CN108627130A - A kind of tailing dam surface displacement monitoring point structure and method for arranging - Google Patents
A kind of tailing dam surface displacement monitoring point structure and method for arranging Download PDFInfo
- Publication number
- CN108627130A CN108627130A CN201810455715.4A CN201810455715A CN108627130A CN 108627130 A CN108627130 A CN 108627130A CN 201810455715 A CN201810455715 A CN 201810455715A CN 108627130 A CN108627130 A CN 108627130A
- Authority
- CN
- China
- Prior art keywords
- displacement monitoring
- monitoring point
- surface displacement
- point
- dam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01B—MEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
- G01B21/00—Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
- G01B21/02—Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring length, width, or thickness
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/10—Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Revetment (AREA)
Abstract
A kind of tailing dam surface displacement monitoring point structure and method for arranging.Monitoring point is divided into:Surface displacement monitoring point and displacement monitoring basic point;Surface displacement monitoring point distributing position is:34 row's surface displacement monitoring points are set, often row's surface displacement monitoring point is arranged on same straight line, first row and end row surface displacement monitoring point are arranged in initial dam dam crest and fill dam dam crest, and the setting position of the surface displacement monitoring point between first row and end row is according to the stability Calculation slip circle location determination of flood operating mode.Displacement monitoring basic point distributing position is:Displacement monitoring basic point is arranged in the solid and reliable position of both sides massif, and point is no less than 3.By above structure and method, the invention provides a kind of needs of adaptation Safety of Tailings Dam monitoring, and ensure to have it is firm, accurate, simple, reduce cost monitoring point structure a little and method for arranging.
Description
Technical field
The invention belongs to geotechnical engineering monitoring works technical field.A kind of tailing dam surface displacement monitoring point knot is provided
Structure and method for arranging have many advantages, such as firm, accurate, low cost, construction is simple.
Background technology
Major hazard source of the Tailings Dam as mine repeatedly occurs considerable safety and environmental accident, seriously threatens in recent years
The people's lives and property safety, causing severe social influence and environment influences.Therefore, it improves Safety of Tailings Dam and monitors water
It is flat, it is ensured that Safety of Tailings Dam operation has important strategic importance.Surface displacement, which belongs in Safety of Tailings Dam monitoring, must survey item
Mesh establishes firm, cheap, easy for construction monitoring point structure, and reasonable Arrangement surface displacement monitoring point, is to realize standard
The basic condition of true safety monitoring and displacement early warning.In current Tailings Dam monitoring works, since monitoring point structure type is improper
With construction method complexity, the effect, accuracy and project cost of monitoring are affected.Therefore, the invention provides a kind of new
The tailing dam surface displacement monitoring point structure and method for arranging of type, have broad application prospects.
Invention content
In view of the above problems, the invention proposes a kind of tailing dam surface displacement monitoring point structure and method for arranging, lead to
Surface displacement monitoring point and the displacement monitoring basic point that special construction is arranged in specific position are crossed, it can be effectively to tailing dam table
Face misalignment is monitored.
To achieve the goals above, the technical solution that the invention uses for:A kind of tailing dam surface displacement monitoring point
Method for arranging, which is characterized in that its step is:Monitoring point is divided into:Surface displacement monitoring point and displacement monitoring basic point;
1), surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point, often arranges surface displacement monitoring
Point is arranged on same straight line;
1a), first row and end row's surface displacement monitoring point are arranged in initial dam dam crest and fill dam dam crest;
1b), the setting position of the intermediate row surface displacement monitoring point between first row and end row is according to the stabilization of flood operating mode
The slip circle front and rear edges location determination of calculating;
2), displacement monitoring basic point distributing position is:Displacement monitoring basic point is arranged in the solid and reliable position of both sides massif, point
Position no less than 3.
The surface displacement monitoring point buried depth is 0.6m.
The displacement monitoring basic point buried depth is 1.6m.
Surface displacement monitoring point in the method for arranging of tailing dam surface displacement monitoring point, which is characterized in that its structure is:Packet
External brick enclosure wall is included, rectangular cross section is equipped at brick enclosure wall bosom position and observes pier, is observed in rectangular cross section
Clay is backfilled between pier and brick enclosure wall;The round steel of the pre-buried φ 20mm of rectangular cross section observation socle;Described is brick
It is stamped cover board in enclosure wall top surface.
The round steel exposes rectangular cross section observation pier 30mm.
The rectangular cross section observation pier makes raw material and slag or volcano grey matter cement, rank is used to be more than or equal to 32.5
Grade;Stone uses grain size for the middle sand of 0.15-3mm using the natural pebble or hard rubble, sand of grading qualification, clay content
Less than or equal to 3%;Sulphates content is less than or equal to 1% in mixing water.
The invention has the beneficial effect that:
1, the intermediate row position of monitoring point is determined according to the flood stable conditions result of calculation of maximum height of dam section, is compensated for
The conventional method of intermediate row position is determined by experience array pitch, and there is scientific theory foundation.
2, observation pier, which makes, preferentially uses slag or volcano grey matter cement, it is therefore prevented that freeze thawing influences, and compensates for using fine coal
The deficiency of ash concrete.
3, the monitoring point for displacement architecture basics are firm, cheap, easy for construction, through live operation test, may be implemented
Accurate safety monitoring and displacement early warning.
Description of the drawings
Fig. 1:Tailing dam monitoring point for displacement floor plan.
Fig. 2:Dam stability analysis result figure.
Fig. 3:Monitoring point for displacement sectional structure chart.
Fig. 4:Monitoring point for displacement plan view.
Specific implementation mode
A kind of tailing dam surface displacement monitoring point method for arranging, step are:Monitoring point is divided into:Surface displacement monitoring point 1
With displacement monitoring basic point 2;
1, surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point 1, often arranges surface displacement monitoring
Point 1 is arranged on same straight line;
1a, first row and end row's surface displacement monitoring point 1 are arranged in initial dam dam crest and fill dam dam crest;
The setting position of intermediate row surface displacement monitoring point 1 between 1b, first row and end row is according to the stabilization of flood operating mode
The slip circle front and rear edges of calculating determine and (if preceding (rear) edge is located at dam crest, should merge with first (end) row monitoring point);
1c, with row surface displacement monitoring point spacing according to《Safety of Tailings Dam Specifications of Monitoring Technology》Regulation determine;
2,2 distributing position of displacement monitoring basic point is:Displacement monitoring basic point 2 is arranged in the solid and reliable position of both sides massif,
Point is no less than 3.
1 buried depth of surface displacement monitoring point is 0.6m.
2 buried depth of displacement monitoring basic point is 1.6m.
Surface displacement monitoring point 1 in the method for arranging of tailing dam surface displacement monitoring point, structure are:Include external
Brick enclosure wall 1-1, brick enclosure wall 1-1 height are 240mm.Rectangular cross section is equipped at brick enclosure wall 1-1 bosoms position to see
Pier 1-2 is examined, the rectangular cross section observes pier 1-2 and uses C20 concrete, length of side 200mm.Make raw material using slag and
Volcano grey matter cement, rank are more than or equal to 32.5 grades;Stone is adopted natural troubled times or hard rubble, sand using grading qualification
The middle sand for being 0.15-3mm with grain size, clay content are less than or equal to 3%;Sulphates content is less than or equal to 1% in mixing water.In rectangle
Section observes backfill clay 1-5 between pier 1-2 and brick enclosure wall 1-1;The rectangular cross section observation pier 1-2 pre-buried φ in top
The round steel 1-3, the round steel 1-3 of 20mm exposes rectangular cross section observation pier 1-230mm.
Cover board 1-4 is stamped in the top surfaces brick enclosure wall 1-1, and cover board 1-4 is reinforced concrete cover plate, matches 6@of φ, 100 steel
Muscle net.
2 structure of displacement monitoring basic point is identical as 1 structure of surface displacement monitoring point, and only buried depth is different.
The invention is to provide for simple, the effective tailing dam surface displacement monitoring point structure of one kind and arrangement side
Method, adapts to the needs that Safety of Tailings Dam monitors, and guarantee has many advantages, such as firm, accurate, simple, reduction cost.
More than, the technical solution in the invention embodiment is clearly and completely described.Obviously, described
Embodiment be only the invention a part of the embodiment, instead of all the embodiments.Based on the reality in the invention
Example is applied, every other embodiment obtained by those of ordinary skill in the art without making creative efforts all belongs to
In the range of the invention protection.
Claims (6)
1. a kind of tailing dam surface displacement monitoring point method for arranging, which is characterized in that its step is:Monitoring point is divided into:Surface position
Move monitoring point (1) and displacement monitoring basic point (2);
1), surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point (1), often arranges surface displacement monitoring point
(1) it is arranged on same straight line;
1a), first row and end row surface displacement monitoring point (1) are arranged in initial dam dam crest and fill dam dam crest;
1b), the setting position of the intermediate row surface displacement monitoring point (1) between first row and end row is according to the stabilimeter of flood operating mode
Calculate slip circle location determination;
2), displacement monitoring basic point (2) distributing position is:Displacement monitoring basic point (2) is arranged in the solid and reliable position of both sides massif,
Point is no less than 3.
2. a kind of tailing dam surface displacement monitoring point according to claim 1 method for arranging, it is characterised in that:The table
Face monitoring point for displacement (1) buried depth is 0.6m.
3. a kind of tailing dam surface displacement monitoring point according to claim 1 method for arranging, it is characterised in that:The position
It is 1.6m to move monitoring basic point (2) buried depth.
4. the surface displacement monitoring point (1) in the method for arranging of tailing dam surface displacement monitoring point described in a kind of claim 1,
It is characterized in that, its structure is:Include the brick enclosure wall (1-1) of outside, is set at brick enclosure wall (1-1) bosom position
There is rectangular cross section to observe pier (1-2), the backfill clay (1-5) between rectangular cross section observation pier (1-2) and brick enclosure wall (1-1);
The round steel (1-3) of the rectangular cross section observation pre-buried φ 20mm in the top pier (1-2);The top surface brick enclosure wall (1-1) lid
There is cover board (1-4).
5. surface displacement monitoring point (1) according to claim 4, it is characterised in that:The round steel (1-3) exposes rectangle
Section observes pier (1-2) 30mm.
6. surface displacement monitoring point (1) according to claim 4, it is characterised in that:The rectangular cross section observation pier (1-
2) making raw material uses slag or volcano grey matter cement, rank to be more than or equal to 32.5 grades;Stone uses the natural ovum of grading qualification
Stone or hard rubble, sand use grain size for the middle sand of 0.15-3mm, and clay content is less than or equal to 3%;Sulfate contains in mixing water
Amount is less than or equal to 1%.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810455715.4A CN108627130A (en) | 2018-05-14 | 2018-05-14 | A kind of tailing dam surface displacement monitoring point structure and method for arranging |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810455715.4A CN108627130A (en) | 2018-05-14 | 2018-05-14 | A kind of tailing dam surface displacement monitoring point structure and method for arranging |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108627130A true CN108627130A (en) | 2018-10-09 |
Family
ID=63693195
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810455715.4A Pending CN108627130A (en) | 2018-05-14 | 2018-05-14 | A kind of tailing dam surface displacement monitoring point structure and method for arranging |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108627130A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110617798A (en) * | 2019-10-16 | 2019-12-27 | 辽宁大学 | Monitoring tube structure for tailing dam infiltration line and distribution thereof |
CN111964621A (en) * | 2020-08-14 | 2020-11-20 | 洛阳理工学院 | Layout method of displacement monitoring points in tailing pond based on dangerous sliding arc |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632461A (en) * | 2004-12-29 | 2005-06-29 | 西安华腾光电有限责任公司 | Symmetrical closed laser arch dam deformation monitoring method |
CN102590085A (en) * | 2012-01-18 | 2012-07-18 | 清华大学 | Method for identifying cross joint state during arch dam construction period |
CN102878966A (en) * | 2012-10-13 | 2013-01-16 | 云南新立有色金属有限公司 | Method for monitoring movement of dam body of five-level tailings pond |
CN203008434U (en) * | 2012-06-06 | 2013-06-19 | 中国有色金属长沙勘察设计研究院有限公司 | Protective device for mine tailing dam electronic equipment and electronic apparatus |
CN104978843A (en) * | 2015-06-25 | 2015-10-14 | 辽宁有色勘察研究院 | Tailings reservoir saturation line on-line monitoring point layout and zigbee networking structure |
CN105444804A (en) * | 2015-06-25 | 2016-03-30 | 辽宁有色勘察研究院 | Tailing pond online safety monitoring and comprehensive early-warning system |
CN207147511U (en) * | 2017-09-11 | 2018-03-27 | 中国有色金属长沙勘察设计研究院有限公司 | A kind of Tailings Dam monitors point protection device on-line |
-
2018
- 2018-05-14 CN CN201810455715.4A patent/CN108627130A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632461A (en) * | 2004-12-29 | 2005-06-29 | 西安华腾光电有限责任公司 | Symmetrical closed laser arch dam deformation monitoring method |
CN102590085A (en) * | 2012-01-18 | 2012-07-18 | 清华大学 | Method for identifying cross joint state during arch dam construction period |
CN203008434U (en) * | 2012-06-06 | 2013-06-19 | 中国有色金属长沙勘察设计研究院有限公司 | Protective device for mine tailing dam electronic equipment and electronic apparatus |
CN102878966A (en) * | 2012-10-13 | 2013-01-16 | 云南新立有色金属有限公司 | Method for monitoring movement of dam body of five-level tailings pond |
CN104978843A (en) * | 2015-06-25 | 2015-10-14 | 辽宁有色勘察研究院 | Tailings reservoir saturation line on-line monitoring point layout and zigbee networking structure |
CN105444804A (en) * | 2015-06-25 | 2016-03-30 | 辽宁有色勘察研究院 | Tailing pond online safety monitoring and comprehensive early-warning system |
CN207147511U (en) * | 2017-09-11 | 2018-03-27 | 中国有色金属长沙勘察设计研究院有限公司 | A kind of Tailings Dam monitors point protection device on-line |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110617798A (en) * | 2019-10-16 | 2019-12-27 | 辽宁大学 | Monitoring tube structure for tailing dam infiltration line and distribution thereof |
CN111964621A (en) * | 2020-08-14 | 2020-11-20 | 洛阳理工学院 | Layout method of displacement monitoring points in tailing pond based on dangerous sliding arc |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE112016005692B4 (en) | A method for designing support parameters of the transition support of the excavation joint in the fully mechanical mixed offset reduction | |
CN105926544A (en) | Economical debris flow blocking dam structure and construction method thereof | |
CN108627130A (en) | A kind of tailing dam surface displacement monitoring point structure and method for arranging | |
Teng et al. | Surface subsidence characteristics of grout injection into overburden: case study of Yuandian No. 2 coalmine, China | |
CN108867378A (en) | A kind of Techniques of Tunnel-Type Anchorage for Suspension Bridge and construction method | |
CN105332392B (en) | A kind of method of surface mine hole bottom leakage preventing structure and Anti-seeping technology | |
CN207452824U (en) | A kind of vertical type barricade in hydraulic engineering river | |
CN103410160A (en) | Combined supporting method for bedding extra-high rock side slope | |
CN105971605B (en) | A kind of underground mines exploration without waster method | |
Kuranchie et al. | Load–settlement behaviour of a strip footing resting on iron ore tailings as a structural fill | |
CN209538128U (en) | A kind of dam structure promoted for reservoir landscape | |
CN203284795U (en) | Buttressed retaining wall with anchor board | |
CN207619863U (en) | A kind of box culvert backfill structure | |
CN103866775A (en) | Protection method of cold region dispersive soil side slope | |
CN203559398U (en) | Simple water gate | |
CN207685789U (en) | A kind of dam structure of dam | |
CN207537987U (en) | The narrow toe board arrangement of the high CFRD in Narrow Valleys area | |
Day et al. | Validation of Composite Geological Strength Index for healed rockmass structure in deep mine access and production tunnels | |
CN208762976U (en) | The rock and spillway for taking into account toe board and guide-wall lead wall connection structure | |
CN207079600U (en) | A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope | |
CN209066527U (en) | A kind of clear slot leveling unit of foundation pit | |
CN203096686U (en) | Novel composite structure combining long piled wharf and shore-connecting structure | |
CN208884549U (en) | A kind of supporting construction of large size talus slide | |
CN207582476U (en) | A kind of civil engineering slopes ruggedized construction | |
CN206205038U (en) | A kind of good bucket tooth set played a protective role to bucket tooth of stationarity |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181009 |
|
WD01 | Invention patent application deemed withdrawn after publication |