CN108808656A - The provincial control zone of interconnected network adjusts the AGC control methods of spare Real-Time Sharing - Google Patents
The provincial control zone of interconnected network adjusts the AGC control methods of spare Real-Time Sharing Download PDFInfo
- Publication number
- CN108808656A CN108808656A CN201810502297.XA CN201810502297A CN108808656A CN 108808656 A CN108808656 A CN 108808656A CN 201810502297 A CN201810502297 A CN 201810502297A CN 108808656 A CN108808656 A CN 108808656A
- Authority
- CN
- China
- Prior art keywords
- control area
- control
- ace
- provincial
- agc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
Description
技术领域technical field
本发明属电力系统有功控制领域,涉及一种适应于大规模新能源并网大发或夏季负荷高峰时段导致省调调节备用严重不足后调节备用实时控制方法,该方法提出分调和省调实时协调控制策略,通过省级电网调节备用的实时共享,实现全网一体化的AGC(Automatic Generation Control,自动发电控制)控制。The invention belongs to the field of active power control of electric power systems, and relates to a real-time control method for adjusting standby after large-scale new energy grid-connected large-scale generation or summer load peak period causes serious shortage of provincial regulation and reserve. The method proposes real-time coordination of separate regulation and provincial regulation The control strategy realizes the integrated AGC (Automatic Generation Control, automatic generation control) control of the whole network through the real-time sharing of provincial power grid regulation backup.
背景技术Background technique
在区域电网大范围协调控制方面,目前国内外主要的协同策略有:In terms of large-scale coordinated control of regional power grids, the main coordinated strategies at home and abroad are as follows:
1)实体控制区联合:是将多个(两个或两个以上)控制区联合在一起形成一个新的大控制区,调度业务集中到某一个区域的调度机构,或者另成立一个调度机构负责全网的有功平衡任务,该调度机构仍采用常规的计划编制方式和控制手段,只是权力范围更大,可调用的资源更多。这里相当于扩大控制区的范围,在我国的分中心(分部调度中心)调控模式下类似于分中心-省调的调度控制权一体化,分调直接控制区内所有机组,省调并没有实际调度权。1) Unity of physical control areas: it is to combine multiple (two or more) control areas to form a new large control area, and dispatch business to a dispatching organization in a certain area, or set up another dispatching organization to be responsible For the active power balance task of the entire network, the dispatching organization still adopts conventional planning and control methods, but the scope of power is larger and more resources can be mobilized. This is equivalent to expanding the scope of the control area. Under the control mode of the sub-center (sub-division dispatching center) in my country, it is similar to the integration of sub-center-provincial dispatching control rights. The dispatching directly controls all units in the area, and the provincial dispatching does not Actual scheduling rights.
2)ACE(Area Control Error,区域控制偏差)差异性交换方法。该方法主要是利用实时运行中互联电网内各区域ACE符号的差异性。该策略是根据AGC和负荷跟踪调节方向的正或负(调用正备用或负备用)来减少总的调节量,这主要是考虑到某些区域设置的调节方向并不与ACE同号,比如某些控制区为了满足CPS(Control Performance Standard,控制性能标准)标准可能出现追求调节方向相反的行为。2) ACE (Area Control Error, regional control deviation) difference exchange method. This method mainly utilizes the difference of ACE symbols in each region in the interconnected grid in real-time operation. This strategy is to reduce the total adjustment amount according to the positive or negative of AGC and load tracking adjustment direction (calling positive reserve or negative reserve). This is mainly because the adjustment direction of some regional settings is not the same as that of ACE. In some control areas, in order to meet the CPS (Control Performance Standard, Control Performance Standard) standard, there may be behaviors that pursue the opposite direction of regulation.
上述两种方法目前主要应用于国外电力市场环境下。其中第一种方法主要是从电力有功调控政策和机制上实现多区域的协调控制,这种协调控制方式是将下属的调管权收回至上级调度,不适应我国现有的分级调度、分省平衡的调度现状。方法二主要应用于市场环境下通过控制区间ACE反向抵消来降低机组的无谓调节和频率波动,这种多区域间的协调配合策略局限于减少机组调节,没有从减少全网备用的角度调集所有资源保证电网运行安全。The above two methods are currently mainly used in foreign power market environments. The first method is mainly to realize multi-regional coordinated control from the policy and mechanism of electric power active power regulation. This coordinated control method is to take back the subordinate's regulation and control power to the superior dispatching, which is not suitable for my country's existing hierarchical dispatching and sub-provincial dispatching. Balanced scheduling status. The second method is mainly used in the market environment to reduce the unnecessary adjustment and frequency fluctuation of the unit through the reverse offset of the control interval ACE. This multi-regional coordination strategy is limited to reducing the adjustment of the unit, and does not mobilize all from the perspective of reducing the backup of the entire network. resources to ensure the safety of grid operation.
发明内容Contents of the invention
本发明的目的是:针对当前电网新能源大规模并网运行后新能源全额消纳导致电网调节下备用不足,或者在夏季负荷高峰阶段部分省级电网上备用不足的运行现状,采用在分调统筹考虑全网各省调的调节备用,通过将相邻控制区自动融合的方式,将全网各个省调的调节备用统筹分配,将不具备调节备用控制区的调节责任自动转移至相邻有调节能力的控制区,实现控制区之间调节备用的实时共享,最大限度的利用全网的AGC调节能力,促进全网新能源的消纳,保证电网的运行安全。The purpose of the present invention is to: in view of the insufficient backup of the grid regulation caused by the full consumption of new energy after the large-scale grid-connected operation of the new energy in the current power grid, or the insufficient backup of some provincial power grids during the peak load period in summer, the use of distributed The adjustment and planning of the provinces in the whole network are considered in the overall planning, and the adjustment and backup of the provinces in the whole network are coordinated and allocated through the automatic fusion of adjacent control areas. The control area of the regulation ability realizes the real-time sharing of the regulation reserve among the control areas, maximizes the use of the AGC regulation ability of the whole network, promotes the consumption of new energy in the whole network, and ensures the operation safety of the power grid.
为了实现上述目的,本发明是采取以下的技术方案来实现的:In order to achieve the above object, the present invention is achieved by taking the following technical solutions:
一种互联电网省级控制区调节备用实时共享AGC控制方法,包括下列步骤:A method for controlling the real-time shared AGC of the province-level control area of an interconnected power grid, comprising the following steps:
1)在分部调度中心(以下简称分调)AGC(Automatic Generation Control,自动发电控制,AGC)应用中建立主控制区域,实施分调整体区域的有功控制;在分调AGC中建立分调调管范围内的所有省级控制区作为省级AGC;1) Establish the main control area in the AGC (Automatic Generation Control, AGC) application of the sub-dispatch center (hereinafter referred to as sub-dispatch), and implement the active power control of the sub-dispatching overall area; All provincial-level control areas within the scope serve as provincial-level AGCs;
2)省级控制区的模型包括频率模型和联络线模型,每个省级控制区采用同一个频率量测测点(在AGC里每个数据点称为量测,每个量测有几个测点使用),联络线模型中的联络线实际量测模型和联络线计划量测模型都采用输出为正的建模方法;2) The model of the provincial control area includes a frequency model and a tie line model. Each provincial control area uses the same frequency measurement point (in AGC, each data point is called a measurement, and each measurement has several measuring points), the actual measurement model of the tie line and the planned measurement model of the tie line in the tie line model both adopt the modeling method with positive output;
3)由分调AGC按照TBC(Tie-Line Bias Control,联络线偏差控制)模式计算各个省级控制区的ACE(Area Control Error,区域控制偏差),通过遥测转发将省级控制区的ACE实时发送到各个省级控制区,由省级控制区AGC对ACE进行控制;3) The sub-dispatching AGC calculates the ACE (Area Control Error, regional control deviation) of each provincial control area according to the TBC (Tie-Line Bias Control, tie-line deviation control) mode, and transmits the ACE of the provincial control area in real time through telemetry forwarding Send to each provincial control area, and the provincial control area AGC controls ACE;
4)在实时控制过程中,由各个省级AGC实时统计计算各自控制区的调节备用,统计计算方法为式(1),并实时上送至分调AGC:4) During the real-time control process, each provincial-level AGC counts and calculates the adjustment reserves of their respective control areas in real time. The statistical calculation method is formula (1), and sends it to the sub-dispatching AGC in real time:
式中:Rup为控制区的上调节备用,Gi-up-limit为机组i的调节上限,Gi-gen为机组i的实际出力,Rdown为控制区的下调节备用,Gi-down_limit为机组i的调节下限,n为控制区AGC机组总数;In the formula: R up is the up-regulation reserve of the control area, G i-up-limit is the upper limit of the adjustment of unit i, G i-gen is the actual output of unit i, R down is the down-regulation reserve of the control area, G i- down_limit is the adjustment lower limit of unit i, n is the total number of AGC units in the control area;
5)分调实时监视各省级AGC的调节备用,按照负荷/备用比统计各个省级电网的备用情况;5) The sub-dispatcher monitors the adjustment and backup of each provincial AGC in real time, and counts the backup status of each provincial power grid according to the load/standby ratio;
6)当某个省级电网由于负荷高导致上调节备用不足,或者由于电网新能源发电大导致下调节备用不足时,进行调节备用共享申请;6) When a provincial power grid has insufficient up-regulation reserve due to high load, or insufficient down-regulation reserve due to large new energy power generation in the grid, apply for regulation reserve sharing;
7)当分部调度中心监视到原先调节备用不足控制区备用超过恢复门槛时,解除虚拟控制区控制,每个控制区的ACE按照原有的TBC模式进行计算并下发给控制区进控制;7) When the branch dispatching center monitors that the original adjustment reserve is insufficient and the control area reserve exceeds the recovery threshold, the control of the virtual control area is released, and the ACE of each control area is calculated according to the original TBC mode and sent to the control area for control;
8)在控制区合并控制过程中,分部调度中心按照实际下发给各个省调控制区AGC的ACE和电网整体频率采用A标准或CPS标准对控制区进行考核评价。8) In the process of merging the control areas, the branch dispatching center evaluates the control areas by using the A standard or CPS standard according to the ACE and the overall frequency of the power grid actually issued to the AGCs of each provincial control area.
主控制区域的控制目标为维持电网的频率在控制范围内,或维持本控制区域与其他相邻控制区域交换功率为给定计划值,或上述两个控制目标同时满足;省级AGC控制目标为维持本省电网的频率在控制范围内,或维持本省控制区域与其他相邻控制区域交换功率为给定计划值,或上述两个控制目标同时满足。The control objective of the main control area is to maintain the frequency of the power grid within the control range, or to maintain the exchange power between this control area and other adjacent control areas at a given planned value, or to meet the above two control objectives at the same time; the provincial AGC control objective is Maintain the frequency of the province's power grid within the control range, or maintain the exchange power between the province's control area and other adjacent control areas at a given planned value, or meet the above two control objectives at the same time.
步骤(6)所述调节备用共享申请包括:The adjustment standby sharing application described in step (6) includes:
(61)由下级调度电话申请,分部调度中心调度员审核通过后启动调节备用实时共享功能;(61) Apply by the subordinate dispatching phone, and the dispatcher of the branch dispatching center will start the real-time sharing function of the adjustment backup after reviewing and passing;
(62)根据约定的自动启动机制,分调AGC根据各省备用情况自动启动省间调节备用实时共享策略。(62) According to the agreed automatic start-up mechanism, the sub-dispatch AGC automatically starts the inter-provincial adjustment and backup real-time sharing strategy according to the backup situation of each province.
省间调节备用实时共享策略包括:Alternative real-time sharing strategies for inter-provincial regulation include:
(71)分调AGC首先判断调节备用不足控制区A的位置,优先选用相邻控制区调节备用最大控制区B,自动增加一个虚拟的合并控制区(A+B),总体调节备用为A控制区调节备用和B控制区调节备用之和;(71) Dispatch AGC first judges the position of the insufficient control area A for adjusting the reserve, preferentially selects the adjacent control area to adjust the maximum control area B for the reserve, automatically adds a virtual merged control area (A+B), and the overall adjustment reserve is controlled by A The sum of the regulation reserve of the zone and the regulation reserve of the B control zone;
(72)新构造的合并控制区(A+B)的控制区ACE计算方法为式(2)所示:(72) The calculation method of the control area ACE of the newly constructed merged control area (A+B) is shown in formula (2):
ACEA+B=ACEA+ACEB (2)ACE A+B = ACE A +ACE B (2)
式中:ACEA+B为合并控制区(A+B)的ACE,ACEA为控制区A的ACE,ACEB为控制区B的ACE;In the formula: ACE A+B is the ACE of the combined control area (A+B), ACE A is the ACE of the control area A, and ACE B is the ACE of the control area B;
(73)计算完合并控制区的ACE后,按照预定义的ACE分配策略进行控制。(73) After calculating the ACE of the merged control area, control according to the predefined ACE allocation strategy.
ACE分配策略包括:ACE allocation strategies include:
(81)分配策略1:如果控制区A调节备用不足,将控制区A全部调整到调节上限(上备用不足时)或全部调节到调节下限(下备用不足时),A控制区剩余的调节责任全部由B控制区承担,控制区A的ACE设置为0,合并控制区(A+B)的ACE为两个控制区(控制区A和控制器B)的ACE之和;(81) Allocation strategy 1: If the adjustment reserve in control area A is insufficient, adjust all control area A to the upper limit of adjustment (when the upper reserve is insufficient) or to the lower limit of adjustment (when the lower reserve is insufficient), the remaining adjustment responsibility of the control area A All are assumed by the B control area, the ACE of the control area A is set to 0, and the ACE of the merged control area (A+B) is the sum of the ACEs of the two control areas (control area A and controller B);
(82)分配策略2:将总体ACE(合并控制区(A+B)的ACE)按照调节备用比例分配至各两个控制区(控制区A和控制器B),计算方法如下式所示:(82) Allocation strategy 2: Allocate the overall ACE (the ACE of the combined control area (A+B)) to each of the two control areas (control area A and controller B) according to the adjusted reserve ratio, and the calculation method is shown in the following formula:
式中:ACE'A为控制区A修正后的ACE,ACE(A+B)为合并控制区(A+B)的控制区ACE,ACE'B为控制区B修正后的ACE,RA为控制区A的调节备用,RA+B为合并控制区(A+B)的总调节备用,RB为控制区B的调节备用。In the formula: ACE' A is the modified ACE of control area A, ACE (A+B) is the ACE of the control area combined with control area (A+B), ACE' B is the modified ACE of control area B, R A is The adjustment reserve of control area A, RA +B is the general adjustment reserve of the combined control area (A+B), and RB is the adjustment reserve of control area B.
步骤8)具体包括:Step 8) specifically includes:
采用A标准进行考核:在控制区合并后,如果采用分配策略1进行ACE分配,不考核A1指标;被合并控制区(指控制区A)的A2指标ACE平均值考核门槛Ld按照备用裕度分段取值,主合并控制区(控制区B)的A2指标ACE平均值考核门槛按照被合并控制区Ld对应进行分段取值;Standard A is used for assessment: after the control area is merged, if the allocation strategy 1 is used for ACE allocation, the A1 index will not be assessed; the A2 index ACE average value assessment threshold Ld of the merged control area (referring to the control area A) is divided according to the spare margin Segment value, the A2 index ACE average assessment threshold of the main merged control area (control area B) is segmented according to the Ld of the merged control area;
采用CPS标准进行考核,在控制区合并控制期间,被合并控制区CPS1指标不进行考核,主合并控制区CPS1考核指标计算中按照合并控制区总的B系数进行计算;被合并控制区的CPS2指标考核门槛L10按照备用裕度分段取值,主合并控制区的CPS2考核门槛L10按照被合并控制区L10对应进行分段取值。The CPS standard is used for assessment. During the merger control period of the control area, the CPS1 index of the merged control area is not assessed, and the CPS1 assessment index calculation of the main merged control area is calculated according to the total B coefficient of the merged control area; the CPS2 index of the merged control area The assessment threshold L10 is valued in segments according to the spare margin, and the CPS2 assessment threshold L10 of the main merged control area is valued in segments corresponding to the merged control area L10.
本发明的所达到的有益效果:本发明提出的互联电网省级控制区调节备用实时共享AGC控制方法,应用于调度AGC的实时控制,着眼于全网调节备用的共享以及频率和电网运行安全;通过对分调和省调的两级协调控制,能够在更大范围内实现备用的实时共享,通过各个省调调节备用的实时共享和分级调用,从更大范围内保证了电网对新能源的消纳以及电网的安全稳定运行。The beneficial effects achieved by the present invention: the provincial control area of the interconnected grid proposed by the present invention adjusts and reserves the real-time shared AGC control method, which is applied to the real-time control of dispatching AGC, focusing on the sharing of the entire network's regulation and reserve, as well as the safety of frequency and power grid operation; Through the two-level coordinated control of sub-regulation and provincial regulation, the real-time sharing of backup can be realized in a wider range. Through the real-time sharing and hierarchical call of each provincial regulation and regulation backup, the consumption of new energy by the power grid can be guaranteed in a wider range. and the safe and stable operation of the power grid.
附图说明Description of drawings
图1为本发明一种互联电网省级控制区调节备用实时共享AGC控制方法模型示意图。FIG. 1 is a schematic diagram of a model of an AGC control method for regulating and standby real-time shared AGC in a provincial control area of an interconnected power grid according to the present invention.
具体实施方式Detailed ways
下面结合附图和具体的实施例对本发明技术方案作进一步的详细描述,以使本领域的技术人员可以更好的理解本发明并能予以实施,但所举实施例不作为对本发明的限定。The technical scheme of the present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments, so that those skilled in the art can better understand the present invention and implement it, but the examples given are not intended to limit the present invention.
如图1所示,下面结合附图1对本发明作进一步说明。As shown in Fig. 1, the present invention will be further described below in conjunction with Fig. 1 .
一种互联电网省级控制区调节备用实时共享的AGC控制方法,包括以下步骤,A kind of AGC control method that the province-level control area of interconnected power grid regulates standby real-time sharing, comprises the following steps,
1)在分部调度中心(以下简称分调)AGC(Automatic Generation Control,自动发电控制,AGC)应用中建立主控制区域,实施分调整体区域的有功控制,主控制区域的控制目标为维持电网的频率在控制范围内,或维持本控制区域与其他相邻控制区域交换功率为给定计划值,或上述两个控制目标同时满足;1) Establish the main control area in the application of AGC (Automatic Generation Control, automatic generation control, AGC) in the branch dispatching center (hereinafter referred to as sub-dispatching), and implement the active power control of the distribution and adjustment overall area. The control goal of the main control area is to maintain the power grid The frequency is within the control range, or the exchange power between this control area and other adjacent control areas is maintained at a given planned value, or the above two control objectives are met at the same time;
在分调AGC应用中建立分调调管范围内的所有省级控制区作为省级AGC,省级AGC控制目标为维持本省电网的频率在控制范围内,或维持本省控制区域与其他相邻控制区域交换功率为给定计划值,或上述两个控制目标同时满足。In the sub-dispatching AGC application, all provincial-level control areas within the scope of sub-dispatching and regulating tubes are established as provincial AGCs. The provincial AGC control goal is to maintain the frequency of the provincial power grid within the control range, or maintain the provincial control area and other adjacent control areas. The exchange power is a given planned value, or the above two control objectives are satisfied at the same time.
2)省级控制区的模型包括频率模型和联络线模型,每个省级控制区采用同一个频率量测测点(在AGC里每个数据点称为量测,每个量测有几个测点使用),联络线模型中的联络线实际量测模型和联络线计划量测模型都采用输出为正的建模方法;2) The model of the provincial control area includes a frequency model and a tie line model. Each provincial control area uses the same frequency measurement point (in AGC, each data point is called a measurement, and each measurement has several measuring points), the actual measurement model of the tie line and the planned measurement model of the tie line in the tie line model both adopt the modeling method with positive output;
3)在正常情况下,由分调AGC按照TBC(Tie-Line Bias Control,联络线偏差控制)模式计算各个省级控制区的ACE(Area Control Error,区域控制偏差),再通过遥测转发将省级控制区的ACE实时发送到各个省级控制区,由省级控制区AGC对ACE进行控制;3) Under normal circumstances, the sub-dispatching AGC calculates the ACE (Area Control Error, regional control deviation) of each provincial control area according to the TBC (Tie-Line Bias Control, Tie-Line Bias Control) mode, and then forwards the provincial The ACE of the provincial control area is sent to each provincial control area in real time, and the AGC of the provincial control area controls the ACE;
4)在实时控制过程中,由各个省级AGC实时统计各自控制区的调节备用,统计计算方法为式(1),并实时上送至分调AGC:4) During the real-time control process, each provincial-level AGC makes real-time statistics on the adjustment reserves of their respective control areas. The statistical calculation method is formula (1), and is sent to the sub-dispatch AGC in real time:
式中:Rup为控制区的上调节备用,Gi-up-limit为机组i的调节上限,Gi-gen为机组i的实际出力,Rdown为控制区的下调节备用,Gi-down_limit为机组i的调节下限,n为控制区AGC机组总数;In the formula: R up is the up-regulation reserve of the control area, G i-up-limit is the upper limit of the adjustment of unit i, G i-gen is the actual output of unit i, R down is the down-regulation reserve of the control area, G i- down_limit is the adjustment lower limit of unit i, n is the total number of AGC units in the control area;
5)分调实时监视各省级AGC的调节备用,并按照负荷/备用比统计各个省级电网的备用情况;5) The sub-dispatcher monitors the adjustment and backup of each provincial AGC in real time, and counts the backup status of each provincial power grid according to the load/standby ratio;
6)当某个省级电网由于负荷高导致上调节备用不足,或者由于电网新能源发电大导致下调节备用不足时,可以采用以下几种方式进行调节备用共享申请:6) When a provincial power grid has insufficient up-regulation reserve due to high load, or insufficient down-regulation reserve due to large new energy power generation in the grid, the following methods can be used to apply for regulation reserve sharing:
(61)由下级调度电话申请,分部调度中心调度员审核通过后启动调节备用实时共享功能;(61) Apply by the subordinate dispatching phone, and the dispatcher of the branch dispatching center will start the real-time sharing function of the adjustment backup after reviewing and passing;
(62)根据约定的自动启动功能,分调AGC根据各省备用情况自动启动省间调节备用实时共享策略;(62) According to the agreed automatic start function, the sub-dispatch AGC automatically starts the inter-provincial adjustment and backup real-time sharing strategy according to the backup situation of each province;
7)省间调节备用实时共享策略如下:7) The inter-provincial adjustment backup real-time sharing strategy is as follows:
(71)分调AGC首先判断调节备用不足控制区A的位置,优先选用相邻控制区调节备用最大控制区B,自动增加一个虚拟的合并控制区(A+B),总体调节备用为A控制区调节备用和B控制区调节备用之和;(71) Dispatch AGC first judges the position of the insufficient control area A for adjusting the reserve, preferentially selects the adjacent control area to adjust the maximum control area B for the reserve, automatically adds a virtual merged control area (A+B), and the overall adjustment reserve is controlled by A The sum of the regulation reserve of the zone and the regulation reserve of the B control zone;
(72)新构造的合并控制区(A+B)的控制区ACE计算方法为式(2)所示:(72) The calculation method of the control area ACE of the newly constructed merged control area (A+B) is shown in formula (2):
ACEA+B=ACEA+ACEB (2)ACE A+B = ACE A +ACE B (2)
式中:ACEA+B为合并控制区的ACE,ACEA为控制区的ACE,ACEB为控制区B的ACE;In the formula: ACE A+B is the ACE of the combined control area, ACE A is the ACE of the control area, and ACE B is the ACE of the control area B;
(73)计算完合并控制区的ACE后,再按照预定义的ACE分配策略进行控制:(73) After calculating the ACE of the combined control area, control according to the predefined ACE allocation strategy:
8)ACE分配策略包括:8) ACE allocation strategy includes:
(81)ACE分配策略之一是:如果A控制区调节备用不足,先将A控制区全部调整到调节上限(上备用不足时)或全部调节到调节下限(下备用不足时),A控制区剩余的调节责任全部由B控制区承担,A控制区的ACE设置为0,(A+B)控制区的ACE为两个控制区的ACE之和;(81) One of the ACE allocation strategies is: if the adjustment reserve in the A control area is insufficient, first adjust all the A control area to the upper limit of the adjustment (when the upper reserve is insufficient) or to the lower limit of the adjustment (when the lower reserve is insufficient), and the A control area The rest of the adjustment responsibility is all assumed by the B control area, the ACE of the A control area is set to 0, and the ACE of the (A+B) control area is the sum of the ACEs of the two control areas;
(82)ACE分配策略之二是将总体ACE按照调节备用比例分配至各两个控制区,计算方法如下式所示:(82) The second ACE allocation strategy is to allocate the overall ACE to each of the two control areas according to the adjustment reserve ratio. The calculation method is as follows:
式中:ACE'A为A控制区修正后的ACE,ACE(A+B)为合并控制区(A+B)的控制区ACE,ACE'B为B控制区修正后的ACE,RA为控制区A的调节备用,RA+B为合并控制区(A+B)的总调节备用,RB为控制区B的调节备用;In the formula: ACE' A is the revised ACE of the A control area, ACE (A+B) is the ACE of the merged control area (A+B), ACE' B is the revised ACE of the B control area, R A is The adjustment reserve of control area A, R A+B is the general adjustment reserve of the combined control area (A+B), and R B is the adjustment reserve of control area B;
按照不同的分配策略得到控制区A和控制区B的ACE后,遥测下发通道,下发给各个控制区,由各个控制区去执行;After obtaining the ACEs of control area A and control area B according to different allocation strategies, the telemetry distribution channel is issued to each control area for execution by each control area;
9)当分中心监视到原先调节备用不足控制区备用超过恢复门槛时,自动解除虚拟控制区控制,每个控制区的ACE仍然按照原有的TBC模式进行计算并下发给控制区进控制;9) When the sub-center monitors that the original adjustment reserve is insufficient and the control area reserve exceeds the recovery threshold, it will automatically cancel the control of the virtual control area, and the ACE of each control area will still be calculated according to the original TBC mode and sent to the control area for control;
10)在控制区合并控制过程中,分部调度中心按照实际下发给各个省调控制区AGC的ACE和电网整体频率采用A标准或CPS标准对控制区进行考核评价。10) In the process of merging the control areas, the branch dispatching center evaluates the control areas according to the ACE and the overall frequency of the power grid actually issued to the AGCs of each provincial control area using the A standard or the CPS standard.
101)如果采用A标准进行考核:在控制区合并后,如果采用分配策略(1)进行ACE分配,不考核A1指标。被合并控制区(控制器A,控制区B)的A2指标ACE平均值考核门槛Ld按照备用裕度分段取值,主合并控制区(合并控制器A+B)的A2指标ACE平均值考核门槛按照被合并控制区Ld对应进行分段取值;101) If A standard is used for assessment: after the merger of the control areas, if the allocation strategy (1) is used for ACE allocation, the A1 indicator will not be assessed. The A2 index ACE average value assessment threshold Ld of the merged control area (controller A, control area B) is selected according to the backup margin segmented value, and the A2 index ACE average value evaluation of the main merged control area (merged controller A+B) The threshold is valued in segments according to the merged control area Ld;
102)如果采用CPS标准进行考核,在控制区合并控制期间,被合并控制区CPS1指标不进行考核,主合并控制区CPS1考核指标计算中按照合并控制区总的B系数进行计算。被合并控制区的CPS2指标考核门槛L10按照备用裕度分段取值,主合并控制区的CPS2考核门槛L10按照被合并控制区L10对应进行分段取值。102) If the CPS standard is used for assessment, during the merger control period of the control area, the CPS1 index of the merged control area will not be assessed, and the calculation of the CPS1 assessment index of the main merged control area will be calculated according to the total B coefficient of the merged control area. The CPS2 index assessment threshold L10 of the merged control area is valued in segments according to the spare margin, and the CPS2 assessment threshold L10 of the main merged control area is valued in segments according to the L10 of the merged control area.
步骤5)中,分调实时监视各省调AGC的调节备用,并按照负荷/备用比统计各个省级电网的备用情况;当某个省级电网由于负荷比较高导致上调节备用不足,或者由于电网新能源发电过大导致下调节备用不足时,可以采用由下级调度电话申请,分中心调度员审核通过后启动调节备用实时共享功能,或者根据事先约定的自动启动功能,分中心AGC自动根据各省备用情况自动启动省间调节备用的实时共享功能;In step 5), the sub-dispatcher monitors the adjustment reserve of AGC in each province in real time, and counts the reserve situation of each provincial power grid according to the load/reserve ratio; When the new energy power generation is too large and the down-regulation backup is insufficient, the sub-center dispatcher can apply through the phone call, and the sub-center dispatcher will start the real-time sharing function of the regulation backup after the approval, or according to the pre-agreed automatic start function, the sub-center AGC will automatically adjust according to the provincial backup. The situation automatically starts the real-time sharing function of inter-provincial adjustment and backup;
步骤7)中,分中心AGC首先判断调节备用不足控制区的位置,优先选用相邻控制区调节备用最大控制区,再自动增加一个虚拟的合并控制区,该控制区的总体调节备用为两个控制区调节备用之和,新构造的合并控制区(A+B)的控制区ACE计算方法如式(2)所示,计算完合并控制区的ACE后,再进行ACE控制策略。In step 7), the sub-center AGC first judges the position of the insufficient control area for adjusting the reserve, preferentially selects the adjacent control area to adjust the maximum control area for the reserve, and then automatically adds a virtual merged control area. The overall adjustment reserve of the control area is two The control area adjusts the sum of spares. The ACE calculation method of the newly constructed combined control area (A+B) is shown in formula (2). After the ACE of the combined control area is calculated, the ACE control strategy is carried out.
以上仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above are only preferred embodiments of the present invention, and it should be pointed out that for those of ordinary skill in the art, some improvements and modifications can also be made without departing from the principles of the present invention, and these improvements and modifications should also be considered Be the protection scope of the present invention.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810502297.XA CN108808656B (en) | 2018-05-23 | 2018-05-23 | AGC control method for real-time sharing of regulation reserve in provincial control area of interconnected power grid |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810502297.XA CN108808656B (en) | 2018-05-23 | 2018-05-23 | AGC control method for real-time sharing of regulation reserve in provincial control area of interconnected power grid |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108808656A true CN108808656A (en) | 2018-11-13 |
CN108808656B CN108808656B (en) | 2021-05-07 |
Family
ID=64091485
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810502297.XA Active CN108808656B (en) | 2018-05-23 | 2018-05-23 | AGC control method for real-time sharing of regulation reserve in provincial control area of interconnected power grid |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108808656B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110061505A (en) * | 2019-04-23 | 2019-07-26 | 国电南瑞科技股份有限公司 | A kind of automatic support method of interregional active power of interconnected network |
CN111477046A (en) * | 2020-04-15 | 2020-07-31 | 国电南瑞科技股份有限公司 | Remote management system and method for electric power training system |
CN113131531A (en) * | 2019-12-31 | 2021-07-16 | 国电南瑞科技股份有限公司 | Adjustment standby sharing method and system suitable for different operation conditions of power grid |
CN118646102A (en) * | 2024-08-14 | 2024-09-13 | 中国天楹股份有限公司 | A method and system for controlling active power balance in a wind-solar-hydrogen-storage-ammonia-alcohol park |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070038335A1 (en) * | 2005-07-22 | 2007-02-15 | Mcintyre Timothy J | Real Power Regulation for the Utility Power Grid Via Responsive Loads |
US20090218819A1 (en) * | 2008-02-29 | 2009-09-03 | General Electric Company | Automatic generation control augmentation for wind plant integration |
CN102510063A (en) * | 2011-11-07 | 2012-06-20 | 国电南瑞科技股份有限公司 | Grading frequency regulation control method of interconnected power grid |
CN103795072A (en) * | 2014-02-10 | 2014-05-14 | 国家电网公司 | Responsibility-degree-index-considered extra-high voltage interconnection wire power control method |
CN105552948A (en) * | 2016-02-05 | 2016-05-04 | 国网浙江省电力公司湖州供电公司 | Power grid frequency-modulating method based on flexible direct-current transmission system |
CN106099997A (en) * | 2016-06-27 | 2016-11-09 | 国电南瑞科技股份有限公司 | Consider the interconnected network spare shared capacity allocation method of security constraint |
CN106160000A (en) * | 2016-08-02 | 2016-11-23 | 国电南瑞科技股份有限公司 | Adjust for a kind of point and save the wind-powered electricity generation additional issue control method adjusting two-stage to coordinate |
CN106712117A (en) * | 2017-01-03 | 2017-05-24 | 国电南瑞科技股份有限公司 | ACE sharing-based two-level hierarchical dispatching AGC coordinated control system and method for interconnected power network |
-
2018
- 2018-05-23 CN CN201810502297.XA patent/CN108808656B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070038335A1 (en) * | 2005-07-22 | 2007-02-15 | Mcintyre Timothy J | Real Power Regulation for the Utility Power Grid Via Responsive Loads |
US20090218819A1 (en) * | 2008-02-29 | 2009-09-03 | General Electric Company | Automatic generation control augmentation for wind plant integration |
CN102510063A (en) * | 2011-11-07 | 2012-06-20 | 国电南瑞科技股份有限公司 | Grading frequency regulation control method of interconnected power grid |
CN103795072A (en) * | 2014-02-10 | 2014-05-14 | 国家电网公司 | Responsibility-degree-index-considered extra-high voltage interconnection wire power control method |
CN105552948A (en) * | 2016-02-05 | 2016-05-04 | 国网浙江省电力公司湖州供电公司 | Power grid frequency-modulating method based on flexible direct-current transmission system |
CN106099997A (en) * | 2016-06-27 | 2016-11-09 | 国电南瑞科技股份有限公司 | Consider the interconnected network spare shared capacity allocation method of security constraint |
CN106160000A (en) * | 2016-08-02 | 2016-11-23 | 国电南瑞科技股份有限公司 | Adjust for a kind of point and save the wind-powered electricity generation additional issue control method adjusting two-stage to coordinate |
CN106712117A (en) * | 2017-01-03 | 2017-05-24 | 国电南瑞科技股份有限公司 | ACE sharing-based two-level hierarchical dispatching AGC coordinated control system and method for interconnected power network |
Non-Patent Citations (2)
Title |
---|
A. K. PAL ETAL: "AGC in two-area deregulated power system using reinforced learning neural network controller", 《2014 FIRST INTERNATIONAL CONFERENCE ON AUTOMATION, CONTROL, ENERGY AND SYSTEMS (ACES)》 * |
藤贤亮: "智能电网调度控制系统AGC需求分析及关键技术", 《电力系统自动化》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110061505A (en) * | 2019-04-23 | 2019-07-26 | 国电南瑞科技股份有限公司 | A kind of automatic support method of interregional active power of interconnected network |
CN110061505B (en) * | 2019-04-23 | 2022-08-26 | 国电南瑞科技股份有限公司 | Automatic active power supporting method between interconnected power grid regions |
CN113131531A (en) * | 2019-12-31 | 2021-07-16 | 国电南瑞科技股份有限公司 | Adjustment standby sharing method and system suitable for different operation conditions of power grid |
CN113131531B (en) * | 2019-12-31 | 2022-11-04 | 国电南瑞科技股份有限公司 | Method and system for regulating backup sharing suitable for different operating conditions of power grid |
CN111477046A (en) * | 2020-04-15 | 2020-07-31 | 国电南瑞科技股份有限公司 | Remote management system and method for electric power training system |
CN118646102A (en) * | 2024-08-14 | 2024-09-13 | 中国天楹股份有限公司 | A method and system for controlling active power balance in a wind-solar-hydrogen-storage-ammonia-alcohol park |
Also Published As
Publication number | Publication date |
---|---|
CN108808656B (en) | 2021-05-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112803446B (en) | Multi-energy optimal control method and control system based on client side demand response | |
CN108808656A (en) | The provincial control zone of interconnected network adjusts the AGC control methods of spare Real-Time Sharing | |
CN108092324B (en) | AGC control system and control method for wind power participating in peak shaving frequency modulation | |
CN112838603B (en) | Wind-solar energy storage and pumping multi-source energy AGC coordinated complementary control method and device | |
CN108390405A (en) | Consider the fast slow-action frequency resource coordination control method of energy-storage system SOC | |
CN107423879A (en) | A kind of method that controllable burden participates in Automatic Generation Control | |
CN106712117A (en) | ACE sharing-based two-level hierarchical dispatching AGC coordinated control system and method for interconnected power network | |
CN107968443B (en) | An AGC control method for wind-solar-fire bundling and DC delivery | |
CN106160000B (en) | The wind-powered electricity generation that a kind of point of tune-province's tune two-stage is coordinated issues additional control method | |
CN103956773B (en) | Backup configuration optimization method containing wind power system unit | |
CN103199538B (en) | Plan the generation schedule closed loop control method of multi-scale Retinex a few days ago | |
CN108964144A (en) | Power shortage optimizes methodology after a kind of failure of more direct current sending end power grids | |
CN114498773A (en) | A control method and device for adjustable load to participate in APC frequency regulation of main station | |
CN103066604B (en) | Stair automatic generation control method under factory network coordination mode | |
CN110707757B (en) | Multi-type energy hierarchical coordination control method based on new energy consumption | |
CN103187730B (en) | Advanced control method related to automatic generation control | |
CN110676887A (en) | Two-stage dispatching wind-fire coordination control method for sharing delivery section by regions | |
CN112949892B (en) | Regional power grid new energy power generation absorption decision method, system, equipment and medium | |
CN106887843A (en) | A kind of system reserve capacity decision-making technique for considering demand response | |
CN108377005B (en) | Active power real-time cooperative control method of multi-type power supply based on ACE interval | |
CN110021964A (en) | Network source load distributed coordination control method for stable switching of local isolated network | |
CN104218617A (en) | Consistency control method with flexible load participating in active advanced scheduling | |
CN104578175B (en) | An AGC control method for grid backup regulation | |
CN114884138A (en) | Energy storage power station and power grid active control method with controllable load participating in regulation | |
CN104578113B (en) | Unit control mode self-adapting switching method based on AGC |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |