CN108674578A - Shafting lifts and propeller mounting process - Google Patents

Shafting lifts and propeller mounting process Download PDF

Info

Publication number
CN108674578A
CN108674578A CN201810568476.3A CN201810568476A CN108674578A CN 108674578 A CN108674578 A CN 108674578A CN 201810568476 A CN201810568476 A CN 201810568476A CN 108674578 A CN108674578 A CN 108674578A
Authority
CN
China
Prior art keywords
propeller
shaft
propeller shaft
shafting
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810568476.3A
Other languages
Chinese (zh)
Other versions
CN108674578B (en
Inventor
刘在良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang International Maritime College
Original Assignee
Zhejiang International Maritime College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang International Maritime College filed Critical Zhejiang International Maritime College
Priority to CN201810568476.3A priority Critical patent/CN108674578B/en
Publication of CN108674578A publication Critical patent/CN108674578A/en
Application granted granted Critical
Publication of CN108674578B publication Critical patent/CN108674578B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Earth Drilling (AREA)
  • Shafts, Cranks, Connecting Bars, And Related Bearings (AREA)

Abstract

The invention discloses a kind of lifting of shafting and propeller mounting process, include early-stage preparations successively, garter coil paddle shaft, hydraulic pressure assembly is carried out to propeller, the front and back sealing device for installing propeller shaft, installation jackshaft, the anti-rope cover of installation or fishing net cutter, shaft make being fixed temporarily before lower water.The shafting and propeller of the present invention is installed one by one by tail to head, after ship launching, it carries out being connected to host in school and by them one by one to first by tail on the basis of tailing axle end, this process sequence can reduce the influence of deformation of hull shaft installation quality after ship launching, ensure installation quality.

Description

Shafting lifts and propeller mounting process
Technical field
The present invention relates to shipbuilding technical fields, and in particular to a kind of lifting of shafting and propeller mounting process.
Background technology
In shafting or propeller accident, for example propeller blade fracture, propeller shaft fracture, bearing heating, sealing dress Leakage etc. is set, is more that construction technology is unreasonable, peace other than the design defect such as shafting structure is unreasonable, material selection is improper The unqualified reason of packing quality.Therefore the mounting process of shafting and propeller has a great impact to ship building period, in conjunction with Actual conditions determine that rational mounting process shaft and propeller installation quality have prodigious effect.
Invention content
In order to improve the packing quality of shafting and propeller peace, the present invention provides a kind of lifting of shafting and propeller erectors Skill.
The technical solution adopted by the present invention is as follows:
A kind of lifting of shafting and propeller mounting process, steps are as follows:
Step 1, early-stage preparations:Installation is complete with stern pipe for shafting bracing wire, and each flange fraising of shafting terminates, propeller hoisting eye plate, The welding installation of shafting hoisting eye plate terminates;
Step 2, garter coil paddle shaft, propeller shaft from cabin toward carrying out plug axis, plug axis process and sealing device, spiral shell outside cabin The installation of rotation paddle is interspersed to be carried out at the same time;
Step 3 carries out hydraulic pressure assembly to propeller;
Step 4, preceding sealing device, the rear sealing device for installing propeller shaft;
Step 5, installation jackshaft;
Step 6, the anti-rope cover of installation or fishing net cutter;
Being fixed temporarily before water under step 7, shaft are made.
The beneficial effects of the invention are as follows:The shafting and propeller of the present invention is installed one by one by tail to head, is convenient for ship After lower water, carry out being connected to host in school and by them one by one by tail to head on the basis of tailing axle end, this process sequence can subtract The influence of deformation of hull shaft installation quality, ensures installation quality after few ship launching.
Description of the drawings
Fig. 1 is the mounting shift angle schematic diagram of propeller and host crankshaft in the embodiment of the present invention.
Fig. 2 is the lifting schematic diagram one of Center Screw Shaft of the embodiment of the present invention.
Fig. 3 is the lifting schematic diagram two of Center Screw Shaft of the embodiment of the present invention.
Fig. 4 is the lifting schematic diagram three of Center Screw Shaft of the embodiment of the present invention.
Fig. 5 is the lifting schematic diagram four of Center Screw Shaft of the embodiment of the present invention.
Fig. 6 is the lifting schematic diagram five of Center Screw Shaft of the embodiment of the present invention.
Fig. 7 is the lifting schematic diagram six of Center Screw Shaft of the embodiment of the present invention.
Fig. 8 is the scheme of installation of fair water cone in the embodiment of the present invention.
Fig. 9 is the lifting schematic diagram one of jackshaft in the embodiment of the present invention.
Figure 10 is the lifting schematic diagram two of jackshaft in the embodiment of the present invention.
Figure 11 is the schematic diagram of two kinds of lifting modes of Center Screw Shaft of the embodiment of the present invention.
Figure 12 is the hydraulic pressure assembling schematic diagram of propeller in the embodiment of the present invention.
Figure 13 is temperature-push the amount curve graph that propeller hydraulic pressure assembles in the embodiment of the present invention.
Figure 14 is the data note that amesdial reading-axial direction that propeller hydraulic pressure assembles in the embodiment of the present invention promotes pump pressure Record table figure.
Figure 15 is the support bracket fastened schematic diagram of center shafting of the embodiment of the present invention.
Stern pipe 1, propeller shaft 2, propeller 3, fair water cone 4, jackshaft 5, preceding sealing device 6, rear sealing device 7, skirt 8, hydraulic nut 9, amesdial 10, axial pressure pump 11, radial force (forcing) pump 12, shafting fixing bracket 13.
Specific implementation mode
Using 64000DWT bulk freighters as embodiment and in conjunction with attached drawing, the invention will be further described below.Equipment weight Amount is as follows:It is jackshaft 8.3T, propeller shaft 11.5T, propeller 20.9T, hydraulic nut 0.6T, preceding sealing device 0.2T, rear close Seal apparatus 0.32T.
(One)The shafting of the present embodiment lifts and propeller mounting process, and steps are as follows:
Step 1, early-stage preparations:Installation is complete with stern pipe for shafting bracing wire, and each flange fraising of shafting terminates, propeller hoisting eye plate, The welding installation of shafting hoisting eye plate terminates;
Step 2, garter coil paddle shaft, propeller shaft from cabin toward carrying out plug axis, plug axis process and sealing device, spiral shell outside cabin The installation of rotation paddle is interspersed to be carried out at the same time;
Step 3 carries out hydraulic pressure assembly to propeller;
Step 4, preceding sealing device, the rear sealing device for installing propeller shaft;
Step 5, installation jackshaft;
Step 6, the anti-rope cover of installation or fishing net cutter;
Being fixed temporarily before water under step 7, shaft are made.
The shafting and propeller of the present embodiment are installed one by one by tail to head, convenient for after ship launching, being with tailing axle end Benchmark is carried out being connected to host in school and by them by tail to head one by one, and hull becomes after this process sequence can reduce ship launching The influence of shape shaft installation quality ensures installation quality.
(Two)In the present embodiment, to reduce the exciting force superposition of host and blade, blade need to need to have centainly with host crankshaft Phase difference, specially:For the first cylinder of host in top dead-centre, propeller is five leaf paddles, and one of blade need to be in peak 17 ° of angles counterclockwise, as shown in Fig. 1.So need to just be determined before shafting bolt fraising and propeller brush propeller with Phase difference between shafting, host, is as follows:
In the first cylinder top dead-centre, the bolt hole of flywheel is eyes, to two bolts hole of flywheel peak for step 1.1, host Carry out mark;
It is corresponding with two bolts hole of host that step 1.2, stern tube shaft need to select 2 bolts hole, and carries out mark, i.e. these two pair bolt It should be in same phase in fraising;
Step 1.3 adjusts the bolt hole marked on the bolt hole marked on propeller shaft and host flywheel to same phase It reams again.
After reaming by above-mentioned steps, propeller install when, see from back to front, by a blade of propeller adjust to spiral Radial line among two selected bolts hole of paddle shaft forms 17 ° of angle counterclockwise, so when mounted, as long as bolt hole according to Fraising corresponds to, and propeller is the phase difference for reaching requirement with host.
(Three)In the present embodiment, the step 2 is specific as follows as shown in Fig. 2 ~ 7:
Step 2.1 waits for that stern tube epoxy resin is solid;
Each installation contact surface of step 2.2, cleaning stern pipe, propeller shaft, preceding sealing device, rear sealing device and propeller, will False bearings are installed in place, each bearing portion oiling,;
Preceding sealing entirety is inserted in propeller shaft front end by step 2.3 together with gasket, sealing ring before propeller shaft plug axis; Rear sealing device, propeller, hydraulic nut are hoisted to the installed position of stern, such as Fig. 2, Fig. 3;
Step 2.4, propeller shaft rear end install skirt, and skirt both ends coat soft material, start lifting and the plug of propeller shaft Axis, plug axis process Center Screw Shaft surface smear lubricating oil shift hoist rope after propeller shaft skirt goes out stern pipe rear flange Onto skirt, to keep propeller shaft to balance, such as Fig. 4;
After step 2.5, propeller shaft go out stern pipe rear end face, rear sealing device, gasket are inserted in propeller shaft together, by propeller In place, propeller inner hole is directed at propeller shaft, and continues backward to fill in propeller shaft for lifting, and lubrication is constantly smeared in movement The brush label of oil, propeller shaft and propeller hub keeps overlapping, until propeller cannot be pushed into, propeller shaft front end at this time Temporary support is arranged in flange, and mobile or vibration occurs during the installation process in prevention propeller shaft, such as Fig. 4, Fig. 6, Fig. 7;
Step 2.6 carries out axially position by design drawing to propeller shaft, and propeller hub keeps the volume of 5 ~ 8mm away from stern pipe rear flange distance External series gap, this gap are the gap needed when lower water rear axle mechanism centering, and centering is completed rear propeller shaft and pulled forward, eliminates around here Gap;And being carried out between propeller and propeller shaft circumferentially positioned, a blade of propeller is adjusted to two selected with propeller shaft Radial line among a bolt hole forms 17 ° of angle counterclockwise.
The propeller shaft of the present embodiment from cabin toward carrying out plug axis, plug axis process and sealing device, propeller outside cabin Installation it is interspersed be carried out at the same time, entire hoisting process is compact, without the additional stand-by period, can reduce the activity duration, improves work Efficiency.
(Four)In the present embodiment, step 2 Center Screw Shaft and jackshaft select lifting side according to length and diameter Formula, specially:Propeller shaft length is less than 4m or fineness ratio is more than 0.03, selects among V-type and hangs;Long axis, that is, length be more than 4m and Fineness ratio is less than 0.03, and two sections of flat pattern is selected to hang.It is wherein hung among V-type, two sections of flat pattern is hung respectively as shown in A, B in Figure 11.This The lifting of propeller shaft and jackshaft can be deformed and is limited in controlled range by the lifting mode that embodiment is selected, and with behaviour Make convenient advantage.
(Five)In embodiment, the step 3 is as shown in figure 12, specific as follows:
Step 3.1 moves on to hydraulic nut on holder, and molybdenum disulfide is then sprayed on hydraulic nut screw thread, moves holder, until Hydraulic nut alignment propeller shaft center keeps the piston of hydraulic nut to be located at plunger shaft bottom according to hand of spiral tightening nut Portion;
Step 3.2 installs hydraulic pump and hose on propeller and hydraulic nut, while installing amesdial in propeller hub front end;
Step 3.3, the air hole cock for opening hydraulic nut, the hydraulic pressure hole oiling to hydraulic nut wait for spillage in air hole Air hole cock is loaded onto when pressure oil and is tightened;The hole cock of propeller hub hydraulic pressure is opened, from lower position hydraulic pressure hole towards oiling in propeller hub, when When higher hydraulic pressure hole spilling is hydraulic oil entirely, it is connect with another hydraulic pressure hole of propeller hub with hydraulic hose;
Step 3.4, axial, the radial oil pump of startup are slowly pressurized, until propeller intrusion reaches design value, stop being pumped;
Step 3.5, after the inspection of shipowner's ship confirms, first lay down radial oil pressure, wait for a period of time, determine propeller without being unloaded again after movement Fall axial oil pressure, position of the label propeller on propeller shaft;
Step 3.6 removes hydraulic hose, and each hydraulic pressure hole injection butter load onto plug screw, fair water cone are finally installed, such as Fig. 8 institutes Show, propeller press-fitting terminates.
The propeller of the present embodiment is no key hydraulic screw paddle, using the hydraulic nut of included piston jack, positioning peace It trues up really, and the activity duration can be reduced, improve working efficiency.What is illustrated is the steps of exhausting in step 3.3, can to the greatest extent may be used The air in propeller hub can be excluded, ensures radial press-fitting effect, ensures the quality of propeller hydraulic pressure assembly.
(Six)In embodiment, the step 3.4 is specific as follows as shown in Figure 12, Figure 13, Figure 14:
Step 3.4.1, propeller hub temperature is measured that is, shown in Figure 13, to be found and worked as by " temperature-push the amount curve graph " in calculated description The indentation magnitude S of propeller at preceding temperature;
Step 3.4.2, radial dilatation pump is not pressurized, axial propulsion pump is pressurized to specified initial pressure(5.375MPa), stop pump Pressure, amesdial is zeroed, at the same with the amount of being axially forced to i.e. amesdial make horizontal axis, it is axial promote the pump pressure masterpiece longitudinal axis to note down table, That is a points in Figure 14;
Step 3.4.3, radial dilatation pump is not pressurized, axial propulsion pump uniformly makees 2 ~ 3 pressurizations(2~10MPa), and by dependency number Strong point is recorded the record sheet, i.e. b, c, d in Figure 14, obtains an amesdial reading and promotes pump pressure the relationship of the two with axial Near linear, the intersection point e of the straight line and horizontal axis is the axial amount of being axially forced to initial point when to promote pump pressure be zero, the axis To intrusion initial point e in record sheet at a distance from origin o be L1;
Step 3.4.4, radial dilatation pump is not pressurized, axial promote pumps uniformly repeatedly pressurization(2~10MPa), until amesdial data No longer change;
Step 3.4.5, radial dilatation pump, axial promote pump simultaneously uniformly repeatedly pressurization(2~10MPa), until amesdial reading is Until L2, meet L2=S-L1.
During propeller hydraulic pressure assembles, propeller shaft is to be difficult to determine to the specific location of intrusion initial point , the indentation magnitude S found according to design sheets is difficult to directly use, and typically estimates that the amount of being axially forced to is initial by experience Point, therefore the quality of propeller hydraulic pressure assembly is difficult to ensure.The present embodiment promotes pump pressure two using amesdial reading with axial The relationship of person's approximately linear obtains the amount of being axially forced to initial point e by graphing method, and reliability is high, while having good weight Renaturation and operability improve the quality of propeller hydraulic pressure assembly.
(Seven)In embodiment, the step 5 is as shown in Figure 9, Figure 10, specific as follows:
In step 5.1, hoisting process, jackshaft position of centre of gravity is paid attention to, according to field condition, reasonable arrangement hoist cable position;
Step 5.2 opens intermediate bearing upper end cover and top bearing shell, is spread in the bearing portion and intermediate bearing lower bearing of jackshaft Lubricating oil, oil product determine the trade mark according to oil plant table;
Step 5.3 gradually hangs jackshaft on ship, by hoisting pad above jackshaft, by jackshaft by crane hoist cable mistake It crosses to hoist cable on ship;
Jackshaft is gradually put off on intermediate bearing and jackshaft falsework, and makes intermediate shaft flange and spiral by step 5.4 The gaps 3mm are stayed between paddle shaft flange, wait for the installation for being fixed temporarily bolt under shafting before water, are completed jackshaft and are lifted work.
(Eight)In embodiment, the step 7 is specific as follows:It is drawn with cucurbit on host top with cucurbit according to field position Firmly;The intermediate washer of 3mm is installed between intermediate shaft flange and propeller shaft flange, intermediate shaft flange and host flywheel end flanges, and Shafting fixing bracket as shown in figure 15 is installed, bolt is connected temporarily with shafting and is connected and fixed shafting and shafting fixing bracket.
The above-mentioned measure of the present embodiment is fixed temporarily for propeller shaft, jackshaft and host, can prevent host, spiral shell Rotation paddle shaft generates rotation and vibration in lower water.
(Nine)Obviously, the above embodiment of the present invention is intended to be merely illustrative of the present example, and not to this The restriction of the embodiment of invention.It for those of ordinary skill in the art, on the basis of the above description can be with Make other various forms of variations or variation.There is no need and unable to give poor example to all embodiments.And these belong to Protection scope of the present invention is still fallen in the connotation changes and variations that derived from of the present invention.

Claims (6)

1. a kind of shafting lifting and propeller mounting process, it is characterized in that steps are as follows:
Step 1, early-stage preparations:Installation is complete with stern pipe for shafting bracing wire, and each flange fraising of shafting terminates, propeller hoisting eye plate, The welding installation of shafting hoisting eye plate terminates;
Step 2, garter coil paddle shaft, propeller shaft from cabin toward carrying out plug axis, plug axis process and sealing device, spiral shell outside cabin The installation of rotation paddle is interspersed to be carried out at the same time;
Step 3 carries out hydraulic pressure assembly to propeller;
Step 4, preceding sealing device, the rear sealing device for installing propeller shaft;
Step 5, installation jackshaft;
Step 6, the anti-rope cover of installation or fishing net cutter;
Being fixed temporarily before water under step 7, shaft are made.
2. shafting lifting according to claim 1 and propeller mounting process, it is characterised in that:Method in the step 1 Blue fraising is specific as follows:
Step 1.1 determines the first cylinder of host in top dead-centre, and the bolt hole of highest point makes marks on select host flywheel, and remembers The angle of record mark bolt hole and vertical direction;
Step 1.2 selectes bolt hole corresponding with the bolt after label on the host flywheel on the flange of propeller shaft, And it marks;
Step 1.3 adjusts the bolt hole marked on the bolt hole marked on propeller shaft and host flywheel to same phase It reams again.
3. shafting lifting according to claim 1 and propeller mounting process, it is characterised in that:The step 2 is specific such as Under:
Step 2.1 waits for that stern tube epoxy resin is solid;
Each installation contact surface of step 2.2, cleaning stern pipe, propeller shaft, preceding sealing device, rear sealing device and propeller, will False bearings are installed in place, each bearing portion oiling;
Preceding sealing entirety is inserted in propeller shaft front end by step 2.3 together with gasket, sealing ring before propeller shaft plug axis; Rear sealing device, propeller, hydraulic nut are hoisted to the installed position of stern;
Step 2.4, propeller shaft rear end install skirt, and skirt both ends coat soft material, start lifting and the plug of propeller shaft Axis, plug axis process Center Screw Shaft surface smear lubricating oil shift hoist rope after propeller shaft skirt goes out stern pipe rear flange Onto skirt, to keep propeller shaft to balance;
After step 2.5, propeller shaft go out stern pipe rear end face, rear sealing device, gasket are inserted in propeller shaft together, by propeller In place, propeller inner hole is directed at propeller shaft, and continues backward to fill in propeller shaft for lifting, and lubrication is constantly smeared in movement The brush label of oil, propeller shaft and propeller hub keeps overlapping, until propeller cannot be pushed into, propeller shaft front end at this time Temporary support is arranged in flange, and mobile or vibration occurs during the installation process in prevention propeller shaft;
Step 2.6 carries out axially position to propeller shaft by design drawing, and between propeller and propeller shaft circumferentially determine Position.
4. shafting lifting according to claim 1 or 3 and propeller mounting process, it is characterised in that:Spiral shell in the step 2 Paddle shaft and jackshaft are revolved, lifting mode is selected according to length and diameter, specially:Propeller shaft length is less than 4m or fineness ratio is big In 0.03, selects among V-type and hang;Long axis, that is, length is more than 4m and fineness ratio is less than 0.03, and two sections of flat pattern is selected to hang.
5. shafting lifting according to claim 1 and propeller mounting process, it is characterised in that:The step 3 is specific such as Under:
Step 3.1 moves on to hydraulic nut on holder, and molybdenum disulfide is then sprayed on hydraulic nut screw thread, moves holder, until Hydraulic nut alignment propeller shaft center keeps the piston of hydraulic nut to be located at plunger shaft bottom according to hand of spiral tightening nut Portion;
Step 3.2 installs hydraulic pump and hose on propeller and hydraulic nut, while installing amesdial in propeller hub front end;
Step 3.3, the air hole cock for opening hydraulic nut, the hydraulic pressure hole oiling to hydraulic nut wait for spillage in air hole Air hole cock is loaded onto when pressure oil and is tightened;The hole cock of propeller hub hydraulic pressure is opened, from lower position hydraulic pressure hole towards oiling in propeller hub, when When higher hydraulic pressure hole spilling is hydraulic oil entirely, it is connect with another hydraulic pressure hole of propeller hub with hydraulic hose;
Step 3.4, axial, the radial oil pump of startup are slowly pressurized, until propeller intrusion reaches design value, stop being pumped;
Step 3.5, after the inspection of shipowner's ship confirms, first lay down radial oil pressure, wait for a period of time, determine propeller without being unloaded again after movement Fall axial oil pressure, position of the label propeller on propeller shaft;
Step 3.6 removes hydraulic hose, and each hydraulic pressure hole injection butter load onto plug screw, finally install fair water cone, propeller pressure With end.
6. shafting lifting according to claim 4 and propeller mounting process, it is characterised in that:The step 3.4 is specific It is as follows:
Step 3.4.1, propeller hub temperature is measured, spiral under Current Temperatures is found by " temperature-push the amount curve graph " in calculated description The indentation magnitude S of paddle;
Step 3.4.2, radial dilatation pump is not pressurized, axial propulsion pump is pressurized to specified initial pressure, stops pump pressure, by amesdial Zero, while horizontal axis made with the amount of being axially forced to i.e. amesdial, axial the pump pressure masterpiece longitudinal axis is promoted to note down table;
Step 3.4.3, radial dilatation pump is not pressurized, axial propulsion pump uniformly makees 2 ~ 3 pressurizations, and relevant data points are recorded The record sheet obtains an amesdial reading and the axial near linear for promoting pump pressure the relationship of the two, the straight line and horizontal axis Intersection point be the axial amount of being axially forced to initial point when to promote pump pressure be zero, the amount of the being axially forced to initial point in record sheet The distance of origin is L1;
Step 3.4.4, radial dilatation pump is not pressurized, axial promote pumps uniformly repeatedly pressurization, until amesdial data no longer change;
Step 3.4.5, radial dilatation pump, axial propulsion pump uniformly repeatedly pressurize simultaneously, full until amesdial reading is L2 Sufficient L2=S-L1.
CN201810568476.3A 2018-06-05 2018-06-05 Shafting lifting and propeller mounting process Active CN108674578B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810568476.3A CN108674578B (en) 2018-06-05 2018-06-05 Shafting lifting and propeller mounting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810568476.3A CN108674578B (en) 2018-06-05 2018-06-05 Shafting lifting and propeller mounting process

Publications (2)

Publication Number Publication Date
CN108674578A true CN108674578A (en) 2018-10-19
CN108674578B CN108674578B (en) 2019-10-18

Family

ID=63809721

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810568476.3A Active CN108674578B (en) 2018-06-05 2018-06-05 Shafting lifting and propeller mounting process

Country Status (1)

Country Link
CN (1) CN108674578B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109625206A (en) * 2019-01-31 2019-04-16 浙江国际海运职业技术学院 Ship drought measuring device
CN110524236A (en) * 2019-07-15 2019-12-03 沪东中华造船(集团)有限公司 A kind of marine shafting installation method
CN110712731A (en) * 2019-10-22 2020-01-21 中国人民解放军海军工程大学 Ship shafting alignment and cyclotron vibration multidisciplinary optimization method
CN111661277A (en) * 2020-05-26 2020-09-15 大连船舶重工集团有限公司 Ship launching seal shaft propeller fixing system
CN111824360A (en) * 2020-06-09 2020-10-27 武汉船用机械有限责任公司 Assembly method of oil distributor of controllable pitch propeller
CN112278188A (en) * 2020-10-28 2021-01-29 中船黄埔文冲船舶有限公司 Installation method of propeller shaft and positioning tool of propeller shaft
CN112298488A (en) * 2020-09-25 2021-02-02 沪东中华造船(集团)有限公司 Method for extracting stern tube stern shaft
CN112498626A (en) * 2020-11-11 2021-03-16 南通中远海运川崎船舶工程有限公司 Method for disassembling propeller shaft of ultra-large container ship
CN114379738A (en) * 2022-02-23 2022-04-22 理工造船(鄂州)股份有限公司 Key-free hydraulic connection installation method for propeller
CN115303441A (en) * 2022-08-22 2022-11-08 武汉理工大学 Visualization and pushing amount intelligent control method for hydraulic assembling process of keyless propeller

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN102627139A (en) * 2012-05-08 2012-08-08 上海江南长兴造船有限责任公司 Final assembly method of ship shafting and rudder system
CN102815370A (en) * 2012-09-04 2012-12-12 中船桂江造船有限公司 One-step centering ship shafting mounting method
CN104960625A (en) * 2015-06-30 2015-10-07 沪东中华造船(集团)有限公司 Mounting method of single-bearing shaft system of large-scale ship

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101367426A (en) * 2008-06-24 2009-02-18 中国长江航运集团江东船厂 Shaft, rudder system mounting process of ten-thousand-ton grade special multipurpose vessel
CN102627139A (en) * 2012-05-08 2012-08-08 上海江南长兴造船有限责任公司 Final assembly method of ship shafting and rudder system
CN102815370A (en) * 2012-09-04 2012-12-12 中船桂江造船有限公司 One-step centering ship shafting mounting method
CN104960625A (en) * 2015-06-30 2015-10-07 沪东中华造船(集团)有限公司 Mounting method of single-bearing shaft system of large-scale ship

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
崔志刚: "船舶推进轴系安装工艺对船舶轴系校中质量的影响分析", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
徐东洋等: "76000t散货船轴系安装及校中", 《船舶》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109625206A (en) * 2019-01-31 2019-04-16 浙江国际海运职业技术学院 Ship drought measuring device
CN109625206B (en) * 2019-01-31 2023-11-21 浙江国际海运职业技术学院 Ship draft measuring device
CN110524236A (en) * 2019-07-15 2019-12-03 沪东中华造船(集团)有限公司 A kind of marine shafting installation method
CN110712731A (en) * 2019-10-22 2020-01-21 中国人民解放军海军工程大学 Ship shafting alignment and cyclotron vibration multidisciplinary optimization method
CN110712731B (en) * 2019-10-22 2021-03-12 中国人民解放军海军工程大学 Ship shafting alignment and cyclotron vibration multidisciplinary optimization method
CN111661277A (en) * 2020-05-26 2020-09-15 大连船舶重工集团有限公司 Ship launching seal shaft propeller fixing system
CN111824360A (en) * 2020-06-09 2020-10-27 武汉船用机械有限责任公司 Assembly method of oil distributor of controllable pitch propeller
CN112298488A (en) * 2020-09-25 2021-02-02 沪东中华造船(集团)有限公司 Method for extracting stern tube stern shaft
CN112278188A (en) * 2020-10-28 2021-01-29 中船黄埔文冲船舶有限公司 Installation method of propeller shaft and positioning tool of propeller shaft
CN112498626A (en) * 2020-11-11 2021-03-16 南通中远海运川崎船舶工程有限公司 Method for disassembling propeller shaft of ultra-large container ship
CN114379738A (en) * 2022-02-23 2022-04-22 理工造船(鄂州)股份有限公司 Key-free hydraulic connection installation method for propeller
CN115303441A (en) * 2022-08-22 2022-11-08 武汉理工大学 Visualization and pushing amount intelligent control method for hydraulic assembling process of keyless propeller

Also Published As

Publication number Publication date
CN108674578B (en) 2019-10-18

Similar Documents

Publication Publication Date Title
CN108674578A (en) Shafting lifts and propeller mounting process
CN108956309B (en) Friction drive hoist wirerope load-carrying properties test device and method
CN109557179B (en) Online monitoring system for cracks of main shaft of elevator and working method of online monitoring system
CN104111166B (en) A kind of charger of wheel fatigue test board
CN106286314B (en) Latent liquid ballast pump
CN112278188A (en) Installation method of propeller shaft and positioning tool of propeller shaft
CN110726495A (en) System and method for testing temperature field of shield main bearing
CN104908536B (en) A kind of tyre crane cart walking mechanism tire assembling method
JP2012018109A (en) Device and method for water pressure test of tire
CN105537926B (en) A kind of method for excluding steering engine and rudder stock mechanical zero deviation
KR20130020168A (en) Load measuring method of shaft for ship
CN104058066B (en) Dismountable stern barrel and boats and ships installation method thereof for boats and ships
CN113067440B (en) Tool for assembling wind driven generator and application method thereof
CN104494804A (en) Ship shafting segmented tail pipe device and installation method thereof
CN1023949C (en) Trailing axle and tube for rolling bearing
CN104111167A (en) Device for delivery test of stern roller and method for using the device
JP5702131B2 (en) Oil seal structure of telescopic cover
CN112478089B (en) Rotary stern shaft equipment in cabin
CN207243161U (en) A kind of coil silk device
CN207347059U (en) A kind of hoist engine
CN219215371U (en) Throwing device based on CADC fixed wing aircraft
CN208429793U (en) A kind of reel Axile connection structure and crane
CN108797663A (en) A kind of environmental protection load box
CN221214469U (en) Marine safety anchor windlass
KR19990081759A (en) Hydraulic cylinder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: ZHOUSHAN LIGANG SHIPBUILDING CO.,LTD.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2023980043472

Denomination of invention: Shafting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20231018

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: Zhoushan Putuo Yaofeng Shipbuilding Co.,Ltd.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2024980011735

Denomination of invention: Shaft hoisting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20240812

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: Daishan Huafeng Shipbuilding Co.,Ltd.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2024980011874

Denomination of invention: Shaft hoisting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20240813

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: ZHEJIANG DAISHAN HUACHEN POLYURETHANE Co.,Ltd.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2024980012041

Denomination of invention: Shaft hoisting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20240814

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: ZHOUSHAN LONGSHENG SHIP INDUSTRY Co.,Ltd.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2024980012469

Denomination of invention: Shaft hoisting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20240821

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20181019

Assignee: Shengsi Leixin Material Management Co.,Ltd.

Assignor: ZHEJIANG INTERNATIONAL MARITIME College

Contract record no.: X2024980013779

Denomination of invention: Shaft hoisting and propeller installation process

Granted publication date: 20191018

License type: Common License

Record date: 20240903