CN108790875B - Bus charging management device and method - Google Patents

Bus charging management device and method Download PDF

Info

Publication number
CN108790875B
CN108790875B CN201810571572.3A CN201810571572A CN108790875B CN 108790875 B CN108790875 B CN 108790875B CN 201810571572 A CN201810571572 A CN 201810571572A CN 108790875 B CN108790875 B CN 108790875B
Authority
CN
China
Prior art keywords
bus
charging
vehicle
transformer substation
battery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810571572.3A
Other languages
Chinese (zh)
Other versions
CN108790875A (en
Inventor
金建东
钟晓蓉
曹炬
洪大能
成跃辉
曹智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhongke Zhengfang Electronic Technology Co ltd
Original Assignee
Zhejiang Zhongke Zhengfang Electronic Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhongke Zhengfang Electronic Technology Co ltd filed Critical Zhejiang Zhongke Zhengfang Electronic Technology Co ltd
Priority to CN201810571572.3A priority Critical patent/CN108790875B/en
Publication of CN108790875A publication Critical patent/CN108790875A/en
Application granted granted Critical
Publication of CN108790875B publication Critical patent/CN108790875B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/60Electric or hybrid propulsion means for production processes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/60Other road transportation technologies with climate change mitigation effect
    • Y02T10/70Energy storage systems for electromobility, e.g. batteries
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/60Other road transportation technologies with climate change mitigation effect
    • Y02T10/7072Electromobility specific charging systems or methods for batteries, ultracapacitors, supercapacitors or double-layer capacitors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02T90/10Technologies relating to charging of electric vehicles
    • Y02T90/12Electric charging stations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02T90/10Technologies relating to charging of electric vehicles
    • Y02T90/14Plug-in electric vehicles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02T90/10Technologies relating to charging of electric vehicles
    • Y02T90/16Information or communication technologies improving the operation of electric vehicles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02T90/10Technologies relating to charging of electric vehicles
    • Y02T90/16Information or communication technologies improving the operation of electric vehicles
    • Y02T90/167Systems integrating technologies related to power network operation and communication or information technologies for supporting the interoperability of electric or hybrid vehicles, i.e. smartgrids as interface for battery charging of electric vehicles [EV] or hybrid vehicles [HEV]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S30/00Systems supporting specific end-user applications in the sector of transportation
    • Y04S30/10Systems supporting the interoperability of electric or hybrid vehicles
    • Y04S30/12Remote or cooperative charging

Abstract

The invention discloses a bus charging management device and a bus charging management method, which comprise a vehicle-mounted terminal, a battery management chip, a vehicle-mounted charger, a national standard gun charging interface and a pantograph which are arranged on a bus, a plurality of transformer substations arranged in each charging station area, transformer substation terminals and a wire network arranged in each transformer substation, and an enterprise platform server; the vehicle-mounted terminal comprises a vehicle-mounted processor, a CAN bus interface, a vehicle-mounted GPS/Beidou positioning module and a vehicle-mounted GPRS wireless communication module; the transformer substation terminal comprises a transformer substation processor, an RS232 interface, a transformer substation GPS/Beidou positioning module and a transformer substation GPRS wireless communication module. The invention has the characteristics of low cost, high charging efficiency and effectively prolonged service life of the battery.

Description

Bus charging management device and method
Technical Field
The invention relates to the technical field of bus charging, in particular to a bus charging management device and method with low cost and high charging efficiency.
Background
The prior art comprises a double-source trackless pure electric bus charging scheme, a charging pile gun charging type charging scheme and a charging pile charging bow type charging scheme; the double-source trackless charging scheme needs to lay a wire net on an operation line in the whole process, so that the urban attractiveness is affected, the wire net laying cost is high, and certain dangerousness exists; the charging pile gun charging type charging scheme can only realize one-to-one charging, and a plurality of charging piles are required to be erected in a centralized outage charging area of a bus at a bus station, so that the cost is high; according to the charging pile charging bow-type charging scheme, a wireless communication system is additionally arranged between a vehicle and the charging piles for charging communication, one-to-one charging can be realized, a plurality of charging piles are required to be erected in a centralized parking charging area of a bus at a bus station, and the cost is high; the existing schemes are not connected with a bus dispatching system, only a fixed charging mode can be used, intelligent charging cannot be realized, and the service life of a battery cannot be reduced;
disclosure of Invention
The invention aims to overcome the defects that the whole-course erection of a wire net is required in the prior art, and the cost is high; or the shortage of one-to-one gun charging, provides a bus charging management device and method with low cost and high charging efficiency.
In order to achieve the purpose, the invention adopts the following technical scheme:
a bus charging management device comprises a vehicle-mounted terminal, a battery management chip, a vehicle-mounted charger, a national standard gun charging interface and a pantograph, a plurality of transformer substations, transformer substation terminals, a wire network and an enterprise platform server, wherein the vehicle-mounted terminal, the battery management chip, the vehicle-mounted charger, the national standard gun charging interface and the pantograph are arranged on a bus; the vehicle-mounted terminal comprises a vehicle-mounted processor, a CAN bus interface, a vehicle-mounted GPS/Beidou positioning module and a vehicle-mounted GPRS wireless communication module; the transformer substation terminal comprises a transformer substation processor, an RS232 interface, a transformer substation GPS/Beidou positioning module and a transformer substation GPRS wireless communication module; the battery management chip, the on-vehicle machine that charges, the national standard rifle fills interface and pantograph and connects in proper order the electricity, on-vehicle treater is connected with CAN bus interface, on-vehicle GPS big dipper orientation module and on-vehicle GPRS wireless communication module electricity respectively, the transformer substation treater is connected with the RS232 interface respectively, transformer substation GPS big dipper orientation module and transformer substation GPRS wireless communication module electricity are connected, the RS232 interface is connected with the industrial control host computer electricity of transformer substation, CAN bus interface is connected with the CAN bus electricity of bus, transformer substation GPRS wireless communication module and on-vehicle GPRS wireless communication module all with enterprise platform server wireless connection.
The invention is suitable for the remote charging of pure electric urban buses, adopts a pantograph charging mode, a vehicle-mounted charger is installed on a vehicle, the vehicle is provided with a national javelin charging interface, a charging place is suitable for being built at a bus starting and ending station and a large transit station where the vehicles are intensively parked, and a transformer station can be erected at a bus station for the vehicle supporting the quick charging of batteries, so that the charging is supplemented in the gap between the parking and the passenger getting on and off; the invention has the advantages of the double-source trolley bus and the pure electric bus, and simultaneously has no defects of the double-source trolley bus that the wire net needs to be erected in the whole process and the pure electric city bus is charged one to one.
And a transformer substation and a wire network are arranged in the charging station area, and the transformer substation converts three-phase alternating current into direct current of about 800V and transmits the direct current to the wire network for charging vehicles. All vehicles entering the station can be simultaneously carried to a wire network through a pantograph to be charged, and the intelligent charging management is realized through a vehicle-mounted terminal installed on the vehicle, a substation terminal installed on a substation and an enterprise platform.
Preferably, the enterprise platform server comprises the following software modules: the system comprises a new energy automobile national standard data monitoring module, an intelligent charging management module, a vehicle data acquisition management module, a transformer substation data acquisition management module and a bus dispatching management module; the vehicle data acquisition management module is used for processing and storing vehicle data uploaded by the vehicle-mounted terminal and storing and managing basic information of the vehicle; and the transformer substation data acquisition management module is used for processing and storing the network data uploaded by the transformer substation terminal and storing and managing the basic information of the transformer substation.
The national standard data monitoring module of the new energy automobile is responsible for realizing the function of a data monitoring part which is forcibly required by the country; the vehicle data acquisition management module is responsible for processing and storing vehicle data uploaded by the vehicle-mounted terminal and storing and managing basic information of the vehicle; the transformer substation data acquisition management module is responsible for processing and storing the network data uploaded by the transformer substation terminal and storing and managing the basic information of the transformer substation; the bus dispatching management module is responsible for dispatching and managing all buses; the intelligent charging management module gives out an optimized charging control strategy according to the information of the vehicle, the information of the transformer substation and the scheduling information of the vehicle, and sends the optimized charging control strategy to the vehicle-mounted terminal to inform the vehicle of executing charging operation.
The intelligent charging management module ensures that the charging load does not exceed the rated load of the substation and also ensures the most effective and economic charging mode. According to the scheduling information, the intelligent charging management module gives the highest charging priority and the highest allowed charging power to the vehicle which is going to walk immediately, and gives the lower charging priority and the lower charging power to the vehicle which is not going to walk urgently, the service life of the battery can be shortened by fast charging, so that the service life of the battery can be prolonged by slow charging without fast charging; meanwhile, the energy conversion efficiency of the quick charge is low compared with that of the slow charge, and part of energy is consumed in the form of heat generated by the battery.
When the load of the wire network exceeds the rated load, the intelligent charging management system can suspend the charging of the vehicle with lower priority, so that the vehicle with higher priority is ensured to finish charging.
And when the load of the transformer substation is below the safety line, the charging of the vehicle with the charging suspension is resumed. Meanwhile, the intelligent charging management module can acquire the state information of the transformer substation through the transformer substation data acquisition management module to know whether the transformer substation runs healthily or not, if the transformer substation runs unhealthy, the highest allowable charging load of the transformer substation is reduced according to the fault level, and a manager is prompted, so that a transformer substation manufacturer can conveniently and timely carry out emergency repair.
A method of a bus charging management device comprises the following steps:
(3-1) initiating a charging request
After each bus enters a charging station, a driver drives a bus A to be charged to the lower part of a wire net, stops the bus, pulls a hand brake, and presses a pantograph lifting button of a charging pantograph; after the bow is lifted to the position, the vehicle-mounted terminal of the bus A sends a charging request and the position information of the bus to the enterprise platform server;
(3-2) vehicle pairing with charging station
After receiving the charging request signal, the enterprise platform server matches the position information of the bus A with each registered charging station area, determines which transformer substation the current vehicle charging request is directed to, and completes the pairing of the bus A and the charging station;
(3-3) the enterprise platform server generates a charging control strategy;
(3-4) issuing a charging control strategy and executing
The enterprise platform server issues the charging control strategy to a vehicle-mounted terminal of the bus A in a wireless communication mode, the vehicle-mounted terminal transmits the highest allowable charging power in the charging control strategy to a battery management chip through a CAN (controller area network) bus of the bus, and the battery management chip of the bus A controls a vehicle-mounted charger to charge a battery;
(3-5) completion of charging, unpairing
When the trickle charging current of the battery is less than 5A and lasts for 30 minutes, the battery management chip of the bus A firstly disconnects the contactor at the negative end of the pantograph and then informs the pantograph to execute pantograph lowering operation; meanwhile, the vehicle-mounted terminal of the bus A sends a charging completion signal to the enterprise platform server, the enterprise platform server withdraws the charging priority of the bus A, and the bus A and the transformer substation are unpaired.
Preferably, the step (3-3) comprises the following specific steps:
(4-1) calculating the SOC target value of the bus A by the enterprise platform server
The SOC target value = ((M S/100)/N) × 1.2, wherein M is the electricity consumption of hundred kilometers, N is the total electricity degree of the battery of the bus A when the SOC of the bus A is fully charged, S is the predicted driving mileage of the next bus A, and 1.2 represents that 20% of the surplus is reserved in the battery of the bus A;
(4-2) calling battery information of the bus A, and determining the highest charging power acceptable by the battery of the bus A; calling information of a transformer substation, and determining residual load information of the transformer substation;
(4-3) calculating the minimum charging power Pmin required by the bus A to reach the SOC target value by using the following minimum charging power calculation formula;
pmin = (((TSOC-CSOC)/100) × N)/t, TSOC is an SOC target value, CSOC is an SOC current value of the bus a, N is a total battery electricity degree number of the bus a, and t is a time length from the bus a to departure;
(4-4) if the Pmin is less than the available load of the transformer substation, generating the highest allowable power
(4-4-1) if the Pmin is less than the highest charging power acceptable by the battery of the bus A, issuing the Pmin as the highest allowable charging power in the charging control strategy of the bus A;
(4-4-2) if the Pmin is larger than or equal to the maximum charging power acceptable by the battery of the bus A, taking the maximum charging power acceptable by the battery of the bus A as the maximum allowable charging power in the charging control strategy of the bus A, and issuing the maximum allowable charging power.
Preferably, the method further comprises the following steps:
(5-1) for the buses which are charged, redistributing the charging priority of the charged buses in the charging station according to the departure time and whether the SOC target value is reached:
(5-1-1) calling all charging control strategies distributed by the current charging station, if the buses charged before do not reach the charging SOC target value, redistributing a unique priority value to each bus charged completely according to the sequence of departure time, wherein the priority value is located in the interval of [1, k ], k is a natural number greater than 10, and the smaller the number is, the higher the priority is;
(5-1-2) when the SOC of a certain bus B which is charged up reaches the SOC target value, the enterprise platform server reduces the charging priority of the bus B, so that the charging priority of the bus B is located in a [ k +1, 2k +2] interval;
(5-1-3) according to departure time, calculating the minimum charging power Pmin required by the departure by using a minimum charging power calculation formula, setting the Pmin as the highest allowable charging power, dynamically generating a new charging control strategy and issuing the new charging control strategy again.
When the transformer substation runs at full load, the vehicles with lower priorities need to be suspended for charging, and the vehicles with higher priorities are ensured to be charged; when the transformer substation is ensured to run under a non-full load, the vehicles with high priority can be ensured to be charged normally.
Preferably, the method further comprises the following steps:
the k is 49, the buses which do not reach the charging SOC target value are corresponding to the charging priorities from 1 to 49, and the buses are arranged according to the sequence of departure time, wherein the closer the departure time is, the smaller the charging priority number is;
when the SOC value reaches the SOC target value, the charging priority is regenerated and falls in the interval of 50-100, the charging priority enters the interval of 50-100 according to the time sequence of entering the interval, and the earlier the charging priority enters the interval of 50-100, the larger the value of the charging priority is. 1 of 1 to 100 has the highest priority, and 100 has the lowest priority.
Therefore, the invention has the following beneficial effects:
(1) only a charging net is laid at a charging station, a plurality of vehicles at the same charging station can be simultaneously meshed for charging without mutual interference, and the one-to-one charging limitation of pile charging is avoided;
(2) the cost of the implementation mode is low, and only extra transformer substation terminals are needed for hardware equipment;
(3) the enterprise platform server can remotely and automatically monitor the transformer substation and control the transformer substation not to run in an overload mode;
(4) the enterprise platform server can issue different charging control strategies to each vehicle, so that charging operation is not influenced, and the service life of the battery can be prolonged;
(5) by the method of allocating a charging priority to each vehicle, the vehicles with high priority are ensured to reach a charging target value firstly, and meanwhile, the vehicles with low priority are suspended firstly when the transformer substation is overloaded;
(6) the automatic charging can be realized, the intelligent distribution charging control strategy can be automatically given to each vehicle, the vehicle can be charged in a slow charging mode with the minimum battery loss while the vehicle operation is guaranteed, and the service life of the battery is effectively prolonged.
Drawings
FIG. 1 is a functional block diagram of the present invention;
fig. 2 is a flow chart of the present invention.
In the figure: the system comprises a vehicle-mounted terminal 1, a battery management chip 2, a vehicle-mounted charger 3, a national javelin charging interface 4, a pantograph 5, a transformer substation terminal 6, an enterprise platform server 7, a vehicle-mounted processor 11, a CAN bus interface 12, a vehicle-mounted GPS/Beidou positioning module 13, a vehicle-mounted GPRS wireless communication module 14, a transformer substation processor 61, an RS232 interface 62, a transformer substation GPS/Beidou positioning module 63, a transformer substation GPRS wireless communication module 64, an industrial control host 65 and a CAN bus 8.
Detailed Description
The invention is further described with reference to the following figures and detailed description.
The embodiment shown in fig. 1 is a bus charging management device, which includes a vehicle-mounted terminal 1, a battery management chip 2, a vehicle-mounted charger 3, a national javelin charging interface 4, a pantograph 5, 20 substations arranged in each charging station area, a substation terminal 6 and a wire network arranged in each substation, and an enterprise platform server 7, wherein the vehicle-mounted terminal 1, the battery management chip 2, the vehicle-mounted charger 3, the national javelin charging interface 4 and the pantograph 5 are arranged on a bus; the vehicle-mounted terminal comprises a vehicle-mounted processor 11, a CAN bus interface 12, a vehicle-mounted GPS/Beidou positioning module 13 and a vehicle-mounted GPRS wireless communication module 14; the transformer substation terminal comprises a transformer substation processor 61, an RS232 interface 62, a transformer substation GPS/Beidou positioning module 63 and a transformer substation GPRS wireless communication module 64; the battery management chip, on-vehicle machine that charges, the national standard rifle fills interface and pantograph and connects in proper order the electricity, on-vehicle treater is connected with CAN bus interface respectively, on-vehicle GPS big dipper orientation module and on-vehicle GPRS wireless communication module electricity are connected, the transformer substation treater is connected with the RS232 interface respectively, transformer substation GPS big dipper orientation module and transformer substation GPRS wireless communication module electricity are connected, the RS232 interface is connected with the industrial control host computer 65 electricity of transformer substation, CAN bus interface is connected with the CAN bus 8 electricity of bus, transformer substation GPRS wireless communication module and on-vehicle GPRS wireless communication module all with enterprise platform server wireless connection.
The enterprise platform server comprises the following software modules: the system comprises a new energy automobile national standard data monitoring module, an intelligent charging management module, a vehicle data acquisition management module, a transformer substation data acquisition management module and a bus dispatching management module; the vehicle data acquisition management module is used for processing and storing vehicle data uploaded by the vehicle-mounted terminal and storing and managing basic information of the vehicle; and the transformer substation data acquisition management module is used for processing and storing the network data uploaded by the transformer substation terminal and storing and managing the basic information of the transformer substation.
As shown in fig. 2, a method of a bus charging management device includes the following steps:
step 100, initiating a charging request
After each bus enters a charging station, a driver drives a bus A to be charged to the lower part of a wire net, stops the bus, pulls a hand brake, and presses a pantograph lifting button of a charging pantograph; after the bow is lifted to the position, the vehicle-mounted terminal of the bus A sends a charging request and the position information of the bus to the enterprise platform server;
step 200, vehicle pairing with charging station
After receiving the charging request signal, the enterprise platform server matches the position information of the bus A with each registered charging station area, determines which transformer substation the current vehicle charging request is directed to, and completes the pairing of the bus A and the charging station;
300, generating a charging control strategy by the enterprise platform server;
step 310, the enterprise platform server calculates the SOC target value of the bus A
The SOC target value = ((M S/100)/N) × 1.2, wherein M is the electricity consumption of hundred kilometers, N is the total electricity degree of the battery of the bus A when the SOC of the bus A is fully charged, S is the predicted driving mileage of the next bus A, and 1.2 represents that 20% of the surplus is reserved in the battery of the bus A;
step 320, calling battery information of the bus A, and determining the highest charging power acceptable by the battery of the bus A; calling information of a transformer substation, and determining residual load information of the transformer substation;
step 330, calculating the minimum charging power Pmin required by the bus A to reach the SOC target value by using the following minimum charging power calculation formula;
pmin = (((TSOC-CSOC)/100) × N)/t, TSOC is an SOC target value, CSOC is an SOC current value of the bus a, N is a total battery electricity degree number of the bus a, and t is a time length from the bus a to departure;
step 340, if the Pmin is less than the available load of the transformer substation, generating the highest allowable power
Step 341, if the Pmin is less than the highest charging power acceptable by the battery of the bus A, the Pmin is issued as the highest allowable charging power in the charging control strategy of the bus A;
and 342, if the Pmin is larger than or equal to the highest charging power acceptable by the battery of the bus A, the highest charging power acceptable by the battery of the bus A is taken as the highest allowable charging power in the charging control strategy of the bus A to be issued.
Step 400, issuing a charging control strategy and executing
The enterprise platform server issues the charging control strategy to a vehicle-mounted terminal of the bus A in a wireless communication mode, the vehicle-mounted terminal transmits the highest allowable charging power in the charging control strategy to a battery management chip through a CAN (controller area network) bus of the bus, and the battery management chip of the bus A controls a vehicle-mounted charger to charge a battery;
step 500, charging is completed and pairing is released
When the trickle charging current of the battery is less than 5A and lasts for 30 minutes, the battery management chip of the bus A firstly disconnects the contactor at the negative end of the pantograph and then informs the pantograph to execute pantograph lowering operation; meanwhile, the vehicle-mounted terminal of the bus A sends a charging completion signal to the enterprise platform server, the enterprise platform server withdraws the charging priority of the bus A, and the bus A and the transformer substation are unpaired.
In addition, for the buses which are charged, the charging priority of the charging buses in the charging station is redistributed according to the departure time and whether the SOC target value is reached:
calling all charging control strategies distributed by the current charging station, if the buses charged before do not reach the charging SOC target value, redistributing a unique priority value to each bus charged completely according to the sequence of departure time, wherein the priority value is located in the interval of [1,49], and the priority is higher when the number is smaller;
when the SOC of a certain bus B which is charged up reaches the SOC target value, the enterprise platform server reduces the charging priority of the bus B, so that the charging priority of the bus B is within the interval of [50, 100 ];
and according to departure time, calculating the minimum charging power Pmin required by the departure by using a minimum charging power calculation formula, setting the Pmin as the highest allowable charging power, dynamically generating a new charging control strategy and issuing the new charging control strategy again.
It should be understood that this example is for illustrative purposes only and is not intended to limit the scope of the present invention. Further, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teaching of the present invention, and such equivalents may fall within the scope of the present invention as defined in the appended claims.

Claims (4)

1. A method of a bus charging management device comprises a vehicle-mounted terminal (1), a battery management chip (2), a vehicle-mounted charger (3), a national javelin charging interface (4) and a pantograph (5) which are arranged on a bus, a plurality of substations arranged in each charging station area, a substation terminal (6) and a wire network which are arranged in each substation, and an enterprise platform server (7); the vehicle-mounted terminal comprises a vehicle-mounted processor (11), a CAN bus interface (12), a vehicle-mounted GPS/Beidou positioning module (13) and a vehicle-mounted GPRS wireless communication module (14); the transformer substation terminal comprises a transformer substation processor (61), an RS232 interface (62), a transformer substation GPS/Beidou positioning module (63) and a transformer substation GPRS wireless communication module (64); the battery management chip, the vehicle-mounted charger, the national standard gun charging interface and the pantograph are sequentially and electrically connected, the vehicle-mounted processor is respectively and electrically connected with the CAN bus interface, the vehicle-mounted GPS/Beidou positioning module and the vehicle-mounted GPRS wireless communication module, the substation processor is respectively and electrically connected with the RS232 interface, the substation GPS/Beidou positioning module and the substation GPRS wireless communication module, the RS232 interface is electrically connected with an industrial control host (65) of a substation, the CAN bus interface is electrically connected with a CAN bus (8) of a bus, and the substation GPRS wireless communication module and the vehicle-mounted GPRS wireless communication module are both in wireless connection with an enterprise platform server; the method is characterized by comprising the following steps:
(1-1) initiating a charging request:
after each bus enters a charging station, a driver drives a bus A to be charged to the lower part of a wire net, stops the bus, pulls a hand brake, and presses a pantograph lifting button of a charging pantograph; after the bow is lifted to the position, the vehicle-mounted terminal of the bus A sends a charging request and the position information of the bus to the enterprise platform server;
(1-2) vehicle pairing with charging station:
after receiving the charging request signal, the enterprise platform server matches the position information of the bus A with each registered charging station area, determines which transformer substation the current vehicle charging request is directed to, and completes the pairing of the bus A and the charging station;
(1-3) the enterprise platform server generates a charging control strategy:
(1-3-1) the enterprise platform server calculates the SOC target value of the bus A:
the SOC target value = ((M S/100)/N) × 1.2, wherein M is the electricity consumption of hundred kilometers, N is the total electricity degree of the battery of the bus A when the SOC of the bus A is fully charged, S is the predicted driving mileage of the next bus A, and 1.2 represents that 20% of the surplus is reserved in the battery of the bus A;
(1-3-2) calling battery information of the bus A, and determining the highest charging power acceptable by the battery of the bus A; calling information of a transformer substation, and determining residual load information of the transformer substation;
(1-3-3) calculating the minimum charging power Pmin required by the bus A to reach the SOC target value by using the following minimum charging power calculation formula;
pmin = (((TSOC-CSOC)/100) × N)/t, TSOC is an SOC target value, CSOC is an SOC current value of the bus a, N is a total battery electricity degree number of the bus a, and t is a time length from the bus a to departure;
(1-3-4) if the Pmin is less than the available load of the transformer substation, generating the highest allowable power:
(1-3-4-1) if the Pmin is less than the highest charging power acceptable by the battery of the bus A, issuing the Pmin as the highest allowable charging power in the charging control strategy of the bus A;
(1-3-4-2) if the Pmin is more than or equal to the highest charging power acceptable by the battery of the bus A, taking the highest charging power acceptable by the battery of the bus A as the highest allowable charging power in the charging control strategy of the bus A and issuing the highest allowable charging power;
(1-4) issuing a charging control strategy and executing:
the enterprise platform server issues the charging control strategy to a vehicle-mounted terminal of the bus A in a wireless communication mode, the vehicle-mounted terminal transmits the highest allowable charging power in the charging control strategy to a battery management chip through a CAN (controller area network) bus of the bus, and the battery management chip of the bus A controls a vehicle-mounted charger to charge a battery;
(1-5) charging is completed, and pairing is released:
when the trickle charging current of the battery is less than 5A and lasts for 30 minutes, the battery management chip of the bus A firstly disconnects the contactor at the negative end of the pantograph and then informs the pantograph to execute pantograph lowering operation; meanwhile, the vehicle-mounted terminal of the bus A sends a charging completion signal to the enterprise platform server, the enterprise platform server withdraws the charging priority of the bus A, and the bus A and the transformer substation are unpaired.
2. The method of the bus charging management device of claim 1, wherein the enterprise platform server comprises the following software modules: the system comprises a new energy automobile national standard data monitoring module, an intelligent charging management module, a vehicle data acquisition management module, a transformer substation data acquisition management module and a bus dispatching management module; the vehicle data acquisition management module is used for processing and storing vehicle data uploaded by the vehicle-mounted terminal and storing and managing basic information of the vehicle; and the transformer substation data acquisition management module is used for processing and storing the network data uploaded by the transformer substation terminal and storing and managing the basic information of the transformer substation.
3. The method of the bus charge management device of claim 1, further comprising the steps of:
(3-1) for the buses which are charged, redistributing the charging priorities of the charged buses in the charging stations according to the departure time and whether the SOC target value is reached:
(3-1-1) calling all charging control strategies distributed by the current charging station, if the buses charged before do not reach the charging SOC target value, redistributing a unique priority value to each bus charged completely according to the sequence of departure time, wherein the priority value is located in the interval of [1, k ], k is a natural number greater than 10, and the smaller the number is, the higher the priority is;
(3-1-2) when the SOC of a certain bus B which is charged up reaches the SOC target value, the enterprise platform server reduces the charging priority of the bus B, so that the charging priority of the bus B is located in a [ k +1, 2k +2] interval;
(3-1-3) according to departure time, calculating the minimum charging power Pmin required by the departure by using a minimum charging power calculation formula, setting the Pmin as the highest allowable charging power, dynamically generating a new charging control strategy and issuing the new charging control strategy again.
4. The method of the bus charge management device of claim 3, further comprising the steps of:
the k is 49, the buses which do not reach the charging SOC target value are corresponding to the charging priorities from 1 to 49, and the buses are arranged according to the sequence of departure time, wherein the closer the departure time is, the smaller the charging priority number is;
when the SOC value reaches the SOC target value, the charging priority is regenerated and falls in the interval of 50-100, the charging priority enters the interval of 50-100 according to the time sequence of entering the interval, and the earlier the charging priority enters the interval of 50-100, the larger the value of the charging priority is.
CN201810571572.3A 2018-06-05 2018-06-05 Bus charging management device and method Active CN108790875B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810571572.3A CN108790875B (en) 2018-06-05 2018-06-05 Bus charging management device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810571572.3A CN108790875B (en) 2018-06-05 2018-06-05 Bus charging management device and method

Publications (2)

Publication Number Publication Date
CN108790875A CN108790875A (en) 2018-11-13
CN108790875B true CN108790875B (en) 2020-07-03

Family

ID=64088787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810571572.3A Active CN108790875B (en) 2018-06-05 2018-06-05 Bus charging management device and method

Country Status (1)

Country Link
CN (1) CN108790875B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116485157B (en) * 2023-06-16 2023-08-22 四川国蓝中天环境科技集团有限公司 Electric bus charging plan optimization method considering charging station vehicle queuing

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5186395B2 (en) * 2009-01-15 2013-04-17 関西電力株式会社 Charging station and rechargeable vehicle
CN205160111U (en) * 2015-10-22 2016-04-13 中兴新能源汽车有限责任公司 Electric vehicle charging system
CN205818961U (en) * 2016-06-22 2016-12-21 北京阳光物网科技有限公司 A kind of public transit system for bus charging and electric bus
CN106025408B (en) * 2016-06-22 2019-07-19 高鸿新能源科技有限公司 A kind of bus charge control method and system
CN106427654B (en) * 2016-11-30 2018-11-23 郑州天迈科技股份有限公司 The pure charging electric car power dynamic allocation method of public transport new energy

Also Published As

Publication number Publication date
CN108790875A (en) 2018-11-13

Similar Documents

Publication Publication Date Title
KR101864197B1 (en) Electrical vehicle charging system and method for controlling thereof
KR101262166B1 (en) System for Electric Car Charging
US8054048B2 (en) Power grid load management for plug-in vehicles
JP5372987B2 (en) Power management system
CN108808760A (en) For under intelligent grid environment to the device and method of electric vehicle charging and electric discharge
CN106025408B (en) A kind of bus charge control method and system
CN105109357A (en) Intelligent charging system and method for electric vehicle
JP7264032B2 (en) Server and power management system
CN104158259A (en) Vehicle-mounted charging and discharging system and control method based on V2G technology
CN106427654A (en) Public transportation new energy pure trolley bus charging power dynamic allocation method
CN112744098B (en) Notification control device, mobile body, power system, and notification method
KR20140114330A (en) Electric battery charging installation and method
CN103441558A (en) Charge control method, electric car car-mounted terminal and charge control system
CN107851997A (en) Charge and discharge device and charge/discharge control method
CN110605986B (en) Off-grid mobile quick charging system and management method thereof
CN108847700A (en) A kind of charging applied to electric car shares power supply and its monitoring system with timesharing
CN109733249A (en) A kind of new-energy automobile charging system and its control method
CN112078687A (en) Charging vehicle and control method thereof
WO2013124841A1 (en) Charging management method and system
CN108891264B (en) Bus charging management system and method
CN108790875B (en) Bus charging management device and method
CN207868809U (en) A kind of vehicle-to-vehicle charging system of new energy vehicle
US11413981B2 (en) Electric power management device
CN108749613B (en) Bus remote charging management device and control method
CN108839575B (en) Bus remote charging management system and control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 321000 bailongqiao Linjiang Industrial Park, Wucheng District, Jinhua City, Zhejiang Province

Patentee after: ZHEJIANG ZHONGKE ZHENGFANG ELECTRONIC TECHNOLOGY Co.,Ltd.

Address before: 321000 no.589 Longtan Road, Wucheng District, Jinhua City, Zhejiang Province