CN108759080A - Combustion boiler with good air inlet pipe sealing performance - Google Patents
Combustion boiler with good air inlet pipe sealing performance Download PDFInfo
- Publication number
- CN108759080A CN108759080A CN201810993401.XA CN201810993401A CN108759080A CN 108759080 A CN108759080 A CN 108759080A CN 201810993401 A CN201810993401 A CN 201810993401A CN 108759080 A CN108759080 A CN 108759080A
- Authority
- CN
- China
- Prior art keywords
- air inlet
- inlet pipe
- boiler
- water tank
- gasket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000007789 sealing Methods 0.000 title abstract description 11
- 238000002485 combustion reaction Methods 0.000 title abstract 2
- 230000000694 effects Effects 0.000 claims abstract description 13
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 50
- 238000010438 heat treatment Methods 0.000 claims description 32
- 239000000779 smoke Substances 0.000 claims description 10
- 238000009434 installation Methods 0.000 claims description 4
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 4
- 239000007789 gas Substances 0.000 description 7
- 239000000567 combustion gas Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 239000000446 fuel Substances 0.000 description 2
- 238000009776 industrial production Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 210000000476 body water Anatomy 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000003137 locomotive effect Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 230000037081 physical activity Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23K—FEEDING FUEL TO COMBUSTION APPARATUS
- F23K5/00—Feeding or distributing other fuel to combustion apparatus
- F23K5/002—Gaseous fuel
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H1/00—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
- F24H1/22—Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating
- F24H1/34—Water heaters other than continuous-flow or water-storage heaters, e.g. water heaters for central heating with water chamber arranged adjacent to the combustion chamber or chambers, e.g. above or at side
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/0005—Details for water heaters
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Steam Or Hot-Water Central Heating Systems (AREA)
Abstract
The invention discloses a combustion boiler with a good air inlet pipe sealing performance, which comprises a boiler main body, wherein an air inlet channel and a through hole are formed in the boiler main body, the through hole is positioned on the right side of the air inlet channel, a vertical rod is fixedly arranged on the inner side of the through hole, two clamping grooves are formed in one side of the boiler main body, the two clamping grooves are respectively positioned above and below the through hole, a sealing gasket is clamped on the inner sides of the two clamping grooves, a threaded rod is movably arranged in the vertical rod, one end of the threaded rod penetrates through the sealing gasket and extends to the outer side of the sealing gasket, the threaded rod is in threaded connection with the sealing gasket, and a rotating disc is fixedly arranged at one end, far away from. According to the invention, after the air inlet pipe and the boiler main body are movably mounted, the rotary table is rotated to drive the threaded rod to rotate, so that the sealing gasket is clamped with the clamping groove and is in precise contact with the clamping groove, and the sealing effect of the connecting pipe is improved.
Description
Technical field
The present invention relates to burning boiler technical field more particularly to a kind of burning boilers of air inlet pipe good airproof performance.
Background technology
Boiler is a kind of energy conversion, and the energy inputted to boiler has chemical energy, electric energy in fuel, boiler output
Steam, high-temperature water with certain thermal energy or organic heat carrier.The original meaning of pot refers to the water container heated on fire, and stove refers to burning
The place of fuel, boiler include pot and stove two large divisions.The hot water or steam generated in boiler can directly be industrial production and people
The people's livelihood, which is lived, provides required thermal energy, mechanical energy can be also converted to by Steam Power Equipment, or again turn mechanical energy by generator
It is changed to electric energy.The boiler for providing hot water is known as hot-water boiler, is mainly used for living, also there is a small amount of application in industrial production.It generates
The boiler of steam is known as steam boiler, is often simply called boiler, is chiefly used in thermal power station, ship, locomotive and industrial and mining enterprises.
The air inlet pipe of burning boiler is all directly to be connect with boiler body currently on the market, when boiler works, due into
Tracheae installs no good sealing effect, can cause certain leakage phenomenon, therefore, there is an urgent need for a kind of air inlet pipe good airproof performances
Burning boiler solves the above problems.
Invention content
The purpose of the present invention is to solve disadvantages existing in the prior art, and a kind of air inlet pipe good airproof performance proposed
Burning boiler.
To achieve the goals above, present invention employs following technical solutions:
A kind of burning boiler of air inlet pipe good airproof performance, including boiler body, the inside of the boiler body offer into
Gas channel and through-hole, the through-hole are located at the right side of inlet channel, montant, the boiler are installed on the inside of the through-hole
The side of main body offers card slot, and the quantity of the card slot is two, and two card slots are located at the top of through-hole under
Side, is connected with gasket on the inside of two card slots, and the internal activity of the montant installs threaded rod, and the one of the threaded rod
End runs through gasket and extends to the outside of gasket, and the threaded rod is threadedly coupled with gasket, and two threaded rods are remote
One end from montant is installed with turntable, and the internal activity of the inlet channel is equipped with air inlet pipe, and the one of the air inlet pipe
End extends through boiler body, montant, gasket and turntable and extends to the outside of turntable, the air inlet pipe respectively with montant,
The bottom of gasket and turntable pivot bush unit, the boiler body is installed with support column, and the quantity of the support column is two
A, the side of one support column is installed with bottom plate, and water tank, the air inlet pipe are installed at the top of the bottom plate
One end of keep away from boiler main body runs through water tank and extends to the outside of water tank.
Preferably, the inside of the boiler body is installed with heating duct, and the adjacent side of the heating duct is solid
Surely it is communicated with heating branch pipe.
Preferably, the inlet channel is located between heating branch pipe and heating duct, and peace is fixed in the bottom of the support column
Equipped with pedestal.
Preferably, water tank is installed between the inner wall of the boiler body both sides, the water tank is located at heating
The lower section of conduit.
Preferably, the bottom of the water tank, which is fixed, is communicated with drainpipe, and boiler body is run through in the bottom end of the drainpipe
And extend to the outside of boiler body.
Preferably, side of the boiler body far from air inlet pipe, which is fixed, is communicated with outlet pipe and water inlet pipe, the heating
The both ends of conduit are connected to outlet pipe and water inlet pipe fixation respectively.
Preferably, the bottom of the boiler body, which is fixed, is communicated with smoke exhaust pipe, and the one of the smoke exhaust pipe keep away from boiler main body
End runs through water tank and extends to the outside of water tank.
Beneficial effects of the present invention are:
1. the burning boiler of the air inlet pipe good airproof performance, by being provided with gasket, by air inlet pipe and boiler body activity
After installation, rotation driven by rotary disc threaded rod rotation, to make gasket be mutually clamped with card slot, and exact contact, the company of improving
The sealing effect taken over.
2. the burning boiler of the air inlet pipe good airproof performance, by being provided with water tank, the tail gas that boiler body work generates is logical
It crosses smoke exhaust pipe and enters water tank and be discharged in air, the water in water tank can absorb the heat of tail gas and be heated to air inlet pipe,
Preheating is achieved the effect that.
3. the burning boiler of the air inlet pipe good airproof performance, by being provided with heating branch pipe, when air inlet pipe is into inlet channel
When being passed through combustion gas makes boiler work, part flow can be diverted to by heating branch pipe inside heating duct, the heat generated to boiler
Amount is fully absorbed, and the utilization rate of resource is improved.
Description of the drawings
Fig. 1 is a kind of air inlet pipe attachment structure schematic diagram of the burning boiler of air inlet pipe good airproof performance proposed by the present invention;
Fig. 2 is a kind of boiler body structural schematic diagram of the burning boiler of air inlet pipe good airproof performance proposed by the present invention;
Fig. 3 is a kind of boiler body sectional structure signal of burning boiler of air inlet pipe good airproof performance proposed by the present invention
Figure.
In figure:1 pedestal, 2 support columns, 3 outlet pipes, 4 boiler bodies, 5 water inlet pipes, 6 inlet channels, 7 air inlet pipe, 8 smoke evacuations
Pipe, 9 water tanks, 10 bottom plates, 11 heating branch pipes, 12 water tanks, 13 drainpipes, 14 through-holes, 15 montants, 16 card slots, 17 gaskets, 18
Threaded rod, 19 turntables, 20 heating ducts.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.
Referring to Fig.1-3, a kind of burning boiler of air inlet pipe good airproof performance, including boiler body 4, the inside of boiler body 4
Inlet channel 6 and through-hole 14 are offered, through-hole 14 is located at the right side of inlet channel 6, and the inside of through-hole 14 is installed with montant
15, the side of boiler body 4 offers card slot 16, and the quantity of card slot 16 is two, and two card slots 16 are located at through-hole 14
Above and below, the inside of two card slots 16 is connected with gasket 17, and the internal activity of montant 15 installs threaded rod 18, threaded rod
18 one end runs through gasket 17 and extends to the outside of gasket 17, and threaded rod 18 is threadedly coupled with gasket 17, two spiral shells
The one end of rasp bar 18 far from montant 15 is installed with turntable 19, and the internal activity of inlet channel 6 is equipped with air inlet pipe 7, air inlet
One end of pipe 7 extends through boiler body 4, montant 15, gasket 17 and turntable 19 and the outside for extending to turntable 19, by air inlet
Pipe 7 is with after 4 activity installation of boiler body, and rotation turntable 19 drives threaded rod 18 to rotate, to make gasket 17 and 16 phase of card slot
Clamping, and exact contact improve the sealing effect of connecting tube 7, air inlet pipe 7 respectively with montant 15, gasket 17 and turntable
19 pivot bush units, the bottom of boiler body 4 are installed with support column 2, and the quantity of support column 2 is two, support column 2
Side is installed with bottom plate 10, and the top of bottom plate 10 is installed with water tank 9, and one end of 7 keep away from boiler main body 4 of air inlet pipe is passed through
It wears water tank 9 and extends to the outside of water tank 9, the tail gas that the work of boiler body 4 generates enters water tank 9 by smoke exhaust pipe 8 and is discharged
Into air, the water in water tank 9 can absorb the heat of tail gas and be heated to air inlet pipe 7, achieve the effect that preheating.
In the present invention, the inside of boiler body 4 is installed with heating duct 20, and the adjacent side of heating duct 20 is fixed
It is communicated with heating branch pipe 11, inlet channel 6 is located between heating branch pipe 11 and heating duct 20, when air inlet pipe 7 is to inlet channel 6
When being inside passed through combustion gas makes boiler work, part flow can be diverted to by heating branch pipe 11 inside heating duct 20, be produced to boiler
Raw heat is fully absorbed, and the utilization rate of resource is improved, and the bottom of support column 2 is installed with pedestal 1, boiler body
Water tank 12 is installed between the inner wall of 4 both sides, water tank 12 is located at the lower section of heating duct 20, the bottom of water tank 12
Fixed to be communicated with drainpipe 13, the bottom end of drainpipe 13 runs through boiler body 4 and extends to the outside of boiler body 4, boiler master
Side of the body 4 far from air inlet pipe 7, which is fixed, is communicated with outlet pipe 3 and water inlet pipe 5, the both ends of heating duct 20 respectively with outlet pipe 3
It is connected to the fixation of water inlet pipe 5, the bottom of boiler body 4, which is fixed, is communicated with smoke exhaust pipe 8, one end of 8 keep away from boiler main body 4 of smoke exhaust pipe
Through water tank 9 and extend to the outside of water tank 9.
Operation principle:In use, by after the 4 activity installation of air inlet pipe 7 and boiler body, rotation turntable 19 drives threaded rod 18
Rotation, to make gasket 17 be clamped with 16 phase of card slot, and exact contact, being passed through combustion gas makes boiler work, 4 work of boiler body
Make the tail gas that generates and enter water tank 9 by smoke exhaust pipe 8 to be discharged in air, the water in water tank 9 can absorb the heat of tail gas and
Air inlet pipe 7 is heated, while flow is passed through into heating duct 20 by water inlet pipe 5, part flow can be by heating branch
Pipe 11 is diverted to inside heating duct 20, and the heat generated to boiler fully absorbs, and after waiting for that kettleman makees, heating is led
The condensed water that pipe 20 generates falls on the bottom of water tank 12, and drainpipe 13 is obliquely installed, so that ponding is passed through drainpipe 13 and flow out
?.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto,
Any one skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its
Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.
Claims (7)
1. a kind of burning boiler of air inlet pipe good airproof performance, including boiler body (4), which is characterized in that the boiler body (4)
Inside offer inlet channel (6) and through-hole (14), the through-hole (14) is located at the right side of inlet channel (6), the through-hole
(14) montant (15) is installed on the inside of, the side of the boiler body (4) offers card slot (16), the card slot (16)
Quantity be two, two card slots (16) are located above and below through-hole (14), two card slots (16)
Inside is connected with gasket (17), the internal activity installation threaded rod (18) of the montant (15), and the one of the threaded rod (18)
End runs through gasket (17) and extends to the outside of gasket (17), and the threaded rod (18) is threadedly coupled with gasket (17),
The one end of two threaded rods (18) far from montant (15) is installed with turntable (19), the inside of the inlet channel (6)
It is movably installed with air inlet pipe (7), one end of the air inlet pipe (7) extends through boiler body (4), montant (15), gasket
(17) and turntable (19) and the outside for extending to turntable (19), the air inlet pipe (7) respectively with montant (15), gasket (17) and
The bottom of turntable (19) pivot bush unit, the boiler body (4) is installed with support column (2), the quantity of the support column (2)
It it is two, the side of one support column (2) is installed with bottom plate (10), is installed at the top of the bottom plate (10)
One end of water tank (9), air inlet pipe (7) the keep away from boiler main body (4) runs through water tank (9) and extends to the outside of water tank (9).
2. a kind of burning boiler of air inlet pipe good airproof performance according to claim 1, which is characterized in that the boiler body
(4) inside is installed with heating duct (20), and the adjacent side of the heating duct (20), which is fixed, is communicated with heating branch pipe
(11)。
3. a kind of burning boiler of air inlet pipe good airproof performance according to claim 1, which is characterized in that the inlet channel
(6) it is located between heating branch pipe (11) and heating duct (20), the bottom of the support column (2) is installed with pedestal (1).
4. a kind of burning boiler of air inlet pipe good airproof performance according to claim 1, which is characterized in that the boiler body
(4) water tank (12) is installed between the inner wall of both sides, the water tank (12) is located at the lower section of heating duct (20).
5. a kind of burning boiler of air inlet pipe good airproof performance according to claim 4, which is characterized in that the water tank
(12) bottom, which is fixed, is communicated with drainpipe (13), and the bottom end of the drainpipe (13) through boiler body (4) and extends to pot
The outside of furnace main body (4).
6. a kind of burning boiler of air inlet pipe good airproof performance according to claim 1, which is characterized in that the boiler body
(4) side far from air inlet pipe (7), which is fixed, is communicated with outlet pipe (3) and water inlet pipe (5), the both ends point of the heating duct (20)
It is not connected to outlet pipe (3) and water inlet pipe (5) fixation.
7. a kind of burning boiler of air inlet pipe good airproof performance according to claim 1, which is characterized in that the boiler body
(4) bottom, which is fixed, is communicated with smoke exhaust pipe (8), and water tank (9) is run through simultaneously in one end of smoke exhaust pipe (8) the keep away from boiler main body (4)
Extend to the outside of water tank (9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810993401.XA CN108759080A (en) | 2018-08-29 | 2018-08-29 | Combustion boiler with good air inlet pipe sealing performance |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810993401.XA CN108759080A (en) | 2018-08-29 | 2018-08-29 | Combustion boiler with good air inlet pipe sealing performance |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108759080A true CN108759080A (en) | 2018-11-06 |
Family
ID=63967937
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810993401.XA Withdrawn CN108759080A (en) | 2018-08-29 | 2018-08-29 | Combustion boiler with good air inlet pipe sealing performance |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108759080A (en) |
-
2018
- 2018-08-29 CN CN201810993401.XA patent/CN108759080A/en not_active Withdrawn
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205119209U (en) | Heating system is united to production and use of marsh gas biological energy source and solar energy | |
CN208968036U (en) | Combustion boiler with good air inlet pipe sealing performance | |
CN100520268C (en) | Fume-fume hot pipe heater exchanger for fume desulphurization in heat-engine plant | |
CN108759080A (en) | Combustion boiler with good air inlet pipe sealing performance | |
CN201496986U (en) | Energy-saving anti-clogging air heater | |
CN208846461U (en) | Smoke exhaust pipeline with high safety performance | |
CN110701939B (en) | Waste heat recovery device for condensing flue gas of energy-saving coal power plant | |
CN208817701U (en) | Combustion boiler with stably installed air inlet pipe | |
CN208846753U (en) | Accumulated water discharging device with efficient sealing for combustion boiler | |
CN208635130U (en) | A kind of coal changes gas boiler heat circulating system | |
CN206037418U (en) | Long service life's water heating device | |
CN208154452U (en) | A kind of energy-saving gas steam boiler | |
CN108800555A (en) | Combustion boiler with double water outlet pipelines | |
CN208059342U (en) | Water resource heat pump waste heat gradient with auxiliary electrical heater utilizes system | |
CN204718131U (en) | Boiler energy-saving device | |
CN201104012Y (en) | Domestic vertical heating boiler | |
CN208859633U (en) | Combustion boiler convenient for waste gas treatment | |
CN208817703U (en) | A kind of boiler that the Industrial Boiler rate of heat addition is fast | |
CN208859865U (en) | Smoke exhaust pipe convenient to overhaul and replace for combustion boiler | |
CN204268447U (en) | A kind of thermal power generation installation | |
CN214536268U (en) | Double-boiler barrel of energy-saving boiler | |
CN202328384U (en) | Rotating cover of water-heating furnace | |
CN208817687U (en) | Combustion boiler with lower-inlet and upper-outlet type heating pipeline | |
CN205807841U (en) | A kind of hot air type boiler of available pluralities of fuel | |
CN208846410U (en) | Air inlet device convenient for replacing air inlet pipe for combustion boiler |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181106 |