CN108729445A - The method for abolishing the drill bit of waste and old solid pile and abolishing old solid pile and new pile being perfused - Google Patents

The method for abolishing the drill bit of waste and old solid pile and abolishing old solid pile and new pile being perfused Download PDF

Info

Publication number
CN108729445A
CN108729445A CN201810916598.7A CN201810916598A CN108729445A CN 108729445 A CN108729445 A CN 108729445A CN 201810916598 A CN201810916598 A CN 201810916598A CN 108729445 A CN108729445 A CN 108729445A
Authority
CN
China
Prior art keywords
scraper plate
pile
baffle ring
drill bit
solid pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810916598.7A
Other languages
Chinese (zh)
Other versions
CN108729445B (en
Inventor
樊敬亮
沈远志
黄海达
赖丰瑜
李帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Junhao Geotechnical Engineering Co ltd
Original Assignee
In Empapk Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Empapk Construction Engineering Co Ltd filed Critical In Empapk Construction Engineering Co Ltd
Priority to CN201810916598.7A priority Critical patent/CN108729445B/en
Publication of CN108729445A publication Critical patent/CN108729445A/en
Application granted granted Critical
Publication of CN108729445B publication Critical patent/CN108729445B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B10/00Drill bits
    • E21B10/42Rotary drag type drill bits with teeth, blades or like cutting elements, e.g. fork-type bits, fish tail bits
    • E21B10/43Rotary drag type drill bits with teeth, blades or like cutting elements, e.g. fork-type bits, fish tail bits characterised by the arrangement of teeth or other cutting elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A kind of method abolished waste and old solid pile the invention discloses drill bit for abolishing waste and old solid pile and using the drill bit of the present invention and new pile is perfused, the drill bit includes mandrel and baffle ring, multiple first scraper plates and the second scraper plate are equipped between mandrel and baffle ring, the inner end of above two scraper plate is connect with mandrel and outer end is connect with baffle ring;The bottom of every piece of scraper plate is equipped with outer low and inner high bottom bevel edge, and the bottom bevel edge of the first scraper plate is equipped with multiple cutter teeths, and the bottom bevel edge of the second scraper plate is equipped with multiple picks;The key of this method is:Old stake is abolished be combined into one with two steps of new pile pore-forming, it is synchronous carry out, solid pile is crushed using cutter teeth and pick.The drill bit and method can effectively be crushed solid pile and efficiency is fast, at low cost.

Description

The method for abolishing the drill bit of waste and old solid pile and abolishing old solid pile and new pile being perfused
Technical field
It is especially a kind of drill bit that abolishing waste and old solid pile and utilization the present invention relates to construction foundation working technical field The method that the drill bit abolishes waste and old solid pile and new pile is perfused.
Background technology
In engineering construction, it is often necessary to by the short demolishing buildings broken always, then build higher more in old place The problem of new building, this relates into place the dismounting of waste and old stake and new pile pouring construction.And what the application was directed to, it is Waste and old solid pile is abolished, and certainly, solid pile here should make the understanding of broad sense, it include cast-in-situ bored pile, CFG, it is real Heart prefabricated pile etc..
The process for abolishing construction of the waste and old stake of the prior art is:It will be useless on ground using the pile-drawing machine with pile pulling casing Old pile pile is extracted, and is then carried out reaming to remaining stake holes after pile pulling and is deepened, forms it into the deeper stake holes of bigger, then carry out Borehole cleaning, is put into steel reinforcement cage, and concrete perfusion is allowed to form new cast-in-situ bored pile.In this way, by the small pile pile of old, bearing capacity It extracts, perfusion is good new, stake diameter bigger, deeper, the stronger cast-in-situ bored pile of bearing capacity.
But there are a huge limitation, the i.e. prior arts to be only capable of processing pile pile for the scheme of the waste and old stake transformation of the prior art, Solid concrete-pile is when it come to arrived, then existing technical solution is helpless, this also constitutes skill in a puzzlement industry The technical barrier of art personnel for many years.And it is even directed to pile pile, there is also more defects for the scheme of the prior art, such as pile-drawing machine The limited length of pile pulling casing is usually no more than 20 meters, therefore can only extract the pile pile within 20 meters of depth;Moreover, to work order For position, it is also a no small cost to be specially equipped with a set of pile pulling device, if purchasing, utilization rate is not low cost-effective, if renting, Its rent is again very high, but also must be born by the expense of equipment transition, therefore deficiency in economic performance, and equipment transition is time-consuming and laborious, very It is difficult be sent in time thus schedule delays;Moreover it is that substep carries out that the process that bigger deeper drills is pulled out and drilled through in above-mentioned old stake , therefore construction efficiency is not high.
Invention content
The invention solves a technical problem be to provide and a kind of can effectively be crushed solid pile and efficiency is fast, at low cost The drill bit for abolishing waste and old solid pile.
The present invention a technical solution be to provide a kind of drill bit for abolishing waste and old solid pile, it include mandrel and Baffle ring, the interconnecting piece for being docked with auger stem is equipped at the top of mandrel, be equipped between mandrel and baffle ring multiple first scraper plates and The inner end of second scraper plate, above two scraper plate is connect with mandrel and outer end is connect with baffle ring;The bottom of every piece of scraper plate is equipped with outer low The bottom bevel edge of interior high bottom bevel edge, the first scraper plate is equipped with multiple cutter teeths, and the bottom bevel edge of the second scraper plate is equipped with multiple picks, baffle ring Internal diameter be more than and be intended to the outer diameter of broken solid pile, protrusion baffle ring base ring face under a cutter teeth of the first scraper plate bottommost.
The present invention abolishes the drill bit of waste and old solid pile compared with prior art, has the following advantages and effect:
Before lower brill, the shield ring sleeve of drill bit is being intended at the top of broken solid pile, plays preliminary position-limiting action, when lower brill, cutter teeth It can be fast and effeciently crushed solid pile concrete, and grind the reinforcing bar on solid pile cages, the levigate mill length of reinforcing bar is made it easily It is disconnected in hinge, and pick can further be crushed solid pile concrete, and the reinforcing bar that breaks is cut with scissors, while pick can hook and enwind disconnected steel Muscle takes it out drilling;Moreover, seeing on the whole, the low inside and high outside scraper plate of polylith together constitutes the cutting face of taper, under During brill, solid pile is cut into pyramidal structure, in this way, being bored under playing stable guiding, ensuring vertically, preventing drilling rod from deviating Effect;To sum up, the drill bit solves the technical barrier perplexed always in industry for many years, that is, realizes the broken removing of solid pile. Moreover two steps of old stake removing and new pile pore-forming are combined into one by drill bit of the invention, synchronous progress, accelerate construction effect Rate;And the depth of old stake removing is no longer influenced by the constraint of the pile pulling casing of pile-drawing machine, lower as needed can bore different depth, with Remove the waste and old solid pile that depth is more than 20 meters;It is combined with drill bit moreover, equipment is removed in above-mentioned old stake, so there is no need to Be further provided with dedicated pile pulling device, reduce cost of carry, lease expenses and the transition expense of pile pulling device, and with with It takes, without waiting for special pile pulling device transition as the prior art, therefore avoids delay the duration;Moreover it is equipped with pick and tooth The bit cuttings of the gear teeth is efficient, pile-forming effect is good, thicker deeper, moreover it is possible to enter rock, so that new pile bearing capacity is strong, meet modern Change the demand of high building.Certainly, this drill bit can be according to the stake diameter size of waste and old solid pile, to use different size of drill bit specification It constructs.
Preferably, the bottom bevel edge of the first scraper plate is less than the bottom bevel edge of the second scraper plate, in this way, the cutter teeth on the first scraper plate Solid pile body can be contacted one step ahead, play the role of main breaking concrete and grinding reinforcing bar, reinforcing bar is ground and is deformed, reinforcing bar is made Become elongated to be easy to be broken, and the pick on the second scraper plate can lag the solid pile body of certain time contact, and it is mixed to play addi-tional crusher The effect of soil and the disconnected reinforcing bar of hinge is coagulated, therefore the time difference of cutter teeth and pick makes the broken pile process of the drill bit have more stereovision, and Cutter teeth first grinds deformation, then is broken by pick hinge and hook winding, and two kinds are bored teeth and cooperated, reasonable design.
As further preferred, mandrel is rotatably sheathed with outer tube, and the first scraper plate inner end is fixed with outer tube, and first scrapes Plate outer end is fixed with baffle ring;Housing tube wall be equipped with the one-to-one p-shaped through-hole of the second scraper plate, p-shaped through-hole is by top The straight hole of reaming and lower part is constituted lateral out, and the height of reaming matches with the height of the second scraper plate inner end lateral out, and straight hole is wide Degree matches with the width of the second scraper plate inner end;Baffle ring inner peripheral surface is equipped with and the one-to-one p-shaped limiting slot of the second scraper plate, P The straight trough that shape limiting slot is extended out slot and lower part by the transverse direction on top is constituted, and laterally extends out the height of the height and the second scraper plate outer end of slot Degree matches, and straight trough width matches with the width of the second scraper plate outer end;Every piece of second scraper plate passes through corresponding p-shaped through-hole, the The inner end of two scraper plates is fixed with mandrel, and the outer end of the second scraper plate is caught in corresponding p-shaped limiting slot.
The operating principle of above structure is, when lower brill, the second scraper plate both ends are stuck in reaming lateral out and laterally extend out In slot, the second scraper plate and pick are in position relatively high in baffle ring, in this way, in the height in space between pick and cutter teeth The time difference of poor and lower brill so that cutter teeth first contacts significantly breaking concrete with pile body and is ground in advance to reinforcing bar, It plays the cutter teeth broken rock intensity obviously advantage bigger than pick, then is followed up by pick and breaking concrete and cut with scissors disconnected be ground Elongated reinforcing bar;After getting into certain depth under and, core pipe is reversely rotated so that the second scraper plate is inverted to above straight hole and straight trough, In this way, after being detached from reaming lateral out and laterally extending out slot limitation, core pipe can drive the second scraper plate that can decline, and make the second scraper plate both ends Straight hole and straight trough bottom are dropped to, i.e., so that the second scraper plate and pick are in position relatively low in baffle ring, convenient for above carrying drill bit When pick winding as much as possible hook broken reinforcing bar, i.e., so that broken reinforcing bar is maximumlly carried out brill by pick Hole;And after drill bit is by upper extraction ground, during the reinforcing bar wound on cutting away pick, the second scraper plate is located at again The upper end of straight hole and straight trough, at this point, worker easily can reset baffle ring by manual rotation in hell so that the second scraper plate both ends Again it is caught in reaming lateral out and laterally extends out in slot, convenient for repeating lower to bore, reversion, above carry.
As still more preferably, baffle ring is equipped with multiple cushion blocks, and cushion block lower part is equipped with crimping, and cushion block top is equipped with bolt Hole, the crimping of cushion block are hooked with baffle ring, and cushion block top is spirally connected with baffle ring, in this way, removable outside baffle ring be mounted with multiple pads Block avoids baffle ring from crossing quick-wearing for protecting baffle ring, moreover, above-mentioned cushion block dismounting is efficient and convenient, it is only necessary to catch on lower part Upper part is spirally connected can be achieved with the Fast Installation of cushion block again by crimping, in this way, after old pad wear, convenient and efficient can more renew Cushion block.
The invention solves another technical problem be to provide and a kind of can effectively be crushed that solid pile and efficiency is fast, cost The low method abolished waste and old solid pile using drill bit of the invention and new pile is perfused.
The technical solution of the present invention, which is to provide, a kind of to be abolished waste and old solid pile using drill bit and new pile is perfused Method, step includes:
It is first intended to the broken solid pile top perimeter soil body to remove to expose stake top, driving drill bit declines so that drill bit Baffle ring entangles solid pile stake top tentatively to limit;Under original state, the second scraper plate inner end is located in the reaming lateral out of p-shaped through-hole And the transverse direction that outer end is located at p-shaped limiting slot extends out in slot, at this point, the second scraper plate and pick are located at a baffle ring high position;
Driving drilling rod is drilled down into, and since the pick of the second scraper plate is located at a baffle ring high position, therefore the cutter teeth of the first scraper plate is first The concrete of pile body, the reinforcing bar on the solid pile cages of simultaneous grinding are contacted and be crushed with solid pile, and are located at a baffle ring high position Second scraper plate and pick, which then follow up, is crushed solid pile concrete, while the reinforcing bar of the disconnected steel reinforcement cage of pick hinge, and will be taken off from steel reinforcement cage From reinforcing bar wind hook;During drill bit is crept into, boring mud is upward through the gap between scraper plate, by the helical blade band of drilling rod Go out ground;
After lower brill certain depth, drilling rod and mandrel are reversely rotated so that the second scraper plate inner end is extended out from the transverse direction of p-shaped through-hole Hole rotates to above straight hole presses to straight hole bottom end again, while the second scraper plate inner end being made to extend out slot from the transverse direction of p-shaped limiting slot Rotate to above straight trough and press to the bottom end of straight trough again so that the second scraper plate and pick drop to baffle ring low level, then after It is continuous to reversely rotate several circles, to ensure that pick hooks the reinforcing bar being more broken;
Hell will be proposed on drill bit again, during above carrying, the second scraper plate both ends can rise to the upper end of straight hole and straight trough, Then the reinforcing bar being wrapped on drill bit pick is cut away with autogenous cutting, and rotates baffle ring so that the both ends of the second scraper plate are caught in again Reaming is extended out with lateral in slot lateral out;
Get into certain depth under continuing, then reversely rotate, make pick that low level be kept to hook reinforcing bar, then on pull out cleaning, and answer Position baffle ring, and so on, until waste and old solid pile is fully erased, then proceed to down the projected depth for getting into new pile;At this point, old Stake is removed and new pile pore-forming is completed;
Borehole cleaning sinks to steel reinforcement cage and pours new pile concrete.
After above step, the method for the present invention has the following advantages:Casing can entangle solid stake top, preliminary to be oriented to, When drilling, each tapered cutting face of spoke type scraper plate group, broken solid pile continues to provide stable guiding simultaneously, ensures vertical Lower brill;Successively contact and breaking concrete, stereovision are strong, efficient, broken thorough for cutter teeth and pick when lower brill;Energy when above carrying Pick is reduced, it is made fully to hook reinforcing bar, bottom hole reinforcing bar remnants is reduced to greatest extent, improves follow-up pile quality;It is synchronous to carry out Waste and old solid pile is crushed and new pile pore-forming, further speeds up construction efficiency;Waste and old solid pile grinding depth is unrestricted, grinding depth More than 20 meters;Without special pile pulling device, cost is saved;New stake holes is thicker deeper, and bearing capacity is stronger.
Description of the drawings
Positive schematic cross-sectional view when Fig. 1 is the pick low level for the drill bit that the present invention abolishes waste and old solid pile.
Positive schematic cross-sectional view when Fig. 2 is a pick high position for the drill bit that the present invention abolishes waste and old solid pile.
Fig. 3 is the structural schematic diagram for the drill bit that the present invention abolishes waste and old solid pile.
Fig. 4 is the structural schematic diagram of the mandrel for the drill bit that the present invention abolishes waste and old solid pile, interconnecting piece and the second scraper plate.
Fig. 5 is the configuration schematic diagram for the drill bit that the present invention abolishes waste and old solid pile.
As shown in the figure 1, mandrel, 2, baffle ring, 3, interconnecting piece, the 4, first scraper plate, the 5, second scraper plate, 6, bolt hole, 7, bottom it is oblique Side, 8, cutter teeth, 9, pick, 10, outer tube, 11, p-shaped through-hole, 11.1, reaming lateral out, 11.2, straight hole, 12, p-shaped limit Slot, 12.1, laterally extend out slot, 12.2, straight trough, 13, cushion block, 14, crimping.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
As shown in figure 1, figure 2, figure 3, figure 4 and figure 5, the present invention abolishes the drill bit of waste and old solid pile, it includes mandrel 1 and gear Circle 2,1 top of mandrel are equipped with the interconnecting piece 3 for being docked with auger stem.
4 and second scraper plate 5 of multiple first scraper plates, 4 He of the first scraper plate in the present embodiment are equipped between mandrel 1 and baffle ring 2 Second scraper plate 5 is three pieces.The first above-mentioned scraper plate 4 and the second scraper plate 5 are spaced laying and the equal spoke type of each scraper plate is circumferentially equal Even distribution.
The bottom of every piece of scraper plate is equipped with outer low and inner high bottom bevel edge 7, the bottom bevel edge 7 of the first scraper plate 4 is rotatably mounted have it is more The bottom bevel edge 7 of a cutter teeth 8, the second scraper plate 5 is fixed with multiple picks 9.The internal diameter of baffle ring 2, which is more than, is intended to the outer of broken solid pile Diameter, 8 times 2 base ring faces of protrusion baffle ring of a cutter teeth of 4 bottommost of the first scraper plate.
The inner end of above two scraper plate is connect with mandrel 1 and outer end is connect with baffle ring 2.Above-mentioned connection type can be solid Fixed, i.e., the inner end of two kinds scraper plates is fixed with mandrel 1 and outer end is fixed with baffle ring 2.At this point, the bottom bevel edge 7 of the first scraper plate 4 is low In the bottom bevel edge 7 of the second scraper plate 5, be first crushed pile body convenient for cutter teeth 8 and pick 9 subsequently follow-up is broken.
The connection of scraper plate and mandrel 1 and baffle ring 2 can also use structure in detail below.
Mandrel 1 is rotatably sheathed with outer tube 10, and 4 inner end of the first scraper plate is fixed with outer tube 10,4 outer end of the first scraper plate with Baffle ring 2 is fixed;10 tube wall of outer tube is equipped with and three 5 one-to-one three p-shaped through-holes 11 of the second scraper plate, p-shaped through-hole 11 It is made of the straight hole 11.2 of the reaming lateral out 11.1 on top and lower part, lateral out in the height of reaming 11.1 and the second scraper plate 5 The height at end matches, i.e., the height of reaming 11.1 is greater than or equal to the height of 5 inner end of the second scraper plate lateral out, and straight hole 11.2 is wide Degree matches with the width of 5 inner end of the second scraper plate;I.e. 11.2 width of straight hole is greater than or equal to the width of 5 inner end of the second scraper plate.
2 inner peripheral surface of baffle ring be equipped with 5 one-to-one p-shaped limiting slot 12 of the second scraper plate, p-shaped limiting slot 12 is by top The straight trough 12.2 for laterally extending out slot 12.1 and lower part is constituted, and the height for laterally extending out slot 12.1 is greater than or equal to outside the second scraper plate 5 The height at end, 12.2 width of straight trough are greater than or equal to the width of 5 outer end of the second scraper plate.
Every piece of second scraper plate 5 passes through corresponding p-shaped through-hole 11, inner end and the mandrel 1 of the second scraper plate 5 to fix, the second scraper plate 5 Outer end be caught in corresponding p-shaped limiting slot 12.
Removable on baffle ring 2 to be connected with multiple cushion blocks 13, specifically, 13 lower part of cushion block is equipped with crimping 14, on cushion block 13 Portion is equipped with bolt hole 6, and crimping 14 and the baffle ring 2 of cushion block 13 hook, and 13 top of cushion block is spirally connected with baffle ring 2.
To make up the hypodynamic problem of 2 central cutting of baffle ring, one group of three tooth bringing together is secured in 1 bottom end of mandrel The gear teeth 8.Above three cutter teeth 8 also with mandrel 1 reversion or above carry and lift, i.e., normal lower when boring, above three gear wheel Tooth 8 is also located at a high position as pick 9, avoids the too low vertical lower brill for influencing drill bit in position.
Using the drill bit of the present invention come the method abolished waste and old solid pile and new pile is perfused, its step are as follows.
According to the size for the waste and old solid pile outer diameter that prospecting obtains, the drill bit of appropriate size is selected.
It is intended to the broken solid pile top perimeter soil body to remove to expose stake top, driving drill bit declines so that the gear of drill bit Circle 2 entangles solid stake top tentatively to limit;More specifically, being that three cutter teeths 8 of three 4 lowermost ends of the first scraper plate resist Tentatively to limit at the top of solid pile.
Under original state, 5 inner end of the second scraper plate is interior positioned at the reaming lateral out 11.1 of p-shaped through-hole 11 and outer end is located at p-shaped The transverse direction of limiting slot 12 extends out in slot 12.1, at this point, the second scraper plate 5 and pick 9 are located at relatively high position in baffle ring 2.
Driving drilling rod is drilled down into, since the pick 9 of the second scraper plate 5 is located at the high position of baffle ring 2, therefore the gear wheel of the first scraper plate 4 Tooth 8 first contacts with solid pile and is crushed the concrete of pile body, the reinforcing bar on the solid pile cages of simultaneous grinding, and is located at baffle ring 2 High-order the second scraper plate 5 and pick 9, which then follows up, continues to be crushed solid pile concrete, while the reinforcing bar of the disconnected steel reinforcement cage of the hinge of pick 9, and The reinforcing bar being detached from from steel reinforcement cage is wound and is hooked;That is, cutter teeth 8 first contacts simultaneously shatter most concrete and grinding steel Muscle, and 9 later stage of pick follows up, further breaking concrete and cut with scissors it is disconnected be ground deformed reinforcing bar, in this way so that boring mud powder It is broken more thorough, it is easy to be discharged.In drilling process, boring mud is upward through the gap between each adjacent scraper plate, then by the spiral shell of drilling rod Vane piece takes ground out of to be discharged.Certainly, synchronous to carry out mud off in drilling rod going down process.And when mud off, it can profit Add water with the mud in stratum and do not have to specially be further provided with mud, therefore can further reduce the cost.
Lower brill certain depth as it is lower bore 2 meters after, reversely rotate drilling rod and mandrel 1 so that 5 inner end of the second scraper plate is from P The reaming lateral out 11.1 of shape through-hole 11 rotates to 11.2 top of straight hole and presses to 11.2 bottom end of straight hole again, while so that second scrapes 5 inner end of plate from the transverse direction of p-shaped limiting slot 12 extends out slot 12.1 and rotates to above straight trough 12.2 presses to the bottom end of straight trough 12.2 again, So that the second scraper plate 5 and pick 9 drop to position relatively low in baffle ring 2, then proceed to reversely rotate several circles, to ensure Pick 9 hooks the reinforcing bar of fracture as much as possible.
Hell will be proposed on drill bit again, during above carrying, 5 both ends of the second scraper plate can rise to straight hole 11.2 and straight trough 12.2 upper end.Drill bit fishes for concrete block and reinforcing bar remaining in hole after being proposed in drilling, then with pawl bucket is rushed, meanwhile, work People cuts away the reinforcing bar being wrapped on bit prong 8 and pick 9, and spinning reduction baffle ring 2 in drilling external application autogenous cutting so that the The both ends of two scraper plates 5 are caught in reaming lateral out 11.1 and laterally extend out in slot 12.1 again.Certainly, the spinning reduction baffle ring 2 can be manual operation, can also be to set convex block in 2 excircle of baffle ring, and ground level is fixed with one section of spiral limit inclined-plane, Inclined-plane is met in 2 uphill process of baffle ring to hinder, it can only be along inclined-plane spiral, that is to say, that during being pulled out on drilling rod, Synchronously complete the spinning reduction of baffle ring 2.
Get into certain depth under continuing, then reversely rotate, make pick 9 that low level be kept to hook reinforcing bar, then on pull out cleaning, and answer Position baffle ring 2, and so on, until waste and old solid pile is fully erased, then proceed to down the projected depth for getting into new pile;At this point, Old stake removing and new pile pore-forming are completed.
Borehole cleaning sinks to steel reinforcement cage and pours new pile concrete.

Claims (5)

1. a kind of drill bit for abolishing waste and old solid pile, it includes mandrel (1) and baffle ring (2), is equipped with and is used for and spiral shell at the top of mandrel (1) The interconnecting piece (3) of rotary drill bar docking, it is characterised in that:Multiple first scraper plates (4) and the are equipped between mandrel (1) and baffle ring (2) The inner end of two scraper plates (5), above two scraper plate is connect with mandrel (1) and outer end is connect with baffle ring (2);The bottom of every piece of scraper plate is set There are outer low and inner high bottom bevel edge (7), the bottom bevel edge (7) of the first scraper plate (4) to be equipped with multiple cutter teeths (8), the bottom of the second scraper plate (5) Bevel edge (7) is equipped with multiple picks (9), and the internal diameter of baffle ring (2) is more than the outer diameter for being intended to broken solid pile, the first scraper plate (4) most bottom Baffle ring (2) base ring face is protruded under one cutter teeth (8) in portion.
2. the drill bit according to claim 1 for abolishing waste and old solid pile, it is characterised in that:The bottom bevel edge of first scraper plate (4) (7) it is less than the bottom bevel edge (7) of the second scraper plate (5).
3. the drill bit according to claim 1 for abolishing waste and old solid pile, it is characterised in that:Mandrel (1) is rotatably sheathed with Outer tube (10), the first scraper plate (4) inner end is fixed with outer tube (10), and the first scraper plate (4) outer end is fixed with baffle ring (2);Housing Manage (10) tube wall be equipped with the one-to-one p-shaped through-hole (11) of the second scraper plate (5), p-shaped through-hole (11) by top lateral out The straight hole (11.2) of reaming (11.1) and lower part is constituted, lateral out the height of the height of reaming (11.1) and the second scraper plate (5) inner end Degree matches, and straight hole (11.2) width matches with the width of the second scraper plate (5) inner end;
Baffle ring (2) inner peripheral surface be equipped with the one-to-one p-shaped limiting slot (12) of the second scraper plate (5), p-shaped limiting slot (12) is by upper The transverse direction in portion extends out slot (12.1) and the straight trough (12.2) of lower part is constituted, and laterally extends out the height and the second scraper plate of slot (12.1) (5) height of outer end matches, and straight trough (12.2) width matches with the width of the second scraper plate (5) outer end;
Every piece of second scraper plate (5) passes through corresponding p-shaped through-hole (11), and the inner end of the second scraper plate (5) and mandrel (1) are fixed, and second The outer end of scraper plate (5) is caught in corresponding p-shaped limiting slot (12).
4. the drill bit according to claim 3 for abolishing waste and old solid pile, it is characterised in that:Baffle ring (2) is equipped with multiple pads Block (13), cushion block (13) lower part are equipped with crimping (14), and cushion block (13) top is equipped with bolt hole (6), the crimping (14) of cushion block (13) It is hooked with baffle ring (2), cushion block (13) top is spirally connected with baffle ring (2).
5. the method abolished waste and old solid pile using the drill bit described in any one of Claims 1 to 44 and new pile is perfused, It is characterized in that:Its step includes:
It is first intended to the broken solid pile top perimeter soil body to remove to expose stake top, driving drill bit declines so that the baffle ring of drill bit (2) solid stake top is entangled tentatively to limit;Under original state, the second scraper plate (5) inner end is located at p-shaped through-hole (11) lateral out The transverse direction that in reaming (11.1) and outer end is located at p-shaped limiting slot (12) extends out in slot (12.1), at this point, the second scraper plate (5) and section Tooth (9) is located at baffle ring (2) high position;
Driving drilling rod is drilled down into, and since the pick (9) of the second scraper plate (5) is located at, baffle ring (2) is high-order, therefore the first scraper plate (4) Cutter teeth (8) first contacts with solid pile and is crushed the concrete of pile body, the reinforcing bar on the solid pile cages of simultaneous grinding, and is located at The second scraper plate (5) and pick (9) of baffle ring (2) high position, which then follow up, is crushed solid pile concrete, while the disconnected steel reinforcement cage of pick (9) hinge Reinforcing bar, and by the reinforcing bar being detached from from steel reinforcement cage wind hook;Drill bit creep into during, boring mud through the gap between scraper plate to On, ground is taken out of by the helical blade of drilling rod;
After lower brill certain depth, drilling rod and mandrel (1) are reversely rotated so that cross of the second scraper plate (5) inner end from p-shaped through-hole (11) Outside reaming (11.1) rotates to above straight hole (11.2) presses to straight hole (11.2) bottom end again, while making the second scraper plate (5) Inner end from the transverse direction of p-shaped limiting slot (12) extends out slot (12.1) and rotates to above straight trough (12.2) presses to straight trough (12.2) again Bottom end then proceedes to reversely rotate several circles, with true so that the second scraper plate (5) and pick (9) drop to baffle ring (2) low level It protects pick (9) and hooks the reinforcing bar being more broken;
Hell will be proposed on drill bit again, during above carrying, the second scraper plate (5) both ends can rise to straight hole (11.2) and straight trough (12.2) then the reinforcing bar being wrapped on drill bit pick (9) is cut away in upper end with autogenous cutting, and rotate baffle ring (2) so that second The both ends of scraper plate (5) are caught in reaming lateral out (11.1) and laterally extend out in slot (12.1) again;
Get into certain depth under continuing, then reversely rotate, make pick (9) that low level be kept to hook reinforcing bar, then on pull out cleaning, and reset Baffle ring (2), and so on, until waste and old solid pile is fully erased, then proceed to down the projected depth for getting into new pile;At this point, Old stake removing and new pile pore-forming are completed;
Borehole cleaning sinks to steel reinforcement cage and pours new pile concrete.
CN201810916598.7A 2018-08-13 2018-08-13 Drill bit for breaking waste solid piles and method for breaking old solid piles and filling new piles Active CN108729445B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810916598.7A CN108729445B (en) 2018-08-13 2018-08-13 Drill bit for breaking waste solid piles and method for breaking old solid piles and filling new piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810916598.7A CN108729445B (en) 2018-08-13 2018-08-13 Drill bit for breaking waste solid piles and method for breaking old solid piles and filling new piles

Publications (2)

Publication Number Publication Date
CN108729445A true CN108729445A (en) 2018-11-02
CN108729445B CN108729445B (en) 2023-12-19

Family

ID=63942709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810916598.7A Active CN108729445B (en) 2018-08-13 2018-08-13 Drill bit for breaking waste solid piles and method for breaking old solid piles and filling new piles

Country Status (1)

Country Link
CN (1) CN108729445B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952916A (en) * 2019-11-28 2020-04-03 武汉金瑞威基础工程有限公司 Construction method for crushing and dismantling deep part of old building pile foundation
CN111877344A (en) * 2020-06-24 2020-11-03 中煤江南建设发展有限公司 Old pipe pile breaking method
CN113897958A (en) * 2021-10-22 2022-01-07 中铁四局集团建筑工程有限公司 Precise cutting construction method for rotary digging pile
CN114352185A (en) * 2021-12-13 2022-04-15 广东君豪高科地下空间建设有限公司 Variable speed drill bit for underground space development field

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1073250A (en) * 1964-11-27 1967-06-21 Stitching Waterbouwkungdig Lab Cutter head for a soil sample cutter
US7198119B1 (en) * 2005-11-21 2007-04-03 Hall David R Hydraulic drill bit assembly
JP2007120123A (en) * 2005-10-27 2007-05-17 Nisshin Kizai Kk Pile extraction device
CA2597819A1 (en) * 2006-08-23 2008-02-23 Bauer Maschinen Gmbh Method and device for producing a borehole in the soil
US20080131211A1 (en) * 2004-07-13 2008-06-05 Nesmith Willie M Installation effort deep foudnation method
CN101324066A (en) * 2008-08-04 2008-12-17 大连大金马基础建设有限公司 Construction method drive type major diameter steel pipe pore-creating filling pile
JP2009052250A (en) * 2007-08-24 2009-03-12 Kimifusa Fukuyama Auger head and shredding equipment with the same
JP2010185188A (en) * 2009-02-10 2010-08-26 Hoei Sangyo Kk Drilling bucket
US8579548B1 (en) * 2013-05-07 2013-11-12 Harold F Schmidt Method of piling remediation
CN103573188A (en) * 2013-11-12 2014-02-12 中铁十局集团有限公司 Abrasion drill bit device for processing uneven geology
CN104024557A (en) * 2011-11-15 2014-09-03 贝克休斯公司 Hybrid Drill Bits Having Increased Drilling Efficiency
CN104879065A (en) * 2015-06-15 2015-09-02 泰州市宝锐石油设备制造有限公司 PDC (polycrystalline diamond compact) bit suitable for gravel formation drilling
CN205025364U (en) * 2015-10-14 2016-02-10 长安大学 Dig drilling tool soon
JP2017122476A (en) * 2016-01-07 2017-07-13 日本電産サンキョー株式会社 Gear unit
CN107090831A (en) * 2017-05-05 2017-08-25 上海易谦岩土工程有限公司 The clear stake drill bit of rotary digging formula
CN208792327U (en) * 2018-08-13 2019-04-26 中地君豪建筑工程有限公司 Abolish the drill bit of waste and old solid pile

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1073250A (en) * 1964-11-27 1967-06-21 Stitching Waterbouwkungdig Lab Cutter head for a soil sample cutter
US20080131211A1 (en) * 2004-07-13 2008-06-05 Nesmith Willie M Installation effort deep foudnation method
JP2007120123A (en) * 2005-10-27 2007-05-17 Nisshin Kizai Kk Pile extraction device
US7198119B1 (en) * 2005-11-21 2007-04-03 Hall David R Hydraulic drill bit assembly
CA2597819A1 (en) * 2006-08-23 2008-02-23 Bauer Maschinen Gmbh Method and device for producing a borehole in the soil
JP2009052250A (en) * 2007-08-24 2009-03-12 Kimifusa Fukuyama Auger head and shredding equipment with the same
CN101324066A (en) * 2008-08-04 2008-12-17 大连大金马基础建设有限公司 Construction method drive type major diameter steel pipe pore-creating filling pile
JP2010185188A (en) * 2009-02-10 2010-08-26 Hoei Sangyo Kk Drilling bucket
CN104024557A (en) * 2011-11-15 2014-09-03 贝克休斯公司 Hybrid Drill Bits Having Increased Drilling Efficiency
US8579548B1 (en) * 2013-05-07 2013-11-12 Harold F Schmidt Method of piling remediation
CN103573188A (en) * 2013-11-12 2014-02-12 中铁十局集团有限公司 Abrasion drill bit device for processing uneven geology
CN104879065A (en) * 2015-06-15 2015-09-02 泰州市宝锐石油设备制造有限公司 PDC (polycrystalline diamond compact) bit suitable for gravel formation drilling
CN205025364U (en) * 2015-10-14 2016-02-10 长安大学 Dig drilling tool soon
JP2017122476A (en) * 2016-01-07 2017-07-13 日本電産サンキョー株式会社 Gear unit
CN107090831A (en) * 2017-05-05 2017-08-25 上海易谦岩土工程有限公司 The clear stake drill bit of rotary digging formula
CN208792327U (en) * 2018-08-13 2019-04-26 中地君豪建筑工程有限公司 Abolish the drill bit of waste and old solid pile

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952916A (en) * 2019-11-28 2020-04-03 武汉金瑞威基础工程有限公司 Construction method for crushing and dismantling deep part of old building pile foundation
CN111877344A (en) * 2020-06-24 2020-11-03 中煤江南建设发展有限公司 Old pipe pile breaking method
CN113897958A (en) * 2021-10-22 2022-01-07 中铁四局集团建筑工程有限公司 Precise cutting construction method for rotary digging pile
CN114352185A (en) * 2021-12-13 2022-04-15 广东君豪高科地下空间建设有限公司 Variable speed drill bit for underground space development field
CN114352185B (en) * 2021-12-13 2024-01-02 广东君豪高科地下空间建设有限公司 Variable speed drill bit for underground space development field

Also Published As

Publication number Publication date
CN108729445B (en) 2023-12-19

Similar Documents

Publication Publication Date Title
CN108729445A (en) The method for abolishing the drill bit of waste and old solid pile and abolishing old solid pile and new pile being perfused
CN110016920B (en) Construction method of secant pile matched with meat and vegetables
CN111379516A (en) Hole forming method of cast-in-situ bored pile
KR101596660B1 (en) Apparatus and method for removing waste PHC pile of reclaimed land
NZ209905A (en) Forming opening portion of well by drilling with auger in casing and securing conductor pipe in bore with filler
US5823276A (en) Diamond-tipped core barrel and method of using same
CN208792327U (en) Abolish the drill bit of waste and old solid pile
CN112360337B (en) Pile foundation construction method
CN102767337A (en) Sleeve type screw pile machine drill and construction method for eliminating barriers
CN109610494A (en) A kind of embedding rock construction technology of large-diameter pile foundation
JP2009052250A (en) Auger head and shredding equipment with the same
CN108798528B (en) Drill bit for breaking waste pipe piles and method for breaking waste pipe piles and filling new piles
JP2007162275A (en) Method of removing existing concrete pile
JP3683229B2 (en) Existing pile removal method and equipment
CN214033711U (en) Rotary drilling bit for removing waste pile
JP5303352B2 (en) Removal method of existing concrete piles
CN107420028B (en) Percussion drill and percussion drill
JP5183510B2 (en) Crusher
CN111962511A (en) Construction method for ultra-deep bored pile of combined rotary drilling rig of full-casing multifunctional drilling rig
JP3205279U (en) Cut bucket
CN206503561U (en) A kind of drill bit for geotechnical boring
CN201330561Y (en) Coring bit with back reaming function
CN214532768U (en) Screw pile machine
CN218542160U (en) DNA-like structure pore-forming device
CN112343510B (en) Construction method for crushing rock and coring by using plasma pulse

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20231117

Address after: 510000, Room 905, Room A02, Nansha Jinmao Bay, No. 5 Jinmao Middle Second Street, Huangge Town, Nansha District, Guangzhou City, Guangdong Province (self made T9 building) (for office only)

Applicant after: Guangzhou Junhao Geotechnical Engineering Co.,Ltd.

Address before: No.2401, 24 / F, West building, Huizhi Plaza, No.399, Qunli Fourth Avenue, Daoli District, Harbin City, Heilongjiang Province

Applicant before: ZHONGDI JUNHAO CONSTRUCTION ENGINEERING CO.,LTD.