CN108613600A CN201810505041.4A CN201810505041A CN108613600A CN 108613600 A CN108613600 A CN 108613600A CN 201810505041 A CN201810505041 A CN 201810505041A CN 108613600 A CN108613600 A CN 108613600A
Authority
CN
China
Prior art keywords
pipes
concrete
outer layer
layer
emulsion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810505041.4A
Other languages
Chinese (zh)
Other versions
CN108613600B (en
Inventor
陈德志
李本伟
胡浩川
罗鹏
周应军
何国敏
甄梦阳
安玉东
陈晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhonggang Wuhan Safety and Environmental Protection Research Institute Co.,Ltd.
Original Assignee
Sinosteel Wuhan Safety & Environmental Protection Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Wuhan Safety & Environmental Protection Research Institute Co Ltd filed Critical Sinosteel Wuhan Safety & Environmental Protection Research Institute Co Ltd
Priority to CN201810505041.4A priority Critical patent/CN108613600B/en
Publication of CN108613600A publication Critical patent/CN108613600A/en
Application granted granted Critical
Publication of CN108613600B publication Critical patent/CN108613600B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Revetment (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of emulsion deep water to bore quick-fried means for loading and processing method.Including:Outer layer PE pipes(3), outer layer PE pipes(3)Bottom pours the taper concrete with pipe outside diameter same diameter(1);Taper concrete(3)Interior pre-buried two J-shaped reinforcing bars(2), internal layer PE pipes(4)Setting is managed in outer layer PE(3)It is interior, form inside and outside bilayer PE pipes, internal layer PE pipes(4), the internal layer PE pipes(4)For loading emulsion;Steel wire rope(5)It is managed along outer layer PE(3)Inner wall and J-shaped reinforcing bar(2)It stays and is welded in the part outside concrete;Steel wire rope(5), the steel wire rope(5)Between two PE pipes;Nonel detonator(6)It is inserted into emulsion(11)In;First layer Rubber washer lid(8)The reserved circular hole in centre, detonator(7)It is pulled out along reserved circular hole;First layer Rubber washer lid(8)It is placed on and has filled emulsion(11)On.Good integrity of the present invention, simple operation is simple under deepwater environment;Lifted using reinforcing bar rope, it is big to bear weight, can explosive payload it is big.

Description

A kind of emulsion deep water bores quick-fried means for loading and processing method
Technical field
The invention belongs to engineering explosion technical fields, and in particular to underwater drilling and blasting technology, more particularly to a kind of emulsification Explosive deep water bores quick-fried means for loading and processing method.
Background technology
The common method of underwater demolition has dobie method, bore blowing-up method and chamber blasting method etc., most common to be Bore blowing-up method.After underwater pore-forming, if not powder charge immediately, silt, which will be flow backwards, to be caused to block.Art methods cannot be satisfied The requirement that quick-burning charge, blind big gun rapid and convenient recycle under deepwater environment.
Invention content
The present invention provides a kind of emulsion deep water and bores quick-fried means for loading and processing side to overcome prior art defect Method.
Purpose to realize the present invention, one aspect of the present invention provide a kind of emulsion deep water brill quick-fried means for loading, packet It includes:
Outer layer PE pipes, the outer layer PE bottom of the tube pour the taper concrete with pipe outside diameter same diameter, make outer layer PE pipes and taper concrete Only in PE tube tops portion, there are the structures of opening for composition one;
Pre-buried two J-shaped reinforcing bars in the taper concrete, J-shaped reinforcing bar bottom are embedded in concrete, and top is stayed in outside taper concrete, tightly Paste outer layer PE inside pipe walls;
Internal layer PE pipes, the internal layer PE pipes are arranged in outer layer PE pipes, form inside and outside bilayer PE pipes, the internal layer PE pipes are for filling Carry emulsion;
Steel wire rope, the steel wire rope are stayed along outer layer PE inside pipe walls and J-shaped reinforcing bar and are welded in the part outside concrete;The steel wire rope Between two PE pipes;
Nonel detonator, the Nonel detonator are inserted into emulsion;
Circular hole is reserved in first layer Rubber washer lid, the first layer Rubber washer lid centre, and detonator is pulled out along reserved circular hole;It is described First layer Rubber washer lid, which is placed on, have been filled on emulsion.
According to embodiments of the present invention, further include second layer Rubber washer, the first layer Rubber washer covers spreading sand, and second Layer Rubber washer, which is placed on, to be laid on sand.
According to embodiments of the present invention, in outer layer PE pipe cavitys, pour concrete again from second layer Rubber washer, detonator and Two steel wire penetrating concretes.
Another aspect of the present invention provides a kind of processing method that emulsion deep water bores quick-fried means for loading, including as follows Step:
(1)Use Mold Making taper concrete;
(2)Pre-buried two J-shaped reinforcing bars when taper concrete are poured, 2cm is reserved in outside taper concrete, 28 is conserved after the completion of taper concrete placings It;
(3)Outer layer PE pipes select water supply PE pipes, and the pipe outside diameter of outer layer PE pipes is identical as taper concrete diameter, by taper concrete placings outer layer PE bottom of the tube, so that outer layer PE pipes and taper concrete is formed one, only in PE tube tops portion, there are the structures of opening;It stays in the J-shaped steel outside concrete Muscles and bones is close to PE inside pipe walls;
(4)Another outer diameter is slightly smaller than outer layer PE pipe, the internal layer PE pipes that are shorter in length than outer layer PE pipes are put into outer layer PE pipes, shape It is managed inside and outside bilayer PE;Internal layer PE pipes are for loading emulsion;
(5)Steel wire rope is in the welding of the part outside concrete along outer layer PE inside pipe walls and reserved J-shaped reinforcing bar, steel wire rope is in two Between a PE pipes;
(6)Along the reserved unique opening of outer layer PE pipes, according still further to emulsion is packed into explosive payload inner layer PE pipes, powder charge is complete At rear insertion Nonel detonator;
(7)Certain size circular hole is reserved with a centre and diameter is slightly less than outer layer PE bores and more than the circle of internal layer PE pipe outside diameters Dish-type first layer Rubber washer lid, which is placed on, have been filled on emulsion, and detonator is pulled out along reserved circular hole;
(8)Spreading sand is covered in first layer Rubber washer, is then placed on the second layer Rubber washer of another identical size again It is laid on sand, detonator is still pulled out along reserved circular hole;
(9)Steel wire rope is close to outer layer PE inside pipe walls and is pierced by always;
(10)In outer layer PE pipe cavitys, concrete, detonator and two steel wire penetrating concretes are poured again from second layer Rubber washer, It is through external, it waits for concrete molding solidification, forms integrated sealing means for loading.
Steel wire rope is lifted when use, accurately can easily be operated means for loading and be carried out drillhole blasting powder charge under deep water conditions Or blind big gun recycling.
The present invention uses PE pipes and taper concrete connector as carrier, according to GB/T13663-2000)PE pipes have preferable Deepwater pressure resistant ability.
Using wire rope pulling means for loading, it can provide preferable stretch according to GB8918-2006 steel wire ropes and carry energy Power.
Using concrete and sand counterweight, be conducive to improve device anti-floating ability.
Using above-mentioned technical proposal, the advantages of present invention compares existing method, has:1, using integral type charge constitution, device Good integrity, simple operation is simple under deepwater environment;2, lifted using reinforcing bar rope, it is big to bear weight, can explosive payload it is big.
Description of the drawings
Fig. 1 is means for loading schematic diagram.
Fig. 2 is taper concrete structure chart.
In figure:1- taper concretes;2-J shape reinforcing bars;3- outer layers PE pipes;4- internal layers PE pipes;5- steel wire ropes;6- detonator thunders Pipe;7- detonators;8- first layer Rubber washers;9- fills sand;10- waterproofs AB glue or concrete;11- emulsions;12- second layer rubber Pad.
Specific implementation mode
The present invention is described further with specific implementation method below in conjunction with the accompanying drawings, not to the limit of its protection domain System.
As shown in Figure 1 and Figure 2, a kind of emulsion deep water bores quick-fried means for loading, including:
Outer layer PE pipes 3,3 bottom of outer layer PE pipes pour the taper concrete 1 with pipe outside diameter same diameter, make outer layer PE pipes 3 and cone Shape concrete 1 forms one, and only in PE tube tops portion, there are the structures of opening;
Pre-buried two J-shaped reinforcing bars 2 in the taper concrete 3,2 bottom of J-shaped reinforcing bar are embedded in concrete, and top is stayed in taper concrete 3 Outside, it is close to 3 inner wall of outer layer PE pipes;
Internal layer PE pipes 4, the internal layer PE pipes 4 are arranged in outer layer PE pipes 3, form inside and outside bilayer PE pipes, and the internal layer PE4 is effective In loading emulsion 11;
Steel wire rope 5, the steel wire rope 5 are stayed along 3 inner wall of outer layer PE pipes and J-shaped reinforcing bar 2 and are welded in the part outside concrete;The steel Cord 5 is between two PE pipes;
Nonel detonator 6 and detonator 7, the Nonel detonator 6 are inserted into emulsion 11;
Circular hole is reserved in first layer Rubber washer 8,8 centre of the first layer Rubber washer, and detonator 7 is pulled out along reserved circular hole;It is described First layer Rubber washer 8, which is placed on, have been filled on emulsion;
8 upper berth stucco of first layer Rubber washer, second layer Rubber washer 12, which is placed on, to be laid in back-up sand 9;
In 3 cavity of outer layer PE pipes, building waterproofing AB glue or concrete 10, detonator 7 and two steel wires are poured from second layer Rubber washer 12 Rope 5 passes through waterproof AB glue or concrete 10.
A kind of processing method that emulsion deep water bores quick-fried means for loading, includes the following steps:
(1)Use Mold Making taper concrete 2;
(2)Pre-buried two J-shaped reinforcing bars 2 when taper concrete 2 are poured, reserve 2cm in outside taper concrete 2, taper concrete 2 is supported after the completion of pouring Shield 28 days;
(3)Outer layer PE pipes 3 select water supply PE pipes, and the pipe outside diameter of outer layer PE pipes 3 is identical as 2 diameter of taper concrete, and taper concrete 2 is poured 3 bottom of outer layer PE pipes, so that outer layer PE pipes 3 and taper concrete 2 is formed one, only in PE tube tops portion, there are the structures of opening;It stays in outside concrete J-shaped reinforcing bar 2 be close to PE inside pipe walls;
(4)Another outer diameter is slightly smaller than outer layer PE pipes 3, the internal layer PE pipes 4 that are shorter in length than outer layer PE pipes 3 are put into outer layer PE pipes 4 It is interior, form inside and outside bilayer PE pipes;Internal layer PE pipes 4 are for loading emulsion;
(5)Steel wire rope 5 is in the part outside concrete along 3 inner wall of outer layer PE pipes and reserved J-shaped reinforcing bar 2 to weld, at steel wire rope 5 Between two PE pipes;
(6)It is filled along unique opening that outer layer PE pipes 3 are reserved according still further to emulsion 11 is packed into explosive payload inner layer PE pipes 4 Nonel detonator 6 is inserted into after the completion of medicine;
(7)Certain size circular hole is reserved with a centre and diameter is slightly less than 3 internal diameter of outer layer PE pipes and more than 4 outer diameter of internal layer PE pipes Collar plate shape first layer Rubber washer lid 8, which is placed on, have been filled on emulsion 11, and detonator 7 is pulled out along reserved circular hole;
(8)In 8 upper berth stucco of first layer Rubber washer lid, then it is placed on again with the second layer Rubber washer 12 of another identical size It has been laid on sand, detonator 7 is still pulled out along reserved circular hole;
(9)Steel wire rope 5 is close to 3 inner wall of outer layer PE pipes and is pierced by always;
(10)In 4 cavity of outer layer PE pipes, concrete is poured again from second layer Rubber washer 12, detonator 7 and two steel wire ropes 5 are worn Concrete is crossed, is gone directly external, concrete molding solidification is waited for, forms integrated sealing means for loading.

Claims (4)

1. a kind of emulsion deep water bores quick-fried means for loading, it is characterised in that including:
Outer layer PE pipes(3), the outer layer PE pipes(3)Bottom pours the taper concrete with pipe outside diameter same diameter(1), outer layer PE is made to manage (3)With taper concrete(1)Only in PE tube tops portion, there are the structures of opening for composition one;
The taper concrete(3)Interior pre-buried two J-shaped reinforcing bars(2), J-shaped reinforcing bar(2)Bottom is embedded in concrete, and top is stayed in cone Shape concrete(3)Outside, it is close to outer layer PE pipes(3)Inner wall;
Internal layer PE pipes(4), the internal layer PE pipes(4)Setting is managed in outer layer PE(3)It is interior, form inside and outside bilayer PE pipes, the internal layer PE is managed(4)For loading emulsion;
Steel wire rope(5), the steel wire rope(5)It is managed along outer layer PE(3)Inner wall and J-shaped reinforcing bar(2)It stays and is welded in the part outside concrete It connects;The steel wire rope(5)Between two PE pipes;
Nonel detonator(6), the Nonel detonator(6)It is inserted into emulsion(11)In;
First layer Rubber washer lid(8), the first layer Rubber washer lid(8)The reserved circular hole in centre, detonator(7)Along reserved circular hole It pulls out;The first layer Rubber washer lid(8)It is placed on and has filled emulsion(11)On.
2. a kind of emulsion deep water according to claim 1 bores quick-fried means for loading, it is characterised in that further include the second layer Rubber washer(12), the first layer Rubber washer lid(8)Upper berth stucco, second layer Rubber washer(12)It is placed on and has been laid on sand.
3. a kind of emulsion deep water according to claim 1 bores quick-fried means for loading, it is characterised in that managed in outer layer PE(3) In cavity, from second layer Rubber washer(12)On pour concrete, detonator again(7)With two steel wire ropes(5)Across concrete.
4. a kind of processing method that emulsion deep water bores quick-fried means for loading, it is characterised in that include the following steps:
(1)Use Mold Making taper concrete(2);
(2)Pour taper concrete(2)When pre-buried two J-shaped reinforcing bars(2), 2cm is reserved in taper concrete(2)Outside, taper concrete(2)It pours It conserves 28 days after the completion;
(3)Outer layer PE pipes(3)Select water supply PE pipes, outer layer PE pipes(3)Pipe outside diameter and taper concrete(2)Diameter is identical, by taper Concrete(2)Pour outer layer PE pipes(3)Bottom makes outer layer PE manage(3)With taper concrete(2)Only in PE tube tops portion, there are openings for composition one Structure;It stays in the J-shaped reinforcing bar outside concrete(2)It is close to PE inside pipe walls;
(4)Another outer diameter is slightly smaller than outer layer PE pipes(3), be shorter in length than outer layer PE pipe(3)Internal layer PE pipe(4)It is put into outer layer PE is managed(4)It is interior, form inside and outside bilayer PE pipes;Internal layer PE pipes(4)For loading emulsion;
(5)By steel wire rope(5)It is managed along outer layer PE(3)Inner wall and reserved J-shaped reinforcing bar(2)Part welding outside concrete, steel Cord(5)Between two PE pipes;
(6)It is managed along outer layer PE(3)Reserved unique opening is managed according still further to explosive payload inner layer PE(4)Middle loading emulsion (11), Nonel detonator is inserted into after the completion of powder charge(6);
(7)Certain size circular hole is reserved with a centre and diameter is slightly less than outer layer PE pipes(3)Internal diameter and more than internal layer PE pipe(4)Outside The collar plate shape first layer Rubber washer lid of diameter(8)It is placed on and has filled emulsion(11)On, detonator(7)It is pulled out along reserved circular hole;
(8)In first layer Rubber washer lid(8)Upper berth stucco, then again with the second layer Rubber washer of another identical size(12) It is placed on and has been laid on sand, detonator(7)Still pulled out along reserved circular hole;
(9)Steel wire rope(5)Always it is close to outer layer PE pipes(3)Inner wall is pierced by;
(10)It is managed in outer layer PE(4)In cavity, from second layer Rubber washer(12)On pour concrete, detonator again(7)With two steel Cord(5)It across concrete, goes directly external, waits for concrete molding solidification, form integrated sealing means for loading.
CN201810505041.4A 2018-05-24 2018-05-24 Deepwater drilling and blasting charging device for emulsion explosive and processing method Active CN108613600B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810505041.4A CN108613600B (en) 2018-05-24 2018-05-24 Deepwater drilling and blasting charging device for emulsion explosive and processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810505041.4A CN108613600B (en) 2018-05-24 2018-05-24 Deepwater drilling and blasting charging device for emulsion explosive and processing method

Publications (2)

Publication Number Publication Date
CN108613600A true CN108613600A (en) 2018-10-02
CN108613600B CN108613600B (en) 2023-08-04

Family

ID=63663599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810505041.4A Active CN108613600B (en) 2018-05-24 2018-05-24 Deepwater drilling and blasting charging device for emulsion explosive and processing method

Country Status (1)

Country Link
CN (1) CN108613600B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114608395A (en) * 2022-03-11 2022-06-10 中铁十九局集团矿业投资有限公司 Blasting method for open-air fracture development rock stratum

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59176600A (en) * 1983-03-28 1984-10-05 株式会社熊谷組 Explosive cartridge and method of initiating detonating fuseby using said explosive cartridge
JPS63124000A (en) * 1986-11-10 1988-05-27 大成建設株式会社 Explosive device
JPH11173800A (en) * 1997-12-08 1999-07-02 Daiho Constr Co Ltd Blasting method and blasting tube
CN2679637Y (en) * 2004-03-15 2005-02-16 王海光 Directional fracture blasting energy-gathering tube
CN102207361A (en) * 2011-05-12 2011-10-05 汉通建设集团有限公司 Packaging cartridges for deep sea (deepwater) explosives and arrangement method
CN205014902U (en) * 2015-09-07 2016-02-03 中国电建集团成都勘测设计研究院有限公司 Drill downthehole deep water blaster
CN205537376U (en) * 2015-11-03 2016-08-31 山东科技大学 Deep hole blasting charging means
CN206772148U (en) * 2017-03-29 2017-12-19 安徽理工大学 A kind of deep hole blasting device
CN208269756U (en) * 2018-05-24 2018-12-21 中钢集团武汉安全环保研究院有限公司 A kind of quick-fried means for loading of emulsion deep water brill

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59176600A (en) * 1983-03-28 1984-10-05 株式会社熊谷組 Explosive cartridge and method of initiating detonating fuseby using said explosive cartridge
JPS63124000A (en) * 1986-11-10 1988-05-27 大成建設株式会社 Explosive device
JPH11173800A (en) * 1997-12-08 1999-07-02 Daiho Constr Co Ltd Blasting method and blasting tube
CN2679637Y (en) * 2004-03-15 2005-02-16 王海光 Directional fracture blasting energy-gathering tube
CN102207361A (en) * 2011-05-12 2011-10-05 汉通建设集团有限公司 Packaging cartridges for deep sea (deepwater) explosives and arrangement method
CN205014902U (en) * 2015-09-07 2016-02-03 中国电建集团成都勘测设计研究院有限公司 Drill downthehole deep water blaster
CN205537376U (en) * 2015-11-03 2016-08-31 山东科技大学 Deep hole blasting charging means
CN206772148U (en) * 2017-03-29 2017-12-19 安徽理工大学 A kind of deep hole blasting device
CN208269756U (en) * 2018-05-24 2018-12-21 中钢集团武汉安全环保研究院有限公司 A kind of quick-fried means for loading of emulsion deep water brill

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114608395A (en) * 2022-03-11 2022-06-10 中铁十九局集团矿业投资有限公司 Blasting method for open-air fracture development rock stratum

Also Published As

Publication number Publication date
CN108613600B (en) 2023-08-04

Similar Documents

Publication Publication Date Title
CN105114125B (en) Tunnel airbag air filling device and tunnel airbag air filling method
EP2929146B1 (en) Rock anchor bolt
CN105839667B (en) The construction manufacture craft of complete prefabricated overlapping assembled underground pipe gallery
CN100564802C (en) The method of crushing rock formation in the colliery
CN105863637B (en) Disposable carbon dioxide fracturing device and preparation method thereof
CN103770909B (en) The buried consolidation anchor of the Zi Luochong of oceanographic engineering
CN107121037A (en) Stone static crushing structure and construction method thereof
CN107859036A (en) A kind of in-situ deposited prefabricated combining structure stake and its construction method suitable for karst region
CN208269756U (en) A kind of quick-fried means for loading of emulsion deep water brill
CN108613600A (en) A kind of emulsion deep water bores quick-fried means for loading and processing method
CN108049890A (en) A kind of suspension device and method for protecting support to empty lane
CN214614083U (en) Grouting assembly for repairing quality defects of karst geological cast-in-place pile
CN106480878A (en) A kind of upper and lower part expansion type soil cement is combined pile tube
CN105370032B (en) Construction method for air bag type concrete project deformation joint water stop cavity mold
CN101545259B (en) Device and method for non-underwater concreting by using drilled pile
CN110130674B (en) Super-large pre-buried crushing hole device for static crushing and using method thereof
CN102828507A (en) Construction method and special hole former for large-diameter cast-in-situ concrete composite pile
CN103306276A (en) New dry construction method for drilled (punched) hole filling pile surrounded by mud
CN109944238A (en) Pile construction method is rammed in full-sleeve full-rotation
CN203145021U (en) Underwater concrete pouring and constructing device
CN203049585U (en) Device for removing slurry on inner wall of steel protective drum of cast-in-situ bored pile
CN106759294B (en) The composite pile that deposited reinforced concrete pile is combined with inflation prestressed steel pipe
CN215290070U (en) Offshore wind turbine pile foundation grouting plugging device
CN207317651U (en) Stone slab static crushing structure
CN207905819U (en) A kind of suspension device to empty lane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 430081 No. 1244 Heping Avenue, Qingshan District, Hubei, Wuhan

Patentee after: Zhonggang Wuhan Safety and Environmental Protection Research Institute Co.,Ltd.

Country or region after: China

Address before: No. 1244 Heping Avenue, Qingshan District, Hubei, Wuhan

Patentee before: SINOSTEEL CORPORATION WUHAN SAFETY AND ENVIRONMENTAL PROTECTION RESEARCH INSTITUTE Co.,Ltd.