CN108625412A - A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method - Google Patents

A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method Download PDF

Info

Publication number
CN108625412A
CN108625412A CN201810625605.8A CN201810625605A CN108625412A CN 108625412 A CN108625412 A CN 108625412A CN 201810625605 A CN201810625605 A CN 201810625605A CN 108625412 A CN108625412 A CN 108625412A
Authority
CN
China
Prior art keywords
pile
long
strain gauge
enclosure structure
deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810625605.8A
Other languages
Chinese (zh)
Inventor
徐长节
朱怀龙
钟庆华
张兴周
刘东海
郦中华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Jiaotong University
Original Assignee
East China Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Jiaotong University filed Critical East China Jiaotong University
Priority to CN201810625605.8A priority Critical patent/CN108625412A/en
Publication of CN108625412A publication Critical patent/CN108625412A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method, include the following steps:(1)Determine the position of experiment pile cutoff;(2)Determine the combination of test pile;(3)Determine the length of test pile;(4)Pile body deformation and deformation measurement;(5)Data acquire.Solve the problems, such as long-short pile combined enclosure structure stress and deformation on-the-spot test well.The test device that the present invention uses includes test pile, steel reinforcement cage, inclinometer pipe, inclinometer, embedded type concrete strain gauge and data collecting instrument.Long-short pile combined enclosure structure stress of the present invention and deformation on-the-spot test method provide effective research technique for the stressing conditions and stress transfer mechanism for studying long-short pile combined enclosure structure pile.Test method of the present invention, can accurately measure internal force and the displacement of long-short pile combined enclosure structure, and effective information is provided for long-short pile combined enclosure structure design, and design method is simple and practical, have good application and popularization value.

Description

A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method
Technical field
The present invention relates to a kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method, the tests of dependent territory wood engineering Method field.
Background technology
The rapid development utilized with urban underground space, the requirement to related foundation pit enclosure technology also correspondingly improve. Foundation pit enclosure structure is usually provisional structure will cause the waste of human and material resources if excessively pursuing safety.
Currently, the method for the foundation pit enclosure design isometric stake of generally use, but in the moment of flexure of the following pile body in foundation pit bottom surface with depth Degree increases and is gradually reduced, and the flexural loading capacity of pile body lower part does not obtain adequately when being laid out pile by the form of isometric stake It plays, is also unable to fully the principle using soil condition and pile soil common action, causes increase and the project cost of duration Waste.So it is increasingly common in engineering using long-short pile combined enclosure structure, but at present still without offer in specification The method of long-short pile combined enclosure structure design, and mostly using model test, but model test asking due to the likelihood ratio Topic can not accurately reflect practical long-short pile combined enclosure structure stress and deformation.Therefore, a kind of rational length of simplicity is found Stake combined enclosure structure stress and deformation on-the-spot test method, be one has the technical issues of engineering application value very much.
Invention content
The object of the present invention is to which in view of the above existing problems in the prior art, the present invention provides a kind of long-short pile groups to surround Protection structure stress and deformation on-the-spot test method.
To achieve the goals above, the present invention provides the following technical solutions:A kind of long-short pile combined enclosure structure stress and On-the-spot test method is deformed, steps are as follows:
(1) position for determining experiment pile cutoff determines examination according to the physical location and excavating condition of live foundation pit enclosure structure Test the position of stake;The foundation pit enclosure structure is cast-in-situ bored pile;
(2) determine that the combination of test pile, the combination of test pile are:One long stake, one stub, a long stake Two stubs, three stubs of a long stake, two long stakes, two stubs;
(3) length for determining test pile is lengthened or shortened on the basis of isometric stake is long originally;
(4) pile body stress and deformation measurement;
(5) data acquire.
The pile body stress and deformation measurement include:
(1) concrete embedded type strain gauge spacing and number are designed:According to the long determining concrete embedded type strain gauge of stake Spacing and number;
(2) embedded type concrete strain gauge is bound:Embedded type concrete strain gauge is bound according to the spacing of design in steel On muscle cage, the position of embedded type concrete strain gauge binding needs on same root reinforcing bar;Strain gauge conducting wire end position needs to use Electric adhesive tape prevents terminal stud to be contaminated and cannot be with the good connection of data collecting instrument as safeguard measure;Embedded type concrete Strain gauge conducting wire need to continue along steel reinforcement cage toward steel reinforcement cage top, and exceed steel reinforcement cage 2-3m;
(3) inclinometer pipe is bound:By the effective thin wire binding of deviational survey on steel reinforcement cage, the position of binding is opposite in strain gauge On position;Inclinometer pipe both ends need to do Seal treatment, prevent inclinometer pipe from being blocked by sundries such as silts;Inclinometer pipe top need to be shorter than steel Muscle cage top end 40-50cm, inclinometer pipe top is destroyed when preventing pile crown from abolishing;
(4) steel reinforcement cage is hung:The steel reinforcement cage that inclinometer pipe and strain gauge are tied up will have been bound to hang onto in the stake holes of pore-forming;
(5) pouring underwater concrete:The pouring underwater concrete in the stake holes for having hung steel reinforcement cage;
(6) pile crown is abolished:The pile crown of test pile is abolished into 0.8-1m, exposes the conducting wire of inclinometer pipe and strain gauge;
(7) inclinometer pipe lengthens:Each inclinometer pipe of test pile lengthens 1.5m;
(8) Guan Liang is constructed:After pile crown is abolished and lengthened with inclinometer pipe, Guan Liang construction is carried out.
The data collection steps are:
(1) embedded type concrete strain gauge conducting wire end is connected on data collecting instrument, record foundation pit often excavates one layer of soil The reading of layer, test are complete until excavation of foundation pit;
(2) inclinometer is put into inclinometer pipe, a data is recorded every 0.5m.
The method includes test pile, steel reinforcement cage, inclinometer pipe, inclinometer, embedded type concrete strain using test device Meter and data collecting instrument.The embedded type concrete strain gauge is bound by the requirement spacing of design on steel reinforcement cage;The deviational survey Effective thin wire binding is on steel reinforcement cage, and the position of binding is on the opposite position of embedded type concrete strain gauge;Binding is good to survey The steel reinforcement cage of inclined tube and embedded type concrete strain gauge is hung onto in the stake holes of pore-forming;Embedded type concrete strain gauge end is logical Conducting wire is crossed to connect with data collecting instrument.
The inclinometer is ZX-806B type inclinometers;The embedded type concrete strain is calculated as BX120-5AA.
The invention has the advantages that using provided by the invention kind of long-short pile combined enclosure structure stress and deformation scene Test method can accurately measure internal force and the displacement of long-short pile combined enclosure structure, be long-short pile combined enclosure structure design Effective information is provided, design method is simple and practical, has good application and popularization value.
Description of the drawings
Fig. 1 is test method flow chart of the present invention;
Fig. 2 is certain building site foundation pit enclosure plan view;
Fig. 3 is test pile strain gauge and inclinometer pipe layout drawing;
Fig. 4 is the vertical view of Fig. 3;
Fig. 5 is the a-quadrant enlarged drawing of Fig. 4;
Fig. 6 is experiment pile cutoff floor map;
Fig. 7 is A1 sections of test pile layout drawings in Fig. 2;
Fig. 8 is A2 sections of test pile layout drawings in Fig. 2;
Fig. 9 is A3 sections of test pile layout drawings in Fig. 2;
Figure 10 is ZX-806B type inclinometer movable probe schematic diagrames.
In figure:1 is test pile, and 2 be steel reinforcement cage, and 3 be Guan Liang, and 4 be inclinometer pipe, and 5 be embedded type concrete strain gauge, and 6 are Electric wire, 7 be inclinometer pipe groove, and 8 be cement mixing pile, and 9 be foundation pit, and 10 be bottom of foundation ditch, and 11 be high guide wheel, and 12 be low guide wheel, 13 be cable.
Specific implementation mode
In conjunction with the drawings and specific embodiments to a kind of long-short pile combined enclosure structure stress proposed by the present invention and deformation On-the-spot test method further illustrates that the embodiment is merely to illustrate the present invention and not limitation of the present invention.
Nanchang basement foundation ditch flat shape is rectangle, foundation pit long 122m, wide 58m, and excavation of foundation pit depth is 11.9m, pattern foundation pit supporting structure floor map are as shown in Figure 2.The present embodiment engineering makees building enclosure using cast-in-situ bored pile, and pile body is straight Diameter 1m, centre-to-centre spacing 0.95m, a length of 19.80m of stake;Setting twice reinforced concrete support is set up in below ground 1.5m respectively And at the positions 7.2m.
A kind of long-short pile combined enclosure structure stress of the present embodiment and deformation on-the-spot test method, as shown in Figure 1, include with Lower step:
(1) position that experiment pile cutoff is determined according to the practical pattern foundation pit supporting structure situation in scene, as shown in Fig. 2, choosing 6 test piles Section is divided into the areas A experiment pile cutoff and the areas B experiment pile cutoff.
(2) combination of test pile is determined:The areas A experiment pile cutoff is divided into A1 (one is long and the other is short), A2 (unexpected misfortune), A3 (length three is short);The areas B experiment pile cutoff is divided into B1 (one is long and the other is short), B2 (unexpected misfortune), B3 (length three is short).Fig. 7, Fig. 8, Fig. 9 For be respectively the areas A test pile combination sectional view
(3) length of test pile is determined:The areas A test pile segment length the stake a length of 19.80m of stake, a length of 17.80m of stub stake;The areas B Test pile segment length's stake a length of 19.80m of stake, a length of 16.80m of stub stake.
(4) Internal forces and deformation measurement:
A, embedded type concrete strain gauge spacing is designed:As shown in Figures 2 and 3, the areas A test pile segment length stake is tied up every 1.5m An embedded type concrete strain gauge 5 is pricked, 13 are installed per root long stake;Stub binds an embedded type concrete every 1.5m and answers Become meter 5, each stub installs 10;The areas B test pile segment length stake binds an embedded type concrete strain gauge 5 every 1.5m, often Root long stake installs 13;Stub binds an embedded type concrete strain gauge 5 every 1.5m, and each stub installs 9;Strain gauge Conducting wire need to continue along steel reinforcement cage toward steel reinforcement cage top, and exceed steel reinforcement cage 2-3m;The specification that embedded type concrete strain gauge 5 is selected Strain gauge conducting wire is connected data collecting instrument and reset by model BX120-5AA.
B, inclinometer pipe is bound:As shown in figure 3, the length of inclinometer pipe is 2m, by connector by 4 spreading of inclinometer pipe, inclinometer pipe Both ends need to make Seal treatment, prevent the sundries such as silt from falling into pipe internal congestion pipeline;The effective thin wire of the deviational survey connected is tied up It pricks on the opposite reinforcing bar of strain gauge;As shown in Figure 4, Figure 5 and Figure 6, the groove 7 of inclinometer pipe should be made to arriving base when inclinometer pipe is bound On the inside of crater wall;Inclinometer pipe top need to be shorter than steel reinforcement cage top 40-50cm, prevent inclinometer pipe when broken pile head from being destroyed.
C, steel reinforcement cage is hung:The steel reinforcement cage for having bound inclinometer pipe 4 and embedded type concrete strain gauge 5 is hung onto into pore-forming Stake holes in and pouring underwater concrete;
D, pile crown is abolished:The pile crown of test pile is abolished into 0.8m, exposes the conducting wire of inclinometer pipe and strain gauge;
E, inclinometer pipe lengthens:Each inclinometer pipe of test pile lengthens 1.5m;
F, Guan Liang is constructed:As shown in figure 3, after pile crown is abolished and lengthened with inclinometer pipe, carries out Guan Liang 3 and construct and expose deviational survey Pipe 4 and embedded type concrete strain gauge conducting wire 6.
(5) data acquire
A, 6 end of concrete embedded type strain gauge conducting wire is connected on data collecting instrument, foundation pit excavates in three times, excavates deep Degree is respectively 3.2m, 4m, 4.7m;Record foundation pit often excavates the reading of one layer of soil layer, and test is complete until excavation of foundation pit;
B, as shown in Figure 10, the movable probe of inclinometer is put into inclinometer pipe, the model ZX-806B types of inclinometer are surveyed The high guide wheel 11 of oblique instrument, movable probe is directed at inclinometer pipe at the groove 7 on the inside of foundation pit walls, stablizes decentralization until from inclinometer pipe Until the 20cm of bottom;Zeros data, it is primary toward pull-up every 0.5m after stablizing, after stablizing, record data.
Measurement data acquisition is until excavation of foundation pit is complete.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and Within principle, any, equivalent replacement, improvement for being done etc. are all included in the scope of protection of the present invention.

Claims (5)

1. a kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method, which is characterized in that the method step is such as Under:
(1)Determine that the position of experiment pile cutoff determines test pile according to the physical location and excavating condition of live foundation pit enclosure structure Position;The foundation pit enclosure structure is cast-in-situ bored pile;
(2)Determine the combination of test pile, the combination of test pile is one of following manner:One long stake, one stub, One long stake, two stubs, three stubs of a long stake, two long stakes, two stubs;
(3)The length for determining test pile is lengthened or shortened on the basis of isometric stake is long originally;
(4)Pile body stress and deformation measurement;
(5)Data acquire.
2. a kind of long-short pile combined enclosure structure stress according to claim 1 and deformation on-the-spot test method, feature It is, the pile body stress and deformation measurement include:
(1)Design embedded type concrete strain gauge spacing:According to the spacing and number of the long determining embedded type concrete strain gauge of stake;
(2)Bind embedded type concrete strain gauge:Embedded type concrete strain gauge is bound according to the spacing of design in steel reinforcement cage On, the position of concrete embedded type strain gauge binding needs on same root reinforcing bar;Strain gauge conducting wire end position needs electricity consumption glue Band prevents terminal stud to be contaminated and cannot be with the good connection of data collecting instrument as safeguard measure;Strain gauge conducting wire need to be along steel Muscle cage continues toward steel reinforcement cage top, and exceeds steel reinforcement cage 2-3m;
(3)Bind inclinometer pipe:By deviational survey effective thin wire binding on steel reinforcement cage, the position of the binding position opposite in strain gauge On;Inclinometer pipe both ends need to do Seal treatment, prevent inclinometer pipe from being blocked by sundries;Inclinometer pipe top need to be shorter than steel reinforcement cage top 40-50cm;
(4)Hang steel reinforcement cage:The steel reinforcement cage that inclinometer pipe and strain gauge are tied up will have been bound to hang onto in the stake holes of pore-forming and be perfused Underwater concrete;
(5)Pile crown is abolished:The pile crown of test pile is abolished into 0.8-1m, exposes the conducting wire of inclinometer pipe and strain gauge;
(6)Inclinometer pipe lengthens:Each inclinometer pipe of test pile lengthens 1.5m;
(7)Guan Liang is constructed:After pile crown is abolished and lengthened with inclinometer pipe, Guan Liang construction is carried out.
3. a kind of long-short pile combined enclosure structure stress according to claim 1 and deformation on-the-spot test method, feature It is, the data collection steps are:
(1)Embedded type concrete strain gauge conducting wire end is connected on data collecting instrument, record foundation pit often excavates one layer of soil layer Reading, test are complete until excavation of foundation pit;
(2)Inclinometer is put into inclinometer pipe, a data are recorded every 0.5m.
4. a kind of long-short pile combined enclosure structure stress according to claim 1 and deformation on-the-spot test method, feature Be, the method using test device include test pile, steel reinforcement cage, inclinometer pipe, inclinometer, embedded type concrete strain gauge and Data collecting instrument;The embedded type concrete strain gauge is bound by the requirement spacing of design on steel reinforcement cage;The deviational survey is effective Thin wire is bound on steel reinforcement cage, and the position of binding is on the opposite position of embedded type concrete strain gauge;Inclinometer pipe is bound It is hung onto in the stake holes of pore-forming with the steel reinforcement cage of embedded type concrete strain gauge;Embedded type concrete strain gauge end is by leading Line is connect with data collecting instrument.
5. a kind of long-short pile combined enclosure structure stress according to claim 4 and deformation on-the-spot test method, feature It is, the inclinometer is ZX-806B type inclinometers;The embedded type concrete strain is calculated as BX120-5AA.
CN201810625605.8A 2018-06-18 2018-06-18 A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method Pending CN108625412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810625605.8A CN108625412A (en) 2018-06-18 2018-06-18 A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810625605.8A CN108625412A (en) 2018-06-18 2018-06-18 A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method

Publications (1)

Publication Number Publication Date
CN108625412A true CN108625412A (en) 2018-10-09

Family

ID=63691786

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810625605.8A Pending CN108625412A (en) 2018-06-18 2018-06-18 A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method

Country Status (1)

Country Link
CN (1) CN108625412A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112197806A (en) * 2020-09-25 2021-01-08 中煤科工开采研究院有限公司 Method for installing equipment for monitoring movement deformation, hydrology and stress of coal mining subsidence area

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011415A (en) * 2010-10-26 2011-04-13 珠海市建设工程质量监督检测站 Method and device for detecting strain/stress of pile body by prestress pipe file field static load test
CN207062955U (en) * 2017-04-20 2018-03-02 中南勘察设计院(湖北)有限责任公司 The foundation pit supporting construction that a kind of thick long stake is combined with thin stub
CN108035388A (en) * 2018-01-17 2018-05-15 杭州鲁尔物联科技有限公司 Friction pile condition monitoring system and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011415A (en) * 2010-10-26 2011-04-13 珠海市建设工程质量监督检测站 Method and device for detecting strain/stress of pile body by prestress pipe file field static load test
CN207062955U (en) * 2017-04-20 2018-03-02 中南勘察设计院(湖北)有限责任公司 The foundation pit supporting construction that a kind of thick long stake is combined with thin stub
CN108035388A (en) * 2018-01-17 2018-05-15 杭州鲁尔物联科技有限公司 Friction pile condition monitoring system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
石钰锋等: ""紧邻铁路偏压基坑围护结构变形与内力测试分析"", 《岩石力学与工程学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112197806A (en) * 2020-09-25 2021-01-08 中煤科工开采研究院有限公司 Method for installing equipment for monitoring movement deformation, hydrology and stress of coal mining subsidence area
CN112197806B (en) * 2020-09-25 2021-08-06 中煤科工开采研究院有限公司 Method for installing equipment for monitoring movement deformation, hydrology and stress of coal mining subsidence area

Similar Documents

Publication Publication Date Title
Shen et al. Field measurements of an earth support system
CN111851597B (en) Penetration protection structure of pipe jacking close-distance downward-penetrating pipe gallery and construction method
CN203701157U (en) Inner support clamp of simple geotechnical centrifuge for simulating pit excavation experiment
CN106400768B (en) Collapsible loess tunnel submerging test method
Zhang et al. Deformation monitoring and performance analysis on the shield tunnel influenced by adjacent deep excavations
CN101343869A (en) Underground continuous wall construction method of city-across pipeline
CN102620715A (en) Observation method of foundation settlement based on liquid level difference
CN202562470U (en) Buried type foundation settlement observing device
CN108625412A (en) A kind of long-short pile combined enclosure structure stress and deformation on-the-spot test method
Öser et al. Geotechnical assessment and rehabilitation of retaining structures collapsed partially due to environmental effects
Tei et al. A study of soil nailing in sand
KR101010333B1 (en) Level surveying using a assembly level point device
KR101710499B1 (en) Automatic apparatus for sinking measuring of soft ground
CN207159983U (en) A kind of soft clay area building lot structure of cement mixing method combination Pulling-Resistant Anchor Rod
CN108843265A (en) A kind of clinometer probe fishing device
CN101381991A (en) Geothermal heat pump buried pipe in pile and construction method
CN109029338B (en) Embedded concrete strain measurement device and construction method thereof
Zhu et al. New improvement of the combined optical fiber transducer for landslide monitoring
Deepa et al. Centrifuge model tests on soil-nailed slopes subjected to seepage
CN110055957A (en) A kind of strong development ultra-fine hole pile construction method in karst region
CN206554112U (en) Detachable cantilever retaining wall
CN106948388A (en) A kind of magnet ring type test excavation of foundation pit causes the device and method that ground swells
CN201250401Y (en) Embedded pipe in a pile of a geothermal heat pump
McRostie et al. The performance of tied-back sheet piling in clay
Viswanadham et al. Evaluation of performance of soil-nailed slopes subjected to seepage in a centrifuge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181009