CN108683210A - Determine the method and system of the minimum annual utilization hours of power grid Small And Medium Capacity unit - Google Patents

Determine the method and system of the minimum annual utilization hours of power grid Small And Medium Capacity unit Download PDF

Info

Publication number
CN108683210A
CN108683210A CN201810348855.1A CN201810348855A CN108683210A CN 108683210 A CN108683210 A CN 108683210A CN 201810348855 A CN201810348855 A CN 201810348855A CN 108683210 A CN108683210 A CN 108683210A
Authority
CN
China
Prior art keywords
unit
power grid
day
typical
mode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810348855.1A
Other languages
Chinese (zh)
Other versions
CN108683210B (en
Inventor
宋云亭
张晨
王正风
陈得治
吴旭
李立新
张鑫
陈湘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Research Institute Co Ltd CEPRI
State Grid Anhui Electric Power Co Ltd
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Research Institute Co Ltd CEPRI, State Grid Anhui Electric Power Co Ltd filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN201810348855.1A priority Critical patent/CN108683210B/en
Publication of CN108683210A publication Critical patent/CN108683210A/en
Application granted granted Critical
Publication of CN108683210B publication Critical patent/CN108683210B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明提供一种确定电网中小容量机组最低年利用小时数的方法和系统,其根据电网全年负荷曲线确定电网负荷的典型日;根据所述每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式;根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合;根据电网全年负荷曲线和全年分时段开机方式的组合计算中小机组的最低年利用小时数。本发明所述的方法和系统充分考虑了电网安全稳定运行、迎峰度夏度冬、机组检修及供热供汽需求等约束条件和影响因素,提高了计算精度,保证了计算结果的合理性。

The present invention provides a method and system for determining the minimum annual utilization hours of small and medium capacity units in the power grid, which determines the typical day of the power grid load according to the annual load curve of the power grid; according to the load data of each typical day, the unit maintenance plan and the unit For heating and steam supply demand, check the safety and stability of the power grid and optimize the start-up mode one by one for the typical days, and obtain the optimal start-up mode that minimizes the start-up of small and medium-sized units on each typical day; according to the characteristics of the annual load curve of the power grid, determine The typical daily optimal start-up mode is extended to a combination of time-divided start-up modes throughout the year; the minimum annual utilization hours of small and medium-sized units are calculated according to the combination of the annual load curve of the grid and the time-divided start-up mode throughout the year. The method and system of the present invention fully consider the constraints and influencing factors such as the safe and stable operation of the power grid, peaking in summer and winter, unit maintenance, heating and steam supply requirements, etc., which improves the calculation accuracy and ensures the rationality of the calculation results .

Description

确定电网中小容量机组最低年利用小时数的方法和系统Method and system for determining the minimum annual utilization hours of small and medium-capacity generating units in a power grid

技术领域technical field

本发明涉及电力市场领域,并且更具体地,涉及一种确定电网中小容量机组最低年利用小时数的方法和系统。The invention relates to the field of electric power market, and more specifically, relates to a method and system for determining the minimum annual utilization hours of medium and small-capacity generating sets in a power grid.

背景技术Background technique

随着我国电力市场交易规模的不断扩大,由于60万千瓦及以上大机组相比于30万千瓦及以下中小机组具有效率高、发电成本低、单位排放少等优势,市场份额逐渐向大机组集中,导致中小机组的年利用小时数逐渐下降,可能导致迎峰度夏度冬备用不足,部分运行方式下局部地区线路过载或电压水平较低等问题,进而影响电网安全稳定运行。因此,中小机组的最低年利用小时数的计算对电网电力市场交易规模分析具有重要参考意义。With the continuous expansion of the transaction scale of my country's electricity market, compared with small and medium-sized units of 300,000 kilowatts and below, large units of 600,000 kilowatts and above have advantages such as high efficiency, low power generation costs, and low unit emissions, and the market share is gradually concentrated in large units. , leading to a gradual decline in the annual utilization hours of small and medium-sized units, which may lead to insufficient backup during peak summer and winter, overloading of lines in some areas or low voltage levels in some operating modes, which will affect the safe and stable operation of the power grid. Therefore, the calculation of the minimum annual utilization hours of small and medium-sized units has important reference significance for the analysis of the transaction scale of the grid power market.

现有机组最低利用小时数的计算方法主要根据运行经验采用最小开机方式和机组平均发电负荷率进行估算,存在较大误差。The calculation method of the minimum utilization hours of the existing units is mainly based on the operating experience, using the minimum start-up mode and the average generating load rate of the units to estimate, and there are large errors.

发明内容Contents of the invention

为了解决背景技术存在的现在技术中根据运行经验采用最小开机方式和机组平均发电负荷率进行估算误差大的技术方法,提供一种确定电网中小容量机组最低年利用小时数的方法,所述方法包括:In order to solve the technical method existing in the background technology that uses the minimum start-up mode and the average generating load rate of the unit to estimate the large error in the current technology based on operating experience, a method for determining the minimum annual utilization hours of small and medium-capacity units in the power grid is provided. The method includes :

根据电网全年负荷曲线确定电网负荷的典型日,其中,所述典型日包括电网全年负荷曲线中的每月最大负荷日、法定节假日和各月代表月平均负荷的工作日;Determine the typical day of the grid load according to the annual load curve of the grid, wherein the typical day includes the monthly maximum load day in the grid's annual load curve, legal holidays and working days representing the monthly average load in each month;

根据所述每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式;According to the load data of each typical day, the maintenance plan of the unit and the heating and steam supply demand of the unit, check the safety and stability of the power grid and optimize the start-up mode for each typical day, and obtain the minimum start-up of small and medium-sized units on each typical day Optimal boot mode;

根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合;According to the characteristics of the annual load curve of the power grid, the determined typical daily optimal start-up mode is extended to a combination of time-segmented start-up modes throughout the year;

根据电网全年负荷曲线和全年分时段开机方式的组合计算中小机组的最低年利用小时数。Calculate the minimum annual utilization hours of small and medium-sized units according to the combination of the annual load curve of the power grid and the start-up mode in different time periods throughout the year.

进一步地,在根据电网全年负荷曲线确定电网负荷的典型日之前还包括采集电网数据,其中所述数据包括电网全年负荷曲线、电网分地区全年负荷曲线、机组检修计划和机组供热供汽需求。Further, before determining the typical day of the power grid load according to the annual load curve of the power grid, it also includes collecting grid data, wherein the data includes the annual load curve of the grid, the annual load curve of the grid by region, the maintenance plan of the unit and the heat supply of the unit. steam demand.

进一步地,所述根据每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式包括:Further, according to the load data of each typical day, the maintenance plan of the unit, and the heating and steam supply demand of the unit, the safety and stability of the power grid and the optimization of the start-up mode are performed on the typical day one by one, and the small and medium-sized units are obtained for each typical day. The optimal boot mode with the smallest boot size includes:

根据每个典型日的负荷数据计算典型日电网的机组总输出功率和机组备用容量;According to the load data of each typical day, calculate the total output power of the unit and the reserve capacity of the unit of the typical day grid;

根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模;Calculate the starting scale of the generating set of the grid according to the total output power of the generating set and the reserve capacity of the generating set;

根据机组检修计划和机组供热供汽需求,确定每个典型日的检修机组和保留机组;According to the unit overhaul plan and the heat and steam supply demand of the unit, determine the overhaul unit and reserved unit for each typical day;

根据开机规模确定每个典型日的中小机组和中小机组以外的机组的开机方式;Determine the start-up mode of small and medium-sized units and units other than small and medium-sized units on each typical day according to the start-up scale;

在每个典型日最大负荷下对电网进行基础潮流、静态安全、暂态安全校核;Check the basic power flow, static safety and transient safety of the power grid under the maximum load of each typical day;

当对电网进行的基础潮流、静态安全、暂态安全校核通过后,对每个典型日的腰荷和谷荷进行的电网安全稳定校核也通过后,则根据开机规模确定的每个典型日的中小机组和中小机组以外的机组的开机方式即是所述典型日最优开机方式。After the basic power flow, static safety, and transient safety checks of the power grid are passed, and the grid safety and stability checks for the waist load and valley load of each typical day are also passed, each typical load determined according to the start-up scale The start-up mode of daily small and medium-sized units and units other than small and medium-sized units is the optimal start-up mode of the typical day.

进一步地,根据每个典型日的负荷数据计算电网的机组总输出功率和机组备用容量的公式为:Further, the formula for calculating the total output power of the generator set and the reserve capacity of the generator set of the power grid according to the load data of each typical day is:

式中,第i个典型日机组总输出功率;In the formula, The total output power of the units on the i-th typical day;

第i个典型日电网日最大负荷; The daily maximum load of the power grid on the i-th typical day;

第i个典型日外电网送入功率; Input power of the i-th typical day outside the power grid;

第i个典型日电网送出功率; Power sent by the power grid on the i-th typical day;

第i个典型日的备用容量; Reserve capacity for the ith typical day;

Punit_max:电网最大一台机组装机容量。P unit_max : The maximum installed capacity of one unit in the power grid.

进一步地,所述第i个典型日的备用容量是电网规定的备用容量。Further, the reserve capacity of the ith typical day is the reserve capacity specified by the grid.

进一步地,根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模的公式为:Further, the formula for calculating the start-up scale of the generating set of the grid according to the total output power of the generating set and the reserve capacity of the generating set is:

式中,第i个典型日的开机规模。In the formula, The startup scale of the i-th typical day.

进一步地,所述根据开机规模确定中小机组和中小机组以外的机组的开机方式是指压缩中小机组开机数量,增加中小机组以外的大机组开机数量以达到开机规模。Further, the determination of the start-up mode of small and medium units and other units according to the start-up scale refers to reducing the number of start-ups of small and medium-sized units and increasing the number of start-ups of large units other than small and medium-sized units to achieve the start-up scale.

进一步地,对每个典型日的腰荷和谷荷进行电网安全稳定校核是指根据电网分地区全年负荷曲线,在确定各分区在每个典型日的腰荷值和谷荷值的基础上,对每个典型日的腰荷和谷荷进行电网安全稳定校核。Furthermore, the power grid security and stability check for the waist load and valley load of each typical day refers to the basis of determining the waist load and valley load value of each zone on each typical day according to the annual load curve of the grid subregion In addition, check the safety and stability of the power grid for the waist load and valley load of each typical day.

进一步地,对电网进行基础潮流、静态安全、暂态安全校核不通过,或者对电网进行的基础潮流、静态安全、暂态安全校核通过后,对电网每个典型日的腰荷和谷荷进行电网安全稳定校核不通过时,根据所述典型日电网安全稳定校核中存在的问题重新按照压缩中小机组开机数量,增加中小机组以外的大机组开机数量的方法来调整开机方式并继续进行电网安全稳定校核,直至电网安全稳定。Furthermore, if the basic power flow, static safety, and transient safety checks of the power grid are not passed, or after the basic power flow, static safety, and transient safety checks of the power grid are passed, the waist load and valley If the power grid safety and stability check fails, according to the problems in the typical daily power grid safety and stability check, adjust the start-up mode again according to the method of reducing the number of small and medium-sized units started up and increasing the number of large-scale units other than small and medium-sized units started up, and continue Check the safety and stability of the power grid until the power grid is safe and stable.

进一步地,根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合包括:Further, according to the characteristics of the annual load curve of the power grid, the determined typical daily optimal start-up mode is extended to a combination of time-segmented start-up modes throughout the year including:

以每个典型日最大负荷为基准,将与典型日相邻且属于同一个月,并且最大负荷与典型日最大负荷之差在第一预设值以内的工作日作为典型日时段;Based on the maximum load of each typical day, the working days that are adjacent to the typical day and belong to the same month, and the difference between the maximum load and the maximum load of the typical day is within the first preset value are taken as the typical day period;

将全年除典型日时段外的每个剩余时段,取各时段最大负荷日为基准日,将除基准日负荷以外的日最大负荷与基准日负荷之差在第一预设值以内,且属于同一个月的工作日作为每个剩余时段的第一优化时段,并将每个剩余时段除第一优化时段外属于同一个月的其他时段也作为优化时段;For each remaining period of the year except the typical day period, the maximum load day of each period is taken as the base day, and the difference between the daily maximum load other than the base day load and the base day load is within the first preset value, and belongs to The working day of the same month is used as the first optimization period of each remaining period, and the other periods belonging to the same month are also used as optimization periods for each remaining period except the first optimization period;

针对每个优化时段,选择与所述优化时段最大负荷日相隔时间最短的典型日,并计算所述优化时段最大负荷与典型日最大负荷的差值;For each optimization period, select the typical day with the shortest time interval from the maximum load day in the optimization period, and calculate the difference between the maximum load in the optimization period and the maximum load in a typical day;

根据每个优化时段最大负荷与典型日最大负荷的差值,在选择的典型日最优开机方式的基础上增加或减少与所述差值的绝对值相等的开机容量,使其匹配时段最大负荷,其中,当所述差值大于0时,增加与所述差值的绝对值相等的开机容量,当所述差值小于0时,减少与所述差值的绝对值相等的开机容量;According to the difference between the maximum load of each optimization period and the maximum load of a typical day, on the basis of the selected typical daily optimal start-up mode, increase or decrease the start-up capacity equal to the absolute value of the difference, so that it matches the maximum load of the time period , wherein, when the difference is greater than 0, increase the starting capacity equal to the absolute value of the difference, and when the difference is less than 0, decrease the starting capacity equal to the absolute value of the difference;

根据每个典型日时段和优化时段的开机方式确定电网全年分时段开机方式的组合。According to the start-up mode of each typical day period and optimal time period, the combination of the start-up mode of the power grid in different time periods throughout the year is determined.

进一步地,所述第一预设值的范围为0至0.1。Further, the range of the first preset value is 0 to 0.1.

进一步地,确定中小容量机组最低年利用小时数的公式为:Further, the formula for determining the minimum annual utilization hours of small and medium capacity units is:

式中,In the formula,

ln:第n时段t时刻电网负荷(MW);l n : power grid load (MW) at time t of period n;

lnmax:第n时段的最大负荷值(MW);l nmax : the maximum load value (MW) of the nth period;

un:第n时段机组开机方式;u n : unit startup mode in the nth period;

Pn(un):第n时段在un开机方式下30万千瓦机组的总开机容量(MW);P n (u n ): total start-up capacity (MW) of 300,000-kilowatt units under the start-up mode of u in the nth period;

η:备用率;η: standby rate;

N:时段数;N: number of time slots;

t:时间;t: time;

h:30万千瓦机组利用小时数(h);h: Utilization hours of 300,000-kilowatt units (h);

第i台30万千瓦及以下机组额定容量(MW); The rated capacity (MW) of the i-th unit of 300,000 kilowatts and below;

Q30:30万千瓦及以下机组全年发电量(MWh)。Q 30 : Annual power generation (MWh) of units of 300,000 kilowatts and below.

进一步地,所述备用率的计算公式为:Further, the calculation formula of the standby rate is:

备用率=备用容量/开机规模Reserve ratio = reserve capacity / start-up scale

式中,备用容量是指电网中最大一台机组装机容量或电网规定的备用容量值,开机规模是指电网全年分时段开机方式的组合中每个时段的开机规模。In the formula, the reserve capacity refers to the maximum installed capacity of one unit in the power grid or the reserve capacity value stipulated by the power grid, and the start-up scale refers to the start-up scale of each time period in the combination of time-segmented start-up modes of the power grid throughout the year.

根据本发明的另一方面,本发明提供一种确定电网中小容量机组最低年利用小时数的系统,所述系统包括:According to another aspect of the present invention, the present invention provides a system for determining the minimum annual utilization hours of small- and medium-capacity generating units in a power grid, the system comprising:

典型日确定单元,其用于根据电网全年负荷曲线确定电网负荷的典型日,其中,所述典型日包括电网全年负荷曲线中的每月最大负荷日、法定节假日和各月代表月平均负荷的工作日;A typical day determining unit, which is used to determine the typical day of the grid load according to the annual load curve of the grid, wherein the typical day includes the monthly maximum load day in the grid's annual load curve, statutory holidays and the monthly average load of each month working days;

典型日开机方式确定单元,其用于根据所述每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式;The typical daily start-up mode determination unit is used to check the safety and stability of the power grid and optimize the start-up mode on each typical day according to the load data of each typical day, the unit maintenance plan and the heat supply and steam supply demand of the unit, and obtain The optimal start-up mode that minimizes the start-up of small and medium-sized units in each typical day;

年度开机方式确定单元,其用于根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合;An annual start-up mode determination unit, which is used to expand the determined typical daily optimal start-up mode to a combination of time-segmented start-up modes throughout the year according to the characteristics of the annual load curve of the power grid;

结果分析单元,其用于根据电网全年负荷曲线和全年分时段开机方式的组合计算中小机组的最低年利用小时数。The result analysis unit is used to calculate the minimum annual utilization hours of small and medium-sized units according to the combination of the annual load curve of the power grid and the start-up mode in different periods throughout the year.

进一步地,所述系统还包括数据采集单元,其用于采集电网数据,其中所述数据包括电网全年负荷曲线、电网分地区全年负荷曲线、机组检修计划和机组供热供汽需求。Further, the system further includes a data acquisition unit, which is used to collect grid data, wherein the data includes the annual load curve of the grid, the annual load curve of the grid by region, the maintenance plan of the unit, and the heating and steam supply demand of the unit.

进一步地,所述典型日开机方式确定单元包括:Further, the typical daily power-on mode determination unit includes:

机组开机规模确定单元,其用于根据每个典型日的负荷数据计算典型日电网的机组总输出功率和机组备用容量,并根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模;A generating unit start-up scale determination unit, which is used to calculate the total output power of the generator set and the reserve capacity of the generator set of the typical day grid according to the load data of each typical day, and calculate the generator start-up of the grid according to the total output power of the generator set and the standby capacity of the generator set of the grid scale;

检修和保留机组确定单元,其用于根据机组检修计划和机组供热供汽需求,确定每个典型日的检修机组和保留机组;Overhaul and reserved unit determination unit, which is used to determine the overhauled unit and reserved unit on each typical day according to the unit overhaul plan and the heat and steam supply demand of the unit;

机组开机方式确定单元,其用于根据开机规模确定每个典型日的中小机组和中小机组以外的机组的开机方式,并以所述开机方式为基础,在每个典型日最大负荷下对电网进行基础潮流、静态安全、暂态安全校核,当对电网进行的基础潮流、静态安全、暂态安全校核通过后,对每个典型日的腰荷和谷荷进行的电网安全稳定校核也通过后,则根据开机规模确定的每个典型日的中小机组和中小机组以外的机组的开机方式即是所述典型日最优开机方式。Unit start-up mode determination unit, which is used to determine the start-up mode of small and medium-sized units and units other than small and medium-sized units on each typical day according to the scale of start-up, and based on the start-up mode, perform power grid under the maximum load of each typical day Basic power flow, static security, and transient security checks. After the basic power flow, static security, and transient security checks of the power grid are passed, the grid security and stability checks for waist loads and valley loads in each typical day are also checked. After passing, the start-up mode of small and medium units and units other than small and medium units determined according to the start-up scale on each typical day is the optimal start-up mode for the typical day.

进一步地,根据每个典型日的负荷数据计算电网的机组总输出功率和机组备用容量的公式为:Further, the formula for calculating the total output power of the generator set and the reserve capacity of the generator set of the power grid according to the load data of each typical day is:

式中,第i个典型日机组总输出功率;In the formula, The total output power of the units on the i-th typical day;

第i个典型日电网日最大负荷; The daily maximum load of the power grid on the i-th typical day;

第i个典型日外电网送入功率; Input power of the i-th typical day outside the power grid;

第i个典型日电网送出功率; Power sent by the power grid on the i-th typical day;

第i个典型日的备用容量; Reserve capacity for the ith typical day;

Punit_max:电网最大一台机组装机容量。P unit_max : The maximum installed capacity of one unit in the power grid.

进一步地,所述第i个典型日的备用容量Ps i是电网规定的备用容量。Further, the reserve capacity P s i of the ith typical day is the reserve capacity stipulated by the power grid.

进一步地,根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模的公式为:Further, the formula for calculating the start-up scale of the generating set of the grid according to the total output power of the generating set and the reserve capacity of the generating set is:

式中,第i个典型日的开机规模。In the formula, The startup scale of the i-th typical day.

进一步地,所述根据开机规模确定中小机组和中小机组以外的机组的开机方式是指压缩中小机组开机数量,增加中小机组以外的大机组开机数量以达到开机规模。Further, the determination of the start-up mode of small and medium units and other units according to the start-up scale refers to reducing the number of start-ups of small and medium-sized units and increasing the number of start-ups of large units other than small and medium-sized units to achieve the start-up scale.

进一步地,对每个典型日的腰荷和谷荷进行电网安全稳定校核是指根据电网分地区全年负荷曲线,在确定各分区在每个典型日的腰荷值和谷荷值的基础上,对每个典型日的腰荷和谷荷进行电网安全稳定校核。Furthermore, the power grid security and stability check for the waist load and valley load of each typical day refers to the basis of determining the waist load and valley load value of each zone on each typical day according to the annual load curve of the grid subregion In addition, check the safety and stability of the power grid for the waist load and valley load of each typical day.

进一步地,所述机组开机方式确认单元对电网进行基础潮流、静态安全、暂态安全校核不通过,或者对电网进行的基础潮流、静态安全、暂态安全校核通过后,对电网每个典型日的腰荷和谷荷进行电网安全稳定校核不通过时,根据所述典型日电网安全稳定校核中存在的问题重新按照压缩中小机组开机数量,增加中小机组以外的大机组开机数量的方法来调整开机方式并继续进行电网安全稳定校核,直至电网安全稳定。Further, the power-on mode confirmation unit of the unit fails to pass the basic power flow, static security, and transient security checks on the power grid, or after passing the basic power flow, static security, and transient security checks on the grid, checks each When the power grid safety and stability check of the waist load and valley load of a typical day fails, according to the problems existing in the grid safety and stability check of the typical day, the number of starting-up of small and medium-sized units will be reduced, and the number of starting-up of large-scale units other than small and medium-sized units will be increased. method to adjust the start-up mode and continue to check the safety and stability of the power grid until the power grid is safe and stable.

进一步地,所述年度开机方式确定单元包括:Further, the annual start-up mode determination unit includes:

典型日时段确定单元,其用于以每个典型日最大负荷为基准,将与典型日相邻且属于同一个月,并且最大负荷与典型日最大负荷之差在第一预设值以内的工作日作为典型日时段;The typical day period determination unit is used for the work that is based on the maximum load of each typical day, will be adjacent to the typical day and belongs to the same month, and the difference between the maximum load and the maximum load of the typical day is within the first preset value day as a typical day period;

优化时段确定单元,其用于将全年除典型日时段外的每个剩余时段,取各时段最大负荷日为基准日,将除基准日负荷以外的日最大负荷与基准日负荷之差在第一预设值以内,且属于同一个月的工作日作为每个剩余时段的第一优化时段,并将每个剩余时段除第一优化时段外属于同一个月的其他时段也作为优化时段;The optimization period determination unit is used to take the maximum load day of each period as the reference day for each remaining period of the year except the typical day period, and calculate the difference between the daily maximum load and the reference day load except the reference day load at Within a preset value, the working days belonging to the same month are used as the first optimization period of each remaining period, and other periods belonging to the same month are also used as optimization periods for each remaining period except the first optimization period;

优化年度开机方式确定单元,其用于针对每个优化时段,选择与所述优化时段最大负荷日相隔时间最短的典型日,并计算所述优化时段最大负荷与典型日最大负荷的差值,以及根据每个优化时段最大负荷与典型日最大负荷的差值,在选择的典型日最优开机方式的基础上增加或减少与所述差值的绝对值相等的开机容量,使其匹配时段最大负荷,其中,当所述差值大于0时,增加与所述差值的绝对值相等的开机容量,当所述差值小于0时,减少与所述差值的绝对值相等的开机容量;An optimized annual start-up mode determination unit, which is used to select a typical day with the shortest time interval from the maximum load day of the optimization period for each optimization period, and calculate the difference between the maximum load of the optimization period and the maximum load of a typical day, and According to the difference between the maximum load of each optimization period and the maximum load of a typical day, on the basis of the selected typical daily optimal start-up mode, increase or decrease the start-up capacity equal to the absolute value of the difference, so that it matches the maximum load of the time period , wherein, when the difference is greater than 0, increase the starting capacity equal to the absolute value of the difference, and when the difference is less than 0, decrease the starting capacity equal to the absolute value of the difference;

合并单元,其用于根据每个典型日时段和优化时段的开机方式确定电网全年分时段开机方式的组合。The merging unit is used to determine the combination of the start-up modes of the power grid in different time periods throughout the year according to the start-up modes of each typical day period and optimal period.

进一步地,所述第一预设值的范围为0至0.1。Further, the range of the first preset value is 0 to 0.1.

进一步地,确定中小容量机组最低年利用小时数的公式为:Further, the formula for determining the minimum annual utilization hours of small and medium capacity units is:

式中,In the formula,

ln:第n时段t时刻电网负荷(MW);l n : power grid load (MW) at time t of period n;

lnmax:第n时段的最大负荷值(MW);l nmax : the maximum load value (MW) of the nth period;

un:第n时段机组开机方式;u n : unit startup mode in the nth period;

Pn(un):第n时段在un开机方式下30万千瓦机组的总开机容量(MW);P n (u n ): total start-up capacity (MW) of 300,000-kilowatt units under the start-up mode of u in the nth period;

η:备用率;η: standby rate;

N:时段数;N: number of time slots;

t:时间;t: time;

h:30万千瓦机组利用小时数(h);h: Utilization hours of 300,000-kilowatt units (h);

:第i台30万千瓦及以下机组额定容量(MW); : Rated capacity (MW) of the i-th unit of 300,000 kilowatts and below;

Q30:30万千瓦及以下机组全年发电量(MWh)。Q 30 : Annual power generation (MWh) of units of 300,000 kilowatts and below.

进一步地,所述备用率的计算公式为:Further, the calculation formula of the standby rate is:

备用率=备用容量/开机规模Reserve ratio = reserve capacity / start-up scale

式中,备用容量是指电网中最大一台机组装机容量或电网规定的备用容量值,开机规模是指电网全年分时段开机方式的组合中每个时段的开机规模。In the formula, the reserve capacity refers to the maximum installed capacity of one unit in the power grid or the reserve capacity value stipulated by the power grid, and the start-up scale refers to the start-up scale of each time period in the combination of time-segmented start-up modes of the power grid throughout the year.

本发明所述的在电力市场环境下确定中小容量机组最低年利用小时数的方法和系统,首先获取年度统调负荷预测、机组检修计划、机组供热供汽需求等数据;然后根据年度负荷数据选取典型日逐一进行开机方式优化和电网安全稳定校核,得到各典型日下中小容量机组的最小开机方式,进而细化扩展为全年分时段开机方式组合;最后根据年度负荷数据和分时段最优开机方式,计算中小机组的最低年利用小时数。本发明所述的方法和系统充分考虑了电网安全稳定运行、迎峰度夏度冬、机组检修及供热供汽需求等约束条件和影响因素,提高了计算精度,保证了计算结果的合理性。According to the method and system for determining the minimum annual utilization hours of small and medium-capacity units in the electricity market environment of the present invention, first obtain data such as annual unified load forecast, unit maintenance plan, unit heating and steam supply demand; and then according to the annual load data Select typical days to optimize the start-up mode and check the safety and stability of the power grid one by one to obtain the minimum start-up mode of small and medium-capacity units in each typical day, and then refine and expand it into a combination of start-up modes for the whole year by time period; finally, according to the annual load data and the most Optimum start-up mode, calculate the minimum annual utilization hours of small and medium-sized units. The method and system of the present invention fully consider the constraints and influencing factors such as the safe and stable operation of the power grid, peaking in summer and winter, unit maintenance, heating and steam supply requirements, etc., which improves the calculation accuracy and ensures the rationality of the calculation results .

附图说明Description of drawings

通过参考下面的附图,可以更为完整地理解本发明的示例性实施方式:A more complete understanding of the exemplary embodiments of the present invention can be had by referring to the following drawings:

图1是本发明优选实施方式的确定中小容量机组最低年利用小时数的方法的流程图;Fig. 1 is a flow chart of the method for determining the minimum annual utilization hours of small and medium capacity units in a preferred embodiment of the present invention;

图2是本发明优选实施方式的确定每个典型日使中小容量机组开机最小的最优开机方式的流程图;Fig. 2 is a flow chart of determining the optimal start-up mode for the minimum start-up of small and medium-capacity units in each typical day according to the preferred embodiment of the present invention;

图3是本发明优选实施方式的确定中小容量机组最低年利用小时数的系统的结构图;Fig. 3 is a structural diagram of a system for determining the minimum annual utilization hours of small and medium-capacity units in a preferred embodiment of the present invention;

图4是本发明优选实施方式的安徽电网2018年11月的负荷曲线图。Fig. 4 is a load curve diagram of Anhui Power Grid in November 2018 according to a preferred embodiment of the present invention.

具体实施方式Detailed ways

现在参考附图介绍本发明的示例性实施方式,然而,本发明可以用许多不同的形式来实施,并且不局限于此处描述的实施例,提供这些实施例是为了详尽地且完全地公开本发明,并且向所属技术领域的技术人员充分传达本发明的范围。对于表示在附图中的示例性实施方式中的术语并不是对本发明的限定。在附图中,相同的单元/元件使用相同的附图标记。Exemplary embodiments of the present invention will now be described with reference to the drawings; however, the present invention may be embodied in many different forms and are not limited to the embodiments described herein, which are provided for the purpose of exhaustively and completely disclosing the present invention. invention and fully convey the scope of the invention to those skilled in the art. The terms used in the exemplary embodiments shown in the drawings do not limit the present invention. In the figures, the same units/elements are given the same reference numerals.

除非另有说明,此处使用的术语(包括科技术语)对所属技术领域的技术人员具有通常的理解含义。另外,可以理解的是,以通常使用的词典限定的术语,应当被理解为与其相关领域的语境具有一致的含义,而不应该被理解为理想化的或过于正式的意义。Unless otherwise specified, the terms (including scientific and technical terms) used herein have the commonly understood meanings to those skilled in the art. In addition, it can be understood that terms defined by commonly used dictionaries should be understood to have consistent meanings in the context of their related fields, and should not be understood as idealized or overly formal meanings.

图1是本发明优选实施方式的确定中小容量机组最低年利用小时数的方法的流程图。如图1所示,确定电网中小容量机组最低年利用小时数的方法100从步骤101开始。在本优选实施方式中,以安徽电网2018年为例,收集安徽电网数据,利用电力系统机电暂态仿真软件PSD-BPA建立安徽电网2018年潮流稳态仿真计算模型以及机电暂态仿真计算模型进行电网安全稳定校核,利用数学软件MATLAB进行最低年利用小时数计算。Fig. 1 is a flow chart of a method for determining the minimum annual utilization hours of small and medium-capacity units in a preferred embodiment of the present invention. As shown in FIG. 1 , the method 100 for determining the minimum annual utilization hours of small-capacity generating units in the power grid starts from step 101 . In this preferred implementation mode, taking Anhui Power Grid in 2018 as an example, collect the data of Anhui Power Grid, and use the power system electromechanical transient simulation software PSD-BPA to establish the power flow steady state simulation calculation model of Anhui Power Grid in 2018 and the electromechanical transient simulation calculation model. Check the safety and stability of the power grid, and use the mathematical software MATLAB to calculate the minimum annual utilization hours.

在步骤101,采集电网数据,其中所述数据包括电网全年负荷曲线、电网分地区全年负荷曲线、机组检修计划和机组供热供汽需求。在本优选实施方式中,获取安徽电网2018年统调负荷曲线(时间间隔1h)、各分区负荷曲线、2018年机组检修计划、供热供汽需求机组列表等数据。In step 101, grid data is collected, wherein the data includes the annual load curve of the grid, the annual load curve by region of the grid, the maintenance plan of the unit, and the heating and steam supply demand of the unit. In this preferred embodiment, data such as Anhui Power Grid's 2018 unified load curve (time interval 1h), load curves of each zone, unit maintenance plan in 2018, and list of heating and steam supply demand units are obtained.

在步骤102,根据电网全年负荷曲线确定电网负荷的典型日,其中,所述典型日包括电网全年负荷曲线中的每月最大负荷日、法定节假日和各月代表月平均负荷的工作日。在本优选实施方式中,根据安徽电网年负荷特性,选取每月最大负荷日、典型节假日和补充工作日共25个典型日,获取典型日全网及各分区日负荷曲线,所述典型日如表1所示。In step 102, a typical day of grid load is determined according to the grid annual load curve, wherein the typical day includes the monthly maximum load day in the grid annual load curve, legal holidays and working days representing monthly average load in each month. In this preferred implementation mode, according to the annual load characteristics of Anhui Power Grid, 25 typical days in total, including the maximum load day, typical holidays and supplementary working days, are selected to obtain the typical daily load curves of the entire network and each subregion. The typical days are as follows Table 1 shows.

表1Table 1

在步骤103,根据所述每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式。In step 103, according to the load data of each typical day, the maintenance plan of the unit, and the heating and steam supply demand of the unit, check the safety and stability of the power grid and optimize the start-up mode for each typical day one by one, and obtain the small and medium-sized The optimal start-up mode with the minimum start-up of the unit.

图2是本发明优选实施方式的确定每个典型日使中小容量机组开机最小的最优开机方式的流程图。如图2所示,确定每个典型日使中小容量机组开机最小的最优开机方式的方法200从步骤201开始。Fig. 2 is a flow chart of determining the optimal start-up mode to minimize the start-up of small and medium-capacity units in each typical day according to the preferred embodiment of the present invention. As shown in FIG. 2 , the method 200 for determining the optimal start-up mode for minimizing the start-up of small and medium-capacity generating sets in each typical day starts from step 201 .

在步骤201,根据每个典型日的负荷数据计算典型日电网的机组总输出功率和机组备用容量。In step 201, the total output power of the generating set and the reserve capacity of the generating set of the power grid on a typical day are calculated according to the load data of each typical day.

优选地,根据每个典型日的负荷数据计算电网的机组总输出功率和机组备用容量的公式为:Preferably, the formula for calculating the total output power of the generating set and the reserve capacity of the generating set of the power grid according to the load data of each typical day is:

式中,第i个典型日机组总输出功率;In the formula, The total output power of the units on the i-th typical day;

第i个典型日电网日最大负荷; The daily maximum load of the power grid on the i-th typical day;

第i个典型日外电网送入功率; Input power of the i-th typical day outside the power grid;

第i个典型日电网送出功率; Power sent by the power grid on the i-th typical day;

第i个典型日的备用容量; Reserve capacity for the ith typical day;

Punit_max:电网最大一台机组装机容量。P unit_max : The maximum installed capacity of one unit in the power grid.

优选地,所述第i个典型日的备用容量是电网规定的备用容量。Preferably, the reserve capacity of the ith typical day is the reserve capacity specified by the grid.

在步骤202,根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模。In step 202, the start-up scale of the generating set of the grid is calculated according to the total output power of the generating set and the reserve capacity of the generating set.

优选地,根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模的公式为:Preferably, the formula for calculating the start-up scale of the generating set of the grid according to the total output power of the generating set and the reserve capacity of the generating set is:

式中,第i个典型日的开机规模。In the formula, The startup scale of the i-th typical day.

在步骤203,根据机组检修计划和机组供热供汽需求,确定每个典型日的检修机组和保留机组。当因电网安全和供热供热供汔影响无法安排机组全停时,需要至少保留一台机组可运行。In step 203, according to the unit maintenance plan and the heating and steam supply demand of the unit, the maintenance unit and reserved unit for each typical day are determined. When it is not possible to arrange a full stop of the unit due to the influence of grid security and heating and supply, at least one unit needs to be kept in operation.

在步骤204,根据开机规模确定每个典型日的中小机组和中小机组以外的机组的开机方式。In step 204, the start-up mode of the small and medium-sized units and the units other than the small and medium-sized units is determined on each typical day according to the start-up scale.

优选地,所述根据开机规模确定中小机组和中小机组以外的机组的开机方式是指压缩中小机组开机数量,增加中小机组以外的大机组开机数量以达到开机规模。Preferably, determining the start-up mode of small and medium-sized units and units other than small and medium-sized units according to the start-up scale refers to reducing the number of start-ups of small and medium-sized units and increasing the number of start-ups of large units other than small and medium-sized units to achieve the start-up scale.

在步骤205,在每个典型日最大负荷下对电网进行基础潮流、静态安全、暂态安全校核。In step 205, basic power flow, static security, and transient security checks are performed on the power grid under the maximum load in each typical day.

在步骤206,当对电网进行的基础潮流、静态安全、暂态安全校核通过后,对每个典型日的腰荷和谷荷进行的电网安全稳定校核也通过后,则根据开机规模确定的每个典型日的中小机组和中小机组以外的机组的开机方式即是所述典型日最优开机方式。In step 206, after the basic power flow, static security, and transient security checks of the power grid are passed, and the grid security and stability checks for the waist load and valley load of each typical day are also passed, the power grid is determined according to the scale of start-up. The start-up mode of small and medium units and units other than small and medium units on each typical day is the optimal start-up mode for the typical day.

优选地,对每个典型日的腰荷和谷荷进行电网安全稳定校核是指根据电网分地区全年负荷曲线,在确定各分区在每个典型日的腰荷值和谷荷值的基础上,对每个典型日的腰荷和谷荷进行电网安全稳定校核。由于电网不同分区日负荷变化规律不同,各分区在典型日的腰荷值和谷荷值根据电网分地区全年负荷曲线得到。Preferably, checking the safety and stability of the power grid for the waist load and valley load of each typical day refers to the basis of determining the waist load and valley load value of each zone on each typical day according to the annual load curve of the power grid subregion In addition, check the safety and stability of the power grid for the waist load and valley load of each typical day. Due to the different patterns of daily load variation in different subregions of the power grid, the waist load value and valley load value of each subregion in a typical day are obtained from the annual load curve of the subregion of the power grid.

优选地,对电网进行基础潮流、静态安全、暂态安全校核不通过,或者对电网进行的基础潮流、静态安全、暂态安全校核通过后,对电网每个典型日的腰荷和谷荷进行电网安全稳定校核不通过时,根据所述典型日电网安全稳定校核中存在的问题重新按照压缩中小机组开机数量,增加中小机组以外的大机组开机数量的方法来调整开机方式并继续进行电网安全稳定校核,直至电网安全稳定。Preferably, the basic power flow, static security, and transient security checks of the power grid fail, or after the basic power flow, static security, and transient security checks of the grid are passed, the waist load and valley load of each typical day of the grid If the power grid safety and stability check fails, according to the problems in the typical daily power grid safety and stability check, adjust the start-up mode again according to the method of reducing the number of small and medium-sized units started up and increasing the number of large-scale units other than small and medium-sized units started up, and continue Check the safety and stability of the power grid until the power grid is safe and stable.

本优选实施方式中,安徽电网2018年每个典型日的开机方式如表2所示。In this preferred implementation manner, the start-up mode of Anhui Power Grid on each typical day in 2018 is shown in Table 2.

表2Table 2

在所述表中,倾斜数字为受电网安全约束须开机组,加下划线数字为检修机组。In the above table, the inclined numbers are the units that must be started due to the safety constraints of the power grid, and the underlined numbers are the maintenance units.

在步骤104,根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合。In step 104, according to the characteristics of the grid's annual load curve, the determined typical daily optimal start-up mode is extended to a combination of time-segmented start-up modes throughout the year.

优选地,根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合包括:Preferably, according to the characteristics of the annual load curve of the power grid, extending the determined typical daily optimal start-up mode to a combination of time-segmented start-up modes throughout the year includes:

以每个典型日最大负荷为基准,将与典型日相邻且属于同一个月,并且最大负荷与典型日最大负荷之差在第一预设值以内的工作日作为典型日时段,具体公式如下:Based on the maximum load of each typical day, the working days that are adjacent to the typical day and belong to the same month, and the difference between the maximum load and the maximum load of the typical day is within the first preset value are taken as the typical day period. The specific formula is as follows :

Ti(n)=(date(i)-j,date(i)+k)T i (n)=(date(i)-j, date(i)+k)

式中,In the formula,

Ti(n):第i个典型日及其相邻的前j天和后k天构成的典型日时段,时段编号为n;T i (n): the typical day period composed of the i-th typical day and its adjacent j days and next k days, the period number is n;

date(i):第i个典型日的日期;date(i): the date of the i-th typical day;

δ:第一预设值;δ: the first preset value;

d:典型日时段内的任意一天;d: Any day within the typical day period;

典型日时段内任意一天的最大负荷。 The maximum load on any day during a typical day period.

将全年除典型日时段外的每个剩余时段,取各时段最大负荷日为基准日,将除基准日负荷以外的日最大负荷与基准日负荷之差在第一预设值以内,且属于同一个月的工作日作为每个剩余时段的第一优化时段,并将每个剩余时段除第一优化时段外属于同一个月的其他时段也作为优化时段;For each remaining period of the year except the typical day period, the maximum load day of each period is taken as the base day, and the difference between the daily maximum load other than the base day load and the base day load is within the first preset value, and belongs to The working day of the same month is used as the first optimization period of each remaining period, and the other periods belonging to the same month are also used as optimization periods for each remaining period except the first optimization period;

针对每个优化时段,选择与所述优化时段最大负荷日相隔时间最短的典型日,并计算所述优化时段最大负荷与典型日最大负荷的差值,所述每个优化时段的具体公式如下:For each optimization period, select the typical day with the shortest time interval from the maximum load day in the optimization period, and calculate the difference between the maximum load in the optimization period and the maximum load in a typical day. The specific formula for each optimization period is as follows:

Trest(n)=(date(n)-j,date(n)+k)T rest (n)=(date(n)-j, date(n)+k)

式中,In the formula,

Trest(n):由基准日date(n)及其相邻的前j天和后k天构成的优化时段,时段编号为nT rest (n): An optimization period consisting of the base date date(n) and its adjacent j days and next k days, the period number is n

date(n):时段Trest(n)内最大负荷日的日期,该时段的基准日;date(n): the date of the maximum load day in the period T rest (n), the base date of this period;

时段Trest(n)内最大负荷的工作日; The working day with the maximum load in the time period T rest (n);

δ:第一预设值;δ: the first preset value;

d:时段Trest(n)内的任意一天;d: Any day within the time period T rest (n);

时段Trest(n)内的任意一天的最大负荷。 The maximum load on any day within the period T rest (n).

根据每个优化时段最大负荷与典型日最大负荷的差值,在选择的典型日最优开机方式的基础上增加或减少与所述差值的绝对值相等的开机容量,使其匹配时段最大负荷,其中,当所述差值大于0时,增加与所述差值的绝对值相等的开机容量,当所述差值小于0时,减少与所述差值的绝对值相等的开机容量;According to the difference between the maximum load of each optimization period and the maximum load of a typical day, on the basis of the selected typical daily optimal start-up mode, increase or decrease the start-up capacity equal to the absolute value of the difference, so that it matches the maximum load of the time period , wherein, when the difference is greater than 0, increase the starting capacity equal to the absolute value of the difference, and when the difference is less than 0, decrease the starting capacity equal to the absolute value of the difference;

根据每个典型日时段和优化时段的开机方式确定电网全年分时段开机方式的组合。According to the start-up mode of each typical day period and optimal time period, the combination of the start-up mode of the power grid in different time periods throughout the year is determined.

优选地,所述第一预设值的范围为0至0.1。Preferably, the range of the first preset value is 0 to 0.1.

在本优选实施方式中,根据安徽电网2018年负荷特性将25个典型日扩展为45个时段,并按照每个时段的最大负荷进行微调得到分时段最优开机方式。In this preferred embodiment, according to the load characteristics of Anhui Power Grid in 2018, 25 typical days are expanded into 45 time periods, and fine-tuning is performed according to the maximum load of each time period to obtain the optimal start-up mode by time period.

图4是本发明优选实施方式的安徽电网2018年11月的负荷曲线图。根据表1已知,安徽电网11月份有2个典型日,分别是11月1日和11月24日,再结合图4所示,安徽电网11月份的负荷曲线图中,以2个典型日为基准,11月1日至11月21日时段负荷水平基本不变,11月22日至11月30日时段负荷明显上升,故将11月份的负荷曲线可扩展为11月1日至11月21日和11月22日至11月30日2个时段。Fig. 4 is a load curve diagram of Anhui Power Grid in November 2018 according to a preferred embodiment of the present invention. According to Table 1, it is known that Anhui Power Grid has two typical days in November, which are November 1 and November 24. Combined with Figure 4, the load curve of Anhui Power Grid in November is based on two typical days As a benchmark, the load level during the period from November 1st to November 21st remains basically unchanged, and the load level increases significantly during the period from November 22nd to November 30th, so the load curve in November can be extended to November 1st to November 21st and 2 periods from November 22nd to November 30th.

在步骤105,根据电网全年负荷曲线和全年分时段开机方式的组合计算中小机组的最低年利用小时数。In step 105, the minimum annual utilization hours of the small and medium-sized units are calculated according to the combination of the annual load curve of the power grid and the annual time-divided start-up mode.

优选地,确定中小容量机组最低年利用小时数的公式为:Preferably, the formula for determining the minimum annual utilization hours of small and medium capacity units is:

式中,In the formula,

ln:第n时段t时刻电网负荷(MW);l n : power grid load (MW) at time t of period n;

lnmax:第n时段的最大负荷值(MW);l nmax : the maximum load value (MW) of the nth period;

un:第n时段机组开机方式;u n : unit startup mode in the nth period;

Pn(un):第n时段在un开机方式下30万千瓦机组的总开机容量(MW);P n (u n ): total start-up capacity (MW) of 300,000-kilowatt units under the start-up mode of u in the nth period;

η:备用率;η: standby rate;

N:时段数;N: number of time slots;

t:时间;t: time;

h:30万千瓦机组利用小时数(h);h: Utilization hours of 300,000-kilowatt units (h);

第i台30万千瓦及以下机组额定容量(MW); The rated capacity (MW) of the i-th unit of 300,000 kilowatts and below;

Q30:30万千瓦及以下机组全年发电量(MWh)。Q 30 : Annual power generation (MWh) of units of 300,000 kilowatts and below.

优选地,所述备用率的计算公式为:Preferably, the formula for calculating the standby rate is:

备用率=备用容量/开机规模Reserve ratio = reserve capacity / start-up scale

式中,备用容量是指电网中最大一台机组装机容量或电网规定的备用容量值,开机规模是指电网全年分时段开机方式的组合中每个时段的开机规模。In the formula, the reserve capacity refers to the maximum installed capacity of one unit in the power grid or the reserve capacity value stipulated by the power grid, and the start-up scale refers to the start-up scale of each time period in the combination of time-segmented start-up modes of the power grid throughout the year.

图3是本发明优选实施方式的确定中小容量机组最低年利用小时数的系统的结构图。如图3所示,本发明优选实施方式所述的确定中小容量机组最低年利用小时数的系统300包括:Fig. 3 is a structural diagram of a system for determining the minimum annual utilization hours of small and medium-capacity units according to a preferred embodiment of the present invention. As shown in Fig. 3, the system 300 for determining the minimum annual utilization hours of small and medium-capacity units described in the preferred embodiment of the present invention includes:

数据采集单元301,其用于采集电网数据,其中所述数据包括电网全年负荷曲线、电网分地区全年负荷曲线、机组检修计划和机组供热供汽需求。The data collection unit 301 is used to collect grid data, wherein the data includes the annual load curve of the grid, the annual load curve of the grid by region, the maintenance plan of the unit, and the heating and steam supply demand of the unit.

典型日确定单元302,其用于根据电网全年负荷曲线确定电网负荷的典型日,其中,所述典型日包括电网全年负荷曲线中的每月最大负荷日、法定节假日和各月代表月平均负荷的工作日;A typical day determining unit 302, which is used to determine the typical day of the grid load according to the grid's annual load curve, wherein the typical day includes the monthly maximum load day in the grid's annual load curve, legal holidays and monthly average working days of load;

典型日开机方式确定单元303,其用于根据所述每个典型日的负荷数据、机组检修计划和机组供热供汽需求,对所述典型日逐一进行电网安全稳定校核和开机方式优化,得到每个典型日使中小机组开机最小的最优开机方式;A typical day start-up mode determination unit 303, which is used to check the safety and stability of the power grid and optimize the start-up mode on each typical day according to the load data, unit maintenance plan and unit heating and steam supply requirements of each typical day, Get the optimal start-up mode that minimizes the start-up of small and medium-sized units in each typical day;

年度开机方式确定单元304,其用于根据电网全年负荷曲线的特性,将确定的典型日最优开机方式扩展为全年分时段开机方式的组合;An annual start-up mode determination unit 304, which is used to expand the determined optimal daily start-up mode to a combination of time-segmented start-up modes throughout the year according to the characteristics of the grid's annual load curve;

结果分析单元305,其用于根据电网全年负荷曲线和全年分时段开机方式的组合计算中小机组的最低年利用小时数。The result analysis unit 305 is used to calculate the minimum annual utilization hours of small and medium-sized units according to the combination of the annual load curve of the power grid and the annual start-up mode in different time periods.

优选地,所述典型日开机方式确定单元303包括:Preferably, the typical daily boot mode determination unit 303 includes:

机组开机规模确定单元331,其用于根据每个典型日的负荷数据计算典型日电网的机组总输出功率和机组备用容量,并根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模;Unit start-up scale determination unit 331, which is used to calculate the total output power of the units and the reserve capacity of the units of the power grid on a typical day according to the load data of each typical day, and calculate the total output power of the units of the power grid and the reserve capacity of the units of the power grid. boot scale;

检修和保留机组确定单元332,其用于根据机组检修计划和机组供热供汽需求,确定每个典型日的检修机组和保留机组;Overhaul and reserved unit determination unit 332, which is used to determine the overhauled unit and reserved unit on each typical day according to the unit overhaul plan and the heat and steam supply demand of the unit;

机组开机方式确定单元333,其用于根据开机规模确定每个典型日的中小机组和中小机组以外的机组的开机方式,并以所述开机方式为基础,在每个典型日最大负荷下对电网进行基础潮流、静态安全、暂态安全校核,当对电网进行的基础潮流、静态安全、暂态安全校核通过后,对每个典型日的腰荷和谷荷进行的电网安全稳定校核也通过后,则根据开机规模确定的每个典型日的中小机组和中小机组以外的机组的开机方式即是所述典型日最优开机方式。Unit start-up mode determination unit 333, which is used to determine the start-up mode of small and medium-sized units and units other than small and medium-sized units on each typical day according to the scale of start-up, and based on the start-up mode, under the maximum load of each typical day. Carry out basic power flow, static safety, and transient safety checks. After the basic power flow, static safety, and transient safety checks of the power grid are passed, check the safety and stability of the power grid for the waist load and valley load of each typical day After it is also passed, the start-up mode of small and medium-sized units and units other than small and medium-sized units determined according to the start-up scale on each typical day is the optimal start-up mode for the typical day.

优选地,根据每个典型日的负荷数据计算电网的机组总输出功率和机组备用容量的公式为:Preferably, the formula for calculating the total output power of the generating set and the reserve capacity of the generating set of the power grid according to the load data of each typical day is:

式中,第i个典型日机组总输出功率;In the formula, The total output power of the units on the i-th typical day;

第i个典型日电网日最大负荷; The daily maximum load of the power grid on the i-th typical day;

第i个典型日外电网送入功率; Input power of the i-th typical day outside the power grid;

第i个典型日电网送出功率; Power sent by the power grid on the i-th typical day;

第i个典型日的备用容量; Reserve capacity for the ith typical day;

Punit_max:电网最大一台机组装机容量。P unit_max : The maximum installed capacity of one unit in the power grid.

优选地,所述第i个典型日的备用容量是电网规定的备用容量。Preferably, the reserve capacity of the ith typical day is the reserve capacity specified by the grid.

优选地,根据所述电网的机组总输出功率和机组备用容量计算电网的机组开机规模的公式为:Preferably, the formula for calculating the start-up scale of the generating set of the grid according to the total output power of the generating set and the reserve capacity of the generating set is:

式中,第i个典型日的开机规模。In the formula, The startup scale of the i-th typical day.

优选地,所述根据开机规模确定中小机组和中小机组以外的机组的开机方式是指压缩中小机组开机数量,增加中小机组以外的大机组开机数量以达到开机规模。Preferably, determining the start-up mode of small and medium-sized units and units other than small and medium-sized units according to the start-up scale refers to reducing the number of start-ups of small and medium-sized units and increasing the number of start-ups of large units other than small and medium-sized units to achieve the start-up scale.

优选地,对每个典型日的腰荷和谷荷进行电网安全稳定校核是指根据电网分地区全年负荷曲线,在确定各分区在每个典型日的腰荷值和谷荷值的基础上,对每个典型日的腰荷和谷荷进行电网安全稳定校核。Preferably, checking the safety and stability of the power grid for the waist load and valley load of each typical day refers to the basis of determining the waist load and valley load value of each zone on each typical day according to the annual load curve of the power grid subregion In addition, check the safety and stability of the power grid for the waist load and valley load of each typical day.

优选地,所述机组开机方式确认单元对电网进行基础潮流、静态安全、暂态安全校核不通过,或者对电网进行的基础潮流、静态安全、暂态安全校核通过后,对电网每个典型日的腰荷和谷荷进行电网安全稳定校核不通过时,根据所述典型日电网安全稳定校核中存在的问题重新按照压缩中小机组开机数量,增加中小机组以外的大机组开机数量的方法来调整开机方式并继续进行电网安全稳定校核,直至电网安全稳定。Preferably, the power-on mode confirmation unit of the unit fails to pass the basic power flow, static security, and transient security checks on the power grid, or after passing the basic power flow, static security, and transient security checks on the grid, checks each When the power grid safety and stability check of the waist load and valley load of a typical day fails, according to the problems existing in the grid safety and stability check of the typical day, the number of starting-up of small and medium-sized units will be reduced, and the number of starting-up of large-scale units other than small and medium-sized units will be increased. method to adjust the start-up mode and continue to check the safety and stability of the power grid until the power grid is safe and stable.

优选地,所述年度开机方式确定单元304包括:Preferably, the annual start-up mode determination unit 304 includes:

典型日时段确定单元341,其用于以每个典型日最大负荷为基准,将与典型日相邻且属于同一个月,并且最大负荷与典型日最大负荷之差在第一预设值以内的工作日作为典型日时段;A typical day period determination unit 341, which is used to take the maximum load of each typical day as a benchmark, will be adjacent to the typical day and belong to the same month, and the difference between the maximum load and the maximum load of the typical day is within the first preset value Weekdays as typical day time slots;

优化时段确定单元342,其用于将全年除典型日时段外的每个剩余时段,取各时段最大负荷日为基准日,将除基准日负荷以外的日最大负荷与基准日负荷之差在第一预设值以内,且属于同一个月的工作日作为每个剩余时段的第一优化时段,并将每个剩余时段除第一优化时段外属于同一个月的其他时段也作为优化时段,;The optimization period determination unit 342 is used to take the maximum load day of each period as the reference day for each remaining period of the year except the typical day period, and calculate the difference between the daily maximum load and the reference day load except the reference day load in Within the first preset value, the working days belonging to the same month are used as the first optimization period of each remaining period, and the other periods of each remaining period except the first optimization period belonging to the same month are also used as optimization periods, ;

优化年度开机方式确定单元343,其用于针对每个优化时段,选择与所述优化时段最大负荷日相隔时间最短的典型日,并计算所述优化时段最大负荷与典型日最大负荷的差值,以及根据每个优化时段最大负荷与典型日最大负荷的差值,在选择的典型日最优开机方式的基础上增加或减少与所述差值的绝对值相等的开机容量,使其匹配时段最大负荷,其中,当所述差值大于0时,增加与所述差值的绝对值相等的开机容量,当所述差值小于0时,减少与所述差值的绝对值相等的开机容量;An optimized annual start-up mode determination unit 343, which is used to select a typical day with the shortest time interval from the maximum load day in the optimization period for each optimization period, and calculate the difference between the maximum load in the optimization period and the maximum load in a typical day, And according to the difference between the maximum load of each optimization period and the maximum load of a typical day, on the basis of the selected typical daily optimal start-up mode, increase or decrease the start-up capacity equal to the absolute value of the difference, so that the matching period is the largest Load, wherein, when the difference is greater than 0, increase the starting capacity equal to the absolute value of the difference, and when the difference is less than 0, reduce the starting capacity equal to the absolute value of the difference;

合并单元344,其用于根据每个典型日时段和优化时段的开机方式确定电网全年分时段开机方式的组合。The merging unit 344 is configured to determine the combination of the time-divided start-up modes of the power grid throughout the year according to the start-up modes of each typical day period and optimal time period.

优选地,所述第一预设值的范围为0至0.1。Preferably, the range of the first preset value is 0 to 0.1.

优选地,确定中小容量机组最低年利用小时数的公式为:Preferably, the formula for determining the minimum annual utilization hours of small and medium capacity units is:

式中,In the formula,

ln:第n时段t时刻电网负荷(MW);l n : power grid load (MW) at time t of period n;

lnmax:第n时段的最大负荷值(MW);l nmax : the maximum load value (MW) of the nth period;

un:第n时段机组开机方式;u n : unit startup mode in the nth period;

Pn(un):第n时段在un开机方式下30万千瓦机组的总开机容量(MW);P n (u n ): total start-up capacity (MW) of 300,000-kilowatt units under the start-up mode of u in the nth period;

η:备用率;η: standby rate;

N:时段数;N: number of time slots;

t:时间;t: time;

h:30万千瓦机组利用小时数(h);h: Utilization hours of 300,000-kilowatt units (h);

:第i台30万千瓦及以下机组额定容量(MW); : Rated capacity (MW) of the i-th unit of 300,000 kilowatts and below;

Q30:30万千瓦及以下机组全年发电量(MWh)。Q 30 : Annual power generation (MWh) of units of 300,000 kilowatts and below.

优选地,所述备用率的计算公式为:Preferably, the formula for calculating the standby rate is:

备用率=备用容量/开机规模Reserve ratio = reserve capacity / start-up scale

式中,备用容量是指电网中最大一台机组装机容量或电网规定的备用容量值,开机规模是指电网全年分时段开机方式的组合中每个时段的开机规模。In the formula, the reserve capacity refers to the maximum installed capacity of one unit in the power grid or the reserve capacity value stipulated by the power grid, and the start-up scale refers to the start-up scale of each time period in the combination of time-segmented start-up modes of the power grid throughout the year.

通常地,在权利要求中使用的所有术语都根据他们在技术领域的通常含义被解释,除非在其中被另外明确地定义。所有的参考“一个/所述/该【装置、组件等】”都被开放地解释为所述装置、组件等中的至少一个实例,除非另外明确地说明。这里公开的任何方法的步骤都没必要以公开的准确的顺序运行,除非明确地说明。Generally, all terms used in the claims are to be interpreted according to their ordinary meaning in the technical field, unless explicitly defined otherwise therein. All references to "a/the/the [means, component, etc.]" are to be construed openly as at least one instance of said means, component, etc., unless expressly stated otherwise. The steps of any method disclosed herein do not have to be performed in the exact order disclosed, unless explicitly stated.

Claims (26)

1. a kind of method of the determining minimum annual utilization hours of power grid Small And Medium Capacity unit, which is characterized in that the method includes:
The typical day of network load is determined according to power grid whole year load curve, wherein typical case's day includes power grid whole year load Monthly peak day, legal festivals and holidays in curve and the working day for representing monthly average load each moon;
According to load data, unit maintenance scheduling and the unit heat supply steam supply demand of each typical day, to the typical day Progress electricity net safety stable is checked one by one and start-up mode optimizes, and obtaining each typical case makes the optimal of medium and small unit booting minimum day Start-up mode;
According to the characteristic of power grid whole year load curve, determining optimal start-up mode of typical day is extended to and annual is switched at times The combination of mode;
It is small that utilizing in minimum year for medium and small unit is calculated according to the combination of power grid whole year load curve and annual start-up mode at times When number.
2. according to the method described in claim 1, it is characterized in that, determining network load according to power grid whole year load curve Further include acquisition electric network data before typical day, wherein the data packet includes power grid whole year load curve, power grid region-by-region whole year Load curve, unit maintenance scheduling and unit heat supply steam supply demand.
3. according to claim 1 or claim 2, which is characterized in that load data, the machine of the basis each typical day Group repair schedule and unit heat supply steam supply demand, carry out electricity net safety stable check one by one to the typical case and start-up mode is excellent days Change, obtaining the optimal start-up mode that each typical case makes medium and small unit booting minimum day includes:
The unit gross output and unit reserve capacity of typical day power grid are calculated according to the load data of each typical day;
According to the unit of the unit gross output of the power grid and unit reserve calculation of capacity power grid booting scale;
According to unit maintenance scheduling and unit heat supply steam supply demand, determines the maintenance unit of each typical day and retain unit;
The start-up mode of the unit other than each medium and small unit and medium and small unit of typical day is determined according to booting scale;
Basic trend, static security, transient security are carried out under each typical Daily treatment cost to power grid to check;
After the basic trend that is carried out to power grid, static security, transient security check pass through, to the waist lotus and paddy of each typical day The electricity net safety stable that lotus carries out is checked also by rear, then according to booting scale each of determine typical day medium and small unit and in The start-up mode of unit other than small unit is the optimal start-up mode of typical day.
4. according to the method described in claim 3, it is characterized in that, calculating the machine of power grid according to the load data of each typical day Group gross output and the formula of unit reserve capacity are:
In formula,I-th of typical day unit gross output;
I-th of typical day power grid Daily treatment cost;
External power grid is sent into power within i-th typical day;
Power grid sends out power within i-th typical day;
The spare capacity of i-th of typical day;
Punit_max:Power grid one unit installed capacity of maximum.
5. according to the method described in claim 3, it is characterized in that, the spare capacity P of described i-th typical days iIt is power grid rule Fixed spare capacity.
6. according to the method described in claim 4 or 5, which is characterized in that according to the unit gross output of the power grid and Unit reserve calculation of capacity power grid unit booting scale formula be:
In formula,The booting scale of i-th of typical day.
7. according to the method described in claim 3, it is characterized in that, described determine medium and small unit and medium and small machine according to booting scale The start-up mode of unit other than group refers to the medium and small unit booting quantity of compression, increases the large-sized unit start number other than medium and small unit Amount is to reach booting scale.
8. according to the method described in claim 3, it is characterized in that, waist lotus and Gu He to each typical day carry out power grid security Stability check refers to determining waist charge values and Gu He of each subregion in each typical day according to power grid region-by-region whole year load curve On the basis of value, electricity net safety stable check is carried out to the waist lotus and Gu He of each typical day.
9. according to the method described in claim 3, it is characterized in that, carrying out basic trend, static security, transient security to power grid Check does not pass through, or the basic trend to power grid progress, static security, transient security are checked after passing through, to each allusion quotation of power grid It is obstructed out-of-date that the waist lotus of type day and Gu He progress electricity net safety stables are checked, in being checked according to the typical day electricity net safety stable There are the problem of be switched on quantity according to compressing medium and small unit again, increase the method for the large-sized unit booting quantity other than medium and small unit It is checked to adjust start-up mode and continue electricity net safety stable, until electricity net safety stable.
10., will be determining according to the method described in claim 1, it is characterized in that, according to the characteristic of power grid whole year load curve The combination that typical day optimal start-up mode is extended to annual start-up mode at times includes:
On the basis of each typical Daily treatment cost, will be adjacent with typical day and belong to the same moon, and peak load and allusion quotation Working day of the difference of type Daily treatment cost within the first preset value is as typical period day;
By whole year each of in addition to typical period day the remaining period, take day on the basis of day part peak day, will remove the Base day The difference of Daily treatment cost and benchmark daily load other than load is within the first preset value, and the working day for belonging to the same moon is made Optimize the period for the first of each remaining period, and each remaining period is belonged into its of the same moon in addition to the first optimization period Also period as an optimization his period;
For each optimization period, selection and the optimization period peak day interval time shortest typical day, and calculate The difference of the optimization period peak load and typical Daily treatment cost;
According to the difference of each optimization period peak load and typical Daily treatment cost, in the optimal start-up mode of typical day of selection On the basis of increase or decrease the booting capacity equal with the absolute value of the difference, make its match period peak load, wherein When the difference is more than 0, increase the booting capacity equal with the absolute value of the difference, when the difference is less than 0, reduces The booting capacity equal with the absolute value of the difference;
The combination of power grid whole year start-up mode at times is determined according to the start-up mode of each typical period day and optimization period.
11. according to the method described in claim 10, it is characterized in that, ranging from the 0 to 0.1 of first preset value.
12. according to the method described in claim 10, it is characterized in that, determining the minimum annual utilization hours of Small And Medium Capacity unit Formula is:
In formula,
ln:N-th period t moment network load (MW);
lnmax:The peak load value (MW) of n-th period;
un:N-th period unit start-up mode;
Pn(un):N-th period is in unTotal booting capacity (MW) of 300,000 kilowatts of units under start-up mode;
η:Percentage reserve;
N:When hop count;
t:Time;
h:300000 kilowatts of units utilize hourage (h);
I-th 300,000 kilowatts and following unit rated capacity (MW);
Q30:300000 kilowatts and following unit whole year generated energy (MWh).
13. according to the method for claim 12, which is characterized in that the calculation formula of the percentage reserve is:
Percentage reserve=spare capacity/booting scale
In formula, spare capacity refers to spare capacity value, booting rule as defined in a maximum unit installed capacity or power grid in power grid Mould refers to the booting scale of each period in the combination of start-up mode at times of power grid whole year.
14. a kind of system of the determining minimum annual utilization hours of power grid Small And Medium Capacity unit, which is characterized in that the system packet It includes:
Typical day determination unit is used to determine the typical day of network load according to power grid whole year load curve, wherein the allusion quotation Type day includes the work for representing monthly peak day, legal festivals and holidays and each moon monthly average load in power grid whole year load curve Make day;
Typical day start-up mode determination unit, be used for according to the load data of each typical day, unit maintenance scheduling and Unit heat supply steam supply demand carries out electricity net safety stable check day to the typical case and start-up mode optimizes, obtains each one by one The optimal start-up mode for making medium and small unit booting minimum typical day;
Annual start-up mode determination unit, is used for the characteristic according to power grid whole year load curve, and determining typical day is optimal Start-up mode is extended to the combination of annual start-up mode at times;
Interpretation of result unit is used to be calculated according to the combination of power grid whole year load curve and annual start-up mode at times medium and small The minimum annual utilization hours of unit.
15. system according to claim 14, which is characterized in that the system also includes data acquisition units, are used for Electric network data is acquired, wherein the data packet includes power grid whole year load curve, power grid region-by-region whole year load curve, unit maintenance Plan and unit heat supply steam supply demand.
16. according to the system described in claim 14 or 15, which is characterized in that typical case's day start-up mode determination unit packet It includes:
Unit booting scale determination unit, the unit for being used to calculate typical case's day power grid according to the load data of each typical day are total Output power and unit reserve capacity, and according to the unit gross output of the power grid and unit reserve calculation of capacity power grid Unit booting scale;
Maintenance and reservation unit determination unit are used to, according to unit maintenance scheduling and unit heat supply steam supply demand, determine each The maintenance unit and reservation unit of typical day;
Unit start-up mode determination unit is used to determine the medium and small unit of each typical day and medium and small unit according to booting scale The start-up mode of unit in addition, and based on the start-up mode, power grid is carried out under each typical Daily treatment cost Basic trend, static security, transient security are checked, when basic trend that power grid is carried out, static security, transient security check it is logical Later, the electricity net safety stable that the waist lotus to each typical day and Gu He are carried out is checked also by rear, then true according to booting scale The medium and small unit of each of fixed typical case's day and the start-up mode of the unit other than medium and small unit are the typical day optimal booting Mode.
17. system according to claim 16, which is characterized in that calculate power grid according to the load data of each typical day The formula of unit gross output and unit reserve capacity is:
In formula,I-th of typical day unit gross output;
I-th of typical day power grid Daily treatment cost;
External power grid is sent into power within i-th typical day;
Power grid sends out power within i-th typical day;
The spare capacity of i-th of typical day;
Punit_max:Power grid one unit installed capacity of maximum.
18. system according to claim 16, which is characterized in that the spare capacity of described i-th typical dayIt is power grid Defined spare capacity.
19. according to the system described in claim 17 or 18, which is characterized in that according to the unit gross output of the power grid It is with the be switched on formula of scale of the unit of unit reserve calculation of capacity power grid:
In formula,The booting scale of i-th of typical day.
20. system according to claim 16, which is characterized in that described to determine medium and small unit and medium and small according to booting scale The start-up mode of unit other than unit refers to the medium and small unit booting quantity of compression, increases the large-sized unit booting other than medium and small unit Quantity is to reach booting scale.
21. system according to claim 16, which is characterized in that carry out power grid peace to the waist lotus and Gu He of each typical day Full stability check refers to determining waist charge values and paddy of each subregion in each typical day according to power grid region-by-region whole year load curve On the basis of charge values, electricity net safety stable check is carried out to the waist lotus and Gu He of each typical day.
22. system according to claim 16, which is characterized in that the unit start-up mode confirmation unit carries out power grid Basic trend, static security, transient security check do not pass through, or pacify to basic trend, static security, the transient state that power grid carries out After whole school's core passes through, to power grid, each the waist lotus of typical day and Gu He progress electricity net safety stable checks are obstructed out-of-date, according to institute The problem of typical day electricity net safety stable is checked is stated again according to medium and small unit booting quantity is compressed, and increases medium and small unit The method of large-sized unit booting quantity in addition is checked to adjust start-up mode and continue electricity net safety stable, until power grid is pacified It is complete to stablize.
23. system according to claim 16, which is characterized in that it is described year start-up mode determination unit include:
Typical period day determination unit is used on the basis of each typical Daily treatment cost, will be adjacent with typical day and be belonged to The same moon, and peak load and the difference of typical Daily treatment cost are when the working day within the first preset value is as typical day Section;
Optimize period determination unit, is used for whole year the remaining period each of in addition to typical period day, takes day part maximum negative Day on the basis of lotus day, by the difference of Daily treatment cost and benchmark daily load in addition to benchmark daily load within the first preset value, And belong to first optimization period of the working day as each residue period of the same moon, and it is excellent each remaining period will to remove first Change and belongs to also period as an optimization other periods of the same moon outside the period;
The annual start-up mode determination unit of optimization was used for for each optimization period, and selection is negative with the optimization period maximum Lotus day interval time shortest typical day, and the difference of the optimization period peak load and typical Daily treatment cost is calculated, with And difference according to each optimization period peak load and typical Daily treatment cost, in the optimal start-up mode of typical day of selection On the basis of increase or decrease the booting capacity equal with the absolute value of the difference, make its match period peak load, wherein when When the difference is more than 0, increase the booting capacity equal with the absolute value of the difference, when the difference is less than 0, reduce and The equal booting capacity of the absolute value of the difference;
Combining unit is used to determine that power grid whole year opens at times according to the start-up mode of each typical period day and optimization period The combination of machine mode.
24. system according to claim 23, which is characterized in that ranging from the 0 to 0.1 of first preset value.
25. system according to claim 23, which is characterized in that determine the minimum annual utilization hours of Small And Medium Capacity unit Formula is:
In formula,
ln:N-th period t moment network load (MW);
lnmax:The peak load value (MW) of n-th period;
un:N-th period unit start-up mode;
Pn(un):N-th period is in unTotal booting capacity (MW) of 300,000 kilowatts of units under start-up mode;
η:Percentage reserve;
N:When hop count;
t:Time;
h:300000 kilowatts of units utilize hourage (h);
I-th 300,000 kilowatts and following unit rated capacity (MW);
Q30:300000 kilowatts and following unit whole year generated energy (MWh).
26. system according to claim 25, which is characterized in that the calculation formula of the percentage reserve is:
Percentage reserve=spare capacity/booting scale
In formula, spare capacity refers to spare capacity value, booting rule as defined in a maximum unit installed capacity or power grid in power grid Mould refers to the booting scale of each period in the combination of start-up mode at times of power grid whole year.
CN201810348855.1A 2018-04-18 2018-04-18 Method and system for determining the minimum annual utilization hours of small-capacity units in the power grid Active CN108683210B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810348855.1A CN108683210B (en) 2018-04-18 2018-04-18 Method and system for determining the minimum annual utilization hours of small-capacity units in the power grid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810348855.1A CN108683210B (en) 2018-04-18 2018-04-18 Method and system for determining the minimum annual utilization hours of small-capacity units in the power grid

Publications (2)

Publication Number Publication Date
CN108683210A true CN108683210A (en) 2018-10-19
CN108683210B CN108683210B (en) 2021-04-23

Family

ID=63801100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810348855.1A Active CN108683210B (en) 2018-04-18 2018-04-18 Method and system for determining the minimum annual utilization hours of small-capacity units in the power grid

Country Status (1)

Country Link
CN (1) CN108683210B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110262422A (en) * 2019-06-21 2019-09-20 华南理工大学 The determination method of the design basis day of industry park cool and thermal power terminal energy sources supply system
CN110826778A (en) * 2019-10-23 2020-02-21 上海电机学院 A load characteristic optimization calculation method that actively adapts to the development of new energy

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104578122A (en) * 2015-02-04 2015-04-29 华北电力科学研究院有限责任公司 Method for determining capacity of pumped storage power station

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104578122A (en) * 2015-02-04 2015-04-29 华北电力科学研究院有限责任公司 Method for determining capacity of pumped storage power station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吕泉等: "基于调峰能力分析的电网弃风情况评估方法", 《电网技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110262422A (en) * 2019-06-21 2019-09-20 华南理工大学 The determination method of the design basis day of industry park cool and thermal power terminal energy sources supply system
CN110826778A (en) * 2019-10-23 2020-02-21 上海电机学院 A load characteristic optimization calculation method that actively adapts to the development of new energy
CN110826778B (en) * 2019-10-23 2023-07-07 上海电机学院 A load characteristic optimization calculation method that actively adapts to the development of new energy sources

Also Published As

Publication number Publication date
CN108683210B (en) 2021-04-23

Similar Documents

Publication Publication Date Title
CN102593853B (en) Energy storage system capacity configuration optimizing method capable of enhancing wind power receiving capacity
CN108133322B (en) Power and electric quantity balance index calculation method based on time sequence operation simulation
CN111799772B (en) An Optimal Scheduling Method for Electric Heating System Considering Deep Peak Regulation of Units
Denholm et al. Simulating the value of concentrating solar power with thermal energy storage in a production cost model
CN111416388B (en) Method for determining energy storage demand and energy storage duration of high-proportion new energy system
Belmili et al. A computer program development for sizing stand-alone Photovoltaic-Wind hybrid systems
CN112488374A (en) Generalized demand response optimization proportioning research method based on time sequence production simulation
CN114744638A (en) Power system adjustable load capacity optimization method based on new energy consumption
CN108683210A (en) Determine the method and system of the minimum annual utilization hours of power grid Small And Medium Capacity unit
CN114492085A (en) Regional power and electric quantity balancing method related to load and power supply joint probability distribution
CN112329263A (en) A comprehensive energy system optimization method and terminal equipment
CN106257792A (en) A kind of new forms of energy priority scheduling method based on two benches Unit Combination
CN109038589A (en) A kind of more provinces and regions electric network coordination operation production analogy methods
CN110415139B (en) A heat storage capacity allocation method for thermal power units with heat storage considering peak shaving costs
CN106451569A (en) Daily on-off type peak load operation method of gas engine set
CN112418537B (en) Optimized scheduling method for multi-energy cloud energy storage system
CN113991749A (en) New energy equivalent internet-surfing electricity price analysis method
CN108960564A (en) Supply of cooling, heating and electrical powers type microgrid distribution system dispatching method based on centralization modeling
CN110224397B (en) User-side battery energy storage cost benefit analysis method under wind and light access background
CN116505512A (en) Micro-grid optimization operation method considering load demand response
CN107453377B (en) Solar thermal power generation heat storage proportion analysis method
CN112528210B (en) Combined cooling heating and power system and control method
CN108364104B (en) Multi-energy complementary power generation method
CN116805792B (en) Method and system for determining thermal power-energy storage regulation demand in high-proportion new energy systems
CN113762643A (en) Energy storage capacity optimal configuration method of regional comprehensive energy system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant