CN108764335A - A kind of integrated energy system multi-energy requirement typical scene generation method and device - Google Patents

A kind of integrated energy system multi-energy requirement typical scene generation method and device Download PDF

Info

Publication number
CN108764335A
CN108764335A CN201810524561.XA CN201810524561A CN108764335A CN 108764335 A CN108764335 A CN 108764335A CN 201810524561 A CN201810524561 A CN 201810524561A CN 108764335 A CN108764335 A CN 108764335A
Authority
CN
China
Prior art keywords
cluster
vector
energy requirement
typical scene
cluster centre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810524561.XA
Other languages
Chinese (zh)
Inventor
马溪原
郭晓斌
胡洋
周长城
雷金勇
于海洋
喻磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSG Electric Power Research Institute
Research Institute of Southern Power Grid Co Ltd
Original Assignee
Research Institute of Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Research Institute of Southern Power Grid Co Ltd filed Critical Research Institute of Southern Power Grid Co Ltd
Priority to CN201810524561.XA priority Critical patent/CN108764335A/en
Publication of CN108764335A publication Critical patent/CN108764335A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F18/00Pattern recognition
    • G06F18/20Analysing
    • G06F18/23Clustering techniques
    • G06F18/232Non-hierarchical techniques
    • G06F18/2321Non-hierarchical techniques using statistics or function optimisation, e.g. modelling of probability density functions
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

The invention discloses a kind of integrated energy system multi-energy requirement typical scene generation methods and device, this method to include:S1:The multi-energy requirement load vector for getting each day, obtains vectorial set;S2:If obtaining iterative instruction, S3 is executed, if obtaining assessment instruction, executes S4;S3:In each iteration, the cluster centre of corresponding number is determined in vector is gathered, until judging that the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is less than preset value, it is determined that when all cluster centres of previous iteration are typical scene;S4:Obtain the value range of cluster centre number, in value range, the cluster centre of corresponding number is determined in vector is gathered according to each value, and calculate the corresponding cluster evaluation index of each value, determine that the corresponding all cluster centres of minimum cluster evaluation index are typical scene.The typical scene that method through the invention generates, can comprehensively, accurately analyze integrated energy system.

Description

A kind of integrated energy system multi-energy requirement typical scene generation method and device
Technical field
The present invention relates to integrated energy system fields more particularly to a kind of integrated energy system multi-energy requirement typical scene to give birth to At method and device.
Background technology
Integrated energy system is related to production, transfer and the consumption of the various energy resources such as electric, hot, cold, gas.In integrated energy system Planning stage and operation mode design phase etc. are required to carry out it a large amount of Simulation Analysis, can portray comprehensive energy The typical scene of system multi-energy requirement is these Simulation Analysis necessity input datas.
However, if all analyzed annual load data, computation burden can be significantly greatly increased and without generally representing Property.More scene analysis technologies reduce the similar scene in corresponding time scale by data analysis, have efficiently extracted several Typical day scene, convergence effect is preferable, avoids cumbersome calculating, alleviates the burden of system-computed analysis.
It is more mature to the method for the scenario building of power load at present, mainly by " rich big, rich small, withered big, withered It is small " or the input of the extreme scenes as simulation model such as " summer is big, the summer is small, the winter is big, winter small ", it is negative in difference to analyze electric system Problems faced under lotus scene, but this mode consider a problem it is overly conservative, for pursue economic benefit based on synthesis energy Source system is more suitable in terms of system run all right and reliability only in the case where analyzing extreme event, but is simulated to long-term operation With economic analysis and be not suitable for, it is difficult to obtain the solution of closing to reality on probability.
Invention content
An embodiment of the present invention provides a kind of integrated energy system multi-energy requirement typical scene generation method and devices, can Generate the typical scene for carrying out comprehensive reliable analysis to integrated energy system.
According to an aspect of the present invention, a kind of integrated energy system multi-energy requirement typical scene generation method is provided, is wrapped It includes:
S1:The multi-energy requirement load vector for getting each day, obtains vectorial set;
S2:If obtaining iterative instruction, S3 is executed, if obtaining assessment instruction, executes S4;
S3:In each iteration, the cluster centre of corresponding number is determined in the vector set, until judging current The difference of the cluster square-error of the cluster square-error of secondary iteration and last iteration is less than preset value, it is determined that works as previous iteration All cluster centres be typical scene;
S4:The value range for obtaining cluster centre number, in the value range, according to each value in the vector The cluster centre of corresponding number is determined in set, and calculates the corresponding cluster evaluation index of each value, determines that minimum cluster is commented It is typical scene to estimate the corresponding all cluster centres of index.
Preferably, the multi-energy requirement load vector is born by the gas turbine heating load of each period, user's electricity in one day Lotus and garden are formed with cold demand.
It is preferably, described that the cluster centre of corresponding number is determined in all vector set in each iteration, Until judging that the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is less than preset value, then really All cluster centres of settled previous iteration specifically include for typical scene:
S31:Iterations N=1 is initialized, the cluster centre of corresponding number is determined in the vector set, and to poly- Class center is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
S32:Iterations N=N+1 is enabled, the cluster centre of corresponding number is determined in the vector set, and to cluster Center is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
S33:Judge whether the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is small In preset value, if being not less than, S32 is re-executed, if being less than, executes S34;
S34:Determine that all cluster centres when previous iteration are typical scene.
Preferably, the calculation formula of the cluster square-error is:
In formula, K is the corresponding cluster centre number of iteration each time, njFor the multi-energy requirement load vector number of jth class, mjFor the cluster centre that the cluster centre to jth class is updated, xiFor i-th of multi-energy requirement load vector of jth class.
Preferably, described to determine that the cluster centre of corresponding number specifically includes in the vector set:
T0:I=1 is enabled, and obtains constant M and cluster centre number K;
T1:In the vector set, the distance between vector two-by-two is calculated;
T2:It determines all distances with i-th of multi-energy requirement load vector correlation, and by being ranked up from small to large, takes Density parameter of the m-th distance as i-th of multi-energy requirement load vector;
T3:I=i+1 is enabled, step T2 is re-executed, until determining the density parameter of all multi-energy requirement load vectors;
T4:All multi-energy requirement load vectors are ranked up from small to large by density parameter, by row in institute's directed quantity Sequence takes the vector of preset proportion, obtains high density vector set;
T5:The multi-energy requirement load vector of density parameter minimum is determined as first cluster centre;
T6:In the high density vector set, calculate between each vector and each fixed cluster centre away from From, minimum range corresponding with fixed each cluster centre is taken, is maximized in all minimum ranges, it will be maximum It is worth corresponding multi-energy requirement load vector to increase as new cluster centre;
T7:Judge whether the number of cluster centre equal to K re-executes T6 if being not equal to, if being equal to, terminates.
Preferably, the distance is Euclidean distance.
Preferably, the calculation formula of the cluster evaluation index is:
dij=| | zi-zj||
In formula, SiIndicate degree of scatter vectorial in ith cluster, SjIndicate the degree of scatter of vector in j-th of cluster, dijIndicate that the distance between ith cluster and j-th of cluster, K values are cluster number, CiFor ith cluster, niIt is poly- for i-th The vectorial number of class.
According to another aspect of the present invention, a kind of integrated energy system multi-energy requirement typical scene generating means are provided, are wrapped It includes:
First acquisition module, the multi-energy requirement load vector for getting each day, obtains vectorial set;
If second acquisition module triggers the first determining module for obtaining iterative instruction, if obtaining assessment instruction, Trigger the second determining module;
First determining module, in each iteration, being determined in the vector set in the cluster of corresponding number The heart, until judge that the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is less than preset value, Then determine that all cluster centres when previous iteration are typical scene;
Second determining module, the value range for obtaining cluster centre number, in the value range, according to each Value determines the cluster centre of corresponding number in the vector set, and calculates the corresponding cluster evaluation index of each value, Determine that the corresponding all cluster centres of minimum cluster evaluation index are typical scene.
According to another aspect of the present invention, a kind of integrated energy system multi-energy requirement typical scene generating means are provided, are wrapped It includes:Memory, and it is coupled to the processor of the memory;
The processor is configured as, based on the instruction being stored in the memory devices, executing as described above comprehensive Close energy resource system multi-energy requirement typical scene generation method.
According to another aspect of the present invention, a kind of computer-readable medium is provided, computer program is stored thereon with, the journey Above-described integrated energy system multi-energy requirement typical scene generation method is realized when sequence is executed by processor.
As can be seen from the above technical solutions, the embodiment of the present invention has the following advantages:
The present invention provides a kind of integrated energy system multi-energy requirement typical scene generation method and devices, wherein the party Method includes:S1:The multi-energy requirement load vector for getting each day, obtains vectorial set;S2:If obtaining iterative instruction, execute S3 executes S4 if obtaining assessment instruction;S3:In each iteration, in determining the cluster of corresponding number during vector is gathered The heart, until judge that the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is less than preset value, Then determine that all cluster centres when previous iteration are typical scene;S4:The value range for obtaining cluster centre number, in value In range, the cluster centre of corresponding number is determined in vector is gathered according to each value, and calculate the corresponding collection of each value Group's evaluation index determines that the corresponding all cluster centres of minimum cluster evaluation index are typical scene.The present invention passes through two kinds of sides Formula generates the typical scene for being analyzed integrated energy system, when obtaining the instruction without limitation scene number, then leads to The number for crossing cluster centre is iterated and then generates typical scene, when obtaining the instruction of limitation scene number value range, Then by accordingly carrying out cluster assessment to each value, and then generate typical scene.The typical case that method through the invention generates Scene, can comprehensively, accurately integrated energy system is analyzed.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention without having to pay creative labor, may be used also for those of ordinary skill in the art To obtain other attached drawings according to these attached drawings.
Fig. 1 is a kind of one embodiment of integrated energy system multi-energy requirement typical scene generation method provided by the invention Flow diagram;
Fig. 2 is a kind of another implementation of integrated energy system multi-energy requirement typical scene generation method provided by the invention The flow diagram of example;
Fig. 3 is a kind of one embodiment of integrated energy system multi-energy requirement typical scene generating means provided by the invention Structural schematic diagram.
Specific implementation mode
An embodiment of the present invention provides a kind of integrated energy system multi-energy requirement typical scene generation method and devices, can Generate the typical scene for carrying out comprehensive reliable analysis to integrated energy system.
In order to make the invention's purpose, features and advantages of the invention more obvious and easy to understand, below in conjunction with the present invention Attached drawing in embodiment, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that disclosed below Embodiment be only a part of the embodiment of the present invention, and not all embodiment.Based on the embodiments of the present invention, this field All other embodiment that those of ordinary skill is obtained without making creative work, belongs to protection of the present invention Range.
Referring to Fig. 1, one of a kind of integrated energy system multi-energy requirement typical scene generation method provided by the invention Embodiment, including:
101, the multi-energy requirement load vector for getting each day, obtains vectorial set;
If 102, obtaining iterative instruction, 103 are executed, if obtaining assessment instruction, executes 104;
103, in each iteration, the cluster centre of corresponding number is determined in vector is gathered, until judging when previous The difference of the cluster square-error of the cluster square-error of iteration and last iteration is less than preset value, it is determined that when previous iteration All cluster centres are typical scene;
104, the value range for obtaining cluster centre number, in value range, according to each value in vector is gathered It determines the cluster centre of corresponding number, and calculates the corresponding cluster evaluation index of each value, determine minimum cluster evaluation index Corresponding all cluster centres are typical scene.
The present invention generates the typical scene for being analyzed integrated energy system by two ways, unlimited when obtaining When the instruction of scene number processed, then typical scene is generated by the number of cluster centre is iterated, when acquisition limiting field When the instruction of scape number value range, then by accordingly carrying out cluster assessment to each value, and then typical scene is generated.Pass through The present invention method generate typical scene, can comprehensively, accurately integrated energy system is analyzed.
It is above a kind of one embodiment of integrated energy system multi-energy requirement typical scene generation method, to be had more The explanation of body is provided below a kind of another embodiment of integrated energy system multi-energy requirement typical scene generation method, please join Read Fig. 2, a kind of another embodiment of integrated energy system multi-energy requirement typical scene generation method provided by the invention, packet It includes:
201, the multi-energy requirement load vector for getting each day, obtains vectorial set;
In the present embodiment, in order to facilitate more scene analysis, the definition for having unified to data object is needed, by multi-energy requirement Load vector be defined as that the cold demand in gas turbine heating load, user's electric load and the garden of each period in one day forms to Amount:
In formula, T is total period in one day, and n is the total number of days of statistics of initial scene, and i is to belong to a certain in n days set It, H is the heating load of gas turbine, and L is user's electric load, and C is the cold demand of use of garden.
If 202, obtaining iterative instruction, 203 are executed, if obtaining assessment instruction, executes 207;
In the present embodiment, typical scene is sought can generating by two ways.The first is not provided with scene quantity The upper limit, second be by give scene quantity be arranged a value range, carry out exploration assessment.It is understood that working as When getting iterative instruction, then the first scene acquiring method is carried out, when getting assessment instruction, then carries out second of scene Acquiring method.
203, iterations N=1 is initialized, the cluster centre of corresponding number is determined in vector is gathered, and in cluster The heart is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
204, iterations N=N+1 is enabled, the cluster centre of corresponding number is determined in vector is gathered, and to cluster centre It is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
205, judge whether the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is small In preset value, if being not less than, 204 are re-executed, if being less than, executes 206;
206, determine that all cluster centres when previous iteration are typical scene;
Step 203 to step 206 is the first scene acquiring method (i.e. iterative process), in the present embodiment, cluster The calculation formula (criterion function) of square-error is:
In formula, K is the corresponding cluster centre number of iteration each time, njFor the multi-energy requirement load vector number of jth class, mjFor the cluster centre that the cluster centre to jth class is updated, xiFor i-th of multi-energy requirement load vector of jth class.
In the above iterative process, the cluster centre quantity of iteration is arranged in advance each time, and each iteration Cluster centre quantity is and other are secondary inconsistent, common, can increase cluster centre quantity with the increase of iterations Add, or other set-up modes are not specifically limited herein.
In an iterative process, first time iteration only generates corresponding cluster centre and calculates corresponding cluster square-error, Since second of iteration, then start to calculate the difference for clustering square-error between iteration twice, such as when previous iteration is second When secondary iteration, then the difference of the cluster square-error of second of iteration cluster square-error and first time iteration is calculated, judges difference Whether convergence criterion is met, if meeting criterion, it is determined that the cluster centre of second of grey iterative generation is typical scene, if discontented Foot, then continue third time iteration.
In the present invention, the general formula for calculating the difference of the cluster square-error of iteration twice is:
Δ J=| Jc(iter+1)-Jc(iter) | (iter=0,1,2 ...)
In formula, iter is cluster iterations, is sequence of natural numbers.In the present invention, J is definedc(0)=0.It needs to illustrate , when Δ J is less than preset value, that is, determine that the criterion function when previous iteration is restrained, therefore, when gathering for previous grey iterative generation The typical scene that class center as finally determines.
207, the value range for obtaining cluster centre number, in value range, according to each value in vector is gathered It determines the cluster centre of corresponding number, and calculates the corresponding cluster evaluation index of each value, determine minimum cluster evaluation index Corresponding all cluster centres are typical scene.
The calculation formula of cluster evaluation index is:
Dij=| | zi-zj||
In formula, SiIndicate degree of scatter vectorial in ith cluster, SjIndicate the degree of scatter of vector in j-th of cluster, dijIndicate that the distance between ith cluster and j-th of cluster, K values are cluster number, CiFor ith cluster, niIt is poly- for i-th The vectorial number of class.
It is understood that the value range of cluster centre number can be a value set, i.e., the collection of different K values It closes, after each K values correspond to and generate respective cluster centre, the corresponding cluster of each K values can be calculated by above formula and commented Estimate index, the fine or not key for evaluating Clustering Effect is that the data similarity in class is higher, and discrimination is relatively low, on the contrary, between class Data field indexing is higher, and similarity is relatively low.It is, DBI is smaller, then show that Clustering Effect is better.Therefore the minimum index value of selection Corresponding K values, the typical scene that the cluster centre generated as finally determines.
Either the first scene acquiring method or second of scene acquiring method determine corresponding in vector is gathered The process of several cluster centres is specially:
T0:I=1 is enabled, and obtains constant M and cluster centre number K;
It should be noted that constant M is used to determine the density parameter of each vector, and cluster centre number K then can root Determined according to situation, if the first scene acquiring method, into each iteration can corresponding true defining K value, and in second of scene In acquiring method, multiple assignment can be carried out to K in value range.
T1:In vector is gathered, the distance between vector two-by-two is calculated;
In the present embodiment, which is Euclidean distance:
D=| | xi-xj||2i,j∈(1,2,…,n)j≠i
In formula, | | | |2For two norm oeprators, i.e. Euclidean distance operation.
T2:It determines all distances with i-th of multi-energy requirement load vector correlation, and by being ranked up from small to large, takes Density parameter of the m-th distance as i-th of multi-energy requirement load vector;
It is understood that by multi-energy requirement load vector xiWith xj(j=1's, 2 ..., n, j ≠ i) arranges apart from ascending order, M-th distance is used as x in sortingiDensity parameter εi
T3:I=i+1 is enabled, step T2 is re-executed, until determining the density parameter of all multi-energy requirement load vectors;
T4:All multi-energy requirement load vectors are ranked up from small to large by density parameter, by row in institute's directed quantity Sequence takes the vector of preset proportion, obtains high density vector set;
It should be noted that by institute's directed quantity by density parameter by being ranked up from small to large after, these vector in the past Face takes the vector of preset proportion as high density vector set.
T5:The multi-energy requirement load vector of density parameter minimum is determined as first cluster centre;
T6:In high density vector set, the distance between each vector and each fixed cluster centre are calculated, is taken Minimum range corresponding with fixed each cluster centre, is maximized in all minimum ranges, and maximum value is corresponding Multi-energy requirement load vector increases as new cluster centre;
It should be noted that when only determining first cluster centre z1When, second cluster centre z2It then can be by each Vector and z1The distance between determine, be minimized in multiple distances, the minimum value it is corresponding vector be second cluster Center z2.Then third cluster centre then first needs to calculate each vector and z1、z2The distance between, respectively in z1With other to It is minimized in all distance values between amount, in z2All distance values between other vectors are minimized, finally two It is maximized between a minimum value, the corresponding vector of the maximum value is third cluster centre z3, subsequent cluster centre with This analogizes, and details are not described herein again.Its general formula is:
max(min(d(xi,z1)),min(d(xi,z2)),...,min(d(xi,zj-1)))。
T7:Judge whether the number of cluster centre equal to K re-executes T6 if being not equal to, if being equal to, terminates.
Be above a kind of integrated energy system multi-energy requirement typical scene generation method provided by the invention is carried out it is detailed It describes in detail bright, a kind of integrated energy system multi-energy requirement typical scene generating means provided by the invention will be illustrated below, Referring to Fig. 3, a kind of one embodiment of integrated energy system multi-energy requirement typical scene generating means provided by the invention, packet It includes:
First acquisition module 301, the multi-energy requirement load vector for getting each day, obtains vectorial set;
If second acquisition module 302 triggers the first determining module 303 for obtaining iterative instruction, refers to if obtaining assessment It enables, then triggers the second determining module 304;
First determining module 303, in each iteration, being determined in vector set in the cluster of corresponding number The heart, until judge that the difference of the cluster square-error when the cluster square-error and last iteration of previous iteration is less than preset value, Then determine that all cluster centres when previous iteration are typical scene;
Second determining module 304, the value range for obtaining cluster centre number, in value range, according to each Value determines the cluster centre of corresponding number in vector is gathered, and calculates the corresponding cluster evaluation index of each value, determines The corresponding all cluster centres of minimum cluster evaluation index are typical scene.
Optionally, multi-energy requirement load vector by the gas turbine heating load of each period in one day, user's electric load and Garden is formed with cold demand.
Optionally, the first determining module 303 includes:
Initialization submodule, for initializing iterations N=1, in determining the cluster of corresponding number during vector is gathered The heart, and cluster centre is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
Iteration submodule determines the cluster centre of corresponding number for enabling iterations N=N+1 in vector is gathered, and Cluster centre is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
Judging submodule, for judging the cluster square-error when the cluster square-error and last iteration of previous iteration Difference whether be less than preset value, if being not less than, retriggered iteration submodule triggers determination sub-module if being less than;
Determination sub-module, for determining that all cluster centres when previous iteration are typical scene.
Optionally, the calculation formula for clustering square-error is:
In formula, K is that the corresponding cluster centre number of iteration, nj are the multi-energy requirement load vector number of jth class each time, Mj is the cluster centre being updated to the cluster centre of jth class, xiFor i-th of multi-energy requirement load vector of jth class.
Optionally, initialization submodule, iteration submodule and the second determining module include:Determination unit, for The cluster centre of corresponding number is determined in duration set;
Determination unit includes:
Subelement is obtained, for enabling i=1, and obtains constant M and cluster centre number K;
Computation subunit calculates the distance between vector two-by-two used in gathering in vector;
First sorting subunit for determining all distances with i-th of multi-energy requirement load vector correlation, and is pressed from small To being ranked up greatly, density parameter of the m-th distance as i-th of multi-energy requirement load vector is taken;
Subelement is recycled, for enabling i=i+1, the first sorting subunit of retriggered, until determining that all multi-energy requirements are negative The density parameter of lotus vector;
Second sorting subunit, for all multi-energy requirement load vectors to be ranked up from small to large by density parameter, The vector for taking preset proportion by sequence in institute's directed quantity, obtains high density vector set;
Determination subelement, for the multi-energy requirement load vector of density parameter minimum to be determined as first cluster centre;
Increase subelement, in high density vector set, calculating each vector and each fixed cluster centre The distance between, minimum range corresponding with fixed each cluster centre is taken, is maximized in all minimum ranges, it will The corresponding multi-energy requirement load vector of maximum value increases as new cluster centre;
Judgment sub-unit, for judging whether the number of cluster centre is equal to K, if being not equal to, retriggered increases son Unit terminates if being equal to.
Optionally, distance is Euclidean distance.
Optionally, the calculation formula of cluster evaluation index is:
dij=| | zi-zj||
In formula, SiIndicate degree of scatter vectorial in ith cluster, SjIndicate the degree of scatter of vector in j-th of cluster, dijIndicate that the distance between ith cluster and j-th of cluster, K values are cluster number, CiFor ith cluster, niIt is poly- for i-th The vectorial number of class.
A kind of another embodiment of integrated energy system multi-energy requirement typical scene generating means provided by the invention, packet It includes:Memory, and it is coupled to the processor of the memory;
The processor is configured as, based on the instruction being stored in the memory devices, executing as described above comprehensive Close energy resource system multi-energy requirement typical scene generation method.
The invention further relates to a kind of computer-readable mediums, are stored thereon with computer program, which is held by processor Above-described integrated energy system multi-energy requirement typical scene generation method is realized when row.
It is apparent to those skilled in the art that for convenience and simplicity of description, the system of foregoing description, The specific work process of device and unit, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In several embodiments provided herein, it should be understood that disclosed system, device and method can be with It realizes by another way.For example, the apparatus embodiments described above are merely exemplary, for example, the unit It divides, only a kind of division of logic function, formula that in actual implementation, there may be another division manner, such as multiple units or component It can be combined or can be integrated into another system, or some features can be ignored or not executed.Another point, it is shown or The mutual coupling, direct-coupling or communication connection discussed can be the indirect coupling by some interfaces, device or unit It closes or communicates to connect, can be electrical, machinery or other forms.
The unit illustrated as separating component may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, you can be located at a place, or may be distributed over multiple In network element.Some or all of unit therein can be selected according to the actual needs to realize the mesh of this embodiment scheme 's.
In addition, each functional unit in each embodiment of the present invention can be integrated in a processing unit, it can also It is that each unit physically exists alone, it can also be during two or more units be integrated in one unit.Above-mentioned integrated list The form that hardware had both may be used in member is realized, can also be realized in the form of SFU software functional unit.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can be stored in a computer read/write memory medium.Based on this understanding, technical scheme of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) executes the complete of each embodiment the method for the present invention Portion or part steps.And storage medium above-mentioned includes:USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic disc or CD etc. are various can store journey The medium of sequence code.
The above, the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although with reference to before Stating embodiment, invention is explained in detail, it will be understood by those of ordinary skill in the art that:It still can be to preceding The technical solution recorded in each embodiment is stated to modify or equivalent replacement of some of the technical features;And these Modification or replacement, the spirit and scope for various embodiments of the present invention technical solution that it does not separate the essence of the corresponding technical solution.

Claims (10)

1. a kind of integrated energy system multi-energy requirement typical scene generation method, which is characterized in that including:
S1:The multi-energy requirement load vector for getting each day, obtains vectorial set;
S2:If obtaining iterative instruction, S3 is executed, if obtaining assessment instruction, executes S4;
S3:In each iteration, the cluster centre of corresponding number is determined in the vector is gathered, until judging to change when previous The difference of the cluster square-error of the cluster square-error in generation and last iteration is less than preset value, it is determined that when the institute of previous iteration It is typical scene to have cluster centre;
S4:The value range for obtaining cluster centre number is gathered according to each value in the vector in the value range The cluster centre of middle determining corresponding number, and the corresponding cluster evaluation index of each value is calculated, determine that minimum cluster assessment refers to It is typical scene to mark corresponding all cluster centres.
2. integrated energy system multi-energy requirement typical scene generation method according to claim 1, which is characterized in that described Multi-energy requirement load vector is by the cold requirement groups in the gas turbine heating load of each period, user's electric load and garden in one day At.
3. integrated energy system multi-energy requirement typical scene generation method according to claim 1, which is characterized in that described In each iteration, the cluster centre of corresponding number is determined in all vector set, until judging to work as previous iteration Cluster square-error and the difference of cluster square-error of last iteration be less than preset value, it is determined that it is all when previous iteration Cluster centre specifically includes for typical scene:
S31:Iterations N=1 is initialized, the cluster centre of corresponding number is determined in the vector set, and in cluster The heart is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
S32:Iterations N=N+1 is enabled, the cluster centre of corresponding number is determined in the vector set, and to cluster centre It is updated, then to updated cluster centre calculate the cluster square-error of iv-th iteration;
S33:It is pre- to judge whether the difference when the cluster square-error of the cluster square-error and last iteration of previous iteration is less than If value, if being not less than, re-executes S32, if being less than, executes S34;
S34:Determine that all cluster centres when previous iteration are typical scene.
4. integrated energy system multi-energy requirement typical scene generation method according to claim 3, which is characterized in that described Cluster square-error calculation formula be:
In formula, K is the corresponding cluster centre number of iteration each time, njFor the multi-energy requirement load vector number of jth class, mjFor To the cluster centre that the cluster centre of jth class is updated, xiFor i-th of multi-energy requirement load vector of jth class.
5. integrated energy system multi-energy requirement typical scene generation method according to any one of claims 1 to 4, special Sign is, described to determine that the cluster centre of corresponding number specifically includes in the vector set:
T0:I=1 is enabled, and obtains constant M and cluster centre number K;
T1:In the vector set, the distance between vector two-by-two is calculated;
T2:It determines all distances with i-th of multi-energy requirement load vector correlation, and by being ranked up from small to large, takes m-th Density parameter of the distance as i-th of multi-energy requirement load vector;
T3:I=i+1 is enabled, step T2 is re-executed, until determining the density parameter of all multi-energy requirement load vectors;
T4:All multi-energy requirement load vectors are ranked up from small to large by density parameter, are taken by sequence in institute's directed quantity The vector of preset proportion obtains high density vector set;
T5:The multi-energy requirement load vector of density parameter minimum is determined as first cluster centre;
T6:In the high density vector set, the distance between each vector and each fixed cluster centre are calculated, is taken Minimum range corresponding with fixed each cluster centre, is maximized in all minimum ranges, by maximum value pair The multi-energy requirement load vector answered increases as new cluster centre;
T7:Judge whether the number of cluster centre equal to K re-executes T6 if being not equal to, if being equal to, terminates.
6. the integrated energy system multi-energy requirement typical scene generation method according to claim 5 any one, feature It is, the distance is Euclidean distance.
7. integrated energy system multi-energy requirement typical scene generation method according to claim 1, which is characterized in that described The calculation formula of cluster evaluation index is:
dij=| | zi-zj||
In formula, SiIndicate degree of scatter vectorial in ith cluster, SjIndicate the degree of scatter of vector in j-th of cluster, dijTable Show that the distance between ith cluster and j-th of cluster, K values are cluster number, CiFor ith cluster, niFor ith cluster to Measure number.
8. a kind of integrated energy system multi-energy requirement typical scene generating means, which is characterized in that including:
First acquisition module, the multi-energy requirement load vector for getting each day, obtains vectorial set;
If second acquisition module triggers the first determining module for obtaining iterative instruction, if obtaining assessment instruction, triggers Second determining module;
First determining module, in each iteration, the cluster centre of corresponding number being determined in the vector set, directly It is less than preset value to the difference for judging the cluster square-error when the cluster square-error and last iteration of previous iteration, it is determined that When all cluster centres of previous iteration are typical scene;
Second determining module, the value range for obtaining cluster centre number, in the value range, according to each value The cluster centre of corresponding number is determined in the vector set, and calculates the corresponding cluster evaluation index of each value, is determined The corresponding all cluster centres of minimum cluster evaluation index are typical scene.
9. a kind of integrated energy system multi-energy requirement typical scene generating means, which is characterized in that including:Memory and coupling It is connected to the processor of the memory;
The processor is configured as, based on the instruction being stored in the memory devices, executing as claim 1 to 7 is arbitrary Integrated energy system multi-energy requirement typical scene generation method described in one.
10. a kind of computer-readable medium, is stored thereon with computer program, which is characterized in that the program is executed by processor Integrated energy system multi-energy requirement typical scene generation method described in Shi Shixian claim 1 to 7 any one.
CN201810524561.XA 2018-05-28 2018-05-28 A kind of integrated energy system multi-energy requirement typical scene generation method and device Pending CN108764335A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810524561.XA CN108764335A (en) 2018-05-28 2018-05-28 A kind of integrated energy system multi-energy requirement typical scene generation method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810524561.XA CN108764335A (en) 2018-05-28 2018-05-28 A kind of integrated energy system multi-energy requirement typical scene generation method and device

Publications (1)

Publication Number Publication Date
CN108764335A true CN108764335A (en) 2018-11-06

Family

ID=64002803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810524561.XA Pending CN108764335A (en) 2018-05-28 2018-05-28 A kind of integrated energy system multi-energy requirement typical scene generation method and device

Country Status (1)

Country Link
CN (1) CN108764335A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109685348A (en) * 2018-12-14 2019-04-26 广东电网有限责任公司 A kind of power equipment typical mode of operation determines method
CN110009527A (en) * 2019-04-04 2019-07-12 国家电网有限公司 A kind of integrated energy system user portrait method and system
CN110046801A (en) * 2019-03-25 2019-07-23 国网江苏省电力有限公司经济技术研究院 A kind of typical scene generation method of power distribution network electric system
CN112132111A (en) * 2020-10-10 2020-12-25 安徽江淮汽车集团股份有限公司 Parking typical scene extraction method, device, storage medium and device
CN112258233A (en) * 2020-10-22 2021-01-22 国网新疆电力有限公司经济技术研究院 Method and device for site selection and capacity determination of regional comprehensive energy station
CN112560174A (en) * 2020-12-08 2021-03-26 中国航天空气动力技术研究院 Static aeroelasticity low dynamic test data extraction method, device, medium and equipment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110055212A1 (en) * 2009-09-01 2011-03-03 Cheng-Fa Tsai Density-based data clustering method
CN102819677A (en) * 2012-07-30 2012-12-12 河海大学 Rainfall site similarity evaluation method on basis of single rainfall type
US20160004762A1 (en) * 2014-07-07 2016-01-07 Edward-Robert Tyercha Hilbert Curve Partitioning for Parallelization of DBSCAN
CN105574642A (en) * 2015-11-06 2016-05-11 广东工业大学 Smart grid big data-based electricity price execution checking method
CN106021361A (en) * 2016-05-10 2016-10-12 中国空间技术研究院 Sequence alignment-based self-adaptive application layer network protocol message clustering method
CN106649877A (en) * 2017-01-06 2017-05-10 广东工业大学 Density peak-based big data mining method and apparatus

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110055212A1 (en) * 2009-09-01 2011-03-03 Cheng-Fa Tsai Density-based data clustering method
CN102819677A (en) * 2012-07-30 2012-12-12 河海大学 Rainfall site similarity evaluation method on basis of single rainfall type
US20160004762A1 (en) * 2014-07-07 2016-01-07 Edward-Robert Tyercha Hilbert Curve Partitioning for Parallelization of DBSCAN
CN105574642A (en) * 2015-11-06 2016-05-11 广东工业大学 Smart grid big data-based electricity price execution checking method
CN106021361A (en) * 2016-05-10 2016-10-12 中国空间技术研究院 Sequence alignment-based self-adaptive application layer network protocol message clustering method
CN106649877A (en) * 2017-01-06 2017-05-10 广东工业大学 Density peak-based big data mining method and apparatus

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109685348A (en) * 2018-12-14 2019-04-26 广东电网有限责任公司 A kind of power equipment typical mode of operation determines method
CN110046801A (en) * 2019-03-25 2019-07-23 国网江苏省电力有限公司经济技术研究院 A kind of typical scene generation method of power distribution network electric system
CN110046801B (en) * 2019-03-25 2023-07-21 国网江苏省电力有限公司经济技术研究院 Typical scene generation method of power distribution network power system
CN110009527A (en) * 2019-04-04 2019-07-12 国家电网有限公司 A kind of integrated energy system user portrait method and system
CN112132111A (en) * 2020-10-10 2020-12-25 安徽江淮汽车集团股份有限公司 Parking typical scene extraction method, device, storage medium and device
CN112258233A (en) * 2020-10-22 2021-01-22 国网新疆电力有限公司经济技术研究院 Method and device for site selection and capacity determination of regional comprehensive energy station
CN112560174A (en) * 2020-12-08 2021-03-26 中国航天空气动力技术研究院 Static aeroelasticity low dynamic test data extraction method, device, medium and equipment
CN112560174B (en) * 2020-12-08 2022-12-02 中国航天空气动力技术研究院 Static aeroelasticity low dynamic test data extraction method, device, medium and equipment

Similar Documents

Publication Publication Date Title
CN108764335A (en) A kind of integrated energy system multi-energy requirement typical scene generation method and device
Rhee et al. Active and semi-supervised learning for object detection with imperfect data
CN110163258A (en) A kind of zero sample learning method and system reassigning mechanism based on semantic attribute attention
CN104798043B (en) A kind of data processing method and computer system
CN110245709A (en) Based on deep learning and from the 3D point cloud data semantic dividing method of attention
Liu et al. Partition level constrained clustering
CN113393474B (en) Feature fusion based three-dimensional point cloud classification and segmentation method
CN113486190B (en) Multi-mode knowledge representation method integrating entity image information and entity category information
CN103886048A (en) Cluster-based increment digital book recommendation method
CN103440471B (en) The Human bodys' response method represented based on low-rank
CN110298035A (en) Word vector based on artificial intelligence defines method, apparatus, equipment and storage medium
CN102915448B (en) A kind of three-dimensional model automatic classification method based on AdaBoost
CN110119144A (en) Based on the matched multirobot SLAM algorithm of sub- map feature
CN110222780A (en) Object detecting method, device, equipment and storage medium
CN112199532A (en) Zero sample image retrieval method and device based on Hash coding and graph attention machine mechanism
CN109815541B (en) Method and device for dividing rail transit vehicle product parts and modules and electronic equipment
CN106250933A (en) Method, system and the FPGA processor of data clusters based on FPGA
CN109919172A (en) A kind of clustering method and device of multi-source heterogeneous data
CN106022359A (en) Fuzzy entropy space clustering analysis method based on orderly information entropy
CN111582912A (en) Portrait modeling method based on deep embedding clustering algorithm
CN113222181B (en) Federated learning method facing k-means clustering algorithm
CN109857886B (en) Three-dimensional model retrieval method based on minimum maximum value game theory view approximation
CN105183804B (en) A kind of cluster method of servicing based on ontology
Zhang et al. End‐to‐end generation of structural topology for complex architectural layouts with graph neural networks
CN116993555A (en) Partition method, system and storage medium for identifying territory space planning key region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181106