CN108627130A - A kind of tailing dam surface displacement monitoring point structure and method for arranging - Google Patents

A kind of tailing dam surface displacement monitoring point structure and method for arranging Download PDF

Info

Publication number
CN108627130A
CN108627130A CN201810455715.4A CN201810455715A CN108627130A CN 108627130 A CN108627130 A CN 108627130A CN 201810455715 A CN201810455715 A CN 201810455715A CN 108627130 A CN108627130 A CN 108627130A
Authority
CN
China
Prior art keywords
displacement monitoring
monitoring point
surface displacement
point
dam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810455715.4A
Other languages
Chinese (zh)
Inventor
郝喆
周素航
曹明杰
陈娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning University
Original Assignee
Liaoning University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning University filed Critical Liaoning University
Priority to CN201810455715.4A priority Critical patent/CN108627130A/en
Publication of CN108627130A publication Critical patent/CN108627130A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/02Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring length, width, or thickness
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Revetment (AREA)

Abstract

A kind of tailing dam surface displacement monitoring point structure and method for arranging.Monitoring point is divided into:Surface displacement monitoring point and displacement monitoring basic point;Surface displacement monitoring point distributing position is:34 row's surface displacement monitoring points are set, often row's surface displacement monitoring point is arranged on same straight line, first row and end row surface displacement monitoring point are arranged in initial dam dam crest and fill dam dam crest, and the setting position of the surface displacement monitoring point between first row and end row is according to the stability Calculation slip circle location determination of flood operating mode.Displacement monitoring basic point distributing position is:Displacement monitoring basic point is arranged in the solid and reliable position of both sides massif, and point is no less than 3.By above structure and method, the invention provides a kind of needs of adaptation Safety of Tailings Dam monitoring, and ensure to have it is firm, accurate, simple, reduce cost monitoring point structure a little and method for arranging.

Description

A kind of tailing dam surface displacement monitoring point structure and method for arranging
Technical field
The invention belongs to geotechnical engineering monitoring works technical field.A kind of tailing dam surface displacement monitoring point knot is provided Structure and method for arranging have many advantages, such as firm, accurate, low cost, construction is simple.
Background technology
Major hazard source of the Tailings Dam as mine repeatedly occurs considerable safety and environmental accident, seriously threatens in recent years The people's lives and property safety, causing severe social influence and environment influences.Therefore, it improves Safety of Tailings Dam and monitors water It is flat, it is ensured that Safety of Tailings Dam operation has important strategic importance.Surface displacement, which belongs in Safety of Tailings Dam monitoring, must survey item Mesh establishes firm, cheap, easy for construction monitoring point structure, and reasonable Arrangement surface displacement monitoring point, is to realize standard The basic condition of true safety monitoring and displacement early warning.In current Tailings Dam monitoring works, since monitoring point structure type is improper With construction method complexity, the effect, accuracy and project cost of monitoring are affected.Therefore, the invention provides a kind of new The tailing dam surface displacement monitoring point structure and method for arranging of type, have broad application prospects.
Invention content
In view of the above problems, the invention proposes a kind of tailing dam surface displacement monitoring point structure and method for arranging, lead to Surface displacement monitoring point and the displacement monitoring basic point that special construction is arranged in specific position are crossed, it can be effectively to tailing dam table Face misalignment is monitored.
To achieve the goals above, the technical solution that the invention uses for:A kind of tailing dam surface displacement monitoring point Method for arranging, which is characterized in that its step is:Monitoring point is divided into:Surface displacement monitoring point and displacement monitoring basic point;
1), surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point, often arranges surface displacement monitoring Point is arranged on same straight line;
1a), first row and end row's surface displacement monitoring point are arranged in initial dam dam crest and fill dam dam crest;
1b), the setting position of the intermediate row surface displacement monitoring point between first row and end row is according to the stabilization of flood operating mode The slip circle front and rear edges location determination of calculating;
2), displacement monitoring basic point distributing position is:Displacement monitoring basic point is arranged in the solid and reliable position of both sides massif, point Position no less than 3.
The surface displacement monitoring point buried depth is 0.6m.
The displacement monitoring basic point buried depth is 1.6m.
Surface displacement monitoring point in the method for arranging of tailing dam surface displacement monitoring point, which is characterized in that its structure is:Packet External brick enclosure wall is included, rectangular cross section is equipped at brick enclosure wall bosom position and observes pier, is observed in rectangular cross section Clay is backfilled between pier and brick enclosure wall;The round steel of the pre-buried φ 20mm of rectangular cross section observation socle;Described is brick It is stamped cover board in enclosure wall top surface.
The round steel exposes rectangular cross section observation pier 30mm.
The rectangular cross section observation pier makes raw material and slag or volcano grey matter cement, rank is used to be more than or equal to 32.5 Grade;Stone uses grain size for the middle sand of 0.15-3mm using the natural pebble or hard rubble, sand of grading qualification, clay content Less than or equal to 3%;Sulphates content is less than or equal to 1% in mixing water.
The invention has the beneficial effect that:
1, the intermediate row position of monitoring point is determined according to the flood stable conditions result of calculation of maximum height of dam section, is compensated for The conventional method of intermediate row position is determined by experience array pitch, and there is scientific theory foundation.
2, observation pier, which makes, preferentially uses slag or volcano grey matter cement, it is therefore prevented that freeze thawing influences, and compensates for using fine coal The deficiency of ash concrete.
3, the monitoring point for displacement architecture basics are firm, cheap, easy for construction, through live operation test, may be implemented Accurate safety monitoring and displacement early warning.
Description of the drawings
Fig. 1:Tailing dam monitoring point for displacement floor plan.
Fig. 2:Dam stability analysis result figure.
Fig. 3:Monitoring point for displacement sectional structure chart.
Fig. 4:Monitoring point for displacement plan view.
Specific implementation mode
A kind of tailing dam surface displacement monitoring point method for arranging, step are:Monitoring point is divided into:Surface displacement monitoring point 1 With displacement monitoring basic point 2;
1, surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point 1, often arranges surface displacement monitoring Point 1 is arranged on same straight line;
1a, first row and end row's surface displacement monitoring point 1 are arranged in initial dam dam crest and fill dam dam crest;
The setting position of intermediate row surface displacement monitoring point 1 between 1b, first row and end row is according to the stabilization of flood operating mode The slip circle front and rear edges of calculating determine and (if preceding (rear) edge is located at dam crest, should merge with first (end) row monitoring point);
1c, with row surface displacement monitoring point spacing according to《Safety of Tailings Dam Specifications of Monitoring Technology》Regulation determine;
2,2 distributing position of displacement monitoring basic point is:Displacement monitoring basic point 2 is arranged in the solid and reliable position of both sides massif, Point is no less than 3.
1 buried depth of surface displacement monitoring point is 0.6m.
2 buried depth of displacement monitoring basic point is 1.6m.
Surface displacement monitoring point 1 in the method for arranging of tailing dam surface displacement monitoring point, structure are:Include external Brick enclosure wall 1-1, brick enclosure wall 1-1 height are 240mm.Rectangular cross section is equipped at brick enclosure wall 1-1 bosoms position to see Pier 1-2 is examined, the rectangular cross section observes pier 1-2 and uses C20 concrete, length of side 200mm.Make raw material using slag and Volcano grey matter cement, rank are more than or equal to 32.5 grades;Stone is adopted natural troubled times or hard rubble, sand using grading qualification The middle sand for being 0.15-3mm with grain size, clay content are less than or equal to 3%;Sulphates content is less than or equal to 1% in mixing water.In rectangle Section observes backfill clay 1-5 between pier 1-2 and brick enclosure wall 1-1;The rectangular cross section observation pier 1-2 pre-buried φ in top The round steel 1-3, the round steel 1-3 of 20mm exposes rectangular cross section observation pier 1-230mm.
Cover board 1-4 is stamped in the top surfaces brick enclosure wall 1-1, and cover board 1-4 is reinforced concrete cover plate, matches 6@of φ, 100 steel Muscle net.
2 structure of displacement monitoring basic point is identical as 1 structure of surface displacement monitoring point, and only buried depth is different.
The invention is to provide for simple, the effective tailing dam surface displacement monitoring point structure of one kind and arrangement side Method, adapts to the needs that Safety of Tailings Dam monitors, and guarantee has many advantages, such as firm, accurate, simple, reduction cost.
More than, the technical solution in the invention embodiment is clearly and completely described.Obviously, described Embodiment be only the invention a part of the embodiment, instead of all the embodiments.Based on the reality in the invention Example is applied, every other embodiment obtained by those of ordinary skill in the art without making creative efforts all belongs to In the range of the invention protection.

Claims (6)

1. a kind of tailing dam surface displacement monitoring point method for arranging, which is characterized in that its step is:Monitoring point is divided into:Surface position Move monitoring point (1) and displacement monitoring basic point (2);
1), surface displacement monitoring point distributing position is:3-4 is set and arranges surface displacement monitoring point (1), often arranges surface displacement monitoring point (1) it is arranged on same straight line;
1a), first row and end row surface displacement monitoring point (1) are arranged in initial dam dam crest and fill dam dam crest;
1b), the setting position of the intermediate row surface displacement monitoring point (1) between first row and end row is according to the stabilimeter of flood operating mode Calculate slip circle location determination;
2), displacement monitoring basic point (2) distributing position is:Displacement monitoring basic point (2) is arranged in the solid and reliable position of both sides massif, Point is no less than 3.
2. a kind of tailing dam surface displacement monitoring point according to claim 1 method for arranging, it is characterised in that:The table Face monitoring point for displacement (1) buried depth is 0.6m.
3. a kind of tailing dam surface displacement monitoring point according to claim 1 method for arranging, it is characterised in that:The position It is 1.6m to move monitoring basic point (2) buried depth.
4. the surface displacement monitoring point (1) in the method for arranging of tailing dam surface displacement monitoring point described in a kind of claim 1, It is characterized in that, its structure is:Include the brick enclosure wall (1-1) of outside, is set at brick enclosure wall (1-1) bosom position There is rectangular cross section to observe pier (1-2), the backfill clay (1-5) between rectangular cross section observation pier (1-2) and brick enclosure wall (1-1); The round steel (1-3) of the rectangular cross section observation pre-buried φ 20mm in the top pier (1-2);The top surface brick enclosure wall (1-1) lid There is cover board (1-4).
5. surface displacement monitoring point (1) according to claim 4, it is characterised in that:The round steel (1-3) exposes rectangle Section observes pier (1-2) 30mm.
6. surface displacement monitoring point (1) according to claim 4, it is characterised in that:The rectangular cross section observation pier (1- 2) making raw material uses slag or volcano grey matter cement, rank to be more than or equal to 32.5 grades;Stone uses the natural ovum of grading qualification Stone or hard rubble, sand use grain size for the middle sand of 0.15-3mm, and clay content is less than or equal to 3%;Sulfate contains in mixing water Amount is less than or equal to 1%.
CN201810455715.4A 2018-05-14 2018-05-14 A kind of tailing dam surface displacement monitoring point structure and method for arranging Pending CN108627130A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810455715.4A CN108627130A (en) 2018-05-14 2018-05-14 A kind of tailing dam surface displacement monitoring point structure and method for arranging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810455715.4A CN108627130A (en) 2018-05-14 2018-05-14 A kind of tailing dam surface displacement monitoring point structure and method for arranging

Publications (1)

Publication Number Publication Date
CN108627130A true CN108627130A (en) 2018-10-09

Family

ID=63693195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810455715.4A Pending CN108627130A (en) 2018-05-14 2018-05-14 A kind of tailing dam surface displacement monitoring point structure and method for arranging

Country Status (1)

Country Link
CN (1) CN108627130A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617798A (en) * 2019-10-16 2019-12-27 辽宁大学 Monitoring tube structure for tailing dam infiltration line and distribution thereof
CN111964621A (en) * 2020-08-14 2020-11-20 洛阳理工学院 Layout method of displacement monitoring points in tailing pond based on dangerous sliding arc

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632461A (en) * 2004-12-29 2005-06-29 西安华腾光电有限责任公司 Symmetrical closed laser arch dam deformation monitoring method
CN102590085A (en) * 2012-01-18 2012-07-18 清华大学 Method for identifying cross joint state during arch dam construction period
CN102878966A (en) * 2012-10-13 2013-01-16 云南新立有色金属有限公司 Method for monitoring movement of dam body of five-level tailings pond
CN203008434U (en) * 2012-06-06 2013-06-19 中国有色金属长沙勘察设计研究院有限公司 Protective device for mine tailing dam electronic equipment and electronic apparatus
CN104978843A (en) * 2015-06-25 2015-10-14 辽宁有色勘察研究院 Tailings reservoir saturation line on-line monitoring point layout and zigbee networking structure
CN105444804A (en) * 2015-06-25 2016-03-30 辽宁有色勘察研究院 Tailing pond online safety monitoring and comprehensive early-warning system
CN207147511U (en) * 2017-09-11 2018-03-27 中国有色金属长沙勘察设计研究院有限公司 A kind of Tailings Dam monitors point protection device on-line

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632461A (en) * 2004-12-29 2005-06-29 西安华腾光电有限责任公司 Symmetrical closed laser arch dam deformation monitoring method
CN102590085A (en) * 2012-01-18 2012-07-18 清华大学 Method for identifying cross joint state during arch dam construction period
CN203008434U (en) * 2012-06-06 2013-06-19 中国有色金属长沙勘察设计研究院有限公司 Protective device for mine tailing dam electronic equipment and electronic apparatus
CN102878966A (en) * 2012-10-13 2013-01-16 云南新立有色金属有限公司 Method for monitoring movement of dam body of five-level tailings pond
CN104978843A (en) * 2015-06-25 2015-10-14 辽宁有色勘察研究院 Tailings reservoir saturation line on-line monitoring point layout and zigbee networking structure
CN105444804A (en) * 2015-06-25 2016-03-30 辽宁有色勘察研究院 Tailing pond online safety monitoring and comprehensive early-warning system
CN207147511U (en) * 2017-09-11 2018-03-27 中国有色金属长沙勘察设计研究院有限公司 A kind of Tailings Dam monitors point protection device on-line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617798A (en) * 2019-10-16 2019-12-27 辽宁大学 Monitoring tube structure for tailing dam infiltration line and distribution thereof
CN111964621A (en) * 2020-08-14 2020-11-20 洛阳理工学院 Layout method of displacement monitoring points in tailing pond based on dangerous sliding arc

Similar Documents

Publication Publication Date Title
DE112016005692B4 (en) A method for designing support parameters of the transition support of the excavation joint in the fully mechanical mixed offset reduction
CN105926544A (en) Economical debris flow blocking dam structure and construction method thereof
CN108627130A (en) A kind of tailing dam surface displacement monitoring point structure and method for arranging
Teng et al. Surface subsidence characteristics of grout injection into overburden: case study of Yuandian No. 2 coalmine, China
CN108867378A (en) A kind of Techniques of Tunnel-Type Anchorage for Suspension Bridge and construction method
CN105332392B (en) A kind of method of surface mine hole bottom leakage preventing structure and Anti-seeping technology
CN207452824U (en) A kind of vertical type barricade in hydraulic engineering river
CN103410160A (en) Combined supporting method for bedding extra-high rock side slope
CN105971605B (en) A kind of underground mines exploration without waster method
Kuranchie et al. Load–settlement behaviour of a strip footing resting on iron ore tailings as a structural fill
CN209538128U (en) A kind of dam structure promoted for reservoir landscape
CN203284795U (en) Buttressed retaining wall with anchor board
CN207619863U (en) A kind of box culvert backfill structure
CN103866775A (en) Protection method of cold region dispersive soil side slope
CN203559398U (en) Simple water gate
CN207685789U (en) A kind of dam structure of dam
CN207537987U (en) The narrow toe board arrangement of the high CFRD in Narrow Valleys area
Day et al. Validation of Composite Geological Strength Index for healed rockmass structure in deep mine access and production tunnels
CN208762976U (en) The rock and spillway for taking into account toe board and guide-wall lead wall connection structure
CN207079600U (en) A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope
CN209066527U (en) A kind of clear slot leveling unit of foundation pit
CN203096686U (en) Novel composite structure combining long piled wharf and shore-connecting structure
CN208884549U (en) A kind of supporting construction of large size talus slide
CN207582476U (en) A kind of civil engineering slopes ruggedized construction
CN206205038U (en) A kind of good bucket tooth set played a protective role to bucket tooth of stationarity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181009

WD01 Invention patent application deemed withdrawn after publication