CN108764751A - A kind of assembling line efficiency estimation method - Google Patents

A kind of assembling line efficiency estimation method Download PDF

Info

Publication number
CN108764751A
CN108764751A CN201810573679.1A CN201810573679A CN108764751A CN 108764751 A CN108764751 A CN 108764751A CN 201810573679 A CN201810573679 A CN 201810573679A CN 108764751 A CN108764751 A CN 108764751A
Authority
CN
China
Prior art keywords
assembling
line
assembly
efficiency
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810573679.1A
Other languages
Chinese (zh)
Inventor
夏阳
彭伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG YUTIAN TECHNOLOGY Co Ltd
Original Assignee
ZHEJIANG YUTIAN TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG YUTIAN TECHNOLOGY Co Ltd filed Critical ZHEJIANG YUTIAN TECHNOLOGY Co Ltd
Priority to CN201810573679.1A priority Critical patent/CN108764751A/en
Publication of CN108764751A publication Critical patent/CN108764751A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A90/00Technologies having an indirect contribution to adaptation to climate change
    • Y02A90/10Information and communication technologies [ICT] supporting adaptation to climate change, e.g. for weather forecasting or climate simulation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

The invention belongs to field of automobile, it is proposed that a kind of assembling line efficiency estimation method includes the following steps:Total carbon emissions, time loss based on assembling line and assembly productivity effect, establish the Effectiveness Evaluation Model of assembling line;The acquisition assessment parameter in assembling process;The assessment parameter is inputted into assessment models, obtains assembly line efficiency;Assembly line efficiency of assembling is analyzed, assessment result is obtained.The method of the present invention is from the energy, the benefit of the consumption of time and product, the input and output of assembly line are fully considered, finally obtain the assessment result of entire assembling process, can it is objective, accurately and in time to reflecting assembly line operation conditions, adjusted for inline process flow and the foundation of science be provided.

Description

A kind of assembling line efficiency estimation method
Technical field
The present invention relates to field of automobile, more specifically to a kind of assembling line efficiency estimation method.
Background technology
Since automobile occurs, automobile industry has been increasingly becoming the important angle for promoting entire society's progress and economic development Color, while also having driven each and automobile related industries pillar industry rapid development.But auto manufacturing is also the energy simultaneously Rich and influential family is consumed, a large amount of energy consumption can not only bring cost burden to enterprise, huge pressure can be also brought to environment, is not inconsistent Close environmentally protective manufacturing philosophy.The world today, national governments increasingly attaching importance to environmental protection problem and energy problem, advocates green system It makes, low-carbon manufacture.Under this trend trend, auto manufacturing also actively takes more energy saving, efficient production strategy tissue Production, it is desirable to while keeping productivity effect, energy consumption can be reduced as far as possible.
Currently, in automobile making production process, assembling line is used to carry out parts assembling in large quantities.Utilize dress Whether can reach low-carbon environment-friendly requirement with the process that assembly line is produced, need objective, accurate, the real-time method of one kind to whole A assembling process carries out measures of effectiveness, otherwise and current appraisal procedure is subjective judgement, assessment result shortage science, stabilization Property or be that evaluation system is not reasonable, can not really reflect the efficiency variation of assembling process, assessment result is inclined with practical situation Difference is larger, and strong decision basis can not be provided for subsequent process modification.
Invention content
In view of this, the purpose of the present invention is to provide a kind of assembling line efficiency estimation methods, by assembly line On parts assembling process carry out real-time data acquisition, science is carried out to the efficiency of assembly line assembling process, is accurately assessed, To provide basis for flow line production technique adjustment decision.
In order to achieve the above object, the present invention provides the following technical solutions:
A kind of assembling line efficiency estimation method, which is characterized in that include the following steps:
Total carbon emissions, time loss based on assembling line and assembly productivity effect, establish the effect of assembling line It can assessment models;
The acquisition assessment parameter in assembling process;
The assessment parameter is inputted into assessment models, obtains assembly line efficiency;
Assembly line efficiency of assembling is analyzed, assessment result is obtained.
Further, the step of Effectiveness Evaluation Model for establishing assembling line includes:
Establish the total carbon emissions model E of assembling line generationA, the total carbon emissions that the assembling line generates include dress The carbon emission that the carbon emission and transmission generated with process generates;
Establish the time loss model T on assembling linea, the time loss on the assembling line includes assembler Sequence time loss and transmission process time loss;
Establish assembly productivity effect Model Ba
According to the carbon emission model, time loss model and assembly productivity effect model, assembling line is established Effectiveness Evaluation Model obtains assembly line efficiency CB functions.
Further, the total carbon emissions CE that the assembling line generatesACalculation formula be:
In formula, n indicates that assembling process includes n assembly process;tiIndicate the assembly time of i-th of process;ρ indicates electric energy Carbon emission conversion coefficient;EiIndicate the unit of electrical energy consumption of the assembly equipment of i-th of process;CEtransiIndicate i-th of process mistake The carbon emission of transmission device is assembled in journey;LiIndicate the transmission range for being transferred to i-th of process;PiIndicate the part once transmitted Number.
Further, the total carbon emissions that the assembling process assembly line generates further include the carbon emission that manufacturing procedure generates and Process the carbon emission that transmission process generates.
Further, the total carbon emissions CE that the assembling line generatesACalculation formula be:
In formula, m indicates that process includes m manufacturing procedure;tjIndicate the process time of j-th of process;ρ indicates electric energy Carbon emission conversion coefficient;EjIndicate the unit of electrical energy consumption of the process equipment of j-th of process;CEtransjIndicate j-th of process mistake The carbon emission of transmission device in journey;LjIndicate the transmission range for being transferred to j-th of process;PjIndicate the parts count once transmitted.
Further, the time loss T on the assembling lineaCalculation formula is as follows:
Ta=Ttrans+Ty,
Wherein, TyIndicate the consumption of bottleneck activity time, Ty=max { T1, T2, T3..., Tr, r indicates work on assembling line The sum of sequence;TtransIndicate the transmission total time of each inter process.
Further, the Effectiveness Evaluation Model function CB of the assembling line is as follows:
Further, described to analyze assembly line efficiency of assembling, the method for obtaining assessment result is:It will obtain in real time Efficiency of assembling value CB and preset efficiency of assembling threshold value CBminIt is compared, works as CB-CBminWhen≤0, illustrate assembling line It needs to adjust;Work as CB-CBminWhen > 0, illustrate that assembling line need not adjust.
Further, described to analyze assembly line efficiency of assembling, the method for obtaining assessment result further includes:
For every equipment on assembly line, carbon emission constraints and time constraint condition are set;
The assessment parameter of every equipment on assembly line is inputted into assessment models, the carbon emission and time for obtaining every equipment disappear Consumption;
Whether the carbon emission and time loss for judging every equipment meet carbon emission constraints and time-constrain item Part;
Selection is unsatisfactory for carbon emission constraints and/or the equipment of time constraint condition, is adjusted correspondingly.
The present invention provides a kind of assembling line efficiency estimation methods, are disappeared based on the carbon emission in assembling process, time Consumption and the productivity effect of assembly establish assembling line Effectiveness Evaluation Model, and the flow line production data acquired in real time are inputted Assessment models finally obtain the measures of effectiveness knot of assembly line to obtain assembly line efficiency according to assembly line efficiency Fruit, judges whether existing technological process meets the requirement of green production, further which can also be derived according to assessment result Technological process or equipment need to adjust, to provide scientific basis for final decision.The method of the present invention disappears from the energy, time Consumption and the benefit of product are set out, and have been fully considered the input and output of assembly line, have finally been obtained the assessment knot of entire assembling process Fruit, the assessment result more have practice significance, can it is objective, accurately and in time to reflect assembly line operation conditions, be flowing water Wiring technology flow adjusts the foundation of offer science.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Obtain other attached drawings according to these attached drawings.
Fig. 1 is a kind of flow chart of assembling line efficiency estimation method of the present invention;
Fig. 2 is the flow chart of assembling line Effectiveness Evaluation Model method for building up of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, the present invention proposes that a kind of efficiency estimation method of assembling line, this method are based in assembling process Carbon emission, the productivity effect of time efficiency and product the efficiency of entire assembly line is assessed, policymaker can be according to commenting Estimate result to be adjusted the technological process of assembly line.Specifically include following steps:
The Effectiveness Evaluation Model of S10, assembling line are established.
As shown in Fig. 2, in order to carry out Analysis of Policy Making to assembly integrated artistic scheme, the dress of assembly product is considered With time, productivity effect and carbon emission amount, the overall efficiency assessment models of assembly line are established.
S11 establishes the carbon emission model of assembling process generation.The carbon emission of assembling process refers to each zero to be assembled Part is combined into generated carbon emission during final assembly.Assembling line generally all includes more than two assembling works Sequence, intermediate will be assembled by also needing between each assembling procedure is transferred to next work station by a upper work station.Therefore, it assembles The carbon emission of process includes the carbon emission of each assembly process and the carbon emission that transmission process generates.
The total carbon emissions CE of assembling processA(unit kgCO2Eq it) can be indicated by following formula (1):
Wherein, n indicates that assembling process includes n process;tiIndicate the assembly time of i-th of process;CEαiIt indicates i-th The unit carbon emission of process, unit kgCO2eq;CEβiIndicate that the carbon emission being transferred in i-th of process, unit are kgCO2eq。
The unit carbon emission CE α of i-th of processiFor the carbon emission that the energy consumption of the assembly equipment of i-th of process is converted into, by Following formula (2) indicates:
CEαi=ρ Ei (2)
Wherein, ρ indicates the carbon emission conversion coefficient of electric energy, generally takes 2.41kgCO2eq/kWh;EiIndicate i-th process The unit of electrical energy of assembly equipment consumes, unit kWh.
The carbon emission CE β being transferred in i-th of processiIt is obtained by formula (3):
Wherein, CEtransiIndicate the carbon emission of assembly transmission device in i-th of process;LiExpression is transferred to i-th The transmission range of process, unit m;PiIndicate the parts count once transmitted.Similarly, transmission is assembled in i-th of process The carbon emission CEtrans of equipmentiThe power consumption in transmission time can be first measured, power consumption is then converted into carbon emission again.
It is obtained by discussed above, the total carbon emissions CE of assembling processAFinally it is calculated by formula (4):
Further, the assembling line of some factories is other than with the process for assembling parts, and also some are to zero The process that component is processed.In order to carry out measures of effectiveness, assembly miscarriage line to assembling line whole process more fully hereinafter Carbon emission other than the carbon emission including assembling process, can also include each parts machining process to be assembled produced by Carbon emission.
Similarly, the carbon emission of process includes the carbon emission of each manufacturing procedure and the carbon emission that transmission process generates. So carbon emission CE ' (the unit kgCO of parts machining process2Eq it) can be obtained by following formula (5):
Wherein, m indicates that parts machining process includes m process;tjIndicate the process time of j-th of process;CEηjIt indicates The unit carbon emission of j-th of process, unit kgCO2eq;CEμjIndicate the carbon emission being transferred in j-th of process, unit For kgCO2eq。
The unit carbon emission CE η of j-th of processjIt can be converted and be calculated by power consumption:
CEηj=ρ Ej (6)
Wherein, ρ indicates that the carbon emission conversion coefficient of electric energy, the coefficient indicate that carbon dioxide caused by consumption kilowatt-hour is worked as The amount of the greenhouse gases of amount, according to the difference of power generation mode and power production process, there are certain fluctuations for the coefficient, real Can voluntarily it be arranged according to actual conditions in the production of border.In general, the carbon emission conversion coefficient of electric energy is about in China Power power grid For 0.96kgCO2eq/kWh;EjIndicate the unit of electrical energy consumption of the process equipment of j-th of process, unit kWh.
The carbon emission CE μ j during j-th of manufacturing procedure are transferred to obtain by formula (7):
Wherein, CEtransj indicates the carbon emission of transmission device during j-th of manufacturing procedure;Lj expressions are transferred to jth The transmission range of a process, unit m;PjIndicate the parts count once transmitted.Similarly, it is passed during j-th of manufacturing procedure The carbon emission CEtrans of transfer devicejThe power consumption in transmission time can be first measured, power consumption is then converted into carbon row again It puts.
In conclusion the carbon emission CE of parts machining process2Finally it is calculated by formula (8):
Therefore, when on assembling line there is also manufacturing procedure in the case of, the total carbon emissions CE of entire assembling lineA It can be indicated by formula (9):
S12 establishes assembling process time loss model.The assembly time of assembly refers to assembly from being initially assembled to At All Time.The length of assembly time depends primarily on equipment and the design of technological process, equipment in good condition and Rational technological design can reduce entire assembly time significantly.
Assembly total time includes the transmission time of parts built-up time and each inter process.Formula (10) table can be used Show:
Ta=Tz+Ttrans (10)
Wherein, TaIndicate assembly total time;TzIndicate the assembling total time of each process of parts;TtransIndicate each work Transmission total time between sequence.
Further, for the large automatic mode of production of pipeline system, can all there be a work in process of production Make the highest process of load, this process is process most slow in a production procedure, is to restrict whole flow line production efficiency The step of, this process can become bottleneck process.In order to simplify each process of parts assembling total time calculating, can be with The assembling total time of each process is replaced with the time of bottleneck process.The time T of bottleneck processyIt is obtained by formula (11):
Ty=max { T1,T2,T3,…,Tr, (11)
Wherein, r represents the sum of process on assembling line, when manufacturing procedure is not present on assembling line, r=n; When on assembling line there is also when manufacturing procedure, r=n+m.
So assembly can be indicated total time by formula (12):
Ta=Ttrans+Ty。 (12)
S13 establishes assembly productivity effect model.The benefit of final assembly is to evaluate the important side of assembly line efficiency Face, so the measures of effectiveness of assembling line be unable to do without assembly productivity effect factor.Assembly produces in the method for the present invention Benefit BaComputational methods be:The appearance price of assembly subtracts assembly cost.The method of the present invention in practical applications, is assembled Body productivity effect BaIt can be configured or adjust according to practical situation, assembly productivity effect BaCan it is expected to produce effect Benefit.
S14, the foundation of Effectiveness Evaluation Model.In method proposed by the present invention, assembling line efficiency is given birth to based on assembly Three production benefit, assembly time and carbon emission aspects are assessed.In actual production practice, the productivity effect of assembly is got over Height, then the efficiency of assembling line is higher, indicates that assembly profit is better;And assembly time is fewer, then the effect of assembling line Can be higher, indicate that the efficiency of assembly line is higher;The carbon emission generated in assembling process is fewer, then the efficiency of assembling line is got over Height indicates that the energy consumption of assembly line is fewer, more meets environmentally protective requirement.Therefore, measures of effectiveness function can be established accordingly, obtained To assembly line efficiency CB, as shown in formula (13):
S20 acquires the assessment parameter in assembling process.According to aforementioned measures of effectiveness function, need to adopt in assembling process Collect the unit interval power consumption of equipment in each assembly process, the transmission that each process corresponds between the time of consumption, each process is set Transmission time between standby power consumption, each process.Wherein, power consumption can be surveyed by electric power detection device, can also It is calculated according to the output power of equipment or other known means measures, this will not be repeated here.Various take can be Corresponding sensor is installed to measure on assembly line.And transmission range LiThe parts count P once transmittediComparatively compare Relatively stablize, can be configured according to actual conditions, when readjusting the technological process of production, then be updated.
Similarly, when on assembling line there is also manufacturing procedure in the case of, it is also necessary to the further each processing work of acquisition The unit interval power consumption of equipment in sequence, each process correspond to the power consumption, each of the transmission device between the time of consumption, each process The transmission time of inter process.Correspondingly, transmission range LjThe parts count P once transmittedjComparatively more stable, it can be with It is configured according to actual conditions, is updated again when readjusting the technological process of production.
The assessment parameter acquired during assembly line is inputted the Effectiveness Evaluation Model by S30, obtains assessment knot Fruit.
In actual production, assembly line efficiency threshold CB can be setmin, the efficiency of assembling value CB that obtains in real time with Threshold value CBminIt is compared, works as CB-CBminWhen≤0, illustrates that current technological process can no longer meet production and operation demand, answer This makes corresponding adjustment as early as possible;Work as CB-CBminWhen > 0, illustrate that inline process is good, it can be with meet demand.
It is possible to further which carbon emission constraints and assembly time constraints is arranged, work as CB-CBminWhen≤0, to sentence It is disconnected that whether carbon emission and/or assembly time have exceeded preset range.
Shown in carbon emission constraints such as formula (14):
CEA-CEmax≤0 (14)
Wherein, CEmaxIndicate preset maximum acceptable carbon emission.
When the carbon emission of assembling process is unsatisfactory for constraints, illustrate that the energy consumption of equipment cannot be satisfied needs.May be There is the failure that can not be discovered in equipment or equipment aging occurs and energy consumption is increased, and needs correspondingly to carry out trouble shooting Or more new equipment.
Shown in assembly time constraints such as formula (15):
Ta-Tmax≤0 (15)
Wherein, TmaxIndicate preset maximum acceptable assembly time.
When being unsatisfactory for constraints between when assembling, in the case of no failure, it may illustrate the transport Stream of parts Journey needs to be optimized, or needs to update transmission device, to improve efficiency of transmission.
Further, can also corresponding carbon row further be set for each equipment in process on the basis of the above It puts and assembly time constraints.In this way, working as CB-CBminWhen≤0, carbon emission and the assembly of every equipment can be further analyzed Whether the time cannot be satisfied constraints, to more accurately find out the reason of assembly line efficiency declines, carry out more It targetedly adjusts, dispose.It is as follows:
For every equipment on assembly line, carbon emission constraints and time constraint condition are set;
The assessment parameter of every equipment on assembly line is inputted into assessment models, the carbon emission and time for obtaining every equipment disappear Consumption;
Judge whether the carbon emission of every equipment and time loss meet corresponding carbon emission constraints and time Constraints;
Selection is unsatisfactory for carbon emission constraints and/or the equipment of time constraint condition, is adjusted correspondingly, including inspection Repair equipment or update parts etc..
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest range caused.

Claims (9)

1. a kind of assembling line efficiency estimation method, which is characterized in that include the following steps:
Total carbon emissions, time loss based on assembling line and assembly productivity effect, the efficiency for establishing assembling line are commented Estimate model;
The acquisition assessment parameter in assembling process;
The assessment parameter is inputted into assessment models, obtains assembly line efficiency;
Assembly line efficiency of assembling is analyzed, assessment result is obtained.
2. assembling line efficiency estimation method according to claim 1, which is characterized in that described to establish assembling line Effectiveness Evaluation Model the step of include:
Establish the total carbon emissions model E of assembling line generationA, the total carbon emissions that the assembling line generates include assembler The carbon emission that the carbon emission and transmission that sequence generates generate;
Establish the time loss model T on assembling linea, when the time loss on the assembling line includes assembly process Between consumption and transmission process time loss;
Establish assembly productivity effect Model Ba
According to the carbon emission model, time loss model and assembly productivity effect model, the efficiency of assembling line is established Assessment models obtain assembly line efficiency CB functions.
3. the efficiency estimation method of assembling line according to claim 2, which is characterized in that the assembling line production Raw total carbon emissions CEACalculation formula be:
In formula, n indicates that assembling process includes n assembly process;tiIndicate the assembly time of i-th of process;ρ indicates the carbon of electric energy Discharge conversion coefficient;EiIndicate the unit of electrical energy consumption of the assembly equipment of i-th of process;CEtransiIt indicates in i-th of process Assemble the carbon emission of transmission device;LiIndicate the transmission range for being transferred to i-th of process;PiIndicate the parts count once transmitted.
4. the efficiency estimation method of assembling line according to claim 3, which is characterized in that the assembling process flowing water The total carbon emissions that line generates further include the carbon emission that the carbon emission that manufacturing procedure generates and processing transmission process generate.
5. the efficiency estimation method of assembling line according to claim 4, which is characterized in that the assembling line production Raw total carbon emissions CEACalculation formula be:
In formula, m indicates that process includes m manufacturing procedure;tjIndicate the process time of j-th of process;ρ indicates the carbon of electric energy Discharge conversion coefficient;EjIndicate the unit of electrical energy consumption of the process equipment of j-th of process;CEtransjIt indicates in j-th of process The carbon emission of transmission device;LjIndicate the transmission range for being transferred to j-th of process;PjIndicate the parts count once transmitted.
6. according to the efficiency estimation method of claim 3~5 any one of them assembling line, which is characterized in that the dress With the time loss T on assembly lineaCalculation formula is as follows:
Ta=Ttrans+Ty,
Wherein, TyIndicate the consumption of bottleneck activity time, Ty=max { T1,T2,T3,…,Tr, r indicates process on assembling line Sum;TtransIndicate the transmission total time of each inter process.
7. the efficiency estimation method of assembling line according to claim 6, which is characterized in that the assembling line Effectiveness Evaluation Model efficiency of assembling function CB is as follows:
8. the efficiency estimation method of assembling line according to claim 7, which is characterized in that described to assembly line Efficiency is analyzed, and the method for obtaining assessment result is:By the efficiency of assembling value CB obtained in real time and preset efficiency of assembling threshold Value CBminIt is compared, works as CB-CBminWhen≤0, illustrate that assembling line needs to adjust;Work as CB-CBminWhen > 0, illustrate to assemble Assembly line need not adjust.
9. the efficiency estimation method of assembling line according to claim 8, which is characterized in that described to assembly line Efficiency is analyzed, and the method for obtaining assessment result further includes:
For every equipment on assembly line, carbon emission constraints and time constraint condition are set;
The assessment parameter of every equipment on assembly line is inputted into assessment models, obtains the carbon emission and time loss of every equipment;
Whether the carbon emission and time loss for judging every equipment meet carbon emission constraints and time constraint condition;
Selection is unsatisfactory for carbon emission constraints and/or the equipment of time constraint condition, is adjusted correspondingly.
CN201810573679.1A 2018-06-06 2018-06-06 A kind of assembling line efficiency estimation method Pending CN108764751A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810573679.1A CN108764751A (en) 2018-06-06 2018-06-06 A kind of assembling line efficiency estimation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810573679.1A CN108764751A (en) 2018-06-06 2018-06-06 A kind of assembling line efficiency estimation method

Publications (1)

Publication Number Publication Date
CN108764751A true CN108764751A (en) 2018-11-06

Family

ID=63999039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810573679.1A Pending CN108764751A (en) 2018-06-06 2018-06-06 A kind of assembling line efficiency estimation method

Country Status (1)

Country Link
CN (1) CN108764751A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110909995A (en) * 2019-11-13 2020-03-24 张家口卷烟厂有限责任公司 Method and device for analyzing production efficiency
CN114444980A (en) * 2022-04-07 2022-05-06 南昌菱形信息技术有限公司 Control method and device for intelligent factory production equipment based on 5G technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140200696A1 (en) * 2013-01-11 2014-07-17 J&L Group International, Llc Process flow optimization in manufacturing
CN105260836A (en) * 2015-10-13 2016-01-20 天津大学 Automobile manufacture enterprise carbon emission acquisition checking system and method
CN105654240A (en) * 2015-12-30 2016-06-08 江南大学 Machine tool manufacturing system energy efficiency analysis method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20140200696A1 (en) * 2013-01-11 2014-07-17 J&L Group International, Llc Process flow optimization in manufacturing
CN105260836A (en) * 2015-10-13 2016-01-20 天津大学 Automobile manufacture enterprise carbon emission acquisition checking system and method
CN105654240A (en) * 2015-12-30 2016-06-08 江南大学 Machine tool manufacturing system energy efficiency analysis method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
周亚兰 等: "汽车生产过程中能源消耗的碳排放计算与分析", 《巢湖学院学报》 *
张春庭 等: "离散制造能效评估方法的研究", 《新型工业化》 *
张铁山 等: "汽车制造企业生产过程碳排放核算与策略", 《企业经济》 *
程海琴: "基于碳效益的机械产品多工艺低碳制造决策模型及应用", 《中国优秀硕士学位论文全文数据库 工程科技II辑(月刊)》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110909995A (en) * 2019-11-13 2020-03-24 张家口卷烟厂有限责任公司 Method and device for analyzing production efficiency
CN114444980A (en) * 2022-04-07 2022-05-06 南昌菱形信息技术有限公司 Control method and device for intelligent factory production equipment based on 5G technology
CN114444980B (en) * 2022-04-07 2022-07-29 南昌菱形信息技术有限公司 Control method and device for intelligent factory production equipment based on 5G technology

Similar Documents

Publication Publication Date Title
CN111291963B (en) Park comprehensive energy system planning method for coordinating economy and reliability
CN106651722B (en) Industrial carbon emission accounting method
CN102074954B (en) Comprehensive energy-conservation evaluation and decision-making method for urban and rural distribution network
CN103955777B (en) Photovoltaic generation accesses power distribution network conceptual design and analysis and evaluation accessory system
CN109828539B (en) Big data heat supply energy management and control platform system based on PDCA system
CN109283898A (en) A kind of plant area's energy consumption monitoring management system
CN109830955B (en) Electric-gas distribution network flexible planning method considering flexible constraint and full-period cost
CN104283222B (en) A kind of area power grid reactive voltage control system
CN108197805A (en) A kind of electric energy and natural gas competitiveness integrated evaluating method that planning guidance is substituted available for electric energy
KR101809205B1 (en) Factory Energy Management System
CN111738498A (en) Comprehensive energy system robust planning method and system
CN108764751A (en) A kind of assembling line efficiency estimation method
CN107918368A (en) The dynamic prediction method and equipment of iron and steel enterprise's coal gas yield and consumption
CN115392547A (en) Virtual power plant energy comprehensive control platform based on data analysis
CN116128688A (en) Marketing evaluation method oriented to energy efficiency industry
CN102592004B (en) System and method for on-line analysis and diagnosis of whole-process energy-consuming conditions of integrated iron and steel works
CN113154517B (en) Production operation scheduling control system for centralized heating autonomous driving
CN117540972A (en) Method for adjusting electric energy supply and demand fluctuation and improving electric energy consumption ratio in chemical industry
CN111509715A (en) Power distribution network technical transformation method and system considering key indexes to improve operation effect
CN115049004B (en) Power distribution network line loss management aid decision-making system based on multi-source data fusion
CN105335824A (en) Power distribution network fault first-aid repair commanding method and system based on data center
CN112365087B (en) Method for predicting annual uninterrupted operation demand
CN101834438A (en) Distribution network state and operation mode optimization method based on DSCADA system
CN109471381A (en) Energy efficiency of equipment integrated control method based on big data fusion
CN116484149A (en) Quantitative evaluation method for distribution network power outage overhaul plan

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181106