CN108678129A - Precast concrete assembled piping shaft and preparation method thereof and installation method - Google Patents

Precast concrete assembled piping shaft and preparation method thereof and installation method Download PDF

Info

Publication number
CN108678129A
CN108678129A CN201810817398.6A CN201810817398A CN108678129A CN 108678129 A CN108678129 A CN 108678129A CN 201810817398 A CN201810817398 A CN 201810817398A CN 108678129 A CN108678129 A CN 108678129A
Authority
CN
China
Prior art keywords
prefabricated
section
standard
piping shaft
end cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810817398.6A
Other languages
Chinese (zh)
Inventor
唐进丰
胡永琴
唐方方
唐元元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810817398.6A priority Critical patent/CN108678129A/en
Publication of CN108678129A publication Critical patent/CN108678129A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/0401Gullies for use in roads or pavements

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The present invention proposes a kind of precast concrete assembled piping shaft and preparation method thereof and installation method, piping shaft are formed by connecting by multiple pipe elements, and the pipe element includes precast base, A standard paragraphs, B standard section, prefabricated end cap and secondary pours section;The precast base, A standard paragraphs, B standard section and prefabricated end cap are prefabricated standard component, are provided with connection structure on the interface between the prefabricated standard component, pipeline connection port is provided on the tube wall of A standard paragraphs;The pipe element docking connection, precast base and prefabricated end cap are located at both ends, and the secondary pipe element for pouring the both sides Duan Yuqi, which pours, to link into an integrated entity.Standardization, large-scale production may be implemented in the piping shaft that the present invention makes; it is easy for installation, quick, labor intensity can be mitigated, improve production efficiency; product cost is effectively reduced, country's encouragement, the building industry industrialization of promotion and energy-saving and emission-reduction, environmentally protective policy are met.

Description

Precast concrete assembled piping shaft and preparation method thereof and installation method
Technical field
The present invention relates to a kind of drainpipe wells, more particularly to a kind of precast concrete assembled piping shaft and its making Method and installation method.
Background technology
With the development of Urbanization in China, the development of urban infrastructure is accelerated, especially urban drainage pipe network Development, which increases, needs piping shaft largely mating with pipeline, for precipitating husky and waste residue and receiving dirty, rainwater.But existing pipeline Well construction majority is also manually built by laying bricks or stones using brick body Material at Construction Site or concrete on construction site cast-type operation, construction quality obtain Less than guarantee.And with the increase of cost of labor, low side building materials are that labour cost is projecting with fee of material already, and labour cost is higher than Fee of material, as accelerating to for China human mortality aging is come, cost of labor but will increase in building trade.Due to piping shaft product Particularity, each piping shaft must be consistent with road and conduit slope absolute altitude, needs the piping shaft of different length, this is just restricted The development of the production of piping shaft standardization scale, constrains the industrialization development of piping shaft.
Invention content
In view of the deficiencies of the prior art, the present invention provides a kind of precast concrete assembled piping shaft, may be implemented Standardization, large-scale production, it is easy for installation, quick, labor intensity can be mitigated, production efficiency is improved, effectively reduce product Cost;And provide the production method and installation method of aforementioned tubular duct well.
For the purpose for reaching above-mentioned, a kind of technical solution provided by the invention is:
A kind of precast concrete assembled piping shaft, is formed by connecting by multiple pipe elements, and the pipe element includes pre- Pedestal processed, A standard paragraphs, B standard section, prefabricated end cap and secondary pour section;The precast base, A standard paragraphs, B standard section with And prefabricated end cap is prefabricated standard component, and connection structure is provided on the interface between the prefabricated standard component, A standard paragraphs Pipeline connection port is provided on tube wall;The pipe element docking connection, precast base and prefabricated end cap are located at both ends, secondary to pour The pipe element for building the both sides Duan Yuqi is poured and is linked into an integrated entity.
The piping shaft that above-mentioned technical proposal is provided is formed by connecting by multiple prefabricated pipe elements, prefabricated pipeline structure Prefabricated standard component can be made in part, prefabricated standard component is selected according to piping shaft length and the design requirement of pipeline connection port, just It is arranged connection by design requirement as played with building blocks, B standard section is more than one, is mainly used for piecing together piping shaft length, These prefabricated pipe elements connect into two sections of end cap section and base section, and it is secondary to pour to reserve suitable distance between this two sections Section is poured, end cap section and base section are linked into an integrated entity by the secondary section that pours, thus most simply assemble prefabricated standard component At design requirement length and with the piping shaft of required pipeline connection port.
Further, for convenience of overhauling, the prefabricated end cap includes canister portion and well lid, and well lid is assemblied in the platform of canister portion one end In rank, the connection structure is compatible groove or tongue, and groove is simple in structure with tongue, can fast implement and be located by connecting, Not easy to leak after docking.
Further, the A standard paragraphs are at least one, and the pipeline connection port on the A standard paragraphs is at least one, institute State pipeline connection port axis it is vertical with the axis of A standard paragraphs or tilt intersect.A standard paragraphs can be designed to be connected with pipelines The different size of interface, in case selecting.
Further, the B standard section is at least one, and B standard section includes two kinds of prefabricated components, and a kind of prefabricated component is both ends Face is respectively provided with the connection structure, and another prefabricated component is end face setting connection structure, and connection steel is extended on other end Part.For B standard section mainly with piecing together the length of piping shaft, both ends are connection structure for being connect with other prefabricated standard components, And have the B standard section that one end is provided with connection steel part for being connect with the secondary section that pours, it connects steel part and is poured in section with secondary The bar connecting of stretching.
Further, as specific embodiment, the connection steel part is the connection reinforcing bar or junction steel plate of welding.
Further, for convenience of installing and transporting, the precast base includes bottom plate and pipe portion, one end of bottom plate and pipe portion Connection, is provided with suspension hook on bottom plate.
Further, it is preferably antiseep, the prefabricated standard component is between the joint face of connection structure and connects Seam peripheral surface is provided with waterproof coating layer.
Further, as preferably embodiment, the pipe element is square tube or pipe.
The present invention also provides a kind of production methods of above-mentioned precast concrete assembled piping shaft, include the following steps: (1) first prefabricated to complete the precast base, A standard paragraphs, B standard section and prefabricated end cap these prefabricated standard components, in case assembly It selects;(2) according to the design requirement of piping shaft length and pipeline connection port, prefabricated standard component and the on demand company of being arranged are selected It is connected into two sections of end cap section and base section, the one end of end cap section and base section far from prefabricated end cap or precast base is B standard section, this Connection steel part is extended on the outer end end face of B standard section, each prefabricated standard component is between joint face and connecting sewing peripheral surface applies Brushed with waterproof coating layer;(3) end cap section and base section is opposite, between two sections there are one it is intersegmental every and so that piping shaft overall length is equal to Design length, then the interval is placed into pipeline internal model, by the connection steel part of the secondary embedded bar for pouring section and B standard section Welding, then pipeline external mold is placed, pouring the secondary section that pours makes it link into an integrated entity with end cap section and base section.
The present invention also provides a kind of installation methods of above-mentioned precast concrete assembled piping shaft:The piping shaft is transported Erecting bed is transported to, piping shaft is sling and installs pedestal facing downward;The ground includes foundation stone bed course and public affairs from the bottom up Divide stone bed course, the foundation stone size of foundation stone bed course is 15-23 centimetres, and the centimetre stone size of centimetre stone bed course is 4-8 centimetres, centimetre stone Bed course is laid on above foundation stone bed course and is filled in the gap of foundation stone bed course centimetre stone, and the centimetre stone cushion thickness is 8-13 Centimetre, when installation, now lays cement screed on ground, and ground is leveled up and be bonded consolidation with pedestal by cement sand bed;It will pipe Road is connect with the pipeline connection port on piping shaft, then backfills the earthwork.
Compared with prior art, the beneficial effects of the invention are as follows:1, can pipe quickly be made to modular assembly in factory Road well is whole, realizes batch production, large-scale production, and can meet different piping shaft design lengths and connecting pipe position;2、 Construction site installation is simple, convenient and efficient, is directly lifted on site foundation and installs from transport vehicle, connects pipeline inspection qualification After can backfill, can reduce labor intensity, improve production efficiency, reduce cost;3, meet country energetically encourage, advocate, The assembled architecture of popularization, building industry industrialization and energy-saving and emission-reduction, environmentally protective principles and policies.
Description of the drawings
Fig. 1 is the connection relationship diagram of the embodiment of the present invention 1.
Fig. 2 is a kind of structural schematic diagram of B standard section in Fig. 1.
Fig. 3 is the structural schematic diagram of another B standard section in Fig. 1.
Fig. 4 is the structural schematic diagram after the embodiment of the present invention 1 is installed.
Fig. 5 is the structural schematic diagram after the embodiment of the present invention 2 is installed.
Fig. 6 is the structural schematic diagram of the embodiment of the present invention 3.
Fig. 7 is the overlooking structure diagram of the embodiment of the present invention 4.
The detailed description further illustrated to present invention work below in conjunction with the accompanying drawings.
Specific implementation mode
Embodiment 1:
As shown in Figures 1 to 4, a kind of precast concrete assembled piping shaft, is formed by connecting by multiple pipe elements, described Pipe element include precast base 1, A standard paragraphs 2, B standard section 3, prefabricated end cap 4 and it is secondary pour section 5, pipe element is circle Pipe;The precast base 1, A standard paragraphs 2, B standard section 3 and prefabricated end cap 4 are prefabricated standard component, in the prefabricated standard component Between interface on be provided with connection structure.For convenience of installing and transporting, the precast base 1 includes bottom plate and pipe portion, bottom One end of plate and pipe portion connects, and suspension hook 11 is provided on bottom plate.For convenience of maintenance, the prefabricated end cap 4 includes canister portion and well Lid 41, well lid 41 are assemblied in the step of canister portion one end.
Each pipe element docking connection, precast base 1 and prefabricated end cap 4 are located at both ends, secondary to pour section 5 and its The pipe element of both sides, which pours, to link into an integrated entity.Pipeline connection port 21 is provided on the tube wall of A standard paragraphs 2, A standard paragraphs 2 are at least It it is one, the pipeline connection port 21 on the A standard paragraphs 2 is at least one, axis and the A standard paragraphs of the pipeline connection port 21 2 axis is vertical or tilts intersection.A standard paragraphs 2 can design the different size with pipelines connector 21, with alternative With the A standard paragraphs 2 in the present embodiment are one, and there are two pipeline connection ports 21 for setting.B standard section 3 is more than one, main It is used to piece together piping shaft length, these prefabricated pipe elements connect into two sections of end cap section and base section, between this two sections Reserve suitable distance pour it is secondary pour section 5, end cap section and base section are linked into an integrated entity by the secondary section 5 that pours, thus Prefabricated standard component is simply most assembled into design requirement length and there is the piping shaft of required pipeline connection port 21.
In the present embodiment, it is located by connecting to fast implement and makes simple in structure, the connection structure is compatible groove 6 Or tongue 7, groove 6 dock not easy to leak with tongue 7.These prefabricated standard components between groove 6 and the joint face of tongue 7 with And connecting sewing peripheral surface is provided with waterproof coating layer (not shown), with preferably antiseep.
As shown in Figures 2 and 3, B standard section 3 includes two kinds of prefabricated components, and a kind of prefabricated component is that both ends of the surface are respectively provided with the company Binding structure, another prefabricated component are end face setting connection structures, and connection steel part 31 is extended on other end.Due to B standard For section 3 mainly with the length for piecing together piping shaft, both ends are this just for being connect with other prefabricated standard components of connection structure, and Another kind is the B standard section 3 for having one end to be provided with connection steel part 31, just for being connect with the secondary section 5 that pours, connects steel part 31 It is welded to connect with the secondary embedded bar 51 stretched out in section 5 that pours.Connection steel part 31 is that the connection reinforcing bar of welding either connects Steel plate is connect, is located in B standard section 3 using connection reinforcing bar, one section of connection reinforcing bar in the present embodiment, another section from the one of B standard section 3 Side end face is stretched out.A kind of be exclusively used in and the secondary B standard section 3 for pouring section 5 and connecting is set, so that it may so that other prefabricated standard components are not Steel part 31 is connected with setting, reduces the type of prefabricated standard component, simplifies production.It is of course also possible on other prefabricated standard components Unilateral side setting connection steel part 31, so that it may directly be connect with the secondary section 5 that pours.
The production method of above-mentioned precast concrete assembled piping shaft is to include the following steps:(1) first described in prefabricated completion These prefabricated standard components of precast base 1, A standard paragraphs 2, B standard section 3 and prefabricated end cap 4, in case assembly is selected;(2) according to pipe The design requirement of road well length and pipeline connection port 21, selects prefabricated standard component, and according to piping shaft length, both ends are connection structures B standard section 3 can select multiple, connect into two sections of end cap section and base section to be arranged on demand, each prefabricated standard component When connection between joint face and connecting sewing peripheral surface brushing waterproof coating layer;End cap section and base section are far from prefabricated end cap 4 Or one end of precast base 1 is also B standard section 3, connection steel part 31 is extended on the outer end end face of such B standard section 3, with two It is secondary to pour the connection of section 5;(3) end cap section and base section is opposite, between two sections there are one it is intersegmental every and so that piping shaft overall length is equal to Design length, then the interval is placed into pipeline internal model, by the connection of the secondary embedded bar 51 and B standard section 3 for pouring section 5 Steel part 31 welds, then places pipeline external mold, and pouring the secondary section 5 that pours makes it link into an integrated entity with end cap section and base section.
The installation method of above-mentioned precast concrete assembled piping shaft is:The piping shaft is transported to erecting bed, such as Shown in Fig. 4, piping shaft is sling and is mounted on pedestal on ground 8 downward;The ground 8 includes foundation stone bed course 81 from the bottom up Foundation stone size with centimetre stone bed course 82, foundation stone bed course 81 is 15-23 centimetres, preferably 20 centimetres or so sizes, centimetre stone bed course 82 centimetre stone size is 4-8 centimetres, and centimetre stone bed course 82 is laid in 81 top of foundation stone bed course and the gap of foundation stone bed course 81 Filled with centimetre stone, 82 thickness of centimetre stone bed course is 8-13 centimetres, and when installation now spreads the water of 3-4 cm thicks on ground 8 Silt particle pulp layer 9 levels up ground 8 with pedestal and be bonded consolidation by cement sand bed 9;Pipeline is connect with the pipeline on piping shaft Mouth 21 connects, then backfills the earthwork by industry job specfication.
Embodiment 2:
The structure of each building block of precast concrete assembled piping shaft in the present embodiment and each building block Between correlation, it is substantially the same manner as Example 1, except that as shown in figure 5, A standard paragraphs 2 be two, each A standards There are one pipeline connection ports 21 for setting in section 2.
Embodiment 3:
The structure of each building block of precast concrete assembled piping shaft in the present embodiment and each building block Between correlation, it is substantially the same manner as Example 1, except that as shown in fig. 6, being also provided with connection in 2 unilateral side of A standard paragraphs Steel part 31, so that it may directly be connect with the secondary section 5 that pours.
Embodiment 4:
The structure of each building block of precast concrete assembled piping shaft in the present embodiment and each building block Between correlation, it is substantially the same manner as Example 1, except that as shown in fig. 7, pipe element be square tube, precast base 1 Also it is rectangular, well lid 41 is circular lid, and versatility is good.
Piping shaft provided by the present invention is formed by connecting by multiple prefabricated pipe elements, and prefabricated pipe element can be with Prefabricated standard component is made, prefabricated standard component is selected according to piping shaft length and the design requirement of pipeline connection port, as taking product It is arranged connection by design requirement as wood, piping shaft entirety can quickly be made to modular assembly in factory, realize work Factory, large-scale production, and different piping shaft design lengths and connecting pipe position can be met, construction site installation is simple, It is convenient and efficient, it is directly lifted on site foundation 8 and installs from transport vehicle, can backfill, can subtract after connecting pipeline inspection qualification Few labor intensity, improves production efficiency, reduces cost, meets the assembled architecture that country encourages, advocates, promotes energetically, Building industry industrializes and energy-saving and emission-reduction, environmentally protective principles and policies.
The above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although with reference to preferred embodiment to this hair It is bright to be described in detail, it will be understood by those of ordinary skill in the art that, it can modify to technical scheme of the present invention Or equivalent replacement should all cover the claim in the present invention without departing from the spirit of the technical scheme of the invention and range In range.

Claims (10)

1. a kind of precast concrete assembled piping shaft, it is characterised in that:It is formed by connecting by multiple pipe elements, the pipeline structure Part includes precast base, A standard paragraphs, B standard section, prefabricated end cap and secondary pours section;The precast base, A standard paragraphs, B Standard paragraphs and prefabricated end cap are prefabricated standard component, and connection structure, A are provided on the interface between the prefabricated standard component It is provided with pipeline connection port on the tube wall of standard paragraphs;The pipe element docking connection, precast base and prefabricated end cap are located at two End, the secondary pipe element for pouring the both sides Duan Yuqi, which pours, to link into an integrated entity.
2. precast concrete assembled piping shaft according to claim 1, it is characterised in that:The prefabricated end cap includes cylinder Portion and well lid, well lid are assemblied in the step of canister portion one end, and the connection structure is compatible groove or tongue.
3. precast concrete assembled piping shaft according to claim 1, it is characterised in that:The A standard paragraphs are at least One, the pipeline connection port on the A standard paragraphs is at least one, the axis of the axis and A standard paragraphs of the pipeline connection port Vertical or inclination intersection.
4. precast concrete assembled piping shaft according to claim 1, it is characterised in that:The B standard section is at least One, B standard section includes two kinds of prefabricated components, and a kind of prefabricated component is that both ends of the surface are respectively provided with the connection structure, another prefabricated component It is end face setting connection structure, connection steel part is extended on other end.
5. precast concrete assembled piping shaft according to claim 4, it is characterised in that:The connection steel part is welding Connection reinforcing bar or junction steel plate.
6. precast concrete assembled piping shaft according to claim 1, it is characterised in that:The precast base includes bottom One end of plate and pipe portion, bottom plate and pipe portion connects, and suspension hook is provided on bottom plate.
7. according to claim 1-6 any one of them precast concrete assembled piping shafts, it is characterised in that:The prefabricated mark Quasi- part is between the joint face of connection structure and connecting sewing peripheral surface is provided with waterproof coating layer.
8. precast concrete assembled piping shaft according to claim 7, it is characterised in that:The pipe element is square tube Or pipe.
9. a kind of production method making precast concrete assembled piping shaft as claimed in claim 8, which is characterized in that packet Include following steps:(1) first prefabricated to complete the precast base, A standard paragraphs, B standard section and prefabricated end cap these prefabricated standards Part, in case assembly is selected;(2) according to the design requirement of piping shaft length and pipeline connection port, prefabricated standard component and on-demand is selected It is arranged and connects into two sections of end cap section and base section, the one end of end cap section and base section far from prefabricated end cap or precast base It is B standard section, connection steel part is extended on the outer end end face of this B standard section, each prefabricated standard component is between joint face and even Seam peripheral surface is painted with waterproof coating layer;(3) end cap section and base section is opposite, between two sections there are one it is intersegmental every and make pipe Road well overall length is equal to design length, then the interval is placed pipeline internal model, by the secondary embedded bar and B standard for pouring section The connection steel part welding of section, then pipeline external mold is placed, pouring the secondary section that pours makes it link into an integrated entity with end cap section and base section.
10. a kind of installation method of precast concrete assembled piping shaft as claimed in claim 8, it is characterised in that:By institute It states piping shaft to transport to erecting bed, piping shaft is sling and installs pedestal facing downward;The ground includes base from the bottom up The foundation stone size of stone bed course and centimetre stone bed course, foundation stone bed course is 15-23 centimetres, and the centimetre stone size of centimetre stone bed course is 4-8 Centimetre, centimetre stone bed course is laid on above foundation stone bed course and is filled with centimetre stone, the centimetre stone pad in the gap of foundation stone bed course Layer thickness is 8-13 centimetres, and when installation now lays cement screed on ground, and ground and pedestal are leveled up simultaneously by cement sand bed It is bonded consolidation;Pipeline is connect with the pipeline connection port on piping shaft, then backfills the earthwork.
CN201810817398.6A 2018-07-24 2018-07-24 Precast concrete assembled piping shaft and preparation method thereof and installation method Pending CN108678129A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810817398.6A CN108678129A (en) 2018-07-24 2018-07-24 Precast concrete assembled piping shaft and preparation method thereof and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810817398.6A CN108678129A (en) 2018-07-24 2018-07-24 Precast concrete assembled piping shaft and preparation method thereof and installation method

Publications (1)

Publication Number Publication Date
CN108678129A true CN108678129A (en) 2018-10-19

Family

ID=63814727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810817398.6A Pending CN108678129A (en) 2018-07-24 2018-07-24 Precast concrete assembled piping shaft and preparation method thereof and installation method

Country Status (1)

Country Link
CN (1) CN108678129A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110872847A (en) * 2019-11-29 2020-03-10 威海天泽建筑材料有限公司 Building-free inspection well device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340003A (en) * 1991-11-23 1993-12-21 Sun-Ja Kim Method for connecting precast concrete member
CN101787733A (en) * 2010-03-03 2010-07-28 管乃彦 Prefabricated vertical member
CN201883454U (en) * 2010-12-07 2011-06-29 林刚 Prefabricated reinforced-concrete assembly-type combined inspection well chamber
CN102155025A (en) * 2011-03-23 2011-08-17 东南大学 Late poured band type assembled pipe jacking working open caisson
CN103088844A (en) * 2013-03-04 2013-05-08 济南城建集团有限公司 Reinforced concrete inspection well whole prefabricated hoisting construction method
CN103806470A (en) * 2014-03-14 2014-05-21 江苏华光双顺机械制造有限公司 Production and installation method for reinforced concrete inspection well
CN104775516A (en) * 2015-02-16 2015-07-15 清华大学 Field connecting method among prefabricated reinforced concrete columns
CN105019476A (en) * 2015-07-10 2015-11-04 凤阳县凤城建安预制厂 Prefabricated reinforced concrete inspection well
CN207160074U (en) * 2017-07-28 2018-03-30 上海十方生态园林股份有限公司 A kind of non-settling structure of stable public way well body
CN208586722U (en) * 2018-07-24 2019-03-08 唐方方 Precast concrete assembled piping shaft

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340003A (en) * 1991-11-23 1993-12-21 Sun-Ja Kim Method for connecting precast concrete member
CN101787733A (en) * 2010-03-03 2010-07-28 管乃彦 Prefabricated vertical member
CN201883454U (en) * 2010-12-07 2011-06-29 林刚 Prefabricated reinforced-concrete assembly-type combined inspection well chamber
CN102155025A (en) * 2011-03-23 2011-08-17 东南大学 Late poured band type assembled pipe jacking working open caisson
CN103088844A (en) * 2013-03-04 2013-05-08 济南城建集团有限公司 Reinforced concrete inspection well whole prefabricated hoisting construction method
CN103806470A (en) * 2014-03-14 2014-05-21 江苏华光双顺机械制造有限公司 Production and installation method for reinforced concrete inspection well
CN104775516A (en) * 2015-02-16 2015-07-15 清华大学 Field connecting method among prefabricated reinforced concrete columns
CN105019476A (en) * 2015-07-10 2015-11-04 凤阳县凤城建安预制厂 Prefabricated reinforced concrete inspection well
CN207160074U (en) * 2017-07-28 2018-03-30 上海十方生态园林股份有限公司 A kind of non-settling structure of stable public way well body
CN208586722U (en) * 2018-07-24 2019-03-08 唐方方 Precast concrete assembled piping shaft

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110872847A (en) * 2019-11-29 2020-03-10 威海天泽建筑材料有限公司 Building-free inspection well device

Similar Documents

Publication Publication Date Title
CN208586722U (en) Precast concrete assembled piping shaft
CN103821364B (en) The construction method of reinforced concrete water pond
CN105201012B (en) Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN108560684B (en) Heavy-load traffic road inspection well ring and construction method thereof
CN108505805B (en) Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof
CN104775452B (en) Well lid support seat of road inspection well, support seat assembly and pavement construction method
CN203034494U (en) Water draining structure for basement bottom plate back watering belt
CN105780976A (en) Compound concrete shear wall structure and concrete pouring method thereof
CN208933989U (en) A kind of tower-crane foundation structure
CN102116092A (en) Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks
CN112227502A (en) Drainage inspection well construction method
CN206052778U (en) A kind of steel and Combined concrete piping lane
LU501207B1 (en) Structure and method for reinforcing manhole cover anchored with existing road surface foundation by means of dowel bars
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN108678129A (en) Precast concrete assembled piping shaft and preparation method thereof and installation method
CN106400838B (en) A kind of city integrated Pipe rack of prefabricated assembled concrete and construction method
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN107151958A (en) A kind of permanent rural highway cement pavement of easy care
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
CN109811613B (en) Temporary ground facility and integrated construction method thereof
CN216237943U (en) Rural highway cement concrete pavement assembled structure of small traffic
CN208792483U (en) Combined-type sewage well prefabricated component
CN209429046U (en) Gravity dam transverse joint drainage channel structure
CN110438859A (en) A kind of the precast concrete road and its construction method of draining of catchmenting
CN114321494B (en) Municipal pipeline protection structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination