CN108624339A - A kind of winter coke dry quenching furnace annual overhaul heat preserving method - Google Patents

A kind of winter coke dry quenching furnace annual overhaul heat preserving method Download PDF

Info

Publication number
CN108624339A
CN108624339A CN201810446672.3A CN201810446672A CN108624339A CN 108624339 A CN108624339 A CN 108624339A CN 201810446672 A CN201810446672 A CN 201810446672A CN 108624339 A CN108624339 A CN 108624339A
Authority
CN
China
Prior art keywords
boiler
water
valve
dry quenching
coke dry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810446672.3A
Other languages
Chinese (zh)
Other versions
CN108624339B (en
Inventor
魏春满
蒲永新
刘革
李雪冬
徐吉国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Angang Steel Co Ltd
Original Assignee
Angang Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Angang Steel Co Ltd filed Critical Angang Steel Co Ltd
Priority to CN201810446672.3A priority Critical patent/CN108624339B/en
Publication of CN108624339A publication Critical patent/CN108624339A/en
Application granted granted Critical
Publication of CN108624339B publication Critical patent/CN108624339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C10PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
    • C10BDESTRUCTIVE DISTILLATION OF CARBONACEOUS MATERIALS FOR PRODUCTION OF GAS, COKE, TAR, OR SIMILAR MATERIALS
    • C10B39/00Cooling or quenching coke
    • C10B39/02Dry cooling outside the oven

Abstract

The present invention relates to a kind of winter coke dry quenching furnace annual overhaul heat preserving methods, using boiler heat, provide heat source to coke dry quenching furnace, circulating fan, final dusting nitrogen valve, boiler main steam diffusion valve, main steam pressure force regulating valve, main stop valve are closed in coke dry quenching furnace blowing out;Boiler internal pipeline is protected with heat-barrier material;Water on oxygen-eliminating device, interruption are passed through deoxygenation low-pressure steam, 80 DEG C~90 DEG C of control oxygen-eliminating device water temperature;Hot water is passed through boiler in oxygen-eliminating device, and boiler vapor liquid level reaches water in 0mm stoppings;It is spaced starting trouble forced circulation pump;It opens the unrestrained water valve progress boiler of the unrestrained water valve of boiler water wall, the unrestrained water valve of light pipe evaporator, fin evaporator and discharges water in interval;Hot water is added by waterdrainage amount, 40 DEG C~45 DEG C of boiler internal temperature is kept, is taken boiler heat in coke dry quenching furnace to by disposable dust remover, it is 20 DEG C~30 DEG C to make coke dry quenching furnace in-furnace temperature always.Boiler heat source is stablized, convenient for construction.Avoid the security risk of former open fire heat preservation.

Description

A kind of winter coke dry quenching furnace annual overhaul heat preserving method
Technical field
The present invention relates to coke dry quenching furnaces to repair field, more particularly to a kind of winter coke dry quenching furnace annual overhaul heat preserving method.
Background technology
Dry coke quenching annual overhaul is possible to catch up in winter, and when carrying out the work of dry coke quenching annual overhaul in winter, heat preservation is an important work Make, temperature is too low to be unfavorable for constructing, and is had a certain impact simultaneously for dry coke quenching furnace body laying fireproof bricks etc., uses stove in the past The modes such as son are kept the temperature, but effect is limited, and have larger danger.
Invention content
Technical problem to be solved by the invention is to provide a kind of winter coke dry quenching furnace annual overhaul heat preserving methods, and open fire is avoided to protect Temperature ensures safe construction.
To achieve the above object, the present invention is realized using following technical scheme:
A kind of winter coke dry quenching furnace annual overhaul heat preserving method provides heat source, including following step using boiler heat to coke dry quenching furnace Suddenly:
1) it by coke dry quenching furnace blowing out, closes circulating fan, close circulating fan inlet baffle, final dusting nitrogen valve is closed It closes, boiler main steam diffusion valve is closed, and main steam pressure force regulating valve, main stop valve are closed;
2) boiler internal pipeline is protected with heat-barrier material;
3) water on oxygen-eliminating device, interruption are passed through deoxygenation low-pressure steam, 80 DEG C~90 DEG C of control oxygen-eliminating device water temperature;
4) hot water is passed through boiler in oxygen-eliminating device, and boiler vapor liquid level reaches water in 0mm stoppings;
5) it is spaced and starts within 4~5 hours a boiler forced-circulating pump, it is 15~20 minutes to start the time every time;
6) the unrestrained water valve of 4~5 hours opening boiler water walls, the unrestrained water valve of light pipe evaporator, fin evaporator is spaced to dredge Discharging valve is primary, 10~15 minutes every time, carries out boiler and discharges water, boiler vapor liquid level stops putting after dropping to -200~-260mm Water;
7) after discharging water, boiler adds hot water by the waterdrainage amount of step 6), keeps 40 DEG C~45 DEG C of boiler internal temperature, passes through Disposable dust remover takes boiler heat in coke dry quenching furnace to, and it is 20 DEG C~30 DEG C to make coke dry quenching furnace in-furnace temperature always.
Compared with prior art, the beneficial effects of the invention are as follows:
1, avoid being kept the temperature using open fire, avoid catch fire, the security risks such as gas poisoning.
2, boiler heat source is stablized, and heat is higher, convenient for construction.
Description of the drawings
Fig. 1 is coke dry quenching furnace process schematic representation.
Specific implementation mode
The specific implementation mode of the present invention is further illustrated below in conjunction with the accompanying drawings:
A kind of winter coke dry quenching furnace annual overhaul heat preserving method provides heat source, including following step using boiler heat to coke dry quenching furnace Suddenly:
1) it by coke dry quenching furnace blowing out, closes circulating fan, close circulating fan inlet baffle, final dusting nitrogen valve is closed It closes, boiler main steam diffusion valve is closed, and main steam pressure force regulating valve, main stop valve are closed;
2) boiler internal pipeline is protected with heat-barrier material;
3) water on oxygen-eliminating device, interruption are passed through deoxygenation low-pressure steam, 80 DEG C~90 DEG C of control oxygen-eliminating device water temperature;
4) hot water is passed through boiler in oxygen-eliminating device, and boiler vapor liquid level reaches water in 0mm stoppings;
5) it is spaced and starts within 4~5 hours a boiler forced-circulating pump, it is 15~20 minutes to start the time every time;
6) the unrestrained water valve of 4~5 hours opening boiler water walls, the unrestrained water valve of light pipe evaporator, fin evaporator is spaced to dredge Discharging valve is primary, 10~15 minutes every time, carries out boiler and discharges water, boiler vapor liquid level stops putting after dropping to -200~-260mm Water;
7) after discharging water, boiler adds hot water by the waterdrainage amount of step 6), keeps 40 DEG C~45 DEG C of boiler internal temperature, passes through Disposable dust remover takes boiler heat in coke dry quenching furnace to, and it is 20 DEG C~30 DEG C to make coke dry quenching furnace in-furnace temperature always.
Embodiment
A kind of winter coke dry quenching furnace annual overhaul heat preserving method provides heat source, including following step using boiler heat to coke dry quenching furnace Suddenly:
1) it by coke dry quenching furnace blowing out, closes circulating fan, close circulating fan inlet baffle, by secondary filter nitrogen charging point valve Door is closed, and boiler main steam diffuse channel diffusion valve is closed, and main steam line pressure-regulating valve, main stop valve are closed;
2) boiler internal pipeline is protected with heat insulation foam, personnel is avoided to be in direct contact generator tube scald;
3) by deaerated feedwater pump startup, to water on oxygen-eliminating device, oxygen-eliminating device steam-heated pipe line valve opening, by low-pressure steam It is passed through oxygen-eliminating device, stops low-pressure steam after oxygen-eliminating device water temperature is increased to 90 DEG C and is passed through;When oxygen-eliminating device water temperature is less than 80 DEG C, weight It is new to open oxygen-eliminating device steam-heated pipe line valve, it is passed through low-pressure steam, is operated repeatedly, 80 DEG C~90 DEG C of control oxygen-eliminating device water temperature;
4) by boiler feedwater pump startup, for the hot water of oxygen-eliminating device to boiler water filling, boiler vapor liquid level closes pot after reaching 0mm Stove feed pump;
5) it is spaced and starts within 5 hours a boiler forced-circulating pump, it is 20 minutes to start the time every time;
6) it is spaced and opens within 4 hours the unrestrained water valve of boiler water wall, the unrestrained water valve of light pipe evaporator, the unrestrained water of fin evaporator Valve is primary, 12~15 minutes every time, carries out boiler and discharges water, boiler vapor liquid level stops discharging water after dropping to -220mm;
7) after discharging water, boiler adds hot water by the waterdrainage amount of step 6), keeps 40 DEG C~45 DEG C of boiler internal temperature, passes through Disposable dust remover takes boiler heat in coke dry quenching furnace to, and it is 20 DEG C~30 DEG C to make coke dry quenching furnace in-furnace temperature always.
Described above is only the basic principle of the present invention, is not imposed any restrictions to the present invention, every right according to the present invention It carries out equivalent variations and modification, within the scope of the art of this patent protection scheme.

Claims (1)

1. a kind of winter coke dry quenching furnace annual overhaul heat preserving method, which is characterized in that utilize boiler heat, heat source, packet are provided to coke dry quenching furnace Include following steps:
1) it by coke dry quenching furnace blowing out, closes circulating fan, close circulating fan inlet baffle, final dusting nitrogen valve is closed, Boiler main steam diffusion valve is closed, and main steam pressure force regulating valve, main stop valve are closed;
2) boiler internal pipeline is protected with heat-barrier material;
3) water on oxygen-eliminating device, interruption are passed through deoxygenation low-pressure steam, 80 DEG C~90 DEG C of control oxygen-eliminating device water temperature;
4) hot water is passed through boiler in oxygen-eliminating device, and boiler vapor liquid level reaches water in 0mm stoppings;
5) it is spaced and starts within 4~5 hours a boiler forced-circulating pump, it is 15~20 minutes to start the time every time;
6) it is spaced and opens within 4~5 hours the unrestrained water valve of boiler water wall, the unrestrained water valve of light pipe evaporator, the unrestrained water of fin evaporator Valve is primary, 10~15 minutes every time, carries out boiler and discharges water, boiler vapor liquid level stops discharging water after dropping to -200~-260mm;
7) after discharging water, boiler adds hot water by the waterdrainage amount of step 6), 40 DEG C~45 DEG C of boiler internal temperature is kept, by primary Deduster takes boiler heat in coke dry quenching furnace to, and it is 20 DEG C~30 DEG C to make coke dry quenching furnace in-furnace temperature always.
CN201810446672.3A 2018-05-11 2018-05-11 Winter dry quenching furnace annual repair heat preservation method Active CN108624339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810446672.3A CN108624339B (en) 2018-05-11 2018-05-11 Winter dry quenching furnace annual repair heat preservation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810446672.3A CN108624339B (en) 2018-05-11 2018-05-11 Winter dry quenching furnace annual repair heat preservation method

Publications (2)

Publication Number Publication Date
CN108624339A true CN108624339A (en) 2018-10-09
CN108624339B CN108624339B (en) 2020-09-29

Family

ID=63692787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810446672.3A Active CN108624339B (en) 2018-05-11 2018-05-11 Winter dry quenching furnace annual repair heat preservation method

Country Status (1)

Country Link
CN (1) CN108624339B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111706844A (en) * 2020-05-12 2020-09-25 杨思国 Civil high-efficiency heat accumulating type combustion boiler

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001192662A (en) * 2000-01-07 2001-07-17 Nippon Steel Corp Coke dry quenching facility
CN105509495A (en) * 2016-01-24 2016-04-20 中能世华(北京)节能科技有限公司 Energy-saving waste heat power generation system
CN106867549A (en) * 2017-02-24 2017-06-20 中冶焦耐(大连)工程技术有限公司 A kind of coke dry quenching boiler do not stop production realize maintenance method
CN106967448A (en) * 2017-04-07 2017-07-21 安阳钢铁股份有限公司 A kind of furnace drying method after the resistance to material large area replacing of dry quenching system
CN107366895A (en) * 2016-05-12 2017-11-21 鞍钢股份有限公司 A kind of method of quick-replaceable coke dry quenching boiler drum safety valve
CN207262396U (en) * 2017-09-01 2018-04-20 西安华江环保科技股份有限公司 A kind of dry coke quenching superpressure boiler therrmodynamic system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001192662A (en) * 2000-01-07 2001-07-17 Nippon Steel Corp Coke dry quenching facility
CN105509495A (en) * 2016-01-24 2016-04-20 中能世华(北京)节能科技有限公司 Energy-saving waste heat power generation system
CN107366895A (en) * 2016-05-12 2017-11-21 鞍钢股份有限公司 A kind of method of quick-replaceable coke dry quenching boiler drum safety valve
CN106867549A (en) * 2017-02-24 2017-06-20 中冶焦耐(大连)工程技术有限公司 A kind of coke dry quenching boiler do not stop production realize maintenance method
CN106967448A (en) * 2017-04-07 2017-07-21 安阳钢铁股份有限公司 A kind of furnace drying method after the resistance to material large area replacing of dry quenching system
CN207262396U (en) * 2017-09-01 2018-04-20 西安华江环保科技股份有限公司 A kind of dry coke quenching superpressure boiler therrmodynamic system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
曹永方: "《干熄焦装置冬季烘炉管理存在的问题及对策》", 《硅谷》 *
王子毅郎: "《浅谈冬季140t/h干熄焦炉年修注意事项》", 《新疆钢铁》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111706844A (en) * 2020-05-12 2020-09-25 杨思国 Civil high-efficiency heat accumulating type combustion boiler
CN111706844B (en) * 2020-05-12 2022-09-02 佛山市道得金机电设备有限公司 Civil high-efficiency heat accumulating type combustion boiler

Also Published As

Publication number Publication date
CN108624339B (en) 2020-09-29

Similar Documents

Publication Publication Date Title
US10386092B2 (en) Water heater
RU153204U1 (en) HEATING BOILER
CN108709413B (en) Method for dry quenching coke warm air drying oven by adopting flue gas oven
CN108624339A (en) A kind of winter coke dry quenching furnace annual overhaul heat preserving method
RU121042U1 (en) WATER-SOLID FUEL BOILER
CN101440427A (en) Steel pipe normalizing method
RU158389U1 (en) WATER-SOLID FUEL BOILER
KR101094472B1 (en) A firewood boiler
CN103127532A (en) Normal-pressure flash sterilizing room
CN108278854A (en) A kind of diesel oil furnace drying method
CN106182282B (en) A kind of timber heat modification processing method
CN204593835U (en) Vertical and horizontal oil-burning gas-fired boiler
CN210740425U (en) Yellow phosphorus tail gas torch heat energy recoverer
CN208282397U (en) A kind of device producing boiled water or steam
KR101306618B1 (en) Heating, cooking and electricity generation system equipped with charcoal kiln
RU151606U1 (en) GAS AIR HEATER
CN105927956A (en) Boiler
JP4848499B2 (en) Tandem wood processing equipment
CN206092091U (en) Wet saturated steam is used for device of sintering cogeneration
CN204693810U (en) The quick feedway of a kind of dustless hot blast
CN106855352A (en) A kind of furnace drying method of chimney
RU148080U1 (en) WATER BOILER
CN207514970U (en) A kind of stir-fry furnace structure
CN205578751U (en) Fire prevention valve
CN106285810B (en) The apparatus and method that a kind of wet saturated steam is used for sintering waste heat generating

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant