CN108643935A - 富水浅埋地质下隧道的施工方法 - Google Patents

富水浅埋地质下隧道的施工方法 Download PDF

Info

Publication number
CN108643935A
CN108643935A CN201810390047.1A CN201810390047A CN108643935A CN 108643935 A CN108643935 A CN 108643935A CN 201810390047 A CN201810390047 A CN 201810390047A CN 108643935 A CN108643935 A CN 108643935A
Authority
CN
China
Prior art keywords
tunnel
meters
carried out
geology
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810390047.1A
Other languages
English (en)
Inventor
李克智
李检平
赵国庆
李旭
井岩超
韩广宇
张帅领
孙金毅
杨志鸿
王小刚
钟国
李世宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201810390047.1A priority Critical patent/CN108643935A/zh
Publication of CN108643935A publication Critical patent/CN108643935A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

一种富水浅埋地质下隧道的施工方法。其包括在洞口段制作长管棚超前支护,然后在掌子面前方的拱顶部位打设超前小导管并注浆;采用三台阶预留核心土法进行洞身开挖;进行初支施工,进行径向注浆,打设锁脚;采用片石反压+钢板桩进行支护,并进行仰拱开挖;进行二衬施工等步骤;本发明优点:采取短台阶开挖,上、中、下台阶每循环只开挖一榀,锁脚加强,同步径向注浆加固,中下台阶设置积水坑,裂隙水集中引排,采取上述综合措施来有效控制围岩的变形沉降。另外,单工序作业,管超前、严注浆、快支护快封闭,保证施工作业安全可控,使隧道顺利通过地质软弱地段。

Description

富水浅埋地质下隧道的施工方法
技术领域
本发明属于隧道施工技术领域,特别是涉及一种富水浅埋地质下隧道的施工方法。
背景技术
隧道是埋置于地层内的工程建筑物,是人类利用地下空间的一种形式。传统隧道的施工方法均是采用暗挖掘进的常规手段,地表及洞内不做处理。传统隧道洞口段施工常采用Ф108长管棚超前支护方式,开挖工法为四步CD法暗挖掘进,如果该处的地质软弱,富水量较大,若采用上述这种传统方法进行施工就会存在较大的安全风险。
发明内容
为了解决上述问题,本发明的目的在于提供一种富水浅埋地质下隧道的施工方法。
为了达到上述目的,本发明提供的富水浅埋地质下隧道的施工方法包括按顺序进行的下列步骤:
1)首先在隧道的洞口段制作Φ108mm长管棚超前支护,然后在掌子面前方的拱顶部位120°范围内向斜上方打设多环超前小导管,环向间距40cm,10°~40°交错打设,相邻环的超前小导管的水平投影搭接长度大于等于1.5米,并通过这些超前小导管进行注浆,以对该范围内的土体进行加固;
2)采用上、中、下三台阶预留核心土方法进行洞身开挖,并加设仰拱钢架作为临时横向支撑,以用于加强支护,每一循环开挖支设1榀仰拱钢架;并支设初支钢架;
3)在洞内围岩上进行初支施工,然后采用钢花管对隧道两侧的初支外侧的土体进行径向注浆加固,之后在该部位两侧的土体中以向下方倾斜30~45°的方式打设多根钢管作为锁脚,以对初支进行补强,并采用L形钢筋将锁脚与初支钢架连接,以用于固定住拱脚;
4)仰拱开挖前对仰拱端头下台阶掌子面软弱围岩采用片石反压+钢板桩的防护方式进行支护,每一循环开挖支护2.4米;当仰拱的基底软弱层厚度小于1.5米时,将其挖除并采用C20片石混凝土换填,当软弱层厚度大于1.5米时,对仰拱基底以下6米的范围采用钢花管进行竖向注浆加固处理;
5)进行二衬施工,施工处距离掌子面尽量控制在35m内,待隧道两侧的二衬混凝土达到设定强度后再采用每一循环6m的短循环方式进行局部换拱处理,以加快二衬施工进度;
6)在掌子面采用PVC排水管引水,汇水至中下台阶中心线处铺设1m宽防水板作为引水板,将水集中引排至中心水沟排出;
7)洞内每3米设置一处监控量测控制点,量测频率为每天2次,及时关注围岩收敛及地表沉降情况,以便及时动态调整优化施工措施。
在步骤1)中,所述的超前小导管采用直径50mm,壁厚5mm,长度5米的钢花管。
在步骤3)中,所述的钢花管的长度为3米,直径为50mm;锁脚所采用的钢管直径为50mm。
在步骤4)中,所述的进行竖向注浆加固处理采用的钢花管直径为89mm,钢花管的间距为1.5×1.5m,梅花形布置。
本发明提供的富水浅埋地质下隧道的施工方法具有如下优点:采取短台阶开挖,上、中、下台阶每循环只开挖一榀,锁脚加强,同步径向注浆加固,中下台阶设置积水坑,裂隙水集中引排,采取上述综合措施来有效控制围岩的变形沉降。另外,单工序作业,管超前、严注浆、快支护快封闭,保证施工作业安全可控,使隧道顺利通过地质软弱地段。
附图说明
图1为利用本发明提供的富水浅埋地质下隧道的施工方法施工时隧道横向截面处超前小导管及锁脚位置示意图。
图2为利用本发明提供的富水浅埋地质下隧道的施工方法施工时隧道纵向截面处超前小导管位置示意图。
图3为利用本发明提供的富水浅埋地质下隧道的施工方法施工时洞身开挖过程示意图。
图4为利用本发明提供的富水浅埋地质下隧道的施工方法施工时横向截面处初支补强注浆位置示意图。
图5为利用本发明提供的富水浅埋地质下隧道的施工方法施工时钢板桩防护布置图。
具体实施方式
下面结合附图和具体实施例对本发明提供的富水浅埋地质下隧道的施工方法进行详细说明。
如图1至图5所示,本发明提供的富水浅埋地质下隧道的施工方法包括按顺序进行的下列步骤:
1)首先在隧道1的洞口段制作Φ108mm长管棚超前支护,然后在掌子面前方的拱顶部位120°范围内向斜上方打设多环超前小导管2,超前小导管2采用直径50mm,壁厚5mm,长度5米的钢花管,环向间距40cm,10°~40°交错打设,相邻环的超前小导管2的水平投影搭接长度大于等于1.5米,并通过这些超前小导管2进行注浆,以对该范围内的土体进行加固;
2)采用如图2所示的上、中、下三台阶预留核心土方法进行洞身开挖,并如图3所示加设仰拱钢架3作为临时横向支撑,以用于加强支护,每一循环开挖支设1榀仰拱钢架3;并支设初支钢架4;
3)在洞内围岩上进行初支施工,然后如图4所示,采用3米长,50mm直径的钢花管5对隧道1两侧的初支外侧的土体进行径向注浆加固,之后在该部位两侧的土体中以向下方倾斜30~45°的方式打设多根50mm直径的钢管作为锁脚6,以对初支进行补强,并采用L形钢筋将锁脚6与初支钢架4连接,以用于固定住拱脚;
4)如图5所示,仰拱7开挖前对仰拱7端头下台阶掌子面软弱围岩采用片石反压+钢板桩8的防护方式进行支护,每一循环开挖支护2.4米,快支护,快封闭,尽量减少暴露时间;当仰拱7的基底软弱层厚度小于1.5米时,将其挖除并采用C20片石混凝土换填,当软弱层厚度大于1.5米时,对仰拱7基底以下6米的范围采用89mm直径的钢花管进行竖向注浆加固处理,钢花管的间距为1.5×1.5m,梅花形布置;
5)进行二衬施工,施工处距离掌子面尽量控制在35m内,因部分初支段变形较大,为保证施工安全,尽快进行二衬施工,以防止初支变形,待隧道1两侧的二衬混凝土达到设定强度后再采用每一循环6m的短循环方式进行局部换拱处理,以加快二衬施工进度;
6)在掌子面采用PVC排水管引水,汇水至中下台阶中心线处铺设1m宽防水板作为引水板,将水集中引排至中心水沟排出;
7)洞内每3米设置一处监控量测控制点,量测频率为每天2次,及时关注围岩收敛及地表沉降情况,以便及时动态调整优化施工措施。

Claims (4)

1.一种富水浅埋地质下隧道的施工方法,其特征在于:所述的施工方法包括按顺序进行的下列步骤:
1)首先在隧道(1)的洞口段制作Φ108mm长管棚超前支护,然后在掌子面前方的拱顶部位120°范围内向斜上方打设多环超前小导管(2),环向间距40cm,10°~40°交错打设,相邻环的超前小导管(2)的水平投影搭接长度大于等于1.5米,并通过这些超前小导管(2)进行注浆,以对该范围内的土体进行加固;
2)采用上、中、下三台阶预留核心土方法进行洞身开挖,并加设仰拱钢架(3)作为临时横向支撑,以用于加强支护,每一循环开挖支设1榀仰拱钢架(3);并支设初支钢架(4);
3)在洞内围岩上进行初支施工,然后采用钢花管(5)对隧道(1)两侧的初支外侧的土体进行径向注浆加固,之后在该部位两侧的土体中以向下方倾斜30~45°的方式打设多根钢管作为锁脚(6),以对初支进行补强,并采用L形钢筋将锁脚(6)与初支钢架(4)连接,以用于固定住拱脚;
4)仰拱(7)开挖前对仰拱(7)端头下台阶掌子面软弱围岩采用片石反压+钢板桩(8)的防护方式进行支护,每一循环开挖支护2.4米;当仰拱(7)的基底软弱层厚度小于1.5米时,将其挖除并采用C20片石混凝土换填,当软弱层厚度大于1.5米时,对仰拱(7)基底以下6米的范围采用钢花管进行竖向注浆加固处理;
5)进行二衬施工,施工处距离掌子面尽量控制在35m内,待隧道(1)两侧的二衬混凝土达到设定强度后再采用每一循环6m的短循环方式进行局部换拱处理,以加快二衬施工进度;
6)在掌子面采用PVC排水管引水,汇水至中下台阶中心线处铺设1m宽防水板作为引水板,将水集中引排至中心水沟排出;
7)洞内每3米设置一处监控量测控制点,量测频率为每天2次,及时关注围岩收敛及地表沉降情况,以便及时动态调整优化施工措施。
2.根据权利要求1所述的富水浅埋地质下隧道的施工方法,其特征在于:在步骤1)中,所述的超前小导管(2)采用直径50mm,壁厚5mm,长度5米的钢花管。
3.根据权利要求1所述的富水浅埋地质下隧道的施工方法,其特征在于:在步骤3)中,所述的钢花管(5)的长度为3米,直径为50mm;锁脚(6)所采用的钢管直径为50mm。
4.根据权利要求1所述的富水浅埋地质下隧道的施工方法,其特征在于:在步骤4)中,所述的进行竖向注浆加固处理采用的钢花管直径为89mm,钢花管的间距为1.5×1.5m,梅花形布置。
CN201810390047.1A 2018-04-27 2018-04-27 富水浅埋地质下隧道的施工方法 Pending CN108643935A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810390047.1A CN108643935A (zh) 2018-04-27 2018-04-27 富水浅埋地质下隧道的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810390047.1A CN108643935A (zh) 2018-04-27 2018-04-27 富水浅埋地质下隧道的施工方法

Publications (1)

Publication Number Publication Date
CN108643935A true CN108643935A (zh) 2018-10-12

Family

ID=63748154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810390047.1A Pending CN108643935A (zh) 2018-04-27 2018-04-27 富水浅埋地质下隧道的施工方法

Country Status (1)

Country Link
CN (1) CN108643935A (zh)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109578035A (zh) * 2018-11-06 2019-04-05 四川路航建设工程有限责任公司 钢管排水锁脚桩及施工方法
CN109854281A (zh) * 2019-02-01 2019-06-07 安徽建筑大学 上土下岩复合断面地层顶管施工的支护方法
CN110374677A (zh) * 2019-08-02 2019-10-25 中铁九局集团第六工程有限公司 高原富水软岩隧道控排水施工工法
CN110541721A (zh) * 2019-09-11 2019-12-06 中国建筑土木建设有限公司 一种富水流砂地层全风化围岩隧道的支护体系及施工方法
CN110617067A (zh) * 2019-09-02 2019-12-27 中铁十八局集团有限公司 一种极软弱围岩隧道全断面边界超前管棚低风险施工方法
CN110685714A (zh) * 2019-08-30 2020-01-14 中铁十四局集团第四工程有限公司 千枚岩地质下浅埋偏压隧道微台阶预留核心土施工结构及方法
CN111472804A (zh) * 2020-05-29 2020-07-31 中铁隧道局集团有限公司 一种位于基坑中的上软下硬地层越江隧道进洞口施工方法
CN111577344A (zh) * 2020-05-14 2020-08-25 中铁十八局集团有限公司 大倾角发育裂隙涌水洞内治水开挖方法
CN111577355A (zh) * 2020-05-14 2020-08-25 中铁十八局集团有限公司 一种特软岩层隧道间隔二次拱架长锚索锁脚复合施工方法
CN111997624A (zh) * 2020-08-18 2020-11-27 中交二公局第三工程有限公司 一种浅埋大断面暗挖矩形隧道施工方法
CN112065405A (zh) * 2020-09-18 2020-12-11 中国电建集团华东勘测设计研究院有限公司 一种浅埋富水土质隧洞的施工方法
CN112302688A (zh) * 2020-11-04 2021-02-02 沈阳建筑大学 一种适用装配式隧道支护结构背后注浆的端头封堵装置及其施工方法
CN112963177A (zh) * 2021-04-19 2021-06-15 山东建筑大学 一种软弱地层浅埋大断面隧道洞内有洞的支护方法及结构
CN113931637A (zh) * 2021-10-23 2022-01-14 中电建十一局工程有限公司 一种浅埋富水较软岩隧道施工方法
CN114263478A (zh) * 2021-12-25 2022-04-01 中铁二局集团有限公司 一种岩溶隧道穿越深厚砂砾土层施工方法
CN114991783A (zh) * 2022-07-15 2022-09-02 中交(福州)建设有限公司 一种适用于浅埋富水砂土状软弱围岩隧道的开挖方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606173A (zh) * 2012-04-01 2012-07-25 中铁十二局集团有限公司 一种处理隧道变形段、加快掘进的施工方法
CN102953737A (zh) * 2012-10-22 2013-03-06 中铁三局集团有限公司 Ⅵ级富水围岩隧道仰拱施工方法
CN103628915A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 一种大断面富水饱和粉细砂隧道降排水方法
CN203756182U (zh) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 一种应用于软弱岩质区域浅埋公路隧道的支护结构
CN103993892A (zh) * 2014-05-29 2014-08-20 山东大学 一种用于软弱破碎不均匀地层隧道施工的支护方法
CN104389610A (zh) * 2014-09-12 2015-03-04 中铁建大桥工程局集团第二工程有限公司 一种穿越运营高速公路隧道超短台阶施工方法
CN105156121A (zh) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 一种大断面黄土隧道进洞浅埋段的施工方法
CN105781571A (zh) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 一种软岩变形隧道衬砌支护拆换拱施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102606173A (zh) * 2012-04-01 2012-07-25 中铁十二局集团有限公司 一种处理隧道变形段、加快掘进的施工方法
CN102953737A (zh) * 2012-10-22 2013-03-06 中铁三局集团有限公司 Ⅵ级富水围岩隧道仰拱施工方法
CN103628915A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 一种大断面富水饱和粉细砂隧道降排水方法
CN203756182U (zh) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 一种应用于软弱岩质区域浅埋公路隧道的支护结构
CN103993892A (zh) * 2014-05-29 2014-08-20 山东大学 一种用于软弱破碎不均匀地层隧道施工的支护方法
CN104389610A (zh) * 2014-09-12 2015-03-04 中铁建大桥工程局集团第二工程有限公司 一种穿越运营高速公路隧道超短台阶施工方法
CN105156121A (zh) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 一种大断面黄土隧道进洞浅埋段的施工方法
CN105781571A (zh) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 一种软岩变形隧道衬砌支护拆换拱施工方法

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109578035B (zh) * 2018-11-06 2024-04-30 四川路航建设工程有限责任公司 钢管排水锁脚桩及施工方法
CN109578035A (zh) * 2018-11-06 2019-04-05 四川路航建设工程有限责任公司 钢管排水锁脚桩及施工方法
CN109854281A (zh) * 2019-02-01 2019-06-07 安徽建筑大学 上土下岩复合断面地层顶管施工的支护方法
CN110374677A (zh) * 2019-08-02 2019-10-25 中铁九局集团第六工程有限公司 高原富水软岩隧道控排水施工工法
CN110685714B (zh) * 2019-08-30 2021-05-14 中铁十四局集团第四工程有限公司 千枚岩地质下浅埋偏压隧道微台阶预留核心土施工结构及方法
CN110685714A (zh) * 2019-08-30 2020-01-14 中铁十四局集团第四工程有限公司 千枚岩地质下浅埋偏压隧道微台阶预留核心土施工结构及方法
CN110617067A (zh) * 2019-09-02 2019-12-27 中铁十八局集团有限公司 一种极软弱围岩隧道全断面边界超前管棚低风险施工方法
CN110541721A (zh) * 2019-09-11 2019-12-06 中国建筑土木建设有限公司 一种富水流砂地层全风化围岩隧道的支护体系及施工方法
CN111577344A (zh) * 2020-05-14 2020-08-25 中铁十八局集团有限公司 大倾角发育裂隙涌水洞内治水开挖方法
CN111577355A (zh) * 2020-05-14 2020-08-25 中铁十八局集团有限公司 一种特软岩层隧道间隔二次拱架长锚索锁脚复合施工方法
CN111577355B (zh) * 2020-05-14 2023-08-08 中铁十八局集团有限公司 一种特软岩层隧道间隔二次拱架长锚索锁脚复合施工方法
CN111472804A (zh) * 2020-05-29 2020-07-31 中铁隧道局集团有限公司 一种位于基坑中的上软下硬地层越江隧道进洞口施工方法
CN111997624A (zh) * 2020-08-18 2020-11-27 中交二公局第三工程有限公司 一种浅埋大断面暗挖矩形隧道施工方法
CN112065405A (zh) * 2020-09-18 2020-12-11 中国电建集团华东勘测设计研究院有限公司 一种浅埋富水土质隧洞的施工方法
CN112302688A (zh) * 2020-11-04 2021-02-02 沈阳建筑大学 一种适用装配式隧道支护结构背后注浆的端头封堵装置及其施工方法
CN112963177A (zh) * 2021-04-19 2021-06-15 山东建筑大学 一种软弱地层浅埋大断面隧道洞内有洞的支护方法及结构
CN113931637A (zh) * 2021-10-23 2022-01-14 中电建十一局工程有限公司 一种浅埋富水较软岩隧道施工方法
CN114263478A (zh) * 2021-12-25 2022-04-01 中铁二局集团有限公司 一种岩溶隧道穿越深厚砂砾土层施工方法
CN114991783A (zh) * 2022-07-15 2022-09-02 中交(福州)建设有限公司 一种适用于浅埋富水砂土状软弱围岩隧道的开挖方法

Similar Documents

Publication Publication Date Title
CN108643935A (zh) 富水浅埋地质下隧道的施工方法
CN106907159B (zh) 一种浅埋暗挖地铁车站分离开敞式结构及其施工方法
CN104405399B (zh) 一种穿越流沙地层隧道开挖支护体工法
CN102606167B (zh) 浅埋暗挖隧道横向注浆导管沉降控制施工方法
CN101864960B (zh) 岩溶地区双连拱公路隧道施工方法
CN102606162B (zh) 隧道软弱围岩浅埋易坍塌区快速施工方法
CN110821503B (zh) 一种超深盾构区间风井先隧后主体施工方法
CN205742213U (zh) 基坑支护结构
CN110685714B (zh) 千枚岩地质下浅埋偏压隧道微台阶预留核心土施工结构及方法
CN103758123B (zh) 人工挖孔灌注桩护壁衬的施工方法
CN102606168B (zh) 防止浅埋暗挖隧道开挖时沉降变形的施工方法
CN108457656A (zh) 一种出土隧道施工方法
CN111502696A (zh) 暗挖隧道的密网式超前支护系统及施工方法
CN110735653A (zh) 一种针对火成岩富水断层的深孔后退式注浆堵水施工方法
CN104612696B (zh) 大断面暗挖地铁车站在粉细砂层中穿越高架桥柱洞法施工方法
CN107965325B (zh) 一种小净距浅埋隧道初支拱架更换施工方法
CN106522989A (zh) 风井结构和盾构掘进平行施工的方法
CN105863648A (zh) 一种暗挖浅覆大断面隧道施工方法
CN110159298A (zh) 一种地铁暗挖车站初支扣拱施工方法
CN208965598U (zh) 灌浆帷幕与地下洞室相交部位的防渗处理结构
CN109630193A (zh) 地铁区间联络通道开挖出现涌水现象的治理方法
CN104153783B (zh) 一种富含地下水及松散砂卵石引水洞施工工艺
CN105822327B (zh) 一种暗挖小导洞侧向超前预加固施工方法
CN114352292A (zh) 用于风化千枚岩地层的浅埋偏压连拱隧道施工方法
CN208578574U (zh) 一种双侧壁导坑九部支护结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181012

WD01 Invention patent application deemed withdrawn after publication