A kind of prefabricated component embedded nut positioning device Download PDFInfo
- Publication number
- CN108724456A CN108724456A CN201810753444.0A CN201810753444A CN108724456A CN 108724456 A CN108724456 A CN 108724456A CN 201810753444 A CN201810753444 A CN 201810753444A CN 108724456 A CN108724456 A CN 108724456A
- Authority
- CN
- China
- Prior art keywords
- nut
- correction
- reinforcing bar
- frame
- embedded nut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012937 correction Methods 0.000 claims abstract description 35
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 24
- 238000010276 construction Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- -1 electricity Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000010297 mechanical methods and process Methods 0.000 description 1
- 230000005226 mechanical processes and functions Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention discloses a kind of prefabricated component embedded nut positioning devices, including reinforcing bar, sliding shoe, correct nut, connect bolt, frame, clamp, the frame is the square structure of upper and lower opening, frame is put on the ground, the reinforcing bar is continuous bend shape, it is higher than frame 15-20cm in the middle part of reinforcing bar, reinforcing bar both sides are arranged by clamp on frame, the correction nut vertical is arranged in underground, outside is arranged in the middle part of reinforcing bar in the sliding shoe, the sliding shoe is equipped with clamping screw, weld embedded nut in the sliding shoe side, the connection is bolted embedded nut and correction nut, the configuration of the present invention is simple, it is easy to use, three-dimensional ensures the direction of embedded nut, position meets the requirements, to improve prefabricated component quality.
Description
Technical field
The invention belongs to precast concrete manufacture fields, and in particular to a kind of prefabricated component embedded nut positioning device.
Background technology
More and more in the pipeline and cable of provided underground with the development of modern city, effect is had nothing in common with each other,
Then each city starts to greatly develop underground pipe gallery, and underground pipe gallery is in Urban Underground for concentrating laying water, electricity, gas, communication
The public tunnel of equal municipal pipelines, underground pipe gallery generally will be prefabricated in advance, then arrive scene splicing, in prefabrication process, need
Embedded nut is wanted, existing operating method is to have measured size when wire-tiing cage, by nut-welding in reinforcing bar side, but
It is that reinforcing bar, which is possible to position, is not allowed, and causes the position of embedded nut, direction not right, in underground construction in actual mechanical process
When bolt to less than nut location, increasing difficulty of construction, and construction quality can be influenced.
Invention content
To solve the above problems, the invention discloses a kind of prefabricated component embedded nut positioning device, three-dimensional ensures pre-
Bury the direction of nut, position meets the requirements, to improve prefabricated component quality.
In order to achieve the above objectives, technical scheme is as follows:
A kind of prefabricated component embedded nut positioning device, including reinforcing bar, sliding shoe, correction nut, connection bolt, frame, clamp, institute
The square structure that frame is upper and lower opening is stated, frame is put on the ground, and the reinforcing bar is continuous bend shape, is higher than frame in the middle part of reinforcing bar
Frame 15-20cm, reinforcing bar both sides are arranged by clamp on frame, and the correction nut vertical is arranged in underground, the sliding shoe
Outside is set in the middle part of reinforcing bar, and the sliding shoe is equipped with clamping screw, and embedded nut, the company are welded in the sliding shoe side
Connecting bolt connects embedded nut and correction nut.
As an improvement of the present invention, the clamp is g type clamps.
As an improvement of the present invention, the jaw of the g types clamp is semicircle.
As an improvement of the present invention, correction hole, the correction hole and correction nut are equipped with below the correction nut
Vertically, horizontal pin is equipped in correction hole.
As an improvement of the present invention, the sliding shoe is identical as the correction quantity of nut.
The beneficial effects of the invention are as follows:
A kind of prefabricated component embedded nut positioning device of the present invention, simple in structure, easy to use, three-dimensional ensures pre-buried
Direction, the position of nut meet the requirements, to improve prefabricated component quality.
Description of the drawings
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is sliding shoe vertical view of the present invention.
Fig. 3 is clamp schematic diagram of the present invention.
Reference numerals list:
1, reinforcing bar, 2, sliding shoe, 3, correction nut, 4, connection bolt, 5, frame, 6, clamp, 7, clamping screw, 8, pre-buried spiral shell
Mother, 9, ground, 10, the jaw of clamp, 11, horizontal pin.
Specific implementation mode
With reference to the accompanying drawings and detailed description, the present invention is furture elucidated, it should be understood that following specific implementation modes are only
For illustrating the present invention rather than limiting the scope of the invention.It should be noted that word " preceding " used in the following description,
" rear ", "left", "right", "up" and "down" refer to that the direction in attached drawing, word "inner" and "outside" refer respectively to direction or remote
Direction from geometric center of specific component.
As shown, a kind of prefabricated component embedded nut positioning device of the present invention, including reinforcing bar 1, sliding shoe 2, school
Positive nut 3, connection bolt 4, frame 5, clamp 6, the frame 5 are the square structure of upper and lower opening, and frame 5 is placed on ground 9, institute
It is continuous bend shape to state reinforcing bar 1, and 1 middle part of reinforcing bar is higher than frame 15-20cm, and 1 both sides of reinforcing bar are arranged by clamp 6 in frame 5
On, the correction nut 3 is vertically arranged in underground, and the sliding shoe 2 is arranged in the middle part of reinforcing bar outside, is set on the sliding shoe 2
There are clamping screw 7,2 side of the sliding shoe to weld embedded nut 8, the connection bolt 4 connects embedded nut 8 and correction nut
3。
A kind of prefabricated component embedded nut positioning device of the present invention, it is simple in structure, it is easy to use, finally to ensure to connect
Connecting bolt 4 easily connects embedded nut 8 and correction nut 3, just the direction of embedded nut, position can be made to meet the requirements, wherein
Sliding shoe 2 moves left and right the position for the X-direction that can change embedded nut 8;Clamp 6 is unclamped, reinforcing bar can be moved forward and backward, and be adjusted
The position of the Y-direction of embedded nut 8;Connection bolt 4 connects embedded nut 8 and correction nut 3 from top to bottom, can adjust pre-buried spiral shell
The position of the Z-direction of mother 8, and since correction nut 3 is to be vertically arranged, if 8 direction of embedded nut is not right, connect bolt 4
Carry to go down, as long as so connection bolt 4 can easily connect embedded nut 8 with correction nut 3, illustrate the Z of embedded nut 8
The position and direction in direction are accurate, and embedded nut 8 is in the surface of correction nut 3 and coaxial, and the present invention is from three-dimensional
Ensure that direction, the position of embedded nut meet the requirements, to improve prefabricated component quality.
Clamp 6 of the present invention is g type clamps, and the jaw 10 of the g types clamp is semicircle, can firmly clamp steel
The both sides of muscle.
In order to enable connection bolt 4 easily to connect embedded nut 8 and correction nut 3, the lower end of connection bolt 4 is equipped with
Chamfering, convenient for carrying into nut.
The present invention is equipped with correction hole below the correction nut 3, and the correction hole is vertical with correction nut 3, correction hole
It is interior to be equipped with horizontal pin 11, it can ensure that correcting nut 3 is vertically arranged, become the tune-up basis of embedded nut.
Sliding shoe 2 of the present invention is identical as the correction quantity of nut 3, and embedded nut 8 and 3 position of correction nut one are a pair of
It answers, it is ensured that each 8 position of embedded nut, direction are accurate.
The technical means disclosed in the embodiments of the present invention is not limited only to the technological means disclosed in the above embodiment, further includes
By the above technical characteristic arbitrarily the formed technical solution of combination.
Claims (5)
1. a kind of prefabricated component embedded nut positioning device, it is characterised in that:Including reinforcing bar, sliding shoe, correction nut, connection spiral shell
Bolt, frame, clamp, the frame are the square structure of upper and lower opening, and frame is put on the ground, and the reinforcing bar is that Curved Continuous is curved
Shape, reinforcing bar middle part are higher than frame 15-20cm, and reinforcing bar both sides are arranged by clamp on frame, the correction nut vertical setting
In underground, outside is arranged in the middle part of reinforcing bar in the sliding shoe, and the sliding shoe is equipped with clamping screw, the sliding shoe side weldering
Embedded nut is connect, the connection is bolted embedded nut and correction nut.
2. a kind of prefabricated component embedded nut positioning device according to claim 1, it is characterised in that:The clamp is g types
Clamp.
3. a kind of prefabricated component embedded nut positioning device according to claim 2, it is characterised in that:The g types clamp
Jaw is semicircle.
4. a kind of prefabricated component embedded nut positioning device according to claim 1, it is characterised in that:Under the correction nut
Side is equipped with correction hole, and the correction hole is vertical with correction nut, and horizontal pin is equipped in correction hole.
5. a kind of prefabricated component embedded nut positioning device according to claim 1, it is characterised in that:The sliding shoe and school
The quantity of positive nut is identical.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810753444.0A CN108724456A (en) | 2018-07-10 | 2018-07-10 | A kind of prefabricated component embedded nut positioning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810753444.0A CN108724456A (en) | 2018-07-10 | 2018-07-10 | A kind of prefabricated component embedded nut positioning device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108724456A true CN108724456A (en) | 2018-11-02 |
Family
ID=63926650
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810753444.0A Pending CN108724456A (en) | 2018-07-10 | 2018-07-10 | A kind of prefabricated component embedded nut positioning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108724456A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003221832A (en) * | 2002-01-29 | 2003-08-08 | Toyo House Kk | Level anchor bolt |
CN203034818U (en) * | 2013-01-21 | 2013-07-03 | 山西省电力公司送变电工程公司 | Special fixture for installation of adjustable embedded part |
CN203654786U (en) * | 2013-12-19 | 2014-06-18 | 中国建筑土木建设有限公司 | Bolt positioning frame for subgrade contact network support pillar construction |
CN204486727U (en) * | 2013-11-01 | 2015-07-22 | 自贡长征精密铸锻有限公司 | Molding sand embedded nut position corrector |
CN205822808U (en) * | 2016-07-01 | 2016-12-21 | 刘所明 | A kind of building engineering construction datum line actinobacillus device |
CN206233261U (en) * | 2016-12-07 | 2017-06-09 | 西京学院 | It is a kind of to can be used to pour the fixing device for reclaiming ground packing material |
CN107740435A (en) * | 2017-09-12 | 2018-02-27 | 金华送变电工程有限公司 | A kind of pre-embedded bolt pours positioner and its localization method |
CN209408890U (en) * | 2018-07-10 | 2019-09-20 | 江苏金贸科技发展有限公司 | A kind of prefabricated component embedded nut positioning device |
-
2018
- 2018-07-10 CN CN201810753444.0A patent/CN108724456A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003221832A (en) * | 2002-01-29 | 2003-08-08 | Toyo House Kk | Level anchor bolt |
CN203034818U (en) * | 2013-01-21 | 2013-07-03 | 山西省电力公司送变电工程公司 | Special fixture for installation of adjustable embedded part |
CN204486727U (en) * | 2013-11-01 | 2015-07-22 | 自贡长征精密铸锻有限公司 | Molding sand embedded nut position corrector |
CN203654786U (en) * | 2013-12-19 | 2014-06-18 | 中国建筑土木建设有限公司 | Bolt positioning frame for subgrade contact network support pillar construction |
CN205822808U (en) * | 2016-07-01 | 2016-12-21 | 刘所明 | A kind of building engineering construction datum line actinobacillus device |
CN206233261U (en) * | 2016-12-07 | 2017-06-09 | 西京学院 | It is a kind of to can be used to pour the fixing device for reclaiming ground packing material |
CN107740435A (en) * | 2017-09-12 | 2018-02-27 | 金华送变电工程有限公司 | A kind of pre-embedded bolt pours positioner and its localization method |
CN209408890U (en) * | 2018-07-10 | 2019-09-20 | 江苏金贸科技发展有限公司 | A kind of prefabricated component embedded nut positioning device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107299683B (en) | Compound concrete-filled tubular column assembled docks node and connection method | |
CN107965065B (en) | Buckling support Combined type pre-embedded member construction method | |
CN102071808A (en) | Anti-floating positioning method and structure for core mould pipe | |
CN209408890U (en) | A kind of prefabricated component embedded nut positioning device | |
CN108724456A (en) | A kind of prefabricated component embedded nut positioning device | |
CN204626453U (en) | The supporting device of pipeline in Urban Underground pipe gallery | |
CN206988584U (en) | Pipeline combined type suspension and support | |
CN104196023B (en) | A kind of using method of the concrete precast pipe pile pile top of band mechanical connecting device | |
CN203062189U (en) | Adjusting device for butting installation of oxygen pipeline | |
CN216840080U (en) | Be used for terminal box at cast-in-place concrete wall internal erection joint structure | |
CN106049531A (en) | Construction method for high-water-content ultra-soft soil box type multi-chamber cast-in-place frame tunnel | |
CN206685859U (en) | A kind of cable holder stand column being fixed on furrow bank | |
CN206702011U (en) | A kind of multi-functional indent support of adjustable steel pipe diameter | |
CN206815540U (en) | A kind of positioner for concrete structure built-in fitting | |
CN205330156U (en) | Cast -in -place template reinforcing apparatus at position is connected to assembly outer wall and cast -in -place interior wall T type | |
CN210976098U (en) | Underground pipe gallery pre-buried support | |
CN203905306U (en) | Steel bar connection adjustment member between prefabricated reinforced concrete members | |
CN206000173U (en) | A kind of multiple steel sleeve pipe arrangement apparatus in a row in template | |
CN204960065U (en) | Building horizontal direction the hinge mechanism for curtain | |
CN208348766U (en) | A kind of high-strength nuclear power polyethylene electric-melting elbow | |
CN103758288B (en) | Large volume resistance to deformation reinforcing cage and binding method thereof | |
CN211774968U (en) | Accurate positioning and fixing die for line pipe | |
CN206764240U (en) | Pipeline butt welding positioning tool fixture | |
CN204098031U (en) | A kind of concrete precast pipe pile pile top with mechanical connecting device | |
CN205088832U (en) | Connection structure of arch roof and bracket stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181102 |
|
RJ01 | Rejection of invention patent application after publication |