CN108679363A - A kind of sewage conduct robot moving device and its mode of progression - Google Patents

A kind of sewage conduct robot moving device and its mode of progression Download PDF

Info

Publication number
CN108679363A
CN108679363A CN201810614948.4A CN201810614948A CN108679363A CN 108679363 A CN108679363 A CN 108679363A CN 201810614948 A CN201810614948 A CN 201810614948A CN 108679363 A CN108679363 A CN 108679363A
Authority
CN
China
Prior art keywords
drive
gear
central shaft
rotation axis
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810614948.4A
Other languages
Chinese (zh)
Inventor
胡巧玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenling Hada Electric Appliance Co Ltd
Original Assignee
Wenling Hada Electric Appliance Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenling Hada Electric Appliance Co Ltd filed Critical Wenling Hada Electric Appliance Co Ltd
Priority to CN201810614948.4A priority Critical patent/CN108679363A/en
Publication of CN108679363A publication Critical patent/CN108679363A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/26Pigs or moles, i.e. devices movable in a pipe or conduit with or without self-contained propulsion means
    • F16L55/28Constructional aspects
    • F16L55/30Constructional aspects of the propulsion means, e.g. towed by cables
    • F16L55/32Constructional aspects of the propulsion means, e.g. towed by cables being self-contained
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L2101/00Uses or applications of pigs or moles
    • F16L2101/10Treating the inside of pipes
    • F16L2101/12Cleaning

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Manipulator (AREA)

Abstract

The invention discloses a kind of sewage conduct robot moving devices,Including traveling vehicle frame,It is provided with the first power cavity in the traveling vehicle frame,Before and after first power cavity the first central shaft is rotatably mounted in end wall,It is provided with the second power cavity on front side of first power cavity,The second central shaft with first central shaft on the same axis is rotatably mounted with before and after second power cavity in end wall,The front and back through-hole communicated is both provided in first central shaft and the second central shaft,Third central shaft is rotatably mounted in the through-hole,It is installed with the first armature block in the through-hole wall of first central shaft,It is installed with the second armature block in the through-hole wall of second central shaft,The first electromagnet and the second electromagnet coordinated respectively with first armature block and the second armature block is installed in the third central shaft.

Description

A kind of sewage conduct robot moving device and its mode of progression
Technical field
The present invention relates to robot field, specifically a kind of sewage conduct robot moving device and its mode of progression.
Background technology
Sewage conduct is component part important in municipal sewage net, and sewage is discharged by sewage conduct, and sewage conduct Often it can be blocked by the impurity in sewage, if dredged not in time, sewerage can be caused to paralyse, city fortune can be seriously affected Row, pipe robot are that one kind can automatically walk, the one or more sensors of carrying and operation inside or outside small sized pipeline It is integrated to carry out a series of the mechanical, electrical of pipeline operations, instrument under the straighforward operation of staff or computer controlled automatic for machinery Change system;Traditional robot is influenced during traveling by its traveling mode, and the scope of application is small, and sewage conduct inner wall Due to the limitation of preparation process, therefore some places, which have protrusion part, can influence the traveling of pipe robot.
Invention content
Deficiency in view of the above technology, the present invention propose a kind of sewage conduct robot moving device.
A kind of sewage conduct robot moving device of apparatus of the present invention, including traveling vehicle frame are set in the traveling vehicle frame It is equipped with the first power cavity, the first central shaft, first power is rotatably mounted in end wall before and after first power cavity It is provided with the second power cavity on front side of chamber, is rotatably mounted with and first central shaft in end wall before and after second power cavity The second central shaft on the same axis is both provided with the front and back through-hole communicated in first central shaft and the second central shaft, It is rotatably mounted with third central shaft in the through-hole, the first rank is installed in the through-hole wall of first central shaft Iron block is installed with the second armature block in the through-hole wall of second central shaft, is fixedly mounted in the third central shaft There are the first electromagnet and the second electromagnet coordinated respectively with first armature block and the second armature block, the third central shaft Rear end and the driving motor be connected by power being fixedly mounted in the first power cavity aft bulkhead, it is fixed on first central shaft Gear is installed, first bevel gear is installed on second central shaft, first power cavity is symmetrically set both sides up and down It is equipped with the first drive cavity extended forward, is rotatably mounted between first drive cavity and second power cavity up and down The first rotation axis extended, first rotation axis one end extend into second power cavity and are installed with and described the The second bevel gear of one bevel gear engagement, the other end extend into first drive cavity and are installed with second gear, institute State that side of first drive cavity far from first power cavity is symmetrical above and below to be provided with the first sliding groove, first sliding groove is remote Side from first drive cavity is provided with the second sliding groove communicated with outside, and second sliding groove is slided with described first Dynamic slot is connected, and sliding shoe is slidably fitted in first sliding groove, be slidably fitted in second sliding groove with it is described The brake pad that sliding shoe is fixedly connected, is provided with thread groove of the opening towards first drive cavity in the sliding shoe, and first The threaded rod extended up and down is rotatably mounted between sliding groove and first drive cavity, described threaded rod one end is extend into Screw-thread fit, the other end extend into first drive cavity and are installed with and described second in the thread groove and therewith The third gear of gear engagement, described traveling vehicle frame or so are both provided with mounting groove in end face, are fixedly mounted in the mounting groove There is camera probe, it is symmetrical above and below in the walked frame to be provided with walking group to facilitate the situation of observation inside sewage pipeline Part.
Further technical solution, the walking component include be symmetrical set at left and right sides of the sliding shoe and with The swinging chute that first power cavity is connected is equipped with swing arm in the swinging chute by the swing of the second rotation axis, described Second rotation axis is rotatably engaged with the swing arm and close to first power cavity, and two before and after second rotation axis End is installed in rotation on before and after the swinging chute in end wall, be located in the swing arm at second shaft be provided with it is flat Slot is provided with the 4th gear being fixedly connected with second rotation axis and first pulley, the 4th tooth in the flat slot Wheel is engaged with the first gear, is additionally provided with the second drive cavity communicated with the flat slot in the swing arm, and described the The one end of two drive cavities far from second rotation axis is rotatably mounted with third rotation axis, and the third rotation shaft rear end is stretched Go out the swing arm and be installed with traveling wheel, is provided in second drive cavity and is fixedly connected with the third rotation axis The second belt wheel, by transmission belt be connected by power, the walking wheel outer surface is fixed for the first pulley and second belt wheel Skid resistant course is installed, to which frictional force can be improved when offseting with sewage conduct inner wall, to increase traveling stability.
Further technical solution, the swinging chute are installed with and the swing on the end wall of the sliding groove The extension spring that arm is fixedly connected, the swinging chute are installed with solid with the swing arm on the end wall far from the sliding groove Surely the top pressure spring connected, the extension spring and the top pressure spring are making the swing arm be put close to the sliding groove It is dynamic, so as to make the distance between two traveling wheels maximum up and down.
Further technical solution, notch of the swinging chute far from first power cavity are installed with and the pendulum The elastic packing tilt that swing arm is fixedly connected, thus prevents water to enter in the swinging chute.
The beneficial effects of the invention are as follows:
Apparatus of the present invention when in use, the swing arm are stirred far from the sliding groove and is made up and down between two traveling wheels Distance reduce and be tucked into sewage conduct, the traveling vehicle frame is completely into after in the sewage conduct, in the drawing Under the action of stretching spring and the top pressure spring, the traveling wheel can offset with the sewage conduct inner wall, then start institute It states waterproof machine and first electromagnet is made to power on, first electromagnet may act on the armature block after the power is turned on, and The waterproof machine can drive first rotation axis to rotate when driving the second rotation axis rotation, and first rotation axis can The first gear is driven to rotate, the first gear can drive the 4th gear to rotate, and the 4th gear can pass through institute Stating the second rotation axis drives the first pulley rotation, the first pulley to drive second band to rotate by the transmission belt Dynamic, second belt wheel can drive the traveling wheel, so as to make the traveling vehicle frame advance in the sewage conduct;
When the traveling vehicle frame advances to plugging point, make electricity under first electromagnet, and the second electromagnet can be made to power on, by This described waterproof machine can drive the first bevel gear to rotate, and the first bevel gear can be driven by the second bevel gear The second gear turns, and the second gear can drive the threaded rod to rotate by the third gear, and the threaded rod can The sliding shoe is driven to slide in and out, the sliding shoe can drive the brake pad to be held out against with the sewage conduct inner wall, thus The traveling vehicle frame can be made to be relatively fixed with sewage conduct, the dredging component in traveling vehicle frame can then carried out blocking portion Dredging;
Since the swing arm in apparatus of the present invention can be swung with sewage conduct internal diameter, it is thus suitable for the sewage pipe of different-diameter Road, and when sewage conduct inner wall encounters protrusion, can automatically adjust, it does not influence to advance, adaptable, it is suitable for levels Pipeline, tilted tube and vertical pipeline.
Description of the drawings
It, below will be to embodiment or the prior art in order to illustrate more clearly of inventive embodiments or technical solution in the prior art Attached drawing needed in description is briefly described, it should be apparent that, the accompanying drawings in the following description is only one invented A little embodiments for those of ordinary skill in the art without creative efforts, can also be according to these Attached drawing obtains other attached drawings.
Fig. 1 is a kind of structural schematic diagram of sewage conduct robot moving device of the present invention.
Fig. 2 is the structural schematic diagram of arrow direction in Fig. 1.
Specific implementation mode
All features disclosed in this specification or disclosed all methods or in the process the step of, in addition to mutually exclusive spy Other than sign and/or step, it can combine in any way.
Any feature disclosed in this specification unless specifically stated can be equivalent or with similar purpose by other Alternative features are replaced.That is, unless specifically stated, each feature is an example in a series of equivalent or similar characteristics .
As shown in Figure 1 to Figure 2, a kind of sewage conduct robot moving device of apparatus of the present invention, including traveling vehicle frame 10, It is provided with the first power cavity 11 in the traveling vehicle frame 10, is rotatably mounted in end wall before and after first power cavity 11 One central shaft 12, the front side of first power cavity 11 are provided with the second power cavity 110, end wall before and after second power cavity 110 In be rotatably mounted with the second central shaft 45 with first central shaft 12 on the same axis, first central shaft 12 With the front and back through-hole communicated is both provided in the second central shaft 45, be rotatably mounted with third central shaft 40 in the through-hole, The first armature block 44, the through-hole wall of second central shaft 45 are installed in the through-hole wall of first central shaft 12 In be installed with the second armature block 43, be installed in the third central shaft 40 respectively with first armature block 44 and Second armature block 43 cooperation the first electromagnet 41 and the second electromagnet 42,45 rear end of third central shaft be fixedly mounted on 28 be connected by power of driving motor in first power cavity, 11 aft bulkhead is installed with gear on first central shaft 12 13, first bevel gear 37 is installed on second central shaft 45, first power cavity, about 11 both sides are symmetrical arranged There is the first drive cavity 29 extended forward, is rotatably mounted between first drive cavity 29 and second power cavity 110 There are the first rotation axis 35 extended up and down, described first rotation axis, 35 one end to extend into second power cavity 110 and fix The second bevel gear 36 engaged with the first bevel gear 37 is installed, the other end extend into first drive cavity 29 and consolidates Dingan County is equipped with second gear 34, and side of first drive cavity 29 far from first power cavity 11 be symmetrical above and below to be provided with the One sliding groove, side of first sliding groove far from first drive cavity 29 are provided with the second sliding communicated with outside Slot, second sliding groove are connected with first sliding groove, and sliding shoe 33, institute are slidably fitted in first sliding groove The brake pad 32 for being slidably fitted in the second sliding groove and being fixedly connected with the sliding shoe 33 is stated, is provided in the sliding shoe 33 The thread groove being open towards first drive cavity 29, is rotatably mounted between the first sliding groove and first drive cavity 29 There is a threaded rod 31 extended up and down, 31 one end of the threaded rod is extend into the thread groove and screw-thread fit therewith, the other end It extend into first drive cavity 29 and is installed with the third gear 30 engaged with the second gear 34, the traveling Vehicle frame is both provided with mounting groove in 10 or so end faces, and camera probe 101 is installed in the mounting groove, to facilitate observation The situation of inside sewage pipeline, it is symmetrical above and below in the walked frame 10 to be provided with walking component.
Valuably or illustratively, wherein the walking component includes being symmetrical set in the sliding shoe 33 or so Both sides and the swinging chute 15 being connected with first power cavity 11 pass through the second rotation axis 19 in the swinging chute 15 and swing peace Equipped with swing arm 22, second rotation axis 19 is rotatably engaged with the swing arm 22 and close to first power cavity 11, and 19 rear and front end of the second rotation axis is installed in rotation on before and after the swinging chute 15 in end wall, the swing arm It is located in 23 at second shaft 19 and is provided with flat slot 27, is provided in the flat slot 27 and second rotation axis 19 The 4th gear 18 and first pulley 20 being fixedly connected, the 4th gear 18 are engaged with the first gear 13, the swing The second drive cavity 23 communicated with the flat slot 27 is additionally provided in arm 23, second drive cavity 23 is far from described second turn One end of moving axis 19 is rotatably mounted with third rotation axis 19, and the swing arm 22 is stretched out simultaneously in 19 rear end of third rotation axis It is installed with traveling wheel 26, the second band being fixedly connected with the third rotation axis 24 is provided in second drive cavity 23 Wheel 25, the first pulley 20 with second belt wheel 25 by transmission belt be connected by power, fix by 26 outer surface of the traveling wheel Skid resistant course 260 is installed, to which frictional force can be improved when offseting with sewage conduct inner wall, to increase traveling stability.
Valuably or illustratively, wherein the swinging chute 15 be installed on the end wall of the sliding groove with The extension spring 17 that the swing arm 22 is fixedly connected, the swinging chute 15 are installed on the end wall far from the sliding groove The top pressure spring 14 being fixedly connected with the swing arm 22, the extension spring 17 and the top pressure spring 14 are described to make Swing arm 22 is swung close to the sliding groove, so as to make the distance between two traveling wheels 26 maximum up and down.
Valuably or illustratively, wherein notch of the swinging chute 15 far from first power cavity 11 is fixedly mounted There is the elastic packing tilt 16 being fixedly connected with the swing arm 22, water is thus prevented to enter in the swinging chute 15.
Apparatus of the present invention in the initial state, under the action of the extension spring 17 and the top pressure spring 14, institute It states swing arm 22 to swing close to the sliding groove, so as to make the distance between two traveling wheels 26 maximum up and down, the friction Block 32 is contracted in second sliding groove.
In use, the swing arm 22 is stirred far from the sliding groove and between making upper and lower two traveling wheels 26 away from From reducing and be tucked into sewage conduct, the traveling vehicle frame 10 is completely into after in the sewage conduct, in the stretching Under the action of spring 17 and the top pressure spring 14, the traveling wheel 26 can offset with the sewage conduct inner wall, then open The dynamic waterproof machine 28 simultaneously makes first electromagnet 41 power on, and first electromagnet 41 may act on the rank after the power is turned on Iron block 44, and can drive 12 turns of first rotation axis when the waterproof machine 28 drives second rotation axis 40 to rotate Dynamic, first rotation axis 12 can drive the first gear 13 to rotate, and the first gear 13 can drive the 4th gear 18 rotations, the 4th gear 18 can drive the first pulley 20 to rotate by second rotation axis 19, the first band Wheel 20 drives second belt wheel 25 to rotate by the transmission belt 21, and second belt wheel 25 can drive the traveling wheel 26, So as to make the traveling vehicle frame 10 advance in the sewage conduct, when the traveling vehicle frame 10 advances to plugging point, make First electromagnet, 41 times electricity, and the second electromagnet 42 can be made to power on, thus the waterproof machine 28 can drive described first Bevel gear 37 rotates, and the first bevel gear can drive 34 turns of the second gear by the second bevel gear 36, and described the Two gears 34 can drive the threaded rod 31 to rotate by the third gear 30, and the threaded rod 31 can drive the sliding shoe 33 slide in and out, and the sliding shoe 33 can drive the brake pad 32 to be held out against with the sewage conduct inner wall, thus can make described Traveling vehicle frame 10 is relatively fixed with sewage conduct, and the dredging component in traveling vehicle frame 10 can then dredged blocking portion It is logical.
The beneficial effects of the invention are as follows:Apparatus of the present invention are stirred far from the sliding groove when in use, by the swing arm And make up and down the distance between two traveling wheels reduce and be tucked into sewage conduct, the traveling vehicle frame is completely into described After in sewage conduct, under the action of the extension spring and the top pressure spring, the traveling wheel can be with the sewage pipe Road inner wall offsets, and then starts the waterproof machine and first electromagnet is made to power on, first electromagnet after the power is turned on may be used The armature block is acted on, and first rotation axis can be driven when the waterproof machine drives the second rotation axis rotation Rotation, first rotation axis can drive the first gear to rotate, and the first gear can drive the 4th gear to rotate, 4th gear can drive the first pulley to rotate by second rotation axis, and the first pulley passes through the transmission Band drives the second belt wheel rotation, and second belt wheel can drive the traveling wheel, so as to make the traveling vehicle frame in institute It states in sewage conduct and advances;
When the traveling vehicle frame advances to plugging point, make electricity under first electromagnet, and the second electromagnet can be made to power on, by This described waterproof machine can drive the first bevel gear to rotate, and the first bevel gear can be driven by the second bevel gear The second gear turns, and the second gear can drive the threaded rod to rotate by the third gear, and the threaded rod can The sliding shoe is driven to slide in and out, the sliding shoe can drive the brake pad to be held out against with the sewage conduct inner wall, thus The traveling vehicle frame can be made to be relatively fixed with sewage conduct, the dredging component in traveling vehicle frame can then carried out blocking portion Dredging;
Since the swing arm in apparatus of the present invention can be swung with sewage conduct internal diameter, it is thus suitable for the sewage pipe of different-diameter Road, and when sewage conduct inner wall encounters protrusion, can automatically adjust, it does not influence to advance, adaptable, it is suitable for levels Pipeline, tilted tube and vertical pipeline.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and what is described in the above embodiment and the description is only the present invention Principle, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these variation and Improvement is both fallen in claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (5)

1. a kind of sewage conduct robot moving device, including traveling vehicle frame, it is characterised in that:It is provided in the traveling vehicle frame First power cavity, is rotatably mounted with the first central shaft before and after first power cavity in end wall, before first power cavity Side is provided with the second power cavity, is rotatably mounted with first central shaft same in end wall before and after second power cavity The second central shaft on one axis is both provided with the front and back through-hole communicated in first central shaft and the second central shaft, described It is rotatably mounted with third central shaft in through-hole, the first armature is installed in the through-hole wall of first central shaft Block is installed with the second armature block in the through-hole wall of second central shaft, is installed in the third central shaft The first electromagnet and the second electromagnet coordinated respectively with first armature block and the second armature block, after the third central shaft The driving motor be connected by power in the first power cavity aft bulkhead is held and be fixedly mounted on, peace is fixed on first central shaft Equipped with gear, first bevel gear is installed on second central shaft, both sides are symmetrical arranged first power cavity up and down There is the first drive cavity extended forward, is rotatably mounted between first drive cavity and second power cavity downward The first rotation axis stretched, first rotation axis one end extend into second power cavity and are installed with and described first The second bevel gear of bevel gear engagement, the other end extend into first drive cavity and is installed with second gear, described Side of first drive cavity far from first power cavity is symmetrical above and below to be provided with the first sliding groove, and first sliding groove is separate The side of first drive cavity is provided with the second sliding groove communicated with outside, and second sliding groove is slided with described first Slot is connected, and sliding shoe is slidably fitted in first sliding groove, is slidably fitted in second sliding groove and the cunning The brake pad that motion block is fixedly connected is provided with thread groove of the opening towards first drive cavity in the sliding shoe, and first slides Dynamic that the threaded rod extended up and down is rotatably mounted between slot and first drive cavity, described threaded rod one end extend into institute It states in thread groove and screw-thread fit, the other end extend into first drive cavity and be installed with and second tooth therewith The third gear of engagement is taken turns, described traveling vehicle frame or so is both provided with mounting groove in end face, is installed in the mounting groove Camera probe, it is symmetrical above and below in the walked frame to be provided with walking component to facilitate the situation of observation inside sewage pipeline.
2. a kind of sewage conduct robot moving device according to claim 1, it is characterised in that:The walking component packet Include the swinging chute for being symmetrical set at left and right sides of the sliding shoe and being connected with first power cavity, the swinging chute In swing arm is equipped with by the swing of the second rotation axis, second rotation axis is rotatably engaged and close with the swing arm First power cavity, and second rotation axis rear and front end is installed in rotation on before and after the swinging chute in end wall, institute It states in swing arm to be located at second shaft and is provided with flat slot, be provided in the flat slot solid with second rotation axis Surely the 4th gear and first pulley connected, the 4th gear are engaged with the first gear, are also set up in the swing arm There is the second drive cavity communicated with the flat slot, the one end of second drive cavity far from second rotation axis is rotationally Third rotation axis is installed, the third rotation shaft rear end stretches out the swing arm and is installed with traveling wheel, and described second The second belt wheel being fixedly connected with the third rotation axis is provided in drive cavity, the first pulley is logical with second belt wheel Transmission belt be connected by power is crossed, the walking wheel outer surface is installed with skid resistant course, to when offseting with sewage conduct inner wall Frictional force can be improved, to increase traveling stability.
3. a kind of sewage conduct robot moving device according to claim 2, it is characterised in that:The swinging chute is close The extension spring being fixedly connected with the swing arm is installed on the end wall of the sliding groove, the swinging chute is far from described The top pressure spring being fixedly connected with the swing arm, the extension spring and the top are installed on the end wall of sliding groove Pressing spring is to make the swing arm be swung close to the sliding groove, so as to make the distance between upper and lower two traveling wheels most Greatly.
4. a kind of sewage conduct robot moving device according to claim 2, it is characterised in that:The swinging chute is separate The notch of first power cavity is installed with the elastic packing tilt being fixedly connected with the swing arm, thus prevents water It enters in the swinging chute.
5. a kind of mode of progression of sewage conduct robot moving device according to claim 1-4, it is characterised in that:It is first First by the swing arm far from the sliding groove stir and make up and down the distance between two traveling wheels reduce and be tucked into sewage In pipeline, the traveling vehicle frame is completely into after in the sewage conduct, in the extension spring and the top pressure spring Under the action of, the traveling wheel can offset with the sewage conduct inner wall, then start the waterproof machine and make described first Electromagnet powers on, and first electromagnet may act on the armature block after the power is turned on, and in waterproof machine driving described the Two rotation axis can drive first rotation axis to rotate when rotating, first rotation axis can drive the first gear to rotate, The first gear can drive the 4th gear to rotate, and the 4th gear can drive described the by second rotation axis One belt wheel rotates, and the first pulley drives second belt wheel to rotate by the transmission belt, and second belt wheel can drive The traveling wheel, so as to make the traveling vehicle frame advance in the sewage conduct, when the traveling vehicle frame advances to blocking When point, make electricity under first electromagnet, and the second electromagnet can be made to power on, thus the waterproof machine can drive described first Bevel gear rotates, and the first bevel gear can drive the second gear to turn by the second bevel gear, the second gear The threaded rod can be driven to rotate by the third gear, the threaded rod can drive the sliding shoe to slide in and out, described Sliding shoe can drive the brake pad to be held out against with the sewage conduct inner wall, thus can make the traveling vehicle frame and sewage conduct phase To fixation.
CN201810614948.4A 2018-06-14 2018-06-14 A kind of sewage conduct robot moving device and its mode of progression Withdrawn CN108679363A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810614948.4A CN108679363A (en) 2018-06-14 2018-06-14 A kind of sewage conduct robot moving device and its mode of progression

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810614948.4A CN108679363A (en) 2018-06-14 2018-06-14 A kind of sewage conduct robot moving device and its mode of progression

Publications (1)

Publication Number Publication Date
CN108679363A true CN108679363A (en) 2018-10-19

Family

ID=63811008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810614948.4A Withdrawn CN108679363A (en) 2018-06-14 2018-06-14 A kind of sewage conduct robot moving device and its mode of progression

Country Status (1)

Country Link
CN (1) CN108679363A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109945012A (en) * 2019-04-03 2019-06-28 杭州谷典服饰有限公司 A kind of aqueduct detection device
CN110696014A (en) * 2019-10-31 2020-01-17 上海电力大学 Power pipeline inspection robot
CN114709747A (en) * 2022-04-13 2022-07-05 华北电力大学(保定) Self-adaptive special-shaped space cable pipeline inspection robot
CN115626270A (en) * 2022-10-31 2023-01-20 中广核研究院有限公司 Underwater replacement robot for positioning pin of nuclear power plant
CN117340904A (en) * 2023-10-25 2024-01-05 中时讯通信建设有限公司 Security patrol robot based on 5G

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109945012A (en) * 2019-04-03 2019-06-28 杭州谷典服饰有限公司 A kind of aqueduct detection device
CN110696014A (en) * 2019-10-31 2020-01-17 上海电力大学 Power pipeline inspection robot
CN114709747A (en) * 2022-04-13 2022-07-05 华北电力大学(保定) Self-adaptive special-shaped space cable pipeline inspection robot
CN114709747B (en) * 2022-04-13 2023-05-12 华北电力大学(保定) Self-adaptive special-shaped space cable duct inspection robot
CN115626270A (en) * 2022-10-31 2023-01-20 中广核研究院有限公司 Underwater replacement robot for positioning pin of nuclear power plant
CN115626270B (en) * 2022-10-31 2024-05-10 中广核研究院有限公司 Nuclear power plant locating pin underwater replacement robot
CN117340904A (en) * 2023-10-25 2024-01-05 中时讯通信建设有限公司 Security patrol robot based on 5G
CN117340904B (en) * 2023-10-25 2024-06-11 中时讯通信建设有限公司 Security patrol robot based on 5G

Similar Documents

Publication Publication Date Title
CN108679363A (en) A kind of sewage conduct robot moving device and its mode of progression
CN101542163B (en) Transmission for motor and controlling device thereof
CN106439387A (en) Pipeline robot capable of self-adapting to pipe diameter
RU2719112C1 (en) Stepless machine turning gear
RU2009110283A (en) DRIVE, AIRCRAFT CHASSIS ASSEMBLY, AIRCRAFT, ACCESSORIES PARTS SET AND PARTS MOVEMENT METHOD
CN108709047A (en) A kind of pipe robot mode of progression suitable for municipal sewage webmaster
CN109095375B (en) Winch capable of realizing uniform-speed winding based on uniform rope distribution of forward and reverse rotating screws
CN108792584A (en) A kind of follow-on garbage cleaning device
CN108709468A (en) A kind of follow-on demolition set
WO2018210031A1 (en) Continuously variable transmission
NO178276B (en) A vehicle
CN108607728A (en) A kind of car model processing unit (plant)
CN108569804A (en) A kind of flue gas desulfurization waste-water processing method
GB2294093A (en) A water driven power system
CN206071329U (en) A kind of door closure automatic open device
CN108443640B (en) The wheeled T-type pipe robot traction device of big variable diameter
CN104931370B (en) A kind of automotive plastic parts curved surface sliding friction experimental rig
CN108437197A (en) One kind removing formaldehyde environment friendly decorative material
CN108791733A (en) A kind of hydraulic engineering equipment based on big data
CN107524228A (en) A kind of decontamination plant
CN108801059A (en) A kind of mine detection device
CN109604274B (en) Pipeline plug cleaning device
CN108296250A (en) A kind of novel landfill material gas recycling device
SU606957A2 (en) Device for making holes in ground
CN111120596A (en) Automatic transmission and limited slip differential for vehicle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20181019