two telescopic adjustment slide calliper rule 3, positioned by rectangular frame.
Described fixed mount 1 is well cabinet frame, described guide rail 2 is fixed on the opposite side of well cabinet frame, this opposite side is arranged some for regulating the adjustment hole A11 of the spacing of two guide rails 2, described guide rail 2 is fixed on well cabinet frame by the threaded connector be arranged on adjustment hole A11, and threaded connector is for twining silk nail.
Well cabinet frame is welded by 2 2.2m long 100*50*3 square steel pipes and 2 long 100*50*3 square steel pipes of 1.7m, and wherein 2 1.7m long 100*50*3 square steel pipe intermediate distribution have the circular hole of 29 Ф 625, are adjustment hole A11; 2 rectangular steel-pipe weldings of 2.2m are on 2 rectangular steel pipes of 1.7m.
The scale of instruction two telescopic adjustment slide calliper rule 3 spacing is provided with in the middle part of described guide rail 2.
Be provided with some adjustment hole B21 arranged along guide rail 2 bearing of trend in the middle part of described guide rail 2, described slip joint 32 is fixed on guide rail 2 by the threaded connector be arranged on adjustment hole B21, and threaded connector is for twining silk nail.
The small casing 312 that described length adjustment assembly 31 comprises large sleeve pipe 311 and is actively socketed in large sleeve pipe 311.
Large sleeve pipe 311 is the long 100*50*3 square steel pipe of 150mm; Small casing 312 is the long 80*40*3 square steel pipe of 150mm.
Preferably, the circular hole of 50 Ф 625 can being offered on the sidewall of large sleeve pipe 311 and small casing 312, and by twining the fixing large sleeve pipe 311 of silk nail and small casing 312, to be fixed the length adjustment assembly 31 after regulating, increasing shaped steel positioning clamp resistance to overturning.
Described small casing 312 is provided with the scale of instruction two guide rail 2 spacing.
The mouth of pipe of described large sleeve pipe 311 and small casing 312 is provided with rubber ferrule 313.
Described guide rail 2 is C-type steel, and described slip joint 32 is double-J shape dop, and the crotch of double-J shape dop bends laterally.
Guide rail 2 is that the E41-C shaped steel that the long 2.5mm of 2.5m is thick is made, and E41-C shaped steel two ends are provided with circular hole, and described circular hole and 2 1.7m long 100*50*3 square steel pipes in well cabinet frame twine silk by the long Ф 5 of 100mm and follow closely and be fixedly connected with.
Claims (8)
1. a shaped steel positioning clamp, is characterized in that: it comprises fixed mount (1), is parallelly located at the pair of guide rails (2) on fixed mount (1) and is located at a pair telescopic adjustment slide calliper rule (3) between two guide rails (2); Described telescopic adjustment slide calliper rule (3) comprise along perpendicular to the flexible length adjustment assembly (31) of guide rail (2) bearing of trend and be located at length adjustment assembly (31) both ends and the slip joint (32) be slidably matched with guide rail (2).
2. shaped steel positioning clamp according to claim 1, it is characterized in that: described fixed mount (1) is well cabinet frame, described guide rail (2) is fixed on the opposite side of well cabinet frame, this opposite side is arranged some for regulating the adjustment hole A (11) of the spacing of two guide rails (2), described guide rail (2) is fixed on well cabinet frame by the threaded connector be arranged on adjustment hole A (11).
3. shaped steel positioning clamp according to claim 1, is characterized in that: described guide rail (2) middle part is provided with the scale of instruction two telescopic adjustment slide calliper rule (3) spacing.
4. shaped steel positioning clamp according to claim 1, it is characterized in that: described guide rail (2) middle part is provided with some adjustment hole B (21) arranged along guide rail (2) bearing of trend, and described slip joint (32) is fixed on guide rail (2) by the threaded connector be arranged on adjustment hole B (21).
5. the shaped steel positioning clamp according to claim 1-4 any one, is characterized in that: described length adjustment assembly (31) comprises large sleeve pipe (311) and is actively socketed on the small casing (312) in large sleeve pipe (311).
6. shaped steel positioning clamp according to claim 5, is characterized in that: described small casing (312) is provided with the scale of instruction two guide rail (2) spacing.
7. shaped steel positioning clamp according to claim 5, is characterized in that: the mouth of pipe of described large sleeve pipe (311) and small casing (312) is provided with rubber ferrule (313).
8. shaped steel positioning clamp according to claim 5, is characterized in that: described guide rail (2) is C-type steel, and described slip joint (32) is double-J shape dop, and the crotch of double-J shape dop bends laterally.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510344778.9A CN104929127B (en) | 2015-06-19 | 2015-06-19 | Shaped steel positioning clamp |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510344778.9A CN104929127B (en) | 2015-06-19 | 2015-06-19 | Shaped steel positioning clamp |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104929127A true CN104929127A (en) | 2015-09-23 |
CN104929127B CN104929127B (en) | 2017-03-08 |
Family
ID=54116535
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510344778.9A Active CN104929127B (en) | 2015-06-19 | 2015-06-19 | Shaped steel positioning clamp |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104929127B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107989027A (en) * | 2017-11-28 | 2018-05-04 | 浙江亚磊型钢冷拔有限公司 | A kind of section steel positioning device |
CN108824432A (en) * | 2018-07-25 | 2018-11-16 | 中铁五局集团贵州工程有限公司 | Bailey beam trestle steel pipe pile cantilevered adjustable positioning frame in water |
CN111287226A (en) * | 2020-02-24 | 2020-06-16 | 四川道诚建设工程检测有限责任公司 | A quick interfacing apparatus that is used for pile foundation quality detection pipe of large-scale bridge engineering |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202064357U (en) * | 2011-03-29 | 2011-12-07 | 中铁十局集团有限公司 | Spacing headframe |
CN202416321U (en) * | 2012-01-04 | 2012-09-05 | 广东中匠工程建设有限公司 | Simple guide frame for vibratory pile sinking construction in shallow water |
CN203866831U (en) * | 2014-06-19 | 2014-10-08 | 葛洲坝集团第五工程有限公司 | Telescopic splicing guide frame for large-diameter steel protecting cylinder |
KR101524744B1 (en) * | 2014-04-15 | 2015-06-01 | 한국건설기술연구원 | Fabrication Method and Apparatus for Wind Power Tower |
CN204780919U (en) * | 2015-06-19 | 2015-11-18 | 中建海峡建设发展有限公司 | Shaped steel locator card |
-
2015
- 2015-06-19 CN CN201510344778.9A patent/CN104929127B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202064357U (en) * | 2011-03-29 | 2011-12-07 | 中铁十局集团有限公司 | Spacing headframe |
CN202416321U (en) * | 2012-01-04 | 2012-09-05 | 广东中匠工程建设有限公司 | Simple guide frame for vibratory pile sinking construction in shallow water |
KR101524744B1 (en) * | 2014-04-15 | 2015-06-01 | 한국건설기술연구원 | Fabrication Method and Apparatus for Wind Power Tower |
CN203866831U (en) * | 2014-06-19 | 2014-10-08 | 葛洲坝集团第五工程有限公司 | Telescopic splicing guide frame for large-diameter steel protecting cylinder |
CN204780919U (en) * | 2015-06-19 | 2015-11-18 | 中建海峡建设发展有限公司 | Shaped steel locator card |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107989027A (en) * | 2017-11-28 | 2018-05-04 | 浙江亚磊型钢冷拔有限公司 | A kind of section steel positioning device |
CN108824432A (en) * | 2018-07-25 | 2018-11-16 | 中铁五局集团贵州工程有限公司 | Bailey beam trestle steel pipe pile cantilevered adjustable positioning frame in water |
CN111287226A (en) * | 2020-02-24 | 2020-06-16 | 四川道诚建设工程检测有限责任公司 | A quick interfacing apparatus that is used for pile foundation quality detection pipe of large-scale bridge engineering |
Also Published As
Publication number | Publication date |
---|---|
CN104929127B (en) | 2017-03-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929127A (en) | Section steel positioning clip | |
BR112016011062A2 (en) | SYSTEM FOR MOUNTING A STRAIN SENSOR ON A TUBULAR TUBE, METHOD FOR MOUNTING A STRAIN SENSOR ON A TUBULAR TUBE, SYSTEM FOR MOUNTING AT LEAST ONE STRAIN SENSOR ON A TUBULAR TUBE AND METHOD FOR MOUNTING A STRAIN SENSOR ON A TUBE | |
CN105004607A (en) | Universal testing machine tension-compression integrated experimental fixture | |
BR112015005535A2 (en) | method for welding top rail and seat rail adapter bracket to vehicle seat | |
CN204780919U (en) | Shaped steel locator card | |
CN103307364A (en) | Slidable hanger | |
JP2015047620A (en) | Manufacturing method of u-shaped damper | |
CN103454141A (en) | Positioning device for supporting and radially adjusting split hopkinson bar | |
CN106185022A (en) | A kind of tube support arrangement | |
CN103639921A (en) | Connecting rod detection positioning device | |
CN103486948A (en) | Butt joint circular tube measurement standard line tension device | |
CN207557015U (en) | A kind of easy device for measuring Bending Concrete amount of deflection | |
CN105268782A (en) | Handrail correcting device | |
MX2020008646A (en) | Apparatus and method for correcting misalignment of a strip. | |
CN205110448U (en) | Modified I -steel straightener | |
DE502008001911D1 (en) | Adjusting device for a distance between two run on a common rail carriage and method | |
CN203249608U (en) | Apparatus for measuring length of hose assembly | |
CN102620749B (en) | A kind of calibrated mount of centering rod | |
CN204123007U (en) | A kind of guide for automobile welding and assembling clamp | |
CN204817759U (en) | Clamping device who uses during aligning steel pipe | |
CN206399330U (en) | A kind of novel bridge pier stud diameter measuring device | |
CN206366735U (en) | A kind of I-steel gripping mechanism | |
CN205538179U (en) | Direction pipe clamp draws presses testing arrangement | |
CN207888521U (en) | A kind of screw positioning fixture | |
CN204312482U (en) | A kind of self-locking tubing connecting tube |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20170510 Address after: 350899 Fuzhou City, Minqing Province, Mei Town, liberation Avenue, No. (New Century Towers), layer 1004, unit 63, 22 Patentee after: Zhongjian Technology (Fuzhou) Co., Ltd. Address before: 98-1 No. 350000 Fujian province Fuzhou Mawei District Jiangbin East Avenue Patentee before: CSCEC Strait Construction and Development Co., Ltd. |
|