CN108756437A - A kind of construction technology of high-altitude large size assembling shape steel member - Google Patents
A kind of construction technology of high-altitude large size assembling shape steel member Download PDFInfo
- Publication number
- CN108756437A CN108756437A CN201810536371.XA CN201810536371A CN108756437A CN 108756437 A CN108756437 A CN 108756437A CN 201810536371 A CN201810536371 A CN 201810536371A CN 108756437 A CN108756437 A CN 108756437A
- Authority
- CN
- China
- Prior art keywords
- bracing members
- steel member
- lifting
- section
- shape steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
- E04H12/10—Truss-like structures
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/344—Arrangements for lifting tower sections for placing additional sections under them
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of construction technology of high-altitude large size assembling shape steel member, is related to the technical field of construction of large-scale assembling shape steel member, and interim full framing is set up on ground, completes the assembling of large-scale assembling shape steel member upper body structure;Installation several groups promote pylon temporarily, promote pylon and are fixed on by embedded iron parts on the reinforced concrete foundation of vertical bracing members, and fixed lifter is distributed on each group lifting bracket;Bracing members are segmented and are established, it is promoted by being accumulated to the segmentation of bracing members, realize the lifting to top steel member, large-scale, the great steel member of weight need not be lifted using other heavy lifting equipments, the present invention greatly reduces installation difficulty, has great advantage for quality, safety, duration and construction cost control etc..
Description
Technical field
The present invention relates to the technical field of construction of large-scale assembling shape steel member, are especially built upon away from ground relatively high level
The construction technology of the steel member of high-altitude large size assembling.
Background technology
Certain large-scale assembling shape steel members need to pass through bracing members(Lattice column)Branch is in high-altitude, and the large size assembles shape steel structure
Part is again by more than one piece Steel material assembly group, and dead weight is extremely heavy, volume is again huge.
There are two types of the forms of construction work for assembling shape steel member to above-mentioned large size in the past:
A kind of over-the-counter assembly for carrying out Steel material in preparation installation, meanwhile, it is supported in the place of preparation installation(Lattice
Column)Construction, assembled good Steel material is hung to bracing members after both formed, then with large-scale suspender(Lattice column)It is upper
Side, then fixed being formed between assembled good large-scale assembling shape steel member and steel pile.
Another kind is first to carry out bracing members in the place of preparation installation(Lattice column)Construction, then set up the high-altitudes Man Tang
Supporting rack, and the scattered spelling of large-scale assembling shape steel member is carried out above it.
The defect of the first construction method is above:Hyperboloid of revolution rack entirety upper air installing, to hanging device requirement
Especially high, security risk is big, and cost is high, and working at height difficulty is big.
And the defect of second of construction method is:Not only assembly, welding job amount be big, site machinery equipment is difficult full
Sufficient lifting requirements, and required high-altitude spelling moulding bed is difficult to set up, and there are prodigious safety, quality risks.The difficulty of construction is big,
It is unfavorable for the field erected safety, quality of steel construction and the control of duration.
Invention content
Purpose of the present invention is to be directed to disadvantages described above existing for existing construction technology, a kind of material saving, labour-saving high-altitude are proposed
The construction technology of large size assembling shape steel member.
The present invention includes the following steps:
1)Interim full framing is set up on ground, completes the assembling of large-scale assembling shape steel member upper body structure;
2)Installation several groups promote pylon temporarily, promote the armored concrete that pylon is fixed on vertical bracing members by embedded iron parts
On the basis of, fixed lifter is distributed on each group lifting bracket;
3) the vertical bracing members of first section of the assembled large-scale groups steel loading component in pylon periphery are promoted temporarily in each group, and in first section vertical steel
The lower mouth installation of support promotes lifting bindiny mechanism temporarily, passes through bottom between fixed lifter and interim promotion lifting bindiny mechanism
Anchor is connected with steel strand wires;By hydraulic synchronizing lifting system, promotion is synchronized to the vertical bracing members of each first section;
4)The vertical bracing members of secondary segment of the assembled large-scale groups steel loading component in pylon periphery are promoted temporarily in each group, by each secondary segment vertical steel
Support form stable connection with the vertical bracing members of corresponding first section after, by under the vertical bracing members of first section mouth temporarily carry
Hanging load connection mechanism releases, and will promote lifting bindiny mechanism temporarily and be mounted on mouth under the vertical bracing members of secondary segment, then passes through liquid
Synchronization lifting system is pressed, promotion is synchronized to the vertical bracing members of secondary first section;
5)Step 4 is repeated)Operation, until steel member to be promoted to the height of design;
6)Most next section of bracing members are formed a fixed connection with ground;
7)Remove temporary towers, lifting bracket and lifter.
The present invention carries out the assembling of steel member on ground, considerably reduces assembling lifting time of steel member, power consumption, again
The input of type hanging device.Large-scale assembling shape steel member upper body structure of the invention(More than 700 tons, are not required to vertical wind excitation
Carry out steel member structural checking computation under the conditions of the various load cases combinations participated in)First according to building site locality maximum horizontal wind load, use
South Korea's Midas's finite element software carries out each operating mode sequential construction analysis under horizontal wind-force, cannot meet each working condition to part
The rod piece of lower structure safety requirements is replaced, and is changed section wall thickness into and is increased rod piece, is finally pressed checking computation results and is deepened drawing, on ground
Interim full framing is set up in face, and large-scale assembling shape steel member upper body structure is completed by in-depth drawing(Hyperboloid of revolution rack)
Assembling, by bracing members(Lattice column)Segmentation establish, first make most the preceding paragraph, make again multiple interludes, finally make it is most lower
One section, by establishing lifter on lifting bracket, using lifting bracket as each section of bracing members(Lattice column)Climbing frame, will be segmented
Bracing members(Lattice column)It above carries one by one, waits for most next section of bracing members(Lattice column)When the bottom of section is located on ground completely,
I.e. mutual sequentially connected each bracing members(Lattice column)Section has reached entire bracing members(Lattice column)Design height.The present invention
By bracing members(Lattice column)Segmentation is established, by bracing members(Lattice column)Segmentation accumulation promoted, realize to upper square steel structure
The lifting of part lifts large-scale, the great steel member of weight without using other heavy lifting equipments, and the present invention drops significantly
Low installation difficulty, has great advantage for quality, safety, duration and construction cost control etc..
In addition, due to the steel member that high-altitude large size assembles shape steel member bracing members that are very big at a distance from ground, therefore designing
(Lattice column)It is high, such as only lean on bracing members(Lattice column)Steel member is supported, in the more severe area of weather, as wind,
The stability of lattice column cannot be ensured under the conditions of rain, snow etc., therefore in step 6)Implementation process in, also simultaneously each perpendicular
To bracing members(Lattice column)Between establish waist truss and sub-truss, to reinforce each vertical bracing members(Lattice column)Between company
Connect stability.
Large-scale assembling shape steel member upper body structure of the invention(More than 700 tons are not required to participate in vertical wind excitation various
Carry out steel member structural checking computation under the conditions of load cases combination)First according to building site locality maximum horizontal wind load, carry out under horizontal wind-force
Each operating mode sequential construction analysis, the rod piece that each working condition lower structure safety requirements cannot be met to part are replaced, change into
Section wall thickness increases rod piece, finally presses checking computation results and deepens drawing.Then interim full framing is set up on ground again, by in-depth figure
Paper completes large-scale assembling shape steel member upper body structure(Hyperboloid of revolution rack)Assembling.
Description of the drawings
Fig. 1 is the final structure schematic diagram after the completion of present invention construction.
Fig. 2~4 are work progress figure.
Specific implementation mode
Below in the tower 50,000 kilowatts of photo-thermal power generations module secondary reflection tower structural steelwork of somewhere fused salt further
Illustrate the present invention.
One, engine request:
As shown in Figure 1, the reflection tower steel construction of design is by the secondary reflection structure 1 positioned at top and three groups of lattices positioned at bottom
Column 2 forms, need to also be in waist truss 3, the sub-truss 4 between three groups of lattice columns 2.
Wherein, secondary reflection structure is the above-mentioned steel member of the present invention, by square pyramid space grid and minute surface time structure group
At.Secondary reflection tower structure main body is steel construction, and superstructure is hyperboloid of revolution rack, is supported by three lattice columns, hyperbolic
It is 33.316m, peak 75.711m, minimum point 64.651m, separately in 34.5m and 17.25m that facial plane, which projects maximum radius,
Place sets twice sub-truss.
Top of tower secondary reflection structure is reflected, by bolt-ball net frame and minute surface time structure composition.
Two, detail design thinking:
The maximum installed height mark of hyperboloid of revolution rack is+75.711m, according to bulk-breaking high altitude bulk, not only assembly, weldering
Connect heavy workload, site machinery equipment is difficult to meet lifting requirements, and required high-altitude spelling moulding bed is difficult to set up, exist very big
Safety, quality risk.The difficulty of construction is big, is unfavorable for the field erected safety, quality of steel construction and the control of duration.
Therefore the present invention is installed using the mode of the present invention of " ground assembling, accumulation fliping lifting ", promotes total weight about
726 tons, hoisting depth about 65m.
Hyperboloid of revolution rack is assemblied into entirety on the ground immediately below its perspective plane, while being arranged using temporary towers
Promote platform(Upper suspension centre), interim bracket is set with upper suspension centre corresponding position on the rod piece of hyperboloid of revolution rack lattice column
Installation promotes interim suspender(Lower suspension centre), connected with special steel strand wires by special bottom anchor between upper and lower suspension centre.Utilize hydraulic synchronization
Lifting system carries out segmentation accumulation to lattice column and is promoted, and completes installation.
The present invention will substantially reduce installation difficulty, advantageous in quality, safety, duration and construction cost control etc..
Three, construction procedure:
1, hyperboloid of revolution rack is from great(More than 700 tons are not required under the conditions of the various load cases combinations participated in vertical wind excitation
Structural checking computation is carried out, according to building site locality maximum horizontal wind load, is carried out under horizontal wind-force using South Korea's Midas's finite element software
Each operating mode sequential construction analysis, the rod piece that each working condition lower structure safety requirements cannot be met to part are replaced, change into
Section wall thickness increases rod piece, finally presses checking computation results and deepens drawing.
2, interim full framing is set up on ground, hyperboloid of revolution rack secondary reflection structure is completed by in-depth drawing(Rotation
Turn hyperboloid rack)Installation site perspective plane immediately below interim full framing on assembled square pyramid space grid and minute surface
Secondary structure organizes the integral secondary reflection structure promoted, and the bottommost of the secondary reflection structure of formation is away from ground 1255mm.
3, using temporary support pylon, with three groups of lifting brackets 5 of center symmetric setting of secondary reflection structure, and each
Two groups of lifting devices 6 radially are installed respectively on lifting bracket.
Hydraulic synchronizing lifting system equipment, including hydraulic pump source system, lifter, biography are installed in each group lifting device 6
Sensor etc..
4, the first section lattice column 2-1 that height is 4.9m, every section of lattice are established correspondingly three groups of 5 peripheries of lifting bracket
Column 2-1 should be coaxial with the position for the group entirety lattice column 2 that the high-altitude large size of design assembles shape steel member.
And be welded with secondary reflection structure bracket 7 in the upper ends first section lattice column 2-1, then by three groups of brackets 7 respectively with it is corresponding
Secondary reflection structure 1 form fixed welding.
The results are shown in Figure 2 for formation.
5, lifting rope connector is installed in the lower end of lattice column 2-1, and by lifting rope one end of lifter and the lifting rope connector
It is connected firmly.
According to the 20% of design load, 40%, 60%, 70%, 80%, 90%, 95%, 100% sequence multistage loadings, until passing through
Lifter also has gone up each first section lattice column 2-1 Synchronous liftings to the upper end of lifting bracket 5, at this time secondary reflection structure 1
4.9m。
1 lower part of secondary reflection structure is padded with sleeper etc., pause is promoted, then is finely tuned each of secondary reflection structure 1 and hung
The absolute altitude of point is at level, and stands 4~12 hours.
6, second segment lattice are coaxially established one by one in the lower section of three sections of each first section lattice column 2-1 again in 5 periphery of lifting bracket
The length of structure column 2-2, second segment lattice column 2-2 are 10350mm, and by second segment lattice column 2-2 and corresponding first section lattice column
2-1 welds to form stable connection.
In addition, also lifting rope connector need to be installed in the lower end of each second segment lattice column 2-2.
The results are shown in Figure 3.
7, after separating the lower end of the lifting rope of lifter and lattice column 2-1, lifting rope is made to be resetted in lifter, then will be promoted
Lifting rope one end of device and the lifting rope connector of second segment lattice column 2-2 are connected firmly.
Then by lifter by second segment lattice column 2-2 Synchronous liftings to the upper end of lifting bracket 5.
8, check again for secondary reflection structure 1 and hydraulic synchronizing lifting interim measure have it is without exception.Confirmation is no different reason
After condition, step 7 is repeated, passes sequentially through and establishes the third section lattice column 2-3 that length is 10350mm, the 4th that length is 3450mm
Section lattice column 2-4, the 5th section of lattice column 2-5 that length is 10350mm, the 6th section of lattice column 2-6, the length that length is 10350mm
The 7th section of lattice column 2-7 that degree is 10350mm and the 8th section of lattice column 2-8 that length is 7979mm is promoted with segmentation accumulation
Mode, until secondary reflection structure 1 reaches designed elevation.
Then most lower 8th section of lattice column 2-8 is formed a fixed connection with ground.
Step 8 therebetween, it is also necessary to waist truss 3 and sub-truss 4 are established between three groups of steel piles 2.
As a result see Fig. 4.
9, after entire Practical Completion and test reach design requirement, temporary towers, lifting bracket and lifter is removed, is torn open
Except hydraulic lifting device.
Claims (3)
1. a kind of construction technology of high-altitude large size assembling shape steel member, it is characterised in that include the following steps:
1)Interim full framing is set up on ground, completes the assembling of large-scale assembling shape steel member upper body structure;
2)Installation several groups promote pylon temporarily, promote the armored concrete that pylon is fixed on vertical bracing members by embedded iron parts
On the basis of, fixed lifter is distributed on each group lifting bracket;
3) the vertical bracing members of first section of the assembled large-scale groups steel loading component in pylon periphery are promoted temporarily in each group, and in first section vertical steel
The lower mouth installation of support promotes lifting bindiny mechanism temporarily, passes through bottom between fixed lifter and interim promotion lifting bindiny mechanism
Anchor is connected with steel strand wires;By hydraulic synchronizing lifting system, promotion is synchronized to the vertical bracing members of each first section;
4)The vertical bracing members of secondary segment of the assembled large-scale groups steel loading component in pylon periphery are promoted temporarily in each group, by each secondary segment vertical steel
Support form stable connection with the vertical bracing members of corresponding first section after, by under the vertical bracing members of first section mouth temporarily carry
Hanging load connection mechanism releases, and will promote lifting bindiny mechanism temporarily and be mounted on mouth under the vertical bracing members of secondary segment, then passes through liquid
Synchronization lifting system is pressed, promotion is synchronized to the vertical bracing members of secondary first section;
5)Step 4 is repeated)Operation, until steel member to be promoted to the height of design;
6)Most next section of bracing members are formed a fixed connection with ground;
7)Remove temporary towers, lifting bracket and lifter.
2. the construction technology of high-altitude large size assembling shape steel member according to claim 1, it is characterised in that in step 5)In,
Waist truss and sub-truss are established between each vertical bracing members.
3. the construction technology of high-altitude large size assembling shape steel member according to claim 1 or 2, it is characterised in that in step 1)
Before, each operating mode sequential construction analysis under horizontal wind-force is first carried out according to the maximum horizontal wind load of construction site, to that cannot meet
The large-scale assembling shape steel member upper body structural member of each working condition lower structure safety requirements is replaced, and changes cross-sectional wall into
Thickness increases rod piece, finally presses checking computation results and deepens drawing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810536371.XA CN108756437A (en) | 2018-05-30 | 2018-05-30 | A kind of construction technology of high-altitude large size assembling shape steel member |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810536371.XA CN108756437A (en) | 2018-05-30 | 2018-05-30 | A kind of construction technology of high-altitude large size assembling shape steel member |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108756437A true CN108756437A (en) | 2018-11-06 |
Family
ID=64003986
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810536371.XA Pending CN108756437A (en) | 2018-05-30 | 2018-05-30 | A kind of construction technology of high-altitude large size assembling shape steel member |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108756437A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110566029A (en) * | 2019-08-26 | 2019-12-13 | 常州第一建筑集团有限公司 | gradual installation and construction method for high-rise steel tower |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101858162A (en) * | 2010-04-02 | 2010-10-13 | 攀钢集团冶金工程技术有限公司 | Inversion construction method of emission tower |
CN102877547A (en) * | 2012-10-16 | 2013-01-16 | 北京市机械施工有限公司 | Steel net rack installation method for integrally improving high-altitude moving and positioning |
CN103790234A (en) * | 2014-01-03 | 2014-05-14 | 永升建设集团有限公司 | Large-span truss hydraulic multi-point synchronous lifting construction method |
CN104213714A (en) * | 2014-08-27 | 2014-12-17 | 中国建筑第二工程局有限公司 | Lifting point reinforcing structure of ultra-large roof truss and lifting construction method |
CN104662290A (en) * | 2012-10-16 | 2015-05-27 | 马克斯·博格风能股份公司 | Supply frame for a tower, tower with a supply frame and method for erecting a supply frame in the interior of a tower |
WO2017007338A1 (en) * | 2015-07-07 | 2017-01-12 | Kcc Power System As | Method of elevating a section of a derrick, related lowering, and apparatus |
CN106812328A (en) * | 2015-11-27 | 2017-06-09 | 天津三建建筑工程有限公司 | The overall two step lifting construction methods of a string prestressed steel structure rack with hanging layer |
CN107012949A (en) * | 2017-05-10 | 2017-08-04 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
CN107989380A (en) * | 2016-10-27 | 2018-05-04 | 中交三航局第三工程有限公司 | Steel truss gallery hydraulic synchronizing lifting construction technique |
-
2018
- 2018-05-30 CN CN201810536371.XA patent/CN108756437A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101858162A (en) * | 2010-04-02 | 2010-10-13 | 攀钢集团冶金工程技术有限公司 | Inversion construction method of emission tower |
CN102877547A (en) * | 2012-10-16 | 2013-01-16 | 北京市机械施工有限公司 | Steel net rack installation method for integrally improving high-altitude moving and positioning |
CN104662290A (en) * | 2012-10-16 | 2015-05-27 | 马克斯·博格风能股份公司 | Supply frame for a tower, tower with a supply frame and method for erecting a supply frame in the interior of a tower |
CN103790234A (en) * | 2014-01-03 | 2014-05-14 | 永升建设集团有限公司 | Large-span truss hydraulic multi-point synchronous lifting construction method |
CN104213714A (en) * | 2014-08-27 | 2014-12-17 | 中国建筑第二工程局有限公司 | Lifting point reinforcing structure of ultra-large roof truss and lifting construction method |
WO2017007338A1 (en) * | 2015-07-07 | 2017-01-12 | Kcc Power System As | Method of elevating a section of a derrick, related lowering, and apparatus |
CN106812328A (en) * | 2015-11-27 | 2017-06-09 | 天津三建建筑工程有限公司 | The overall two step lifting construction methods of a string prestressed steel structure rack with hanging layer |
CN107989380A (en) * | 2016-10-27 | 2018-05-04 | 中交三航局第三工程有限公司 | Steel truss gallery hydraulic synchronizing lifting construction technique |
CN107012949A (en) * | 2017-05-10 | 2017-08-04 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110566029A (en) * | 2019-08-26 | 2019-12-13 | 常州第一建筑集团有限公司 | gradual installation and construction method for high-rise steel tower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929373B (en) | Large span Square Steel Tubes Truss and its accumulation slippage construction method | |
CN104947942B (en) | Hypervelocity arch grid structure architecture computer controls the installation method extending out accumulation lifting | |
CN201495027U (en) | Hoisting tool for mill housing | |
CN106087752B (en) | Multispan cable-carried arch bridge construction method | |
CN102797643B (en) | A kind of wind power generation tower device | |
CN109184189B (en) | Construction method for conical shell silo top structure of large-diameter silo | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN103643800A (en) | Lifting installation system for buckling restrained supporting member and construction method thereof | |
CN106812328A (en) | The overall two step lifting construction methods of a string prestressed steel structure rack with hanging layer | |
CN109138454A (en) | A kind of installation method of super high-rise building outline border bandy truss | |
CN102535939B (en) | Inversely assembling process for standing stay wire V-type tower | |
CN105484502A (en) | Combination installation method for steel structure roofing purlins and support bars of industrial factory building | |
CN104060836B (en) | The lifting installation method of high curved surface rack | |
CN203394685U (en) | Lattice wind turbine tower and wind turbine generator system comprising same | |
CN107642225A (en) | A kind of hanging scaffold and its assembly and method for dismounting | |
CN206308988U (en) | Tool-type combination construction pylon | |
CN106544959B (en) | The construction method of king-tower lifting segment and bridge main tower saddle containing saddle | |
CN106193284B (en) | The installation method and mounting structure of large span space drop level continuous truss frame | |
CN108756437A (en) | A kind of construction technology of high-altitude large size assembling shape steel member | |
CN202658867U (en) | Overhanging construction platform | |
CN206562827U (en) | A kind of modularization steel-frame structure for tower equipment | |
CN211312514U (en) | Movable ground anchor device for mounting conical section of steel structure cooling tower | |
CN206298286U (en) | A kind of wet electrical dust precipitator body equipment integral hoisting aids in hanging beam | |
CN219296959U (en) | Building construction platform of unloading | |
CN204126297U (en) | A kind of temporary support of steel truss roof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181106 |