CN108612533B - Construction method of gate-shifting section roadway - Google Patents
Construction method of gate-shifting section roadway Download PDFInfo
- Publication number
- CN108612533B CN108612533B CN201810421575.9A CN201810421575A CN108612533B CN 108612533 B CN108612533 B CN 108612533B CN 201810421575 A CN201810421575 A CN 201810421575A CN 108612533 B CN108612533 B CN 108612533B
- Authority
- CN
- China
- Prior art keywords
- roadway
- gate
- door
- section
- shifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 239000000463 material Substances 0.000 claims abstract description 5
- 238000000034 method Methods 0.000 claims description 9
- 230000005641 tunneling Effects 0.000 claims description 9
- 239000004568 cement Substances 0.000 claims description 4
- 238000004873 anchoring Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
- Gates (AREA)
Abstract
The invention discloses a construction method of a gate-shifting section roadway, which relates to the field of mine roadway construction and comprises the following steps: when an original roadway is constructed, the top of the shifting side of the shifting section of the roadway is constructed to a designed height, the section shape of the shifting section of the original roadway close to the shifting side is rectangular, and then the shifting section of the original roadway is permanently supported, so that the invention has the advantages that: the working efficiency is improved, the labor cost is reduced, and the material consumption is reduced.
Description
Technical Field
The invention relates to the field of mine roadway construction, in particular to a construction method of a gate-shifting section roadway.
Background
In the tunnel door-shifting construction, an original tunnel needs to be supported firstly, and then another tunnel needs to be constructed by shifting the door. When the construction of dialling a door, need to choose the top, expand the brush to former tunnel, lead to the strut of former tunnel to become invalid, must strut permanently once more, both extravagant material consumes the manpower again, and work efficiency is not high.
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method of a gate-shifting section roadway, which improves the working efficiency.
The invention solves the technical problems through the following technical scheme: the construction method of the gate-shifting section roadway comprises the steps of constructing the top of the gate-shifting side of the gate-shifting section to a designed height when constructing the original roadway, enabling the section shape of the gate-shifting section of the original roadway close to the gate-shifting side to be rectangular, and then permanently supporting the gate-shifting section of the original roadway.
As an optimized technical scheme, the section shape of the gate-pulling section of the original roadway is half of the section shape of other sections of the original roadway at the part close to the other side, namely the lower part is rectangular, and the upper part is an arched half.
As an optimized technical scheme, the method for permanently supporting the gate-poking section of the original roadway comprises the following steps: and a plurality of anchor cables are arranged at the door-pulling side of the door-pulling section.
As an optimized technical scheme, a plurality of rows of anchor cables are arranged on the gate pulling side of the gate pulling section along the tunneling direction of a roadway, and 1 anchor cable is arranged on the top surface of each row on the gate pulling side.
As an optimized technical scheme, the method for permanently supporting the gate-poking section of the original roadway comprises the following steps: and a plurality of anchor rods are arranged on the door-pulling side of the door-pulling section.
As an optimized technical scheme, a plurality of rows of anchor rods are arranged on the door-shifting side of the door-shifting section along the tunneling direction of a roadway, 2 anchor rods are arranged on the top surface of the door-shifting side of each row, and 3 anchor rods are arranged on the side surface of the door-shifting side.
As an optimized technical scheme, the method for permanently supporting the gate-poking section of the original roadway comprises the following steps: and a plurality of meshes are arranged on the door-shifting side of the door-shifting section.
As an optimized technical scheme, a plurality of rows of net sheets are arranged on the gate-shifting side of the gate-shifting section along the tunneling direction of a roadway, 1 net sheet is arranged on the top surface of the gate-shifting side in each row, and 1 net sheet is arranged on the side surface of the gate-shifting side.
As an optimized technical scheme, the method for permanently supporting the gate-poking section of the original roadway comprises the following steps: and carrying out guniting support on the top surface and the side surface of the door-pulling side of the door-pulling section.
As an optimized technical scheme, the material for guniting support adopts cement or concrete.
The invention has the advantages that: the working efficiency is improved, the labor cost is reduced, and the material consumption is reduced.
Drawings
Fig. 1 is a plan view of roadway gate-driving construction.
Fig. 2 is a schematic view of a gate segment cross section of an original tunnel in a conventional gate segment tunnel construction method.
Fig. 3 is a schematic view of a gate segment section of an original roadway in the gate segment roadway construction method of the present invention.
Detailed Description
As shown in fig. 1, the section AB from point a to point B of the roadway is a gate segment roadway, and the length of the gate segment roadway is 11 m.
As shown in fig. 2, in the construction method of the existing gate-segment roadway, the gate-segment roadway is a straight-wall semicircular arch roadway, and all supports are supported above an arch base line. When the door is pulled, 5 anchor rods in each row on the door pulling side of the original roadway are out of order after the door pulling section of the original roadway is expanded and brushed, 1 anchor cable is out of order, 2 meshes are out of order, 2 anchor rods, 1 anchor cable and 1 mesh need to be installed at the top again, 91 sets of anchor rods, 26 anchor cables, 39 meshes, 26 locksets and 260 anchors are consumed in 13 rows in total, and grout needs to be sprayed at the top again.
As shown in fig. 3, the construction method of the gate-segment roadway of the invention comprises the following steps:
constructing the top of the shifting side of the shifting section of the original roadway to a designed height when constructing the original roadway, so that the section shape of the shifting section of the original roadway is rectangular at the part close to the shifting side; the part close to the other side is a half of the section shape of other sections of the original roadway, namely the lower part is rectangular, and the upper part is an arched half; then, carrying out permanent support on the gate-shifting section of the original roadway; and then another roadway is constructed by shifting the door.
The method for permanently supporting the gate-poking section of the original roadway comprises the following steps: installing 13 rows of anchor cables on the gate pulling side of the gate pulling section along the tunneling direction of the roadway, and installing 1 anchor cable with the diameter of 22 mm and the length of L6200 on the top surface of the gate pulling side in each row; 13 rows of anchor rods are arranged on the door-shifting side of the door-shifting section along the tunneling direction of the roadway, 2 anchor rods phi 22 and L2500 anchor rods are arranged on the top surface of the door-shifting side of each row, and 3 anchor rods phi 22 and L2500 anchor rods are arranged on the side surface of the door-shifting side; 13 rows of net sheets are arranged on the gate-shifting side of the gate-shifting section along the tunneling direction of the roadway, 1 net sheet is arranged on the top surface of the gate-shifting side in each row, and 1 net sheet is arranged on the side surface of the gate-shifting side; and carrying out guniting support on the top and the side of the door-pulling section, wherein the guniting support is made of cement or concrete.
According to the construction method of the gate-poking section roadway, the cross section of the gate-poking section of the original roadway is directly constructed to the cross section of the gate-poking section roadway after the gate-poking section of the original roadway is expanded and brushed in the existing construction method of the gate-poking section roadway, 3 anchor rods on each row of side face are invalid after gate-poking construction, 1 mesh piece is invalid, 65 sets of anchor rods, 13 anchor cables, 26 mesh pieces, 13 locksets and 169 anchor agents are consumed in 13 rows in total, and re-spraying is not needed.
The construction method of the gate-shifting section roadway completes one-time construction of the gate-shifting section of the original roadway, improves the working efficiency and reduces the labor cost. Compared with the construction method of the existing gate-shifting section roadway, the construction method of the gate-shifting section roadway consumes less 26 sets of anchor rods, 13 anchor cables, 13 meshes, 13 locks and 91 anchoring agents, and reduces the consumption of cement and mixture.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included therein.
Claims (10)
1. A construction method of a gate-shifting section roadway is characterized by comprising the following steps: the top of the door-shifting side of the door-shifting section is constructed to the designed height when the original roadway is constructed, the section of the door-shifting section of the original roadway is constructed once, the section shape of the door-shifting section of the original roadway is rectangular at the part close to the door-shifting side, and then the door-shifting section of the original roadway is permanently supported.
2. The construction method of the gate segment roadway according to claim 1, characterized in that: the section shape of the gate section of the original roadway is half of the section shape of other sections of the original roadway at the part close to the other side, namely the lower part is rectangular, and the upper part is an arched half.
3. The construction method of the gate segment roadway of claim 1, wherein the method for permanently supporting the gate segment of the original roadway comprises the following steps: and a plurality of anchor cables are arranged at the door-pulling side of the door-pulling section.
4. The construction method of the gate segment roadway according to claim 3, characterized in that: and a plurality of rows of anchor cables are arranged on the gate-pulling side of the gate-pulling section along the tunneling direction of the roadway, and 1 anchor cable is arranged on the top surface of each row on the gate-pulling side.
5. The construction method of the gate segment roadway of claim 1, wherein the method for permanently supporting the gate segment of the original roadway comprises the following steps: and a plurality of anchor rods are arranged on the door-pulling side of the door-pulling section.
6. The construction method of the gate segment roadway according to claim 5, characterized in that: a plurality of rows of anchor rods are arranged on the door-shifting side of the door-shifting section along the tunneling direction of a roadway, 2 anchor rods are arranged on the top surface of the door-shifting side of each row, and 3 anchor rods are arranged on the side surface of the door-shifting side.
7. The construction method of the gate segment roadway of claim 1, wherein the method for permanently supporting the gate segment of the original roadway comprises the following steps: and a plurality of meshes are arranged on the door-shifting side of the door-shifting section.
8. The construction method of the gate segment roadway according to claim 7, characterized in that: a plurality of rows of net pieces are arranged on the side of the gate poking section along the tunneling direction of the roadway, 1 net piece is arranged on the top surface of the side of the gate poking in each row, and 1 net piece is arranged on the side surface of the side of the gate poking.
9. The construction method of the gate segment roadway of claim 1, wherein the method for permanently supporting the gate segment of the original roadway comprises the following steps: and carrying out guniting support on the top surface and the side surface of the door-pulling side of the door-pulling section.
10. The construction method of the gate segment roadway according to claim 9, characterized in that: the material for guniting support is cement or concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810421575.9A CN108612533B (en) | 2018-05-04 | 2018-05-04 | Construction method of gate-shifting section roadway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810421575.9A CN108612533B (en) | 2018-05-04 | 2018-05-04 | Construction method of gate-shifting section roadway |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108612533A CN108612533A (en) | 2018-10-02 |
CN108612533B true CN108612533B (en) | 2020-06-26 |
Family
ID=63661814
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810421575.9A Active CN108612533B (en) | 2018-05-04 | 2018-05-04 | Construction method of gate-shifting section roadway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108612533B (en) |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4536564B2 (en) * | 2005-03-28 | 2010-09-01 | 西松建設株式会社 | Widening part structure and widening part construction method of shield tunnel |
CN101100945A (en) * | 2006-06-24 | 2008-01-09 | 唐卫东 | Mine tunnel U-shaped mulch area fork door support technology |
CN202360116U (en) * | 2011-12-09 | 2012-08-01 | 鹤壁煤电股份有限公司第八煤矿 | U-shaped shed roadway junction support device |
CN103032073B (en) * | 2012-12-08 | 2015-01-14 | 中铁十二局集团有限公司 | Urban subway mudstone stratum connected aisle and shield tunneling parallel construction method |
CN105927233B (en) * | 2016-05-31 | 2018-07-10 | 中铁第四勘察设计院集团有限公司 | Large span transverse passage-way construction method applied to pipe-plate lining tunnel |
CN107489440B (en) * | 2017-08-11 | 2023-08-15 | 淮北矿业股份有限公司 | Small-angle shed lifting method for roadway and small-angle shed lifting method for shed roadway |
CN108843334A (en) * | 2018-06-19 | 2018-11-20 | 中交公局厦门工程有限公司 | A kind of method of reinforcing building lower section rich water soft soil layer service channel |
CN109083645A (en) * | 2018-08-01 | 2018-12-25 | 南宁轨道交通集团有限责任公司 | Shield tunnel and service channel method for synchronously constructing under the conditions of rich water round gravel stratum |
-
2018
- 2018-05-04 CN CN201810421575.9A patent/CN108612533B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108612533A (en) | 2018-10-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103469939B (en) | A kind of masonry filler wall and main body flexibly connect earthquake resistant structure and construction method thereof | |
CN102337903B (en) | Method of active coupling support in time and space for control of minimum deformation of surrounding rock of deep well roadway | |
CN205742224U (en) | Deep foundation pit supporting construction structure based on campshed Yu anchor cable | |
CN108203984A (en) | A kind of Dangerous Rock Body bolting with wire mesh method | |
CN202925925U (en) | Reinforcing device for brick masonry wall | |
CN202627000U (en) | Anchor-pulling type foundation pit supporting structure with double rows of piles | |
CN206768861U (en) | A kind of reinforcement ring retaining wall | |
CN202194129U (en) | Composite prestress soil-blocking pile | |
CN108612533B (en) | Construction method of gate-shifting section roadway | |
CN111197312A (en) | L-shaped prestress pulling-anchoring engaged double-row pile foundation pit supporting structure and construction method thereof | |
CN103321412A (en) | Hollow floor air bag and construction method of cast-in-place hollow floors | |
CN106522991B (en) | Roadway anchor-shotcrete support flexible integral concrete shotcrete layer and construction method thereof | |
CN112761674A (en) | Anti-bottom-heaving structure of soft rock roadway and construction method thereof | |
CN209323533U (en) | It is a kind of it is upper just under soft system of deep foundation pit support | |
CN102418400A (en) | Pretensioning prestressed reinforced concrete precast beam | |
CN215715392U (en) | Side slope supporting structure | |
RU2471992C1 (en) | Mine barrier | |
CN115263387A (en) | High-stress broken rock mass peak-shifting reinforcing and supporting method | |
CN103680288A (en) | Tunnel micro-step method technology teaching simulation body | |
CN105133664B (en) | Combined frame type isolation protection system and construction method thereof | |
CN204418559U (en) | A kind of bolt-type syndeton for connecting stair upper end | |
CN211038690U (en) | Reinforced structure of small clear distance tunnel | |
CN114086991A (en) | Supporting method for extremely-broken oversized-section roadway with high-altitude frozen soil layer | |
CN102322060A (en) | Composite prestressing retaining pile | |
CN219261108U (en) | Soil fixing structure for preventing water and soil loss |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |