CN108791335A CN201810623562.XA CN201810623562A CN108791335A CN 108791335 A CN108791335 A CN 108791335A CN 201810623562 A CN201810623562 A CN 201810623562A CN 108791335 A CN108791335 A CN 108791335A
Authority
CN
China
Prior art keywords
tunnel
bicycle shed
car body
inspection
diesel engine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810623562.XA
Other languages
Chinese (zh)
Inventor
陈强
任涛龙
赵力
吴超凡
贠泽
赵国栋
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Group Co Ltd
Baoji CRRC Times Engineering Machinery Co Ltd
Original Assignee
Baoji CSR Times Engineering Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoji CSR Times Engineering Machinery Co Ltd filed Critical Baoji CSR Times Engineering Machinery Co Ltd
Priority to CN201810623562.XA priority Critical patent/CN108791335A/en
Publication of CN108791335A publication Critical patent/CN108791335A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B61RAILWAYS
    • B61DBODY DETAILS OR KINDS OF RAILWAY VEHICLES
    • B61D15/00Other railway vehicles, e.g. scaffold cars; Adaptations of vehicles for use on railways
    • B61D15/08Railway inspection trolleys
    • B61D15/12Railway inspection trolleys power propelled
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for
    • B66F11/04Lifting devices specially adapted for particular uses not otherwise provided for for movable platforms or cabins, e.g. on vehicles, permitting workmen to place themselves in any desired position for carrying out required operations

Abstract

A kind of both-end manipulation railcar for realizing full section of tunnel inspection is provided, including car body, vehicle body upper portion front end is equipped with bicycle shed I, vehicle body upper portion rear end is equipped with bicycle shed II, it is equipped among vehicle body upper portion and between bicycle shed I and bicycle shed II for carrying out inspection of construction to tunnel vault, to tunnel wall disease at railway tunnel escape truck do not get off inspection and the same time in three different location height tunnel wall disease inspection comprehensive apparatus for work, comprehensive apparatus for work lower part is connect by levelling device with car body upper surface, sound-light alarm skate case is equipped with inside bicycle shed I and bicycle shed II.The present invention realize to tunnel vault carry out inspection of construction, to tunnel wall disease at railway tunnel escape truck do not get off check and within the same time three different location different heights tunnel wall disease inspection, can tunneling boring detection be carried out to tunnel very well, so that railway tunnel maintenance conditions is become tighter laborsaving, Tunnel testing ability and working efficiency can be effectively improved.

Description

Realize that the both-end of full section of tunnel inspection manipulates railcar
Technical field
The invention belongs to rail vehicle technical fields, and in particular to a kind of both-end manipulation track for realizing full section of tunnel inspection Vehicle.
Background technology
The problem of railway tunnel proportion in railway construction is more and more, tunnel pest and disease damage are consequently increased, China Existing tunnel surface Defect inspection mostly uses scaffold or Ordinary Work vehicle carries personnel and carries out visual, percussion inspection.Wherein, general The mating job platform of logical Operation Van causes the region of contact line or more that can not reach due to the height limitation by contact line, Such as contact net, carrier cable, bracket, return wire, high-voltage line area above etc., there are platforms " can not lifting " and operation blind area etc. Defect, job platform cannot achieve the inspection of not getting off of tunnel wall disease at escape truck, and it is low that there are operating efficiencies, blind area range The problems such as big, job platform can not achieve the detection of same time different location, can not achieve full section of tunnel detection, therefore have Necessity proposes to improve.
Invention content
Present invention solves the technical problem that:A kind of both-end manipulation railcar for realizing full section of tunnel inspection, this hair are provided It is bright realize to tunnel vault carry out inspection of construction, to tunnel wall disease at railway tunnel escape truck do not get off inspection and The tunnel wall disease inspection of three different location different heights in the same time can carry out tunneling boring detection to tunnel very well, make Railway tunnel maintenance conditions become more laborsaving, can effectively improve Tunnel testing ability and working efficiency.
The technical solution adopted by the present invention:Realize that the both-end of full section of tunnel inspection manipulates railcar, including car body, it is described Lower car body front end is equipped with power truck, and the lower car body rear end is equipped with non-powered bogie, among the lower car body Equipped with the dynamical system that its traveling is connect and driven with power truck, the vehicle body upper portion front end is equipped with bicycle shed I, the car body Upper rear end is equipped with bicycle shed II, is equipped between the vehicle body upper portion centre and bicycle shed I and bicycle shed II for being carried out to tunnel vault Inspection of construction, realize railway tunnel escape truck at tunnel wall disease do not get off inspection and the same time in three different locations The comprehensive apparatus for work of the tunnel wall disease inspection of height, the comprehensive apparatus for work lower part pass through levelling device and car body The automatic leveling of the apparatus for work under superelevation of outer rail operating mode is realized in upper surface connection, is equipped with inside the bicycle shed I and bicycle shed II Sound-light alarm skate case.
Wherein, the comprehensive apparatus for work includes the job platform and a rotary operation of two energy horizontal vertical liftings Platform, the lifting of job platform horizontal vertical apply tunnel vault around contact net, carrier cable, bracket, return wire, high-voltage line Work inspection, the rotation of rotary operation platform, pitching lifting, three platforms that the job platform and rotary operation platform combine are same Shi Zuoye can complete different location, different height the inspection of tunnel wall disease and realize at railway tunnel escape truck tunnel wall disease Harmful inspection of not getting off.
Further, the dynamical system includes the diesel engine and hydraulic transmission box being fixed in the middle part of car body lower face, institute It states diesel engine output end to connect with hydraulic transmission box input terminal, the axis that the hydraulic transmission box passes through transmission shaft and power truck Case connects, and the car body lower face of the diesel engine side is equipped with air system and aids in the heat dissipation system of diesel engine heat dissipation The car body lower face of system, the diesel engine other side is equipped with tool box and the exhaust system being connect with diesel engine and air inlet system System, the car body lower face middle part are equipped with the transfer case being connect with another output end of diesel engine, two power takings of the transfer case Hydraulic system and air compressor machine of the promising vehicle hydraulic driving part by power, the car body lower face middle part are separately connected on mouth It is additionally provided with the accumulator box that electric energy is provided for the diesel fuel tanks and hydraulic oil container of diesel engine and hydraulic system fuel feeding and for vehicle.
Further, I interior forward end of the bicycle shed is equipped with preceding driving position, and sleeping berth, alternating current are additionally provided with inside the bicycle shed I Device cabinet, three equipment cabinets, the top of the bicycle shed I are equipped with air conditioner indoor unit, the bicycle shed I and II top of bicycle shed be equipped with warning lamp and Searchlight, the bicycle shed II are internally provided with rear driving position and hand braking, and the car body halfpace is equipped with generating set, bicycle shed I air-conditioner outdoor unit I and the air-conditioner outdoor unit II of bicycle shed II, car body halfpace edge are equipped with railing.
Further, the car body both ends are equipped with input-output socket, train braking hose, multiple unit socket and hitch, Car body both ends lower part is equipped with pilot and compound horn.
The present invention compared with prior art the advantages of:
1, in this programme comprehensive apparatus for work include the lifting of two horizontal verticals job platform and a rotary operation Platform, three job platforms, which combine, can bypass contact net, carrier cable, bracket, return wire, high-voltage line etc., realize to tunnel vault Inspection of construction is carried out, does not get off to tunnel wall disease at railway tunnel escape truck and inspection and realizes in same time three not With the tunnel wall disease inspection of position different height, it can realize that full section of tunnel detects well, make railway tunnel maintenance conditions Become more laborsaving, Tunnel testing ability and working efficiency can be effectively improved;
2, sound-light alarm skate case is equipped in this programme in vehicle bicycle shed, skate is positioned over car convenient for management, if Operating personnel can be reminded by setting acoustic-optic alarm, meet safe driving demand;
3, this programme is equipped with drivers' cab in the bicycle shed at end face both ends on the car body, makes to form both-end drivers' cab on vehicle, Meet driver and conductor and manipulates visual field requirement;
4, this programme is soft in reserved input-output socket, the train braking being connect with other vehicle electricals, gas in vehicle both ends Pipe, multiple unit socket, can preferably adapt to construction of railways field condition.
Description of the drawings
Fig. 1 is the structural front view of the present invention;
Fig. 2 is the structure left view of the present invention;
Fig. 3 is the internal structure schematic diagram of the present invention;
Fig. 4 is the structure upward view of the present invention.
Specific implementation mode
1-4 describes the embodiment of the present invention below in conjunction with the accompanying drawings.
Realize that the both-end of full section of tunnel inspection manipulates railcar, including car body 3, as shown in figure 4,3 lower part of the car body Front end is equipped with power truck 15, and 3 lower part rear end of the car body is equipped with non-powered bogie 11, and the installation of the car body 3 is supported in On power truck 15 and non-powered bogie 11.It is equipped among 3 lower part of the car body and connect and drive with power truck 15 The dynamical system 31 of its traveling is moved, specifically, the dynamical system 31 includes the diesel engine 37 being fixed in the middle part of 3 lower face of car body With hydraulic transmission box 35,37 output end of the diesel engine is connect with 35 input terminal of hydraulic transmission box, and the hydraulic transmission box 35 is logical It crosses transmission shaft to connect with the axle box of power truck 15,3 lower face of car body of 37 side of the diesel engine is equipped with air system 33 and the cooling system 32 of the heat dissipation of diesel engine 37 is aided in, 3 lower face of car body of 37 other side of the diesel engine is equipped with work Tool case 36 and the exhaust system 34 and gas handling system 38 being connect with diesel engine 37,3 lower face of car body middle part is equipped with and bavin The transfer case 30 of 37 another output end of oil machine connection, is separately connected promising vehicle hydraulic on two power taking mouths of the transfer case 30 Driving part provides the hydraulic system 29 and air compressor machine 39 of power, is additionally provided with as 37 He of diesel engine in the middle part of 3 lower face of the car body The diesel fuel tanks and hydraulic oil container 28 of 29 fuel feeding of hydraulic system and the accumulator box 40 that electric energy is provided for vehicle.
3 top front end of the car body is equipped with bicycle shed I 2, and 3 upper rear end of the car body is equipped with bicycle shed II 8, such as the institutes of Fig. 1 and 3 Show, sound-light alarm skate case 18 is equipped with inside the bicycle shed I 2 and bicycle shed II 8, and skate is positioned over interior convenient for management, setting Acoustic-optic alarm can remind operating personnel, meet safe driving demand.I 2 interior forward end of the bicycle shed is equipped with preceding driving position 22, 20, three sleeping berth 21, ac electric apparatus cabinet equipment cabinets 23 are additionally provided with inside the bicycle shed I 2, I 2 top of the bicycle shed is equipped with air conditioning chamber Interior machine 4, the bicycle shed I 2 and II 8 top of bicycle shed are equipped with warning lamp 1 and searchlight 5, and the bicycle shed II 8 is internally provided with rear driving position 17 and hand braking 26.It is equipped with drivers' cab in the bicycle shed at 3 upper surface both ends of car body, makes to form both-end drivers' cab on vehicle, it is full Sufficient driver and conductor manipulates the visual field and requires.3 halfpace of the car body is equipped with the air-conditioner outdoor unit I of generating set 19, bicycle shed I 2 24 and bicycle shed II 8 air-conditioner outdoor unit II 25,3 halfpace edge of the car body be equipped with railing 6.
It is equipped on 3 top halfpace of the car body and between bicycle shed I 2 and bicycle shed II 8 for being applied to tunnel vault Work inspection, realize railway tunnel escape truck at tunnel wall disease do not get off inspection and the same time in three different location height The comprehensive apparatus for work 7 of the tunnel wall disease inspection of degree, as shown in Figure 1, the comprehensive apparatus for work 7 includes two levels The job platform 701 of vertical lift and a rotary operation platform 702,701 horizontal vertical of job platform lifting around contact net, Carrier cable, bracket, return wire, high-voltage line carry out inspection of construction to tunnel vault, and the rotation of rotary operation platform 702, pitching liter rise Three platforms that drop, the job platform 701 and rotary operation platform 702 combine operation simultaneously can complete different location, difference The tunnel wall disease inspection of height simultaneously realizes at railway tunnel escape truck that tunnel wall disease is not got off inspection, can realize well Full section of tunnel detects, and so that railway tunnel maintenance conditions is become tighter laborsaving, can effectively improve Tunnel testing ability and work effect Rate.7 lower part of comprehensive apparatus for work is connect by levelling device 12 with 3 upper surface of car body, is realized in superelevation of outer rail operating mode The automatic leveling of lower apparatus for work.
As shown in Fig. 2, 3 both ends of the car body are equipped with input-output socket 13, the train braking being connect with other vehicles Hose 14, multiple unit socket 16 and hitch 9 can preferably adapt to construction of railways field condition.3 both ends lower part of the car body is equipped with Pilot 10 and compound horn 27.
Above-described embodiment, only presently preferred embodiments of the present invention, is not used for limiting the scope of the present invention, therefore all with this The equivalence changes that content is done described in invention claim should all be included within scope of the invention as claimed.

Claims (5)

1. realizing that the both-end of full section of tunnel inspection manipulates railcar, including car body (3), car body (3) lower front part are equipped with Power truck (15), car body (3) the lower part rear end are equipped with non-powered bogie (11), are set among car body (3) lower part There are the dynamical system (31) for being connect with power truck (15) and driving its traveling, car body (3) the top front end to be equipped with bicycle shed I (2), car body (3) upper rear end is equipped with bicycle shed II (8), it is characterised in that:Car body (3) the top centre and bicycle shed I (2) It is equipped between bicycle shed II (8) for carrying out inspection of construction to tunnel vault, realizing tunnel wall disease at railway tunnel escape truck The comprehensive apparatus for work of the tunnel wall disease inspection of three different location height in harmful do not get off inspection and same time (7), it is super in outer rail to connect realization by levelling device (12) with car body (3) upper surface for comprehensive apparatus for work (7) lower part It is equipped with sound-light alarm skate case inside the automatic leveling of apparatus for work under high operating mode, the bicycle shed I (2) and bicycle shed II (8) (18)。
2. the both-end according to claim 1 for realizing full section of tunnel inspection manipulates railcar, it is characterised in that:It is described complete Orientation apparatus for work (7) includes the job platform (701) and a rotary operation platform (702) that two horizontal verticals lift, institute The lifting of job platform (701) horizontal vertical is stated to carry out tunnel vault around contact net, carrier cable, bracket, return wire, high-voltage line Inspection of construction, rotary operation platform (702) rotation, pitching lifting, three platforms of the comprehensive apparatus for work (7) are same Shi Zuoye can complete different location, different height the inspection of tunnel wall disease and realize at railway tunnel escape truck tunnel wall disease Harmful inspection of not getting off.
3. the both-end according to claim 1 for realizing full section of tunnel inspection manipulates railcar, it is characterised in that:It is described dynamic Force system (31) includes the diesel engine (37) and hydraulic transmission box (35) being fixed in the middle part of car body (3) lower face, the diesel engine (37) output end is connect with hydraulic transmission box (35) input terminal, and the hydraulic transmission box (35) passes through transmission shaft and power truck (15) car body (3) lower face of axle box connection, diesel engine (37) side is equipped with air system (33) and aids in Car body (3) lower face of the cooling system (32) of diesel engine (37) heat dissipation, diesel engine (37) other side is equipped with tool box (36) and with diesel engine (37) exhaust system (34) and gas handling system (38) connecting, car body (3) the lower face middle part are set There is the transfer case (30) being connect with diesel engine (37) another output end, is separately connected on two power taking mouths of the transfer case (30) Promising vehicle hydraulic driving part provides the hydraulic system (29) and air compressor machine (39) of power, car body (3) the lower face middle part It is additionally provided with as the diesel fuel tanks and hydraulic oil container (28) of diesel engine (37) and hydraulic system (29) fuel feeding and provides electric energy for vehicle Accumulator box (40).
4. the both-end according to claim 1,2 or 3 for realizing full section of tunnel inspection manipulates railcar, it is characterised in that: The bicycle shed I (2) interior forward end is equipped with preceding driving position (22), and sleeping berth (21), ac electric apparatus are additionally provided with inside the bicycle shed I (2) Cabinet (20), three equipment cabinets (23), the bicycle shed I (2) top are equipped with air conditioner indoor unit (4), the bicycle shed I (2) and bicycle shed II (8) top is equipped with warning lamp (1) and searchlight (5), and the bicycle shed II (8) is internally provided with rear driving position (17) and hand braking (26), car body (3) halfpace is equipped with generating set (19), the air-conditioner outdoor unit I (24) and bicycle shed II of bicycle shed I (2) (8) air-conditioner outdoor unit II (25), car body (3) the halfpace edge are equipped with railing (6).
5. the both-end according to claim 4 for realizing full section of tunnel inspection manipulates railcar, it is characterised in that:The vehicle Body (3) both ends are equipped with input-output socket (13), train braking hose (14), multiple unit socket (16) and hitch (9), the vehicle Body (3) both ends lower part is equipped with pilot (10) and compound horn (27).
CN201810623562.XA 2018-06-15 2018-06-15 Realize that the both-end of full section of tunnel inspection manipulates railcar Pending CN108791335A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810623562.XA CN108791335A (en) 2018-06-15 2018-06-15 Realize that the both-end of full section of tunnel inspection manipulates railcar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810623562.XA CN108791335A (en) 2018-06-15 2018-06-15 Realize that the both-end of full section of tunnel inspection manipulates railcar

Publications (1)

Publication Number Publication Date
CN108791335A true CN108791335A (en) 2018-11-13

Family

ID=64086564

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810623562.XA Pending CN108791335A (en) 2018-06-15 2018-06-15 Realize that the both-end of full section of tunnel inspection manipulates railcar

Country Status (1)

Country Link
CN (1) CN108791335A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109927610A (en) * 2019-03-26 2019-06-25 中国铁建重工集团有限公司 Existing Railway Line tunnel defect synthetic detection vehicle
CN110161043A (en) * 2019-05-10 2019-08-23 同济大学 A kind of subway tunnel structure synthetic detection vehicle

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102410030A (en) * 2011-11-14 2012-04-11 中铁一局集团有限公司 Multipurpose tunnel operating vehicle
CN103909943A (en) * 2014-03-31 2014-07-09 宝鸡南车时代工程机械有限公司 Railway tunnel internal section maintenance vehicle
CN104960532A (en) * 2015-06-15 2015-10-07 宝鸡南车时代工程机械有限公司 Tunnel detecting vehicle with three work platforms
CN107499320A (en) * 2017-09-20 2017-12-22 宝鸡中车时代工程机械有限公司 Tunnel based on hybrid power transmission checks railcar
CN107654245A (en) * 2017-10-27 2018-02-02 中铁西南科学研究院有限公司 A kind of operation tunnel Disease Treatment installs chassis and operation tunnel Disease Treatment steel arch-shelf mechanization installation method with steel arch-shelf
CN208325221U (en) * 2018-06-15 2019-01-04 宝鸡中车时代工程机械有限公司 Realize that the both-end of full section of tunnel inspection manipulates railcar

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102410030A (en) * 2011-11-14 2012-04-11 中铁一局集团有限公司 Multipurpose tunnel operating vehicle
CN103909943A (en) * 2014-03-31 2014-07-09 宝鸡南车时代工程机械有限公司 Railway tunnel internal section maintenance vehicle
CN104960532A (en) * 2015-06-15 2015-10-07 宝鸡南车时代工程机械有限公司 Tunnel detecting vehicle with three work platforms
CN107499320A (en) * 2017-09-20 2017-12-22 宝鸡中车时代工程机械有限公司 Tunnel based on hybrid power transmission checks railcar
CN107654245A (en) * 2017-10-27 2018-02-02 中铁西南科学研究院有限公司 A kind of operation tunnel Disease Treatment installs chassis and operation tunnel Disease Treatment steel arch-shelf mechanization installation method with steel arch-shelf
CN208325221U (en) * 2018-06-15 2019-01-04 宝鸡中车时代工程机械有限公司 Realize that the both-end of full section of tunnel inspection manipulates railcar

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109927610A (en) * 2019-03-26 2019-06-25 中国铁建重工集团有限公司 Existing Railway Line tunnel defect synthetic detection vehicle
CN110161043A (en) * 2019-05-10 2019-08-23 同济大学 A kind of subway tunnel structure synthetic detection vehicle
CN110161043B (en) * 2019-05-10 2021-03-26 同济大学 Subway tunnel structure comprehensive detection vehicle

Similar Documents

Publication Publication Date Title
CN209142124U (en) The contact net upkeep operation vehicle of internal combustion alternating current drive suitable for long steep grade
CN103213525A (en) Multi-working-face contact network work vehicle
CN107499320A (en) Tunnel based on hybrid power transmission checks railcar
CN106274921A (en) Hydraulic power contact net upkeep operation car
CN110406549A (en) A kind of hybrid power railcar drawn using diesel engine and power accumulator
CN108791335A (en) Realize that the both-end of full section of tunnel inspection manipulates railcar
CN108583597A (en) Tunnel defect based on mixing electric transmission detects vehicle
CN109720219A (en) The explosion-proof flexible transport vehicle of mining supercapacitor mixing accumulator power
CN208325221U (en) Realize that the both-end of full section of tunnel inspection manipulates railcar
CN111572572A (en) Subway overhead contact net overhauls operation car
CN109278770A (en) The contact net upkeep operation vehicle of internal combustion alternating current drive suitable for long steep grade
CN107284460A (en) Contact net based on hybrid power transmission integrates upkeep operation car
CN113371003A (en) Railway maintenance operation vehicle for hydrogen energy power contact network
CN206871066U (en) Contact net synthesis upkeep operation car based on hybrid power transmission
CN207225354U (en) Railway internal combustion electric transmission rescue operation vehicle
CN211947737U (en) Double dynamical source rail car of polishing
CN102849081A (en) Single-unit eight-axle electric transmission shunting diesel locomotive
CN112141141A (en) Multifunctional subway operation vehicle
CN211543518U (en) Hybrid power rail car pulled by diesel engine and power storage battery
CN107985099A (en) A kind of trolleybus
CN110203221A (en) Subway hydraulic power operation vehicle for contact wire
CN109278771B (en) Multi-platform contact net operation vehicle
CN207225358U (en) Tunnel based on hybrid power transmission checks railcar
CN105857324A (en) Official business rail car for narrow gauge railway
CN112301938A (en) Coal absorption vehicle set for railway tunnel sleeper outer track bed and operation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20221031

Address after: 721003 Bao Fu Road, Jintai District, Baoji, Shaanxi Province, No. 118

Applicant after: BAOJI CRRC TIMES ENGINEERING MACHINERY Co.,Ltd.

Applicant after: China National Railway Group Co.,Ltd.

Address before: 721003 No. 118 Baofu Road, Jintai District, Baoji City, Shaanxi Province